• Tidak ada hasil yang ditemukan

ACCA Paper F9 Financial Management Study Materials F9FM Session07 d08

N/A
N/A
Protected

Academic year: 2019

Membagikan "ACCA Paper F9 Financial Management Study Materials F9FM Session07 d08"

Copied!
12
0
0

Teks penuh

(1)

OVERVIEW

Objective

¾

To appraise investment projects where the outcome is not certain.

RISK AND UNCERTAINTY

STATISTICAL MEASURES SENSITIVITY

ANALYSIS

¾ Definition ¾ Method ¾ Advantages ¾ Limitations

SIMULATION

¾ Use ¾ Stages ¾ Advantages ¾ Limitations

¾ Expected values ¾ Standard deviation ¾ Definitions

¾ Sources of risk REDUCTION OF

(2)

1

RISK AND UNCERTAINTY

1.1

Definition

1.1.1

Risk

A condition in which several possible outcomes exist, the probabilities of which can be quantified from historical data.

1.1.2

Uncertainty

The inability to predict possible outcomes due to a lack of historical data being available for quantification.

1.2

Sources of risk in projects

The major risks to the success of an investment project will be the variability of the future cash flows. This could be the variability of income streams or the variability of cost cash flows or a combination of both.

2

SENSITIVITY ANALYSIS

Definition

The analysis of changes made to significant variables in order to determine their effect on a planned course of action.

The cash flows, probabilities, or cost of capital are varied until the decision changes, i.e. the NPV becomes zero. This will show the sensitivity of the decision to changes in those elements.

Therefore the estimation of IRR is an example if sensitivity analysis, in this case on the cost of capital.

Sensitivity analysis can also be referred to as “what if?” analysis.

2.1

Method

Step 1 Calculate the NPV of the project on the basis of best estimates. Step 2 For each element of the decision (cash flows, cost of capital)

calculate the change necessary for the NPV to fall to zero. The sensitivity can be expressed as a % change.

(3)

Sensitivity = 100% considered

flow of PV

NPV ×

Commentary

For change in sales volume, the factor to consider is contribution. This may involve combining a number of flows.

Example 1

Williams has just set up a company, JPR Manufacturing Ltd, and estimates its cost of capital to be 15%. His first project involves investing in $150,000 of equipment with a life of 15 years and a final scrap value of $15,000.

The equipment will be used to produce 15,000 deluxe pairs of rugby boots per annum generating a contribution of $2.75 per pair. He estimates that annual fixed costs will be $15,000 per annum.

Required:

(a) Determine, on the basis of the above figures, whether the project is worthwhile.

(b) Calculate what percentage changes in the factors would cause your decision in (a) change.

(i) initial investment (ii) volume

(4)

Solution

(b) The sensitivity of the decision in (a) can be calculated by expressing the NPV as a percentage of the various factors.

(i) Initial investment

Sensitivity = (ii) Volume

The PV figure of contribution is directly proportional to volume. Sensitivity =

(iii) Fixed costs

Sensitivity =

(iv) Scrap value

Sensitivity =

(v) Sensitivity to cost of capital

This can be found by calculating the project’s IRR:

Year Cash flow factor Present value

(5)

IRR = r

2.2

Advantages of sensitivity analysis

9

It gives an idea of how sensitive the project is to changes in any of the original estimates.

9

It directs management attention to checking the quality of data for the most sensitive variables.

9

It identifies the Critical Success Factors for the project and directs project management.

9

It can be easily adapted for use in spreadsheet packages.

2.3

Limitations

8

Although it can be adapted to deal with multi-variable changes, sensitivity is normally only used to examine what happens when one variable changes and others remain constant.

8

Assumes data for all other variables is accurate.

8

Without a computer it can be time-consuming.

8

Probability of changes is not considered.

3

SIMULATION

3.1

Use of simulation

Simulation is a technique which allows more than one variable to change at the same time. One example of simulation is the “Monte Carlo” method. Calculations will not be required in the exam, an awareness of the stages is sufficient.

3.2

Stages in a Monte Carlo simulation

(1) Specify the major variables.

(2) Specify the relationship between the variables.

(3) Attach probability distributions to each variable and assign random numbers to reflect the distribution.

(6)

(5) Record the outcome of each simulation.

(6) Repeat simulation many times to obtain a probability distribution of the likely outcomes.

3.3

Advantages

9

It gives more information about the possible outcomes and their relative probabilities.

9

It is useful for problems which cannot be solved analytically.

3.4

Limitations

8

It is not a technique for making a decision, only for obtaining more information about the possible outcomes.

8

It can be very time-consuming without a computer.

8

It could prove expensive in designing and running the simulation, even on a computer.

8

Simulations are only as good as the probabilities, assumptions and estimates made.

4

STATISTICAL MEASURES

4.1

Expected values

The quantitative result of weighting uncertain events by the probability of their occurrence.

4.1.1

Calculation

Expected value = weighted arithmetic mean of possible outcomes. =

x p(x)

Where x = value of an outcome, p(x) = probability of that outcome , ∑ = sum

Example 2

State of market Diminishing Static Expanding

Probability 0.4 0.3 0.3

Project 1 100 200 1,000

Project 2 0 500 600

Project 3 180 190 200

Figures represent the net present value of projects under each market state in $m.

