TWEED SHIRE COUNCIL

NOTE - ANNUAL LOAN ALLOCATION $750,000

BRIDGE No. BRIDGE NAME WATERWAY NAME ROAD No. ROAD NAME SEGMENT

No. WORK TYPE LENGTH (M) ESTIMATE

RATE ( $ )

ESTIMATED COST ( $ )

GRANT FUNDING

NET COST TO COUNCIL

2008/09 YEAR

BN2432 O'BRIENS BRIDGE - Purchase of

planks TWEED RIVER MR142 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $205,000 $100,000 $105,000

BN2671

POTTSVILLE BRIDGE RAILING MOOBALL CRK 2184 TWEED COAST RD 10 REPLACE RAILING 88 $81,000 $0 $81,000

BN2670 KINGSCLIFF PEDESTRIAN

BRIDGE CUDGEN CREEK 1258 SUTHERLAND ST 2 NEW PEDESTRIAN BRIDGE 40 $150,000 $0 $150,000

BN2437 PERCH CREEK PERCH CREEK MR142 KYOGLE RD 180 TIMBER REPLACEMENT (RTA 50%) 14 $955,000 $335,000 $620,000

BN162 GIDDYS BRIDGE BILAMBIL CREEK 1371 URLIUP RD 5 TIMBER REPLACEMENT 34 $700,000 $0 $700,000

TOTAL - 2008/09 $2,091,000 $435,000 $1,656,000

AVAILABLE FUNDS = $1,570,506 SHORTFALL FROM TVRS = $85,494 2009/10 YEAR

BN2432 O'BRIENS BRIDGE -

Construction TWEED RIVER MR142 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $445,000 $225,000 $220,000

BN2435 SNAKE CREEK BRIDGE SNAKE CREEK MR142 KYOGLE RD 100 TIMBER REPLACEMENT (RTA 50%) 20 $440,000 $220,000 $220,000

BN2433 TWIN BRIDGE - Commencement TWEED RIVER MR143 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $600,000 $450,000 $150,000

BN2434 BREWER-CHARLES BRIDGE TWEED RIVER MR144 KYOGLE RD 70 TIMBER REPLACEMENT (RTA 50%) 10 $320,000 $160,000 $160,000

TOTAL - 2009/10 $1,805,000 $1,055,000 $750,000

2010/11 YEAR

BN40 CHARLTONS BRIDGE -

Commencement CUDGERA CREEK 371 CUDGERA CREEK RD 2 TIMBER REPLACEMENT 24 $450,000

0 $450,000

BN2433 TWIN BRIDGE - Completion TWEED RIVER MR143 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $300,000 $0 $300,000

TOTAL - 2010/11 $750,000 $750,000

2011/12 YEAR

2008/2009 5 YEAR ROLLING INFRASTRUCTURE PROGRAM - BRIDGES

1. BRIDGE CONSTRUCTION

(2)

BN48 RICHARDS BRIDGE DUNBIBLE CREEK 1242 STOKERS RD 13 TIMBER REPLACEMENT 25 22000 $550,000

0 $550,000

BN40 CHARLTONS BRIDGE CUDGERA CREEK 371 CUDGERA CREEK RD 2 TIMBER REPLACEMENT 24 $200,000

0 $200,000

TOTAL - 2011/12 $750,000 $0 $750,000

2012/13 YEAR

BN2670 KINGSCLIFF TRAFFIC BRIDGE -

Commencement CUDGEN CREEK 1258 SUTHERLAND ST 2 TIMBER REPLACEMENT 40 30000 $600,000

0 $600,000

BN144 UNNAMED CANE DRAIN 86 BARTLETTS RD 3 TIMBER REPLACEMENT 8 22000 $176,000

0 $176,000

TOTAL - 2012/13 $776,000 $0 $776,000

2013/14 YEAR

BN2670 KINGSCLIFF TRAFFIC BRIDGE -

Completion CUDGEN CREEK 1258 SUTHERLAND ST 2 TIMBER REPLACEMENT 40 30000 $1,400,000

0 $1,400,000

TOTAL - 2013/14 $1,400,000 $0 $1,400,000

2014/15 YEAR

BN145 UNNAMED CANE DRAIN 86 BARTLETTS RD 3 TIMBER REPLACEMENT 10 22000 $220,000

0 $220,000

BN47 ANTHONYS BRIDGE DUNBIBLE CREEK 1864 MISTRAL RD 3 DECK REPLACEMENT 44 2500 $110,000

0 $110,000

BN32 SHACKLES BRIDGE BURRINGBAR CREEK 1365 UPPER BURRINGBAR RD 1 TIMBER REPLACEMENT 12 22000 $264,000

0 $264,000

TOTAL - 2014/15 $594,000 $0 $594,000

2015/16 YEAR

BN28 PURLOS BRIDGE UNNAMED 923 OPHIR GLEN RD 1 TIMBER REPLACEMENT 12 22000 $264,000

BN4 UNNAMED UNNAMED 829 MINNOWS RD 1 TIMBER REPLACEMENT 8 22000 $176,000

BN51 UNNAMED (COMMENCEMENT) TWEED RIVER 197 BYRRILL CREEK RD 1 TIMBER REPLACEMENT 46 15000 $690,000

BN51 UNNAMED (COMPLETION) TWEED RIVER 197 BYRRILL CREEK RD 1 TIMBER REPLACEMENT 46 7000 $322,000

BN44 UNNAMED UNNAMED 1112 RICHARDS DEVIATION 1 TIMBER REPLACEMENT 6 22000 $132,000

TOTAL - 2015/16 $454,000