• Tidak ada hasil yang ditemukan

RENCANA ANGGARAN BIAYA.xls

N/A
N/A
Protected

Academic year: 2021

Membagikan "RENCANA ANGGARAN BIAYA.xls"

Copied!
87
0
0

Teks penuh

(1)

PROPINSI

: ACEH

KOTA

: LANGSA

TAHUN ANGGARAN

: 2010

PAKET

: SEKTOR AIR BERSIH DAN DRAINASE

PEKERJAAN

: PEMBANGUNAN JARINGAN PIPA TRANSMISI DAN DRAINASE

KOTA LANGSA

A. UPAH

U01 Pekerja Org/ Hari 49,700.00

U02 Mandor Org/ Hari 82,300.00

U03 Tukang Org/ Hari 78,700.00

U04 Kepala Tukang Org/ Hari 94,500.00

U05 Operator Org/ Hari 122,300.00

U06 Pembantu Operator Org/ Hari 75,000.00

U07 Mekanik Org/ Hari 122,300.00

U08 Mekanik Pembantu Org/ Hari 75,000.00

DAFTAR HARGA SATUAN UPAH, BAHAN DAN SEWA ALAT

(2)

PROPINSI

: ACEH

KOTA

: LANGSA

TAHUN ANGGARAN

: 2010

PAKET

: SEKTOR AIR BERSIH DAN DRAINASE

PEKERJAAN

: PEMBANGUNAN JARINGAN PIPA TRANSMISI DAN DRAINASE

KOTA LANGSA

DAFTAR HARGA SATUAN UPAH, BAHAN DAN SEWA ALAT

B. BAHAN

M01 Air Bersih Pengecoran Liter 150.00

M02 Angker Bolt D22+Mur+Ring Bh 42,000.00

M03 Bar Pengaman Unit 1,200,000.00

M04 Baja profil Kg 28,300.00

M05 Bambu Btg 34,100.00

M06 Batu Bata Buah 600.00

M07 Batukali / Batu Belah (Sungai / Gunung) M3 202,800.00

M08 Batu pecah 3 - 5 cm M3 290,950.00

M09 Batu pecah 2 - 3 cm M3 647,600.00

M10 Baut dan Mur Steel 1 1/2" Bh 22,000.00

M11 Baut Picer Ø16 mm Bh 12,000.00

M12 Base Plat 16 mm Bh 170,000.00

M13 Besi beton polos Kg 16,200.00

M14 Besi beton ulir/strip Kg 24,800.00

M15 Cat Tembok Kg 25,900.00

M16 Cat Menie Besi Kg 22,200.00

M17 Filter Bh 400,000.00

M18 Formite/penjaga jarak bekisting/spacer Bh 4,000.00

M19 Ijuk Kg 13,600.00

M20 Kantor Lapangan (Type C) M2

2,220,000.00

M21 Kawat beton Kg 10,500.00

M22 Kawat Bronjong dia. 5 mm Kg 22,800.00

M23 Kawat las Kg 16,000.00

M24 Koral Beton M3 141,100.00

M25 Balok Kayu Klas II M3 3,926,100.00

M26 Kayu Klas III (Borneo) M3 3,553,900.00

M27 Kayu Klas IV (Sengon) untuk Papan Begesting M3 2,948,100.00

M28 Kayu Dolken Ø 8-10 cm (panjang 4 M) Btg 62,500.00

M29 Lempengan Rumput M2 28,100.00 M30 Minyak Bensin Ltr 8,100.00 M31 Minyak cat Ltr 21,700.00 M32 Minyak Solar Ltr 8,100.00 M33 Minyak Tanah Ltr 6,700.00 M34 Minyak Bekisting Ltr 3,800.00 M35 Paku Kayu Kg 11,600.00 M36 Pasir beton/Kerikil M3 141,100.00 M37 Pasir Pasang M3 129,600.00 M38 Pasir urug M3 112,500.00 M39 Paving blok M2 83,700.00 M40 Pelumas / Oli Ltr 36,200.00 M41 Plywood 9 mm Lbr 150,500.00 M42 Pipa PVC Ø 1 12" Btg 71,900.00

M43 Semen Portland (@ 40 Kg) Zak 50,300.00

M44 Tanah Timbun M3 51,700.00

M45 Tanah Timbun Pilihan M3 122,600.00

M46 Plat Baja, t = 5 mm m2 25,700.00

M47 Pintu Air Sorong (B = 0,7 H = 1,0) Lengkap+pemasangan Set 3,000,000.00

M48 Pintu Air Koklep (B = 0,7 H = 1,25) Lengkap+pemasangan Set 4,000,000.00

M49 Pipa GIP ¢ 75 mm M' 96,006.00 M50 Pipa GIP ¢ 100 mm M' 200,946.00 M51 Pipa GIP ¢ 150 mm M' 272,689.50 M52 Pipa GIP ¢ 200 mm M' 344,433.00 M53 Pipa GIP ¢ 250 mm M' 544,978.00 Harga (Rp) Satuan

