• Tidak ada hasil yang ditemukan

Pavement Management Services - IPWEAQ e-resources

N/A
N/A
Protected

Academic year: 2023

Membagikan "Pavement Management Services - IPWEAQ e-resources"

Copied!
11
0
0

Teks penuh

(1)

Pavement Management

Services

Pavement Testing & Consultancy Est 1981

Subgrade Lime Stabilisation

A Pragmatic Investigation into

Pavement Design, Field Performance

& Construction Quality Control.

(2)

Presentation Rundown

Introduction/Background

Stabilisation

What is it?

Design

How do we do it?

Investigation

How we observed?

Results - What did we learn?

Conclusions

For The Future…

Wirtgen-Group.com.au

(3)

Introduction/Background

2019 ICC commission the Rehabilitation design of Briggs Road, Ipswich (430m).

Industrial Collector Road Servicing Surrounding Industry and Sports Precinct.

Complete Urban Awarded the Contract &

PMS Subcontracted for Pavement Design.

Geotechnical Investigation & Lab Testing of pavement materials provided by council.

The Project

(4)

The Pavement

Pavement Failures, Rutting, Cracking, Extensive Patching, No Kerb & Channel or Pedestrian Facilities.

Subgrade:

Reasonable CBR

Reasonable DCP with Indication of Low strength

High/Very High Expansive Nature

High Moisture and In a Plastic State

Design for Low CBR and Highly Expansive

Existing Pavement Variable

Low Quality Base

Introduction/Background

(5)

Stabilisation

What is it?

A Means of

Strengthening

&

Modify

Pavement Materials Properties.

• The simple act of Working or Kneading the Materials e.g. Compaction .

• Mechanical – Mixing Aggregates to Modify Grading Structure & Particle Interaction.

• Additives–

• Cement, Cement Blends

• Bituminous

• Lime

• Proprietary Products

• Plant orInsituMixed

(6)

Design

How Do We Do It?

(7)

Design

How Do We Do It?

Design Requirement Austroads method A Austroads method B DTMR Method Lime Content To Satisfy Lime Demand and

Achieve Target UCS

To Satisfy Lime Demand and Achieve Design CBR

To Satisfy Lime Demand and Achieve Target UCS Target Lab Strength UCS >1.0 - 2MPa (28 Day) CBR Satisfy Design CBR UCS 1.5MPa (28 Day)

Layer Mechanistic

Design Not Specific Modulus Subgrade

Dependent

Assigned vertical modulus at top of layer

Max Strength Not Specific 150MPa / 15% CBR 200MPa

Nominal Thickness Not Specific 200 - 300mm 250mm - 300mm (300mm

preferable)

Austroads calculates the maximum vertical modulus based on the subgrade support given by:

Method B and TMR both Sublayer into equi-thick layers

TMR Adopt a Nominal 200MPa

Mechanistic Design Parameters

(8)

Investigation

How We Observed?

• PrimarilyFWDand Secondary DCPtesting for Comparison

• FWD Conducted at 5m Intervals staggered– DCP Every 10m

• Backcalculated & Used for Construction QA– Provisions for Deficiencies

• Tested Various Stages of Construction and Over Time*

• Included an Assessment of Different Amelioration Periods (ref paper)

X

(9)

Results

What Did we learn?

Layer modulus increased by factors between 2.8 and 4.1, after 48 hrsof Stabilisation (lowest 10thpercentile results)

The Austroads sublayer methodology was confirmed appropriate

*

The DTMR modulus (200MPa_) was readily Achievable, even with the Austorads Mix Design.

An unexplained reduction in modulus was noted on day 14

The removal of a 12hr Amelioration Period had Little Effect (54MPa) The FWD results of the natural subgrade correlated Very Well with theCBRResults and was Effective as a Quality Control Measure.

DCP Results Were Highly Variable

(10)

Conclusion

For the Future

Austroads Design Modulus is Applicable (when using the Austroads Mix Design)

- The Average Can be Expected to be Higher (Safety Factor, Inconsistencies with Insitu Mixing) Caution using the CBR as an Indicator of Strength/Performance for Mix Design

- Subgrade50MPa(tested) = 200MPa (cap to 150MPa) therefore,

a CBR of15%would be required, results were90%at mix design phase - A CBR 6 times that of the design,to achievethe designmodulus

CBR x 10Correlation isInvalidfor Lime Stabilised Subgrades (As Is Granular Materials) AssestheUCSas well as CBR for AustroadsMethod B

Ameliorationperiod may be relievedfor Method B

(11)

Trent McDonald

tmcdonald@pavement.com.au Ph: (07) 5357 9841

M: (0403) 240 725

THANK YOU

Further Investigations? Wed like to hear from you

• Very Poor Subgrades (CBR <2%)

• Hybrid Stabilisation - Different Blends

• Geogrid Vs. Stabilisation Vs. Replacement

• Foamed Bitumen

• Constriction QA

• Performance Monitoring

Referensi

Dokumen terkait

The method used is to design a dryer model using temperature control with the PID controller method to obtain good drying performance because it can achieve and be

1 2008 survey of WA agricultural lime sources Summary As a service to WA wheatbelt farmers, to assist with cost- effective management of soil acidity, a survey of agricultural lime