• Tidak ada hasil yang ditemukan

ACCA Paper F 7 Financial Reoirting F7FR Session15 d08

N/A
N/A
Protected

Academic year: 2019

Membagikan "ACCA Paper F 7 Financial Reoirting F7FR Session15 d08"

Copied!
18
0
0

Teks penuh

(1)

OVERVIEW

Objective

¾

To describe and explain the accounting treatment for construction contracts.

CONSTRUCTION CONTRACTS

PRESENTATION AND DISCLOSURE RECOGNITION

AND MEASUREMENT

¾ Definitions

¾ Key issue

¾ Revenue

¾ Contract costs

¾ The rules ¾ Calculations

(2)

1

CONSTRUCTION CONTRACTS

1.1

Definitions

¾

A construction contract is a contract specifically negotiated for the construction of:

‰ an asset; or

‰ a combination of assets that are:

closely interrelated; or

interdependent

in terms of their design, technology and function or their ultimate purpose or use.

¾

A fixed price contract is a construction contract in which the contractor agrees to a fixed contract price, or a fixed rate per unit of output, which in some cases is subject to cost escalation clauses.

¾

A cost plus contract is a construction contract in which the contractor is reimbursed for allowable or otherwise defined costs, plus a percentage of these costs or a fixed fee.

¾

Construction contracts include:

‰ Contracts for the rendering of services which are directly related to

the construction of the asset, for example, those for the services of project managers and architects; and

‰ Contracts for the destruction or restoration of assets, and the

restoration of the environment following the demolition of assets.

¾

Contrast this with speculative building work without a firm sale contract.

This is work-in-progress and is valued at the lower of cost and net realisable value.

1.2

Key issue

Revenue and profit recognition

¾

Contracts may last several years. Costs are incurred, and customer is billed, over duration of contract.

¾

Potential treatments (not under IFRS, but technically):

‰ Recognise all revenue and related costs in statement of comprehensive income only

(3)

Commentary

“Completed contract” method” is dominant under some GAAPS – but it is not IFRS.

‰ Recognise revenue and costs in statement of comprehensive income as contract

progresses.

¾

Accruals and prudence

‰ Should recognise revenues and costs as they are earned and incurred.

‰ Should only recognise profits when cash realisation is reasonably certain, but make

provision for costs and losses when foreseen.

‰ Prudence may conflict with accruals.

¾

IAS 11 requires that the costs and revenues associated with a contract should be recognised in the statement of comprehensive income as the contract activity progresses.

1.3

Revenue

¾

Contract revenue should comprise:

‰ The initial amount of revenue agreed in the contract; and ‰ Variations in contract work, claims and incentive payments:

to the extent that it is probable that they will result in revenue; and

they are capable of being reliably measured.

Commentary

Variations may arise if, for example, actual inflation is greater than that assumed when the contract commenced.

¾

Contract revenue is measured at the fair value of the consideration received or receivable.

Commentary

If deferred, fair value should be discounted (i.e. present value of amount receivable).

(4)

Examples

‰ A contractor and a customer may agree variations or claims that increase or decrease

contract revenue in a period subsequent to that in which the contract was initially agreed.

‰ The amount of revenue agreed in a fixed price contract may increase as a result of

cost escalation clauses.

‰ The amount of contract revenue may decrease as a result of penalties arising from

delays caused by the contractor in the completion of the contract.

‰ When a fixed price contract involves a fixed price per unit of output, contract

revenue increases as the number of units is increased.

1.4

Contract costs

¾

Contract costs comprise:

‰ Costs that relate directly to the specific contract;

‰ Costs that are attributable to contract activity in general and can be allocated to the

contract; and

‰ Such other costs as are specifically chargeable to the customer under the terms of

the contract.

¾

Costs that relate directly to a specific contract include:

‰ Site labour costs, including site supervision; ‰ Costs of materials used in construction;

‰ Depreciation of plant and equipment used on the contract;

‰ Costs of moving plant, equipment and materials to and from the contract site; ‰ Costs of hiring plant and equipment;

‰ Costs of design and technical assistance that is directly related to the contract; ‰ The estimated costs of rectification and guarantee work, including expected

warranty costs; and

(5)

2

RECOGNITION AND MEASUREMENT

2.1

The rules

2.1.1

General

¾

Contracts should be considered on a contract by contract basis.

Commentary

There is no “offset” of profits/losses until the final presentation in the financial statements.

¾

In certain circumstances:

‰ two or more contracts may be combined to be considered as one;

Commentary

When they are negotiated as a package, closely inter-related and performed concurrently or in a continuous sequence.