(3)

PROPINSI

: ACEH

KOTA

: LANGSA

TAHUN ANGGARAN

: 2010

PAKET

: SEKTOR AIR BERSIH DAN DRAINASE

PEKERJAAN

: PEMBANGUNAN JARINGAN PIPA TRANSMISI DAN DRAINASE

KOTA LANGSA

DAFTAR HARGA SATUAN UPAH, BAHAN DAN SEWA ALAT

M54 Air Realease CI Ø 50 mm Bh 1,854,412.00

M55 Air Realease CI Ø 75 mm Bh 1,954,412.00

M56 Air Realease CI Ø 100 mm Bh 3,384,171.00

M57 Air Realease CI Ø 150 mm Bh 4,813,930.00

M58 Air Realease CI Ø 200 mm Bh 7,220,895.00

M59 All Range Bend 45° Bh 459,900.00

M60 Bend CI 22.5° Ø 75 mm Bh 179,100.00 M61 Bend CI 45° Ø 75 mm Bh 199,477.00 M62 Bend CI 90° Ø 75 mm Bh 248,240.00 M63 Bend CI 45° Ø 100 mm Bh 258,373.00 M64 Bend CI 45° Ø 150 mm Bh 442,349.00 M65 Bend CI 90° Ø 100 mm Bh 316,185.00 M66 Bend CI 45° Ø 200 mm Bh 626,325.00 M67 Bend CI 90° Ø 200 mm Bh 708,768.00 M68 Bend CI 45° Ø 250 mm Bh 1,310,750.00 M69 Bend CI 90° Ø 250 mm Bh 1,337,500.00 M70 Blinde Flange Bh 326,500.00 M71 Clamp Ø 100 mm Set 52,034.00 M72 Clamp Ø 150 mm Set 89,276.00 M73 Clamp Ø 200 mm Set 208,098.00

M74 Clamp dia. 200 mm dan Angker Bolt+Mur+Ring Set 250,098.00

M75 Clamp dia. 150 mm dan Angker Bolt+Mur+Ring Set 131,276.00

M76 Clamp dia. 100 mm dan Angker Bolt+Mur+Ring Set 94,034.00

M77 Dop GIP Ø 100 mm Bh 268,796.00 M78 Dop GIP Ø 150 mm Bh 383,994.00 M79 Dop GIP Ø 200 mm Bh 499,192.00 M80 Flange GIP Ø 75 mm Bh 100,000.00 M81 Flange GIP Ø 100 mm Bh 130,000.00 M82 Flange GIP Ø 150 mm Bh 165,000.00 M83 Flange GIP Ø 200 mm Bh 200,000.00

M84 Flange Socket GIP dia. 200 mm Bh 590,392.00

M85 Flange Socket GIP dia. 150 mm Bh 419,400.00

M86 Flange Socket GIP dia. 100 mm Bh 248,408.00

M87 Los Flange GIP dia. 100 mm Bh 56,900.00

M88 Los Flange GIP dia. 150 mm Bh 110,700.00

M89 Los Flange GIP dia. 200 mm Bh 164,500.00

M90 Flexible Joint Ø 150 mm Bh 798,200.00

M91 Flexible Joint Ø 200 mm Bh 798,200.00

M92 Gate Valve CI Ø 100 mm Bh 855,754.00

M93 Gate Valve CI Ø 150 mm Bh 1,702,905.00

M94 Gate Valve CI Ø 200 mm Bh 2,822,393.00

M95 Perangkat Mur, Baut & Ring Flange Ø 100 mm Set 35,450.00

M96 Perangkat Mur, Baut & Ring Flange Ø 150 mm Set 127,600.00

M97 Perangkat Mur, Baut & Ring Flange Ø 200 mm Set 137,500.00

M98 Reducer GIP Ø 100-75 mm Bh 250,352.00

M99 Reducer GIP Ø 150-100 mm Bh 330,737.00

M100 Reducer GIP Ø 200-100 mm Bh 421,791.00

M101 Socket GIP Ø 100 mm Bh 162,822.00

M102 Socket GIP Ø 150 mm Bh 187,450.00

M103 Dop Flange GIP dia. 200 mm Bh 516,000.00

M104 Tee GIP Ø 150-150-150 mm Bh 972,162.00

M105 Tee GIP Ø 200-200-200 mm Bh 1,069,378.00

M106 Tee GIP Ø 200 - 100 - 200 mm Bh 1,069,378.00

M107 Tee GIP Ø 150 - 100 - 150 mm Bh 972,162.00

M108 Tee All Flange CI Ø 150-100-150 mm Bh 612,254.00

M109 Tee All Flange CI Ø 200-100-200 mm Bh 991,890.00

M110 Tee All Flange CI Ø 200-150-200 mm Bh 1,030,410.00

(4)