Required:

(7)

Solution

Project 1 Expected value = Project 2 Expected value = Project 3 Expected value =

The best project based on expected values is

4.1.2

Advantages

9

It reduces the information to one number for each choice.

9

The idea of an average is readily understood.

4.1.3

Limitations

8

The probabilities of the different possible outcomes may be difficult to estimate.

8

The average may not correspond to any of the possible outcomes.

8

Unless the same decision has to be made many times, the average will not be achieved; it is therefore not a valid way of making a decision in “one-off” situations.

8

The average gives no indication of the spread of possible results, i.e. it ignores risk.

4.2

Standard deviation

A measure of variation of numerical values from a mean value.

A measure of spread i.e. it indicates the likely level of variation from an expected value. Exam questions are more likely to provide standard deviation for interpretation, rather than to require its calculation.

4.2.1

Calculation

σ = standard deviation =

(xx)2 prob( x)

x = each observation

x = mean of observations

(8)

Example 3

Using the information from Example 2, calculate the standard deviation for each project.

Solution

Project 1

Project 2

Project 3

4.2.2

Advantages

9

It gives an idea of the spread of possible results around the average.

9

It can be used in further mathematical analysis, in particularly using Normal Distributions.”

4.2.3

Limitations

8

The calculation of standard deviation can be difficult.

8

The exact meaning is not widely understood by non-financial managers.

5

REDUCTION OF RISK

Ways of reducing project risk:

¾

Setting a maximum payback period.

¾

Use of a higher discount rate − therefore reducing the influence of distant cash flows.

¾

Select projects with a combination of low standard deviation and acceptable average

predicted outcome.

(9)

Key points

³

Exam calculations on project risk are likely to focus on sensitivity analysis i.e. finding the value of key variables at which NPV = 0.

³

Adjusting the discount rate to reflect a project’s risk is dealt with later in the session on the Capital Asset Pricing Model (CAPM).

FOCUS

You should now be able to:

¾

distinguish between risk and uncertainty;

¾

evaluate the sensitivity of project NPV to changes in key variables;

¾

explain the role of simulation in generating a probability distribution for the NPV of a project;

(10)

EXAMPLE SOLUTIONS

Solution 1 — Sensitivity analysis

(a) Time Cash flow DF @ 15% PV The project is worthwhile as NPV is positive

(b) The sensitivity of the decision in (a) can be calculated by expressing the NPV as a percentage of the various factors.

(i) Initial investment

If the initial investment rises by more than $5,329, the project would be rejected.

(11)

(iv) Scrap value

From the above calculations the decision to accept the project is extremely sensitive to most of the figures given in the question. The project will be rejected in the event of small rises in the initial

investment or fixed cost figures or falls in contribution or volume. It could be seen, for instance, that the project just breaks even if fixed costs become $15,000 × 1.06 = $15,900.

The scrap value is relatively irrelevant to the investment decision – we would have to pay to have the plant taken away before the project would be rejected.

(v) Sensitivity to cost of capital

This can be found by calculating the project’s IRR, which is probably only marginally above 15%.

Year Cash flow 16% factor Present value

If the cost of capital rises from 15% to more than 15.7% the project would be rejected.

Solution 2 — Expected values

(12)

Solution 3 — Standard deviation

Project 1 (100400)2×0.4+(200400)2×0.3+(1,000400)2×3 = 156,000 = 395

Project 2 (0330)2×0.4+(500330)2×0.3+(600330)2×0.2 = 74,100 = 272

Referensi

Dokumen terkait

Agama Khonghucu mempunyai sejarah yang berbeda karena sebelum muncul sekte baru sudah muncul filsafat Konfusinisme yang diajarkan oleh Xun Zi (326-233 SM).. Di Tiongkok,

Universitas Indonesia terdekat.” Akan tetapi, meskipun Al-Qur’an telah menetapkan dengan jelas bagian masing-masing ahli waris atas harta warisan pewaris, namun tidak menutup

 Guru menjelaskan secara singkat tentang pancasila sebagai dasar Negara dan sejarah perumusan pancasila 60’ - Kerja sama - Kesungguhan - Disiplin - Uji diri...

Hasil penelitian menunjukan bahwa, (1) ada tiga faktor yang melatar belakangi pembangunan UPTD Sanggar Kegiatan Belajar (SKB) Buleleng, dilihat dari faktor

7.2 Kondisi untuk penyimpanan yang aman, termasuk ketidakcocokan Bahan atau campuran tidak cocok. Pertimbangan untuk nasihat lain •

Sarung tangan yang kuat, tahan bahan kimia yang sesuai dengan standar yang disahkan, harus dipakai setiap saat bila menangani produk kimia, jika penilaian risiko menunjukkan,

Nama pengapalan yang sesuai dengan PBB : Tidak diatur Kelas Bahaya Pengangkutan : Tidak diatur Kelompok Pengemasan (jika tersedia) : Tidak diatur.. LEMBAR DATA KESELAMATAN

Panitia Pengadaan Barang/ Jasa pada Kecamatan Padang Panjang Timur Kota Padang Panjang akan melaksanakan Pelelangan Umum dengan pascakualifikasi untuk paket