• Tidak ada hasil yang ditemukan

Adelaide Research & Scholarship: Series F, Section 1: Summary of the proceedings of first (re-planting) action October - December 1975.

N/A
N/A
Protected

Academic year: 2025

Membagikan "Adelaide Research & Scholarship: Series F, Section 1: Summary of the proceedings of first (re-planting) action October - December 1975."

Copied!
2
0
0

Teks penuh

(1)

ROTAN TITO ARC OTHSHS v. SIR ALEXANDER WADDELL MD OTHERS

(RE-PLANTIRG ACTION): SUI4MARY OP PROCEEDINGS

FRIDAY, 51 OCTOBER 1975.

1 . The entire day was taken up with the citing of legal

authorities by Mr Macdonald (Counsel for the Banabans) 'to

show that although the Resident Commissioner no longer

existed and could not therefore prescribe the types of trees uo be re-planted in the mined out areas, the Court had the right to intervene and order that his functions be performed.

Siunmary of Proceedings. Monday, 5 November 1975.

2. Mr Macdonald concluded his references to legal authorities which had taken up the whole of Friday, and then turned to

point 6 on his main list of topics, namely, when does the obligation to re-plant arise in respect of (a) the 1913

Agreement, and (b) the A and C deeds. He then made a number of submissions on the construction of the 1913 Agreement., He maintained that land is not "worked out" until either a) all

the phosphate has been removed, or b) under no conceivable circumstances could the Company come bock to re-vvo.rk it. In either case the Company must also have ceased to use the land for access. Mr Macdonald then cited evidence to show that

as late as 1969 the BPC determined that they still required 50^ of the land in the Central and Eastern mining areas for

access and mining. Furthermore, although the other of the land was no longer required by the BPC the Banabans were not informed until 1971 when they heard via the Foreign and

Commonwealth Office. Mr Macdonald argued that it was difficult

for a layman to tell just from looking at the land whether or not it had been fully worked out and that in practice it was quite impossible for the Banabans to know when the BPC no

longer required their land. There was, therefore, he said,

no cause of action until 1969 at the very earliest and therefor^

the question of laches (i.e. unreasonable delay in pursuit of a legal remedy) did not arise. Mr Macdonald pointed out that the leases did not expire until 1999, that access roads were

/shifted

(2)

•y'l

shifted about as and when required and that significant areas of the central mining area were classified as only- part worked out. The Banabans could not, therefore, know- that in 1969 50?o of the land would no longer be required by the BPC unless the BPG informed them, yet i t vras left to the Banabans to take the initiative on the reversion of land.

3* At this stage a technical point was raised by Mr Justice Megarry who vras not happy that certain of the submissions being

put forward by Mr Macdonald were as pleaded. His Lordship said he vrould consider this matter and give a ruling on Tuesday morning. Mr Macdonald then considered the land to

which the re-planting obligation applied on a plot by plot basis. He argued that in nearly all cases there was -no

specific determination by the BPG that they no longer required the land until 1969 and therefore the question of laches did not arise. At this point a discussion arose concerning the exact meaning of the term "delimited area" which appeared in the 1913 Agreement. I t appeared that this phrase could be used to apply to either (a) the whole area covered by the 191 3

Agreement from which the Company could select 250 acres to mine, or (b) the 250 acres actually selected. As Mr McCrindle had already made certain submissions on the proper consumption of the term "the delimited area" i t was agreed that for the

purposes of the discussion then in progress the total area

would be called the "envelope" and the 250 acres Sf^T-^cted would be referred to as "the 250 acre area". As a result of this

discussion Mr Macdonald agreed that henceforth plot 1h3 and plot 29J^ would no longer be considered as they were outside the relevant area. Mr Macdonald was still dealing with topic no.6

when the Court rose.

Pacific Dependent Territories Department Foreign and Commonwealth Office

Referensi

Dokumen terkait

The day v/as taken up with the remainder of Mr Brovrne- V/ilkinson's Counsel for the BPC submissions concerning the measure of damages relating to the purple land, and to the

Nevertheless both the government and Company shov/ed concern to see the replanting was properly done, and the attempts v/ere carried cut under their supervision, Mr Vinelott referred

NOVEMBER 1975 The court did not sit on 21 Novemher and the days of 2k, 25 and 26 Noven/ber v/ers taken up hy plaintiffs' counsel in detailed technical sutmissions concerning the

The obligation was entered into before the land vraa mined and could have been fulfilled if the Pacific Phosphate Company had done what they said they would and left sufficient

I-Ir Justice Megarry pointed out that imder section 271a discretionary powers were limited to those "conferred upon him by this Order", and asked what in the Order conferred the sort

Head 2 The issue raised under t h i s head w^as that "if one were to rely upon a right which is annexed to land, such as the benefit of replanting under the covenant between the

the passing on of the rightwS and obligations under the 1913 Agreement and the A and G deeds not only in 1920 when the Commissioners succeeded to the PacTfi Phosphate Company but also

He put fonward arguments to show that the land known as Rakentai which the plaintiffs claim was wrongfully mined by the BPC vras not in fact in the area where over-mining had taken