PROPINSI

: ACEH

KOTA

: LANGSA

TAHUN ANGGARAN

: 2010

PAKET

: SEKTOR AIR BERSIH DAN DRAINASE

PEKERJAAN

: PEMBANGUNAN JARINGAN PIPA TRANSMISI DAN DRAINASE

KOTA LANGSA

DAFTAR HARGA SATUAN UPAH, BAHAN DAN SEWA ALAT

M112 Wall Flange Ø 200 mm Bh 425,000.00 M113 Pipa PVC RRJ S 12.5 ¢ 75 mm M' 41,578.00 M114 Pipa PVC RRJ S 12.5 ¢ 100 mm M' 70,495.00 M115 Pipa PVC RRJ S 12.5 ¢ 150 mm M' 132,932.50 M116 Pipa PVC RRJ S 12.5 ¢ 200 mm M' 195,370.00 M117 Pipa PVC RRJ S 12.5 ¢ 250 mm M' 307,188.00 M118 Bend 11.25° PVC Ø 75 mm Bh 56,528.00 M119 Bend 45° PVC Ø 75 mm Bh 62,528.00 M120 Bend 90° PVC Ø 75 mm Bh 68,507.00 M121 Bend 11.25° PVC Ø 100 mm Bh 93,723.00 M122 Bend 22.5° PVC Ø 100 mm Bh 96,111.00 M123 Bend 45° PVC Ø 100 mm Bh 99,871.00 M124 Bend 90° PVC Ø 100 mm Bh 117,219.00 M125 Bend 11.25° PVC Ø 200 mm Bh 274,733.00 M126 Bend 22.5° PVC Ø 200 mm Bh 290,533.00 M127 Bend 45° PVC Ø 200 mm Bh 335,333.00 M128 Bend 90° PVC Ø 200 mm Bh 390,532.00 M129 Bend 11.25° PVC Ø 250 mm Bh 586,300.00 M130 Bend 22.5° PVC Ø 250 mm Bh 629,200.00 M131 Bend 45° PVC Ø 250 mm Bh 1,015,938.00 M132 Bend 90° PVC Ø 250 mm Bh 1,206,693.00 M133 Dop PVC Ø 75 mm Bh 27,214.00 M134 Dop PVC Ø 100 mm Bh 96,428.00 M135 Dop PVC Ø 150 mm Bh 199,675.00 M136 Dop PVC Ø 200 mm Bh 302,922.00 M137 Flange Socket PVC Ø 75 mm Bh 102,185.00 M138 Flange Socket PVC Ø 100 mm Bh 122,863.00 M139 Flange Socket PVC Ø 150 mm Bh 294,691.50 M140 Flange Socket PVC Ø 200 mm Bh 466,520.00 M141 Reducer PVC Ø 100-75 mm Bh 64,228.00 M142 Reducer PVC Ø 200-75 mm Bh 337,425.00 M143 Reducer PVC Ø 200-100 mm Bh 337,425.00 M144 Socket PVC Ø 75 mm Bh 60,324.00 M145 Socket PVC Ø 100 mm Bh 81,133.00 M146 Socket PVC Ø 200 mm Bh 275,088.00 M147 Tee PVC Ø 100-100-100 mm Bh 339,546.00 M148 Tee PVC Ø 200-100-200 mm Bh 1,800,000.00 M149 Tee PVC Ø 200-200-200 mm Bh 2,160,000.00 M150 Street Box Bh 225,000.00

M151 Water Meter Box Bh 5,000,000.00

M152 Meter Air Ø 300 mm Bh 28,269,400.00

(5)

PROPINSI

: ACEH

KOTA

: LANGSA

TAHUN ANGGARAN

: 2010

PAKET

: SEKTOR AIR BERSIH DAN DRAINASE

PEKERJAAN

: PEMBANGUNAN JARINGAN PIPA TRANSMISI DAN DRAINASE

KOTA LANGSA

DAFTAR HARGA SATUAN UPAH, BAHAN DAN SEWA ALAT

C. SEWA ALAT

A01 Alat Pengetesan Pipa Hk 75,000.00

A02 Jack Hammer Hk 150,000.00

A03 Concrete Mixer dan Vibrator Hk 100,000.00

A04 Stamper Hk 150,000.00

A05 Excavator Jam 343,208.28

A06 Buldozer Jam 547,125.46

A07 Vibro roller Jam 267,913.36

A08 Mesin Las Hk 100,000.00

A09 Alat Bantu Perpipaan (tracker & katrol) Hk 50,000.00

(6)

