F- ENG 011/00
B
Ref. No : 4-004/FCS-AI/PPAHQ/ENG/IX/23 Date :
Handed to : cc
Up. Bp. Bani Permono / Sibiara
Re : JALAN, TURAP, SALURAN & WATERPOND
Herewith we submit drawing as follow :
NO
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Purpose
X Approval Comment As Requested
Review Action
Submitted by : Febru Sardjono Received by :
Signature : Signature :
Reply / Comment :
CONSULTANT : - OWNER : PT. PUTRA PERKASA ABADI
Approved : - Date : - Approved : Date :
DENAH BAK KONTROL AIR KOTOR INF-15 R0
DETAIL BAK KONTROL AIR KOTOR 1 INF-16
INF-17 DETAIL BAK KONTROL AIR KOTOR 2
R0 R0
DENAH PONDASI PJU DAN PENANGKAL PETIR INF-13 R0
DENAH JALUR KABEL INF-14 R0
DENAH PERKERASAN JALAN INF-11 R0
DETAIL POTONGAN JALAN INF-12 R0
DETAIL DAN POTONGAN RETENTION POND 1 INF-09 R0
DETAIL DAN POTONGAN RETENTION POND 2 INF-10 R0
DETAIL BAK KONTROL (BK1 DAN BK2) INF-07 R0
POTONGAN SALURAN KAWASAN INF-08 R0
R0 DETAIL PERKUATAN LERENG
SITE ENGINEERING INF-06 R0
INF-05A R0
DENAH PEMERATAAN TANAH DAN TURAP
POTONGAN DINDING PENAHAN TANAH
DETAIL DINDING PENAHAN TANAH (1) INF-04
INF-03
DETAIL DINDING PENAHAN TANAH (2) DAN PAGAR PANEL INF-05
FOR CONSTRUCTION SUBMISSIONS
PPA HEADQURATER PROJECT 4 004
A C D
14 September 2023
PT. PUTRA PERKASA ABADI
LANDSCAPE / INFRA
R0
DRAWING TITLE DRAWING NUMBER NOTES
DAFTAR GAMBAR
POTONGAN KONTUR KAWASAN
R0
INF-00 R0
INF-01 R0
INF-02 R0
NOT APPROVED
A APPROVED B
With CommentAPPROVEDC
Revise & ResubmitD REJECTED
(JALAN, TURAP, SALURAN &