OPTIMASI PENJADWALAN DAN RUTE DALAM STRATEGI DISTRIBUSI PUPUK GUNA MENGHEMAT TOTAL BIAYA TRANSPORTASI (Studi Kasus pada PT. Himikarta Malang)

N/A
N/A
Protected

Academic year: 2017

Membagikan "OPTIMASI PENJADWALAN DAN RUTE DALAM STRATEGI DISTRIBUSI PUPUK GUNA MENGHEMAT TOTAL BIAYA TRANSPORTASI (Studi Kasus pada PT. Himikarta Malang)"

Copied!
2
0
0

Teks penuh

(1)

OPTIMASI PENJADWALAN DAN RUTE DALAM STRATEGI DISTRIBUSI

PUPUK GUNA MENGHEMAT TOTAL BIAYA TRANSPORTASI (Studi

Kasus pada PT. Himikarta Malang)

Oleh: ERNI WIJAYANTI (05540039 )

Industrial Engineering

Dibuat: 2009-10-16 , dengan 8 file(s).

Keywords: Optimasi, Periodic Vehicle Routing Problem, Biaya Transportasi

ABSTRAKSI

PT Himikarta merupakan perusahaan distribusi pupuk didaerah Malang. Selama ini dalam proses pendistribusian perusahaan kurang memperhatikan jadwal dan rute, dari segi jadwal sering terjadi keterlambatan pengiriman karena waktu perjalanan dan pelayanan yang cukup lama,

sedangkan dari sisi rute pembagian rute untuk masing – masing kendaraan juga tidak

memperhatikan jarak antar kios sehingga jarak yang ditempuh menjadi jauh dan total durasi waktu satu kali perjalanan cukup lama yang berdampak pada tingginya biaya transportasi.Hal ini, yang menyebabkan terjadinya keterlambatan pengiriman dan peningkatan biaya transportasi. Tujuan utama dari penelitian ini adalah mengurangi keterlambatan dalam pendistribusian pupuk. Integrasi permasalahan penjadwalan dan rute inilah yang akhirnya dikategorikan dalam konsep Periodic Vehicle Routing Problem (PVRP).

Penerapan PVRP dilakukan dengan menentukan kuantitas pengiriman, waktu pengiriman, waktu pelayanan dan biaya transportasi dari gudang ke kios dan antar kios selanjutnya dimasukkan ke dalam model matematis dan pencarian solusi menggunkan software LINGO.

Hasil pencarian solusi menghasilkan jadwal, rute dan total biaya. Jadwal kunjungan setelah menggunkan metode PVRP, untuk Malang kota dan Pakisaji jadwal kunjungan dilakukan 2 kali dalam seminggu pada kombinasi hari senin, kamis dan selasa,jumat, untuk Pujon kunjungan dilakukan 3 kali dalam seminggu pada kombinasi senin, rabu, jumat dan selasa, kamis, sabtu. Sedangkan untuk Batu, Bumiaji, dan Junrejo jadwal pengiriman dilakukan tiap hari.

Pengurangan waktu keterlambatan sebesar 21.85 jam/ minggu untuk semua kendaraan yang ada, sedangkan penghematan total biaya transportasi sebesar 10.05 %.

ABSTRAC

PT Himikarta is a fertilizer distribution company in Malang. Until today, the distribution process of this company less gives attention on scheduling and route, from the schedule side, there is often any delivery delay because travelling time and service time that needs longer time. While, from route, its division for each transportation also do not pay attention on space between retailers so that the distance they take to be far and total of duration time for once travelling is longer and it influence to increased transportation time. It causes the delivery delay and the increment of transportation cost. The main purpose of this study is to decrease the delay in distributing fertilizer. Integrated problems of scheduling and route at last is categorized in the concept of Periodic Vehicle Routing Problem (PVRP).

(2)

after using PVRP method, for Malang downtown and Pakisaji, the schedule of visitation is conducted twice a week on the combination of Monday, Thursday and on Tuesday and Friday. For Pujon, there should be three times a week of visitation schedule; Monday, Wednesday, Friday and Tuesday, Thursday, Saturday. While for Batu, Bumiaji, and Junrejo, the delivery schedule is conducted every day. The reduction of time delay is 21.85 hours/week for all available transportation, while saving of total transportation cost is

Referensi

Dokumen terkait

Peraturan Pemerintah Nomor 3 Tahun 2007 tentang Pedoman Laporan Penyelenggaraan Pemerintahan Daerah Kepada Pemerintah, Laporan Keterangan Pertanggungjawaban Kepala Daerah

sesuai dengan waktu yang telah ditetapkan karena dengan ketepatan produksi yang baik akan menun- jang kelancaran produksi perusahaan, sehingga dapat memaksimalkan laba

Berdasarkan hasil pengamatan sementara terdapat permasalahan yang dihadapi dalam proses perencanaan pembangunan di Kabupaten Halmahera Timur antara lain, perencanaan

Berupa evaluasi awal atau desk evaluation, kemudian evaluasi usulan penelitian dilakukan oleh 2 (dua) reviewer untuk setiap judul penelitian. Untuk penelitian eksternal, seleksi

Berdasarkan analisis masalah di atas, maka solusi yang dapat diusulkan adalah sebuah perangkat lunak pengembangan sistem klasifikasi stadium malaria Plasmodium

Untuk meningkatkan kepuasan pelanggan, perusahaan jasa dapat mengembangkan augmented service terhadap core service-nya, misalnya dengan merancang garansi tertentu atau