Decision of the Hearing Commissioners
Attendances
1 Summary
2 Procedural matters
3 The proposed activities
•
•
3.1 Description of site
3.2 Relevant rules and activity status
RM200638 Discharge biosolids to land
RM200639 Discharge contaminants from biosolid application (mainly odour) to air
RM200640 Land use consent to use and operate Biosolids Acceptance Facility and activities associated with biosolid application in the Rural 2 and Conservation zones
RM200641 Discharge of stormwater and washwater to land from the Biosolids Acceptance Facility
4 Notification and submissions
5 Relevant statutory provisions considered
6 Summary of evidence heard
6.1 The Applicant
6.2 Submitters
ā ā
ā u
ā
6.3 Reporting Officer
6.4 Applicant’s right of reply
7 Principal issues in contention
8 Main findings on the principal issues in contention
8.1 Effects on cultural values and relationships
Findings
9 Decision
10 Reasons for the decision
10.1 Effects on the environment
10.2 Positive effects
10.3 Relevant planning provisions
10.4 Other matters
10.5 Sections 105 and 107
10.6 Part 2 of the Act