PEMBANGUNAN TANGGUL SUNGAI PAOH KOTA LANGSA

(7)
(8)

PEMBANGUNAN TANGGUL SUNGAI PAOH KOTA LANGSA

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan EXCAVATOR 80-140 HP A05

2. Tenaga Pw 80.0 HP

3. Kapasitas Cp 0.5 M3

4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam

c. Harga Alat B 770,000,000 Rupiah

5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru

b. Jam Kerja Dalam 1 Tahun W' 2,000 Jam Alat Baru

c. Harga Alat (*) B' 770,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 77,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33438

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 115,862.57 Rupiah

W'

b. Asuransi, dll = 0.002 x B' F 770.00 Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G 116,632.57 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 97,200.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 43,440.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 57,750.00 Rupiah

perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 17,471.43 Rupiah

5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,714.29 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 226,575.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 343,208.28 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 20.00 % / Tahun

2. Upah Operator / Sopir U1 17,471.43 Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 10,714.29 Rp./Jam

4. Bahan Bakar Bensin Mb 8,100.00 Liter

5. Bahan Bakar Solar Ms 8,100.00 Liter

6. Minyak Pelumas Mp 36,200.00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

URAIAN ANALISA ALAT

(9)

PEMBANGUNAN TANGGUL SUNGAI PAOH KOTA LANGSA

A. URAIAN PERALATAN

1. Jenis Peralatan BULLDOZER 100-150 HP A06

2. Tenaga Pw 140.0 HP

3. Kapasitas Cp 1.5 M3

4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam

c. Harga Alat B 1,210,000,000 Rupiah

5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru

b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru

c. Harga Alat (*) B' 1,210,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 121,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.33438

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 182,069.75 Rupiah

W'

b. Asuransi, dll = 0.002 x B' F 0.00 Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G 182,069.75 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 170,100.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 76,020.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 90,750.00 Rupiah

perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 17,471.43 Rupiah

5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,714.29 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 365,055.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 547,125.46 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 20.00 % / Tahun

2. Upah Operator / Sopir U1 17,471.43 Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 10,714.29 Rp./Jam

4. Bahan Bakar Bensin Mb 8,100.00 Liter

5. Bahan Bakar Solar Ms 8,100.00 Liter

6. Minyak Pelumas Mp 36,200.00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

(10)

PEMBANGUNAN TANGGUL SUNGAI PAOH KOTA LANGSA

URAIAN ANALISA ALAT

No. U R A I A N KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. A07

2. Tenaga Pw 75.0 HP

3. Kapasitas Cp 7.0 Ton

4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun

b. Jam Kerja Dalam 1 Tahun W 1,600.0 Jam

c. Harga Alat B 431,200,000 Rupiah

5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat

b. Jam Kerja Dalam 1 Tahun W' 1,280 Jam Sewa Alat

c. Harga Alat (*) B' 287,466,667 Rupiah Sewa Alat

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x B C 43,120,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A' D 0.38629

-(1 + i)^A' - 1 3. Biaya Pasti per Jam :

a. Biaya Pengembalian Modal = ( B' - C ) x D E 73,740.98 Rupiah

W'

b. Asuransi, dll = 0.002 x B' F 449.17 Rupiah

W'

Biaya Pasti per Jam = ( E + F ) G 74,190.15 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x Ms H 91,125.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 40,725.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B' K 33,687.50 Rupiah

perbaikan = W'

4. Operator = ( 1 Orang / Jam ) x U1 L 17,471.43 Rupiah

5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,714.29 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 193,723.21 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 267,913.36 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 20.00 % / Tahun

2. Upah Operator / Sopir U1 17,471.43 Rp./Jam

3. Upah Pembantu Operator / Pmb.Sopir U2 10,714.29 Rp./Jam

4. Bahan Bakar Bensin Mb 8,100.00 Liter

5. Bahan Bakar Solar Ms 8,100.00 Liter

6. Minyak Pelumas Mp 36,200.00 Liter

7. PPN diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
(27)
(28)

5 5 0 770,000,000 E10 4 1 513,333,333 3 2 308,000,000 2 3 154,000,000 1 4 51,333,333 0 5 0 -1 6 0 -2 7 51,333,333 -3 8 154,000,000 -4 9 308,000,000 -5 10 513,333,333 -6 11 770,000,000 -7 12 1,078,000,000 -8 13 1,437,333,333 -9 14 1,848,000,000 15 > 15th ?

