TWEED SHIRE COUNCIL
NOTE - ANNUAL LOAN ALLOCATION $750,000
BRIDGE No. BRIDGE NAME WATERWAY NAME ROAD No. ROAD NAME SEGMENT
No. WORK TYPE LENGTH (M) ESTIMATE
RATE ( $ )
ESTIMATED COST ( $ )
GRANT FUNDING
NET COST TO COUNCIL
2008/09 YEAR
BN2432 O'BRIENS BRIDGE - Purchase of
planks TWEED RIVER MR142 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $205,000 $100,000 $105,000
BN2671
POTTSVILLE BRIDGE RAILING MOOBALL CRK 2184 TWEED COAST RD 10 REPLACE RAILING 88 $81,000 $0 $81,000
BN2670 KINGSCLIFF PEDESTRIAN
BRIDGE CUDGEN CREEK 1258 SUTHERLAND ST 2 NEW PEDESTRIAN BRIDGE 40 $150,000 $0 $150,000
BN2437 PERCH CREEK PERCH CREEK MR142 KYOGLE RD 180 TIMBER REPLACEMENT (RTA 50%) 14 $955,000 $335,000 $620,000
BN162 GIDDYS BRIDGE BILAMBIL CREEK 1371 URLIUP RD 5 TIMBER REPLACEMENT 34 $700,000 $0 $700,000
TOTAL - 2008/09 $2,091,000 $435,000 $1,656,000
AVAILABLE FUNDS = $1,570,506 SHORTFALL FROM TVRS = $85,494 2009/10 YEAR
BN2432 O'BRIENS BRIDGE -
Construction TWEED RIVER MR142 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $445,000 $225,000 $220,000
BN2435 SNAKE CREEK BRIDGE SNAKE CREEK MR142 KYOGLE RD 100 TIMBER REPLACEMENT (RTA 50%) 20 $440,000 $220,000 $220,000
BN2433 TWIN BRIDGE - Commencement TWEED RIVER MR143 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $600,000 $450,000 $150,000
BN2434 BREWER-CHARLES BRIDGE TWEED RIVER MR144 KYOGLE RD 70 TIMBER REPLACEMENT (RTA 50%) 10 $320,000 $160,000 $160,000
TOTAL - 2009/10 $1,805,000 $1,055,000 $750,000
2010/11 YEAR
BN40 CHARLTONS BRIDGE -
Commencement CUDGERA CREEK 371 CUDGERA CREEK RD 2 TIMBER REPLACEMENT 24 $450,000
0 $450,000
BN2433 TWIN BRIDGE - Completion TWEED RIVER MR143 KYOGLE RD 50 TIMBER REPLACEMENT (RTA 50%) 30 $300,000 $0 $300,000
TOTAL - 2010/11 $750,000 $750,000
2011/12 YEAR
2008/2009 5 YEAR ROLLING INFRASTRUCTURE PROGRAM - BRIDGES
1. BRIDGE CONSTRUCTION
BN48 RICHARDS BRIDGE DUNBIBLE CREEK 1242 STOKERS RD 13 TIMBER REPLACEMENT 25 22000 $550,000
0 $550,000
BN40 CHARLTONS BRIDGE CUDGERA CREEK 371 CUDGERA CREEK RD 2 TIMBER REPLACEMENT 24 $200,000
0 $200,000
TOTAL - 2011/12 $750,000 $0 $750,000
2012/13 YEAR
BN2670 KINGSCLIFF TRAFFIC BRIDGE -
Commencement CUDGEN CREEK 1258 SUTHERLAND ST 2 TIMBER REPLACEMENT 40 30000 $600,000
0 $600,000
BN144 UNNAMED CANE DRAIN 86 BARTLETTS RD 3 TIMBER REPLACEMENT 8 22000 $176,000
0 $176,000
TOTAL - 2012/13 $776,000 $0 $776,000
2013/14 YEAR
BN2670 KINGSCLIFF TRAFFIC BRIDGE -
Completion CUDGEN CREEK 1258 SUTHERLAND ST 2 TIMBER REPLACEMENT 40 30000 $1,400,000
0 $1,400,000
TOTAL - 2013/14 $1,400,000 $0 $1,400,000
2014/15 YEAR
BN145 UNNAMED CANE DRAIN 86 BARTLETTS RD 3 TIMBER REPLACEMENT 10 22000 $220,000
0 $220,000
BN47 ANTHONYS BRIDGE DUNBIBLE CREEK 1864 MISTRAL RD 3 DECK REPLACEMENT 44 2500 $110,000
0 $110,000
BN32 SHACKLES BRIDGE BURRINGBAR CREEK 1365 UPPER BURRINGBAR RD 1 TIMBER REPLACEMENT 12 22000 $264,000
0 $264,000
TOTAL - 2014/15 $594,000 $0 $594,000
2015/16 YEAR
BN28 PURLOS BRIDGE UNNAMED 923 OPHIR GLEN RD 1 TIMBER REPLACEMENT 12 22000 $264,000
BN4 UNNAMED UNNAMED 829 MINNOWS RD 1 TIMBER REPLACEMENT 8 22000 $176,000
BN51 UNNAMED (COMMENCEMENT) TWEED RIVER 197 BYRRILL CREEK RD 1 TIMBER REPLACEMENT 46 15000 $690,000
BN51 UNNAMED (COMPLETION) TWEED RIVER 197 BYRRILL CREEK RD 1 TIMBER REPLACEMENT 46 7000 $322,000
BN44 UNNAMED UNNAMED 1112 RICHARDS DEVIATION 1 TIMBER REPLACEMENT 6 22000 $132,000
TOTAL - 2015/16 $454,000