‰ a contract may be “segmented” into two or more separate contracts.

Commentary

When there are separate proposals/negotiations such that segments can be individually accepted/rejected and separately identifiable costs/revenues.

¾

The impact that a contract will have on the financial statements depends on the estimate of the future outcome of the contract.

¾

The rules in IAS 11 provide for three possibilities, arising on contract review.

‰ Contracts which are expected to make a profit and where the outcome is reasonably

certain. Revenue and cost will be recognised in the statement of comprehensive income resulting in some profit being taken.

‰ Contracts where a loss is expected. The exercise of prudence requires that this loss

be recognised immediately and in full.

‰ Contracts where the outcome cannot be assessed with reasonable certainty.

2.1.2

Specific

(6)

¾

When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.

¾

When the outcome of a construction contract cannot be estimated reliably:

‰ Revenue should be recognised only to the extent of contract costs incurred that it is

probable will be recoverable; and

‰ Contract costs should be recognised as an expense in the period in which they are

incurred.

Situation How is

revenue measured?

How are costs

measured? Commentary

Profit is being

taken By reference to the stage of (percentage) completion method

The costs incurred in reaching the stage of completion are included within cost of sales.

Often this is achieved by applying the percentage completion to the total costs that are expected to occur over the life of the contract.

Revenue exceeds costs therefore profit is recognised.

If the same % completion is applied to revenue and costs then this will result in that percentage of the total estimated profit being recognised

Loss making

contracts By reference to the stage of (percentage) completion method

As a balancing figure to interact with the revenue that has been recognised and generate the required loss.

Loss may be recognised at any stage of a contract. For example an entity may have signed a contract that it knows will make a loss. In such a case the loss should be recognised when the contract is signed.

Contracts where the outcome is uncertain

To equal the

cost figure The costs incurred in the period should be expensed

Revenue = costs

The usual source of

(7)

¾

The accounting should be performed so as to recognise revenue and costs that have arisen in the period. This is done by calculating the amounts in total that should be recognised by the year end and then adjusting them for what has been recognised in earlier years.

2.1.3

Meaning of “can be estimated reliably”

¾

In the case of a fixed price contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied:

‰ total contract revenue can be measured reliably;

‰ it is probable that the economic benefits associated with the contract will flow to the

entity;

‰ both the contract costs to complete the contract and the stage of contract completion

at the end of the reporting period can be measured reliably; and

‰ the contract costs attributable to the contract can be clearly identified and measured

reliably so that actual contract costs incurred can be compared with prior estimates.

¾

In the case of a cost plus contract, the outcome of a construction contract can be

estimated reliably when all the following conditions are satisfied:

‰ it is probable that the economic benefits associated with the contract will flow to the

entity; and

‰ the contract costs attributable to the contract, whether or not specifically

reimbursable, can be clearly identified and measured reliably.

2.1.4

Stage of completion

¾

The recognition of revenue and expenses by reference to the stage of completion of a contract is often referred to as the percentage of completion method.

‰ Contract revenue is matched with the contract costs incurred in reaching the stage

of completion, resulting in the reporting of revenue, expenses and profit which can be attributed to the proportion of work completed.

‰ This method provides useful information on the extent of contract activity and

performance during a period. The standard does not specify a single method for calculating the percentage of completion. Methods include:

the proportion that contract costs incurred for work performed to date bear to the estimated total contract costs;

surveys of work performed; or

completion of a physical proportion of the contract work.
(8)

¾

Note that:

‰ amounts billed are irrelevant in determining revenue to be taken to the statement of

comprehensive income; and

‰ costs incurred by the year end (and therefore appearing in the cost accounts) may

be an irrelevant figure in determining cost of sales.

¾

IAS 11 applies to construction contracts as defined. IAS 18 Revenue requires a similar approach for contracts for the provision of a service.

2.2

Calculations

2.2.1

Basics

¾

Make all calculations on contract by contract basis. There is no netting-off of profits on, or assets relating to, one contract against losses or liabilities on another.

¾

Steps to obtain figures for the statement of comprehensive income.

(a) Calculate total expected profit

$

Contract price X

Less Costs to date (X)

Estimated future costs (X) ___

X ___

(b) Calculate the stage of completion

Acceptable methods include

Sales basis Cost basis

Value of work done to date Costs to date Total sales value Total costs

(IAS 11does not specify a method).

(c) Calculate revenue and costs for the year

(i) Calculate attributable revenue and costs to date (using proportion above) (ii) Deduct any revenue and costs taken in earlier periods.