Kondisi Alat Alat Baru Nilai B' dari

(29)

5 5 0 1,210,000,000 E04 4 1 806,666,667 3 2 484,000,000 2 3 242,000,000 1 4 80,666,667 0 5 0 -1 6 0 -2 7 80,666,667 -3 8 242,000,000 -4 9 484,000,000 -5 10 806,666,667 -6 11 1,210,000,000 -7 12 1,694,000,000 -8 13 2,258,666,667 -9 14 2,904,000,000 15 > 15th ?

Kondisi Alat Alat Baru Nilai B' dari

(30)

4 5 0 431,200,000 E19 4 1 287,466,667 3 2 172,480,000 2 3 86,240,000 1 4 28,746,667 0 5 0 -1 6 0 -2 7 28,746,667 -3 8 86,240,000 -4 9 172,480,000 -5 10 287,466,667 -6 11 431,200,000 -7 12 603,680,000 -8 13 804,906,667 -9 14 1,034,880,000 15 > 15th ?

Kondisi Alat Sewa Alat Nilai B' dari

(31)
(32)
(33)
(34)
(35)
(36)

1. BULDOZER

Kapasitas bucket = 4.40 m3

Beban = 4.4 x 1.65 = 7.26 ton

Koefisien traksi = 0.7

Reaksi kritis = 0.7 x 7.26 = 5.08 ton

Kecepatan maju = 4.7 km/jam = 78.33 m/menit

Kecepatan mundur = 5.5 km/jam = 91.67 m/menit

Jarak dorong rata-rata = 50.00 m

Waktu maju (Wp) = 0.64 menit

Waktu mundur (Wj) = 0.55 menit

Waktu buang/pindah, dll = 0.30 menit

Total waktu (Ws) = 1.48 menit

Trip perjam = 40.44 trip

Produksi maks. alat = 4.4 x 40.44 = 177.93 m3

Faktor koreksi (Fk)

Efisiensi kerja siang (a) = 0.75

Ketrampilan operator (b) = 0.75

Cuaca cerah (C) = 0.90

Cara kerja (d) = 0.90

Kekerasan tanah (e) = 0.75

Total Fk = a x b x c x d x e = 0.34

Taksiran produksi = 177.93 x 0.34 = 60.80 m3/jam

Dibulatkan 61.00 m3/jam

1 m3 tanah diperlukan faktor alat (buldozer) = 0.0164 jam

1 m2 tanah diperlukan faktor alat (buldozer) = 0.0049 jam = 203.33 m2/jam

1 Ha tanah diperlukan faktor alat (buldozer) = 49.1803 jam

= 0.0203 Ha/jam

Sumber : Hasil Perhitungan

2. EXCAVATOR

Kapasitas bucket = 0.80 m3

Beban = 0.8 x 1.65 = 1.32 ton

Berat excavator = 18.50 ton

Berat total = 19.82 ton

Koefisien traksi = 0.55

Reaksi kritis = 0.55 x 19.82 = 10.90 ton

Kecepatan maju = - km/jam = - m/menit

Kecepatan mundur = - km/jam = - m/menit

Jarak dorong rata-rata = - m

Waktu maju (Wp) = - menit

Waktu mundur (Wj) = - menit

Waktu buang/pindah, dll = 0.62 menit

Total waktu (Ws) = 0.62 menit

Trip perjam = 96.77 trip

Produksi maks. alat = 0.8 x 96.77 = 77.42 m3

Faktor koreksi (Fk)

Efisiensi kerja siang (a) = 0.80

Ketrampilan operator (b) = 0.80

Cuaca cerah (C) = 0.90

Faktor muat (d) = 0.90

Kekerasan tanah (e) =

-Total Fk = a x b x c x d = 0.52

Taksiran produksi = 77.42 x 0.52 = 40.13 m3/jam

Dibulatkan 40.00 m3/jam

1 m3 tanah diperlukan faktor alat (buldozer) = 0.0250 jam

1 m2 tanah diperlukan faktor alat (buldozer) = 0.0075 jam = 133.33 m2/jam

1 Ha tanah diperlukan faktor alat (buldozer) = 75.0000 jam

= 0.0133 Ha/jam

1 m3 tanah diperlukan faktor alat (excavator) = 0.0250 jam

Sumber : Hasil Perhitungan

(37)

PERHITUNGAN PRODUