Teori Biaya 2
Macam Biaya
Biaya tetap (
fixed cost
) =
FC
Biaya variabel (
variable cost
) =
VC=v.Q
Biaya total (
total cost
) =
TC=FC+VC
Biaya tetap rata-rata (
average fixed cost
) =
AFC=FC/Q
Biaya variabel rata-rata (
average variable cost
) =
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0
1 4
2 20
3 26
4 30
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50
1 4
2 20
3 26
4 30
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50
1 4 50
2 20 50
3 26 50
4 30 50
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0
1 4 50 50
2 20 50
3 26 50
4 30 50
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0
1 4 50 50
2 20 50 100
3 26 50 150
4 30 50 200
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0 50
1 4 50 50 100
2 20 50 100 150
3 26 50 150 200
4 30 50 200 250
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0 50
1 4 50 50 100 25
2 20 50 100 150 7.50
3 26 50 150 200 7.69
4 30 50 200 250 8.33
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0 50
1 4 50 50 100 25 12.5
2 20 50 100 150 7.50 2.50
3 26 50 150 200 7.69 1.92
4 30 50 200 250 8.33 1.67
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0 50
1 4 50 50 100 25 12.5 12.5
2 20 50 100 150 7.50 2.50 5.00
3 26 50 150 200 7.69 1.92 5.77
4 30 50 200 250 8.33 1.67 6.67
Tabel Biaya
TK Q FC VC TC AC AFC AVC MC
0 0 50 0 50
1 4 50 50 100 25 12.5 12.5 12.5
2 20 50 100 150 7.50 2.50 5.00 3.13
3 26 50 150 200 7.69 1.92 5.77 8.33
4 30 50 200 250 8.33 1.67 6.67 12.5
Contoh kasus