Eathworks Embankment hold point and checklist– VERSION 1 DRAFT

EARTHWORKS EMBANKMENT Hold Point and Checklist

Inspection & Testing Plan (Checklist)

This document is to be completed in conjunction with the Planning Scheme Policy – Operational Works Application and Construction Requirements of the Mackay Region Planning Scheme 2017. Please submit your completed request with all the required supporting material to [email protected].

1. Earthworks Embankment: -

Description: ITP No: C12

Project Name: Lot No:

Project No: Date:

TASK WHEN & TEST FREQUENCY ITP

/ WS

HP WP

Resp. CONFORM

(Y/N) Sign & Date Inspections/Control Points

1 Preliminary Inspections and testing

Underlying and adjacent lots conform.

Yes ☐ No ☐ Approval to proceed, construction procedure documented and available for Council’s perusal and review if required.

Lot register updated

Visual 1/Lot ITP HP RPEQ or

S/intendent

Prior to earthworks

commencing WP Council

Site controls surveyed and set out

Visual Site ITP WP RPEQ or

S/intendent Prior to earthworks

commencing WP Council

Services located and potholed, prior to commencing earthworks,

 Relevant service authority have provided permission to relocate services.

 If not relocating, service protected from damage for duration of works

Visual 1/Lot ITP HP RPEQ or

S/intendent

Prior to earthworks

commencing HP Council

Erosion and sediment control measures are in place for this activity and as per approved plan.

Visual 1/Lot ITP HP RPEQ or

S/intendent As per project

environment plan and WP Council

(2)

Eathworks Embankment hold point and checklist– VERSION 1 DRAFT

No works are to commence until ESC measures are

Erosion and Sediment Control Plan

Approval to proceed with embankment earthworks

Visual 1/Lot ITP HP RPEQ or

S/intendent Prior to earthworks

commencing HP Council

2 Construction Batter Slopes

 Embankment slopes shall be as per the approved drawings (C213.27 and C213.28) and within geometric tolerances +/- 300mm as per table C213.3

Imported Material

 Imported material identified for suitable for reuse as embankment material shall be approved by the RPEQ or

S/intendent.

Foundations of Embankment

 After stripping inspection by RPEQ and council to occur prior to

recompacting and trimming (C213.24)

 Embankment floor to be graded and levelled

 Compaction of 200mm below stripped level shall occur as per C213.24, C213.36, and CQC Sub- Annexure B1.

 Unsuitable material identified to be removed and replaced with material as approved by the RPEQ or S/Intendent. Refer to Hold Point Form 23

 Embankment activities carried out to plans and drawings.

Visual and Survey 1/Lot ITP WP

RPEQ or S/intendent

and Council

Visual and Test 1/Lot ITP WP

RPEQ or S/intendent

and Council

Visual and test 1/Lot ITP HP

RPEQ or S/intendent

and Council

(3)

Eathworks Embankment hold point and checklist– VERSION 1 DRAFT

Visual and test 1/Lot ITP HP

RPEQ or S/intendent

and Council

3 Post Construction All excavated unsuitable material disposed of as approved by RPEQ and/or Environmental Plan.

Visual 1/lot ITP HP RPEQ or

S/intendent As per approved

plans and

Environmental Plan

HP Council

Works Complete &

Conforms, inspection and reports submitted, and all Non Conformance Reports have been reviewed, outcomes approved by Council

Approval to proceed (Incl.

Test Results if appl. And survey results) with subgrade preparation..

Prior to Conformance Reported being endorsed

1/lot ITP HP RPEQ or

S/intendent

Visual HP Council

TASK WHEN & TEST FREQUEN

CY

WS / REPORT

WP HP Test Surv ey

Resp. CONFORM (Y/N) Sign & Date

Test Plan

1 Geometrics Floor levels prior to commencement of embankment activities

Prior to

commencement of embankment activities

1/Lot Survey

Sheet

Test Tester

Survey As per C213

Sub-Annexure

HP RPEQ or

S/intende nt

(4)

Eathworks Embankment hold point and checklist– VERSION 1 DRAFT

Batter slopes during and after embankment filling

B1

2 CBR test Material quality:

Prior to Subgrade activity approval commencing

1/Lot NATA Test Tester

Test AS1289.6.1.1 As per C213 Sub-

Annexure B1

HP RPEQ or

S/intende nt 3 Compaction and Moisture

Embankment floor

Prior to filling activities commencing.

Per Lot NATA Test Tester

Test

AS 1289.5.1.1, AS 1289.5.4.1, AS 1289.5.7.1

As per C213 Sub-

Annexure B1

HP RPEQ or

S/intende nt

2 . Process Checking Authority:

Resp. - Responsibility

Hold Point – Superintendent’s Representative (allow one day for response)

Witness Point – Superintendent’s Representative (one days’ notice required prior to inspection) Test – Designated authority to carry out compliance to specification

Survey - Designated authority to carry out compliance to specification

Conscientiously believing the above statements to be true and correct, signed on behalf of:

Name of Certifier:

RPEQ / AILA No:

Signature: Date: