OVERVIEW
Objective
¾
To appraise investment projects where the outcome is not certain.RISK AND UNCERTAINTY
STATISTICAL MEASURES SENSITIVITY
ANALYSIS
¾ Definition ¾ Method ¾ Advantages ¾ Limitations
SIMULATION
¾ Use ¾ Stages ¾ Advantages ¾ Limitations
¾ Expected values ¾ Standard deviation ¾ Definitions
¾ Sources of risk REDUCTION OF
1
RISK AND UNCERTAINTY
1.1
Definition
1.1.1
Risk
A condition in which several possible outcomes exist, the probabilities of which can be quantified from historical data.
1.1.2
Uncertainty
The inability to predict possible outcomes due to a lack of historical data being available for quantification.
1.2
Sources of risk in projects
The major risks to the success of an investment project will be the variability of the future cash flows. This could be the variability of income streams or the variability of cost cash flows or a combination of both.
2
SENSITIVITY ANALYSIS
Definition
The analysis of changes made to significant variables in order to determine their effect on a planned course of action.
The cash flows, probabilities, or cost of capital are varied until the decision changes, i.e. the NPV becomes zero. This will show the sensitivity of the decision to changes in those elements.
Therefore the estimation of IRR is an example if sensitivity analysis, in this case on the cost of capital.
Sensitivity analysis can also be referred to as “what if?” analysis.
2.1
Method
Step 1 Calculate the NPV of the project on the basis of best estimates. Step 2 For each element of the decision (cash flows, cost of capital)
calculate the change necessary for the NPV to fall to zero. The sensitivity can be expressed as a % change.
Sensitivity = 100% considered
flow of PV
NPV ×
Commentary
For change in sales volume, the factor to consider is contribution. This may involve combining a number of flows.
Example 1
Williams has just set up a company, JPR Manufacturing Ltd, and estimates its cost of capital to be 15%. His first project involves investing in $150,000 of equipment with a life of 15 years and a final scrap value of $15,000.
The equipment will be used to produce 15,000 deluxe pairs of rugby boots per annum generating a contribution of $2.75 per pair. He estimates that annual fixed costs will be $15,000 per annum.
Required:
(a) Determine, on the basis of the above figures, whether the project is worthwhile.
(b) Calculate what percentage changes in the factors would cause your decision in (a) change.
(i) initial investment (ii) volume
Solution
(b) The sensitivity of the decision in (a) can be calculated by expressing the NPV as a percentage of the various factors.
(i) Initial investment
Sensitivity = (ii) Volume
The PV figure of contribution is directly proportional to volume. Sensitivity =
(iii) Fixed costs
Sensitivity =
(iv) Scrap value
Sensitivity =
(v) Sensitivity to cost of capital
This can be found by calculating the project’s IRR:
Year Cash flow factor Present value
IRR = r
2.2
Advantages of sensitivity analysis
9
It gives an idea of how sensitive the project is to changes in any of the original estimates.9
It directs management attention to checking the quality of data for the most sensitive variables.9
It identifies the Critical Success Factors for the project and directs project management.9
It can be easily adapted for use in spreadsheet packages.2.3
Limitations
8
Although it can be adapted to deal with multi-variable changes, sensitivity is normally only used to examine what happens when one variable changes and others remain constant.8
Assumes data for all other variables is accurate.8
Without a computer it can be time-consuming.8
Probability of changes is not considered.3
SIMULATION
3.1
Use of simulation
Simulation is a technique which allows more than one variable to change at the same time. One example of simulation is the “Monte Carlo” method. Calculations will not be required in the exam, an awareness of the stages is sufficient.
3.2
Stages in a Monte Carlo simulation
(1) Specify the major variables.
(2) Specify the relationship between the variables.
(3) Attach probability distributions to each variable and assign random numbers to reflect the distribution.
(5) Record the outcome of each simulation.
(6) Repeat simulation many times to obtain a probability distribution of the likely outcomes.