(9)

Example 1

Tanner Ltd – year ended 31 December 2007

$

Costs to date 1,500

Future expected costs 1,000

Work certified to date 1,800

Expected sales value 3,200

Revenue taken in earlier periods 1,200

Cost taken in earlier periods 950

Required:

Calculate the figures to be taken to the statement of comprehensive income in respect of revenue and costs year ended 31 December 2007 on both:

(i) a sales basis; and (ii) a cost basis.

Proforma solution

(a) Calculate total expected profit

$ Revenue

Less Contract costs to date

Future expected costs ______

Total expected profit

______

(b) Calculate percentage completion

(10)

(c) Calculate revenue/costs for the year

(1) To date (2) Prior (1) To date (2) Prior period $ period $

Revenue

Cost of sales

_____ _____

Profit

_____ _____

(1) Calculate attributable revenue and costs to date

(2) Deduct any revenue and costs taken in earlier periods.

2.2.2

A complication

¾

In the above example the costs have been measured using the same percentage as that used to calculate the revenue.

¾

This assumes that both costs and revenues arise evenly over the life of the contract. This may not be the case. IAS 11 says that the costs that must be measured as those incurred in reaching the stage of completion of the contract.
(11)

Illustration 1

Tanner Ltd – year ended 31 December 2007

$ Costs to date (including a rectification cost of $50) 1,500

Future expected costs 1,000

Work certified to date 1,800

Expected sales value 3,200

Revenue taken in earlier periods 1,200

Cost taken in earlier periods 950

Percentage complete (cost basis as before) 60%

Required:

Calculate the figures to be taken to the statement of comprehensive income in respect of revenue and costs year ended 31 December 2007 on a costs basis. The total costs that are expected to arise over the life of the contract are $2,500. These are made up of two types of cost:

$

Rectification costs 50

Other costs (which arise over the life of the contract) 2,450

To date Prior period This period

Revenue 60% × 3,200 = 1,920 1,200 720

Costs

Rectification 50 – (50)

Other costs 60% × 2,450 = 1,470 950 (520) ____ 150 ____

The % completion could be reworked as =

+1,000

450 , 1

450 ,

1 59%

2.3

Recognition

¾

The basic double entry for each contract is quite straightforward.

¾

When costs are actually incurred on the contract:

Dr Contract account X

(12)

¾

When amounts are billed:

Dr Receivables X

Cr Contract account X

¾

To recognise revenue:

Dr Contract account X

Cr Revenue X

¾

To recognise costs:

Dr Cost of sales X

Cr Contract account X

Commentary

This transfers revenues and costs that have been accumulated in the contract account to the statement of comprehensive income over the duration of the contract.

¾

When payments on account are received/when billings are settled:

Dr Cash X

Cr Receivables X

Illustration 2

$

Revenue to be recognised 1,250

Costs to date 1,080

Costs to be recognised 1,000

Billings 640

Contract account

$

Costs incurred 1,080

Revenue recognised 1,250 ______ 2,330 ______

Balance b/d 690

$

Receivables 640

Costs recognised 1,000

Balance c/f 690

(13)

Commentary

The balance could be negative (a credit balance). This depends on the interaction between the amount invoiced/actual costs and the amounts recognised as revenue and costs.

3

PRESENTATION AND DISCLOSURE

Note

¾

An entity should disclose:

‰ the amount of contract revenue recognised as revenue in the period; ‰ the methods used to determine the contract revenue recognised in the

period; and

‰ the methods used to determine the stage of completion of contracts in

progress.

1

¾

An entity should disclose each of the following for contracts in progress at the end of the reporting period:

‰ the aggregate amount of costs incurred and recognised profits (less

recognised losses) to date;

‰ the amount of advances received; and ‰ the amount of retentions.

2

¾

An entity should present:

‰ the gross amount due from customers for contract work as an asset; and ‰ the gross amount due to customers for contract work as a liability.

3

¾

The gross amount due to or from customers is the net amount of:

‰ costs incurred plus recognised profits; less

‰ the sum of recognised losses and progress billings.

¾

Note that it is also the sum of the balances on the contract account.
(14)

Illustration 3

Using the figures from Illustration 2:

$

Contract revenue recognised as revenue in the period: ______ 1,250 1 Contract costs incurred and recognised profits

(less recognised losses) to date (W) ______ 1,330 2

Gross amounts due from customers

for contract work (W) ______ 690 3

WORKING $

Costs incurred to date 1,080

Recognised profits/(less losses) to date ______ 250

1,330 W1

Less: progress billings (640)

______

Gross amount due from/(to) customers 690 W2

______

Example 2

Company X

Contracts as at 31 December 2007:

A B C

$000 $000 $000

Contract value 100 100 80

Costs to date 40 2 75

Estimated costs to complete 30 58 25

Billings 15.6 − 67

Date started during the year 1 Jan 1 Nov 1 Jan

% completion 45% 3% 80%

Required:

(15)

Proforma solution 2

WORKINGS

A B C $000

Revenue Costs of sales

____________

Recognised profit/(loss)

____________

Disclosures

Contract revenue recognised as revenue in the period:

____________ Contract costs incurred and recognised profits

(less recognised losses) to date:

____________ Gross amounts due from customers for contract work:

____________ Gross amounts due to customers for contract work

____________

FOCUS

You should now be able to:

¾

define a construction contract and discuss the role of accounting concepts in the recognition of profit;

¾

describe the acceptable methods of determining the stage (%) of completion of a contract;
(16)

EXAMPLE SOLUTIONS

Solution 1

(a) Calculate total expected profit

$

Revenue 3,200

Less Contract costs to date (1,500)

Future expected costs (1,000) ______ 700 ______

(b) Percentage completion

Sales basis Costs basis

200 , 3

800 ,

1 = 56.25%

500 , 2

500 ,

1 = 60%

(c) Calculate revenue and costs for the year

To date Prior To date Prior

period $ period $ Revenue 3,200 × 0.5625 1,800 – 1200 = 600 3,200 × 0.6 1,920 – 1200 = 720

= 1,800 = 1,920

Cost of sales 2,500 × 0.5625 1,406 – 950 = (456) 2,500 × 0.6 1,500 – 950 = (550)

= 1,406 = 1,500

______ ______

Profit 144 170

______ ______

Solution 2

W1 W2 W3 $000

Revenue 45 2 64 111

Cost of sales 31.5 2 84 (117.5)

____ ___ ___ _____

Recognised profit/(loss) 13.5 − (20) (6.5)

____ ___ ___ _____

Contract revenue recognised as revenue in the period: 111

Contract costs incurred and recognised profits

(less recognised losses) to date 110.5

Gross amounts due from customers for contract work (37.9 + 2) 39.9

(17)

WORKINGS

A B C Total

Contract costs incurred 40 2 75 117

Recognised profit/(loss) 13.5 – (20) (6.5)

____ ___ ___ _____

53.5 2 55 110.5

Billings (15.6) (67) (82.6)

____ ___ ___ _____

37.9 2 (12) 27.9

____ ___ ___ _____

(1) Contract A Profit making

Contract account

$

Costs incurred 40

Revenue recognised 45

–––– 85 ––––

Balance b/d 37.9

$

Billings 15.6

Costs recognised 31.5

Balance c/f 37.9

–––– 85 ––––

Grossamount owed by customer = 37.9

(2) Contract B too soon to take profit

Contract account

$

Costs incurred 2

Revenue recognised 2

–– 4 ––

Balance b/d 2

$

Billings 0

Costs recognised 2

Balance c/f 2

–– 4 ––

(18)

(3) Contract C − loss making contract

Contract account

$

Costs incurred 75

Revenue recognised 64

Balance c/f 12

––– 151 –––

$

Billings 67

Costs recognised 84

––– 151 –––

Balance b/d 12

Referensi

Dokumen terkait

¾ If it is not practicable to determine the period specific effects of an error on comparative information for prior periods presented, the entity shall restate the opening

Sales are recognised in the income statement at the moment when the significant risks and rewards of ownership of the goods have been transferred to the buyer, which is

¾ After initial recognition, an entity that chooses the cost model shall measure all of its investment property using the cost model in IAS 16 Property, Plant and Equipment, that is

This will give an annual impairment of goodwill of $20,000 which will be charged as an expense in the current years statement of comprehensive income.. The previous

The lease term is six-years (because it is almost certain that Orlick will contract to lease the asset for the secondary period) which is equal to the useful life of

change in capital structure was a 1 for 2 rights issue, on 1 July 2008, at $7 per share when the market value of the shares was $10 (IGNORE THE BONUS. ISSUE IN b AND THE ISSUE

No part of this training material may be translated, reprinted or reproduced or utilised in any form either in whole or in part or by any electronic, mechanical or

The reduction of closing inventory in the consolidated statement of comprehensive income would reduce the profit for the year and hence the accumulated profit/retained earnings