3.3
Advantages
9
It gives more information about the possible outcomes and their relative probabilities.9
It is useful for problems which cannot be solved analytically.3.4
Limitations
8
It is not a technique for making a decision, only for obtaining more information about the possible outcomes.8
It can be very time-consuming without a computer.8
It could prove expensive in designing and running the simulation, even on a computer.8
Simulations are only as good as the probabilities, assumptions and estimates made.4
STATISTICAL MEASURES
4.1
Expected values
The quantitative result of weighting uncertain events by the probability of their occurrence.
4.1.1
Calculation
Expected value = weighted arithmetic mean of possible outcomes. =
∑
x p(x)Where x = value of an outcome, p(x) = probability of that outcome , ∑ = sum
Example 2
State of market Diminishing Static Expanding
Probability 0.4 0.3 0.3
Project 1 100 200 1,000
Project 2 0 500 600
Project 3 180 190 200
Figures represent the net present value of projects under each market state in $m.
Required:
Solution
Project 1 Expected value = Project 2 Expected value = Project 3 Expected value =
The best project based on expected values is
4.1.2
Advantages
9
It reduces the information to one number for each choice.9
The idea of an average is readily understood.4.1.3
Limitations
8
The probabilities of the different possible outcomes may be difficult to estimate.8
The average may not correspond to any of the possible outcomes.8
Unless the same decision has to be made many times, the average will not be achieved; it is therefore not a valid way of making a decision in “one-off” situations.8
The average gives no indication of the spread of possible results, i.e. it ignores risk.4.2
Standard deviation
A measure of variation of numerical values from a mean value.
A measure of spread i.e. it indicates the likely level of variation from an expected value. Exam questions are more likely to provide standard deviation for interpretation, rather than to require its calculation.
4.2.1
Calculation
σ = standard deviation =
∑
(x−x)2 prob( x)x = each observation
x = mean of observations
Example 3
Using the information from Example 2, calculate the standard deviation for each project.
Solution
Project 1
Project 2
Project 3
4.2.2
Advantages
9
It gives an idea of the spread of possible results around the average.9
It can be used in further mathematical analysis, in particularly using Normal Distributions.”4.2.3
Limitations
8
The calculation of standard deviation can be difficult.8
The exact meaning is not widely understood by non-financial managers.5
REDUCTION OF RISK
Ways of reducing project risk:
¾
Setting a maximum payback period.¾
Use of a higher discount rate − therefore reducing the influence of distant cash flows.¾
Select projects with a combination of low standard deviation and acceptable averagepredicted outcome.
Key points
³
Exam calculations on project risk are likely to focus on sensitivity analysis i.e. finding the value of key variables at which NPV = 0.³
Adjusting the discount rate to reflect a project’s risk is dealt with later in the session on the Capital Asset Pricing Model (CAPM).FOCUS
You should now be able to:
¾
distinguish between risk and uncertainty;¾
evaluate the sensitivity of project NPV to changes in key variables;¾
explain the role of simulation in generating a probability distribution for the NPV of a project;EXAMPLE SOLUTIONS
Solution 1 — Sensitivity analysis
(a) Time Cash flow DF @ 15% PV The project is worthwhile as NPV is positive
(b) The sensitivity of the decision in (a) can be calculated by expressing the NPV as a percentage of the various factors.
(i) Initial investment
If the initial investment rises by more than $5,329, the project would be rejected.
(iv) Scrap value
From the above calculations the decision to accept the project is extremely sensitive to most of the figures given in the question. The project will be rejected in the event of small rises in the initial
investment or fixed cost figures or falls in contribution or volume. It could be seen, for instance, that the project just breaks even if fixed costs become $15,000 × 1.06 = $15,900.
The scrap value is relatively irrelevant to the investment decision – we would have to pay to have the plant taken away before the project would be rejected.
(v) Sensitivity to cost of capital
This can be found by calculating the project’s IRR, which is probably only marginally above 15%.
Year Cash flow 16% factor Present value
If the cost of capital rises from 15% to more than 15.7% the project would be rejected.
Solution 2 — Expected values
Solution 3 — Standard deviation
Project 1 (100−400)2×0.4+(200−400)2×0.3+(1,000−400)2×3 = 156,000 = 395
Project 2 (0−330)2×0.4+(500−330)2×0.3+(600−330)2×0.2 = 74,100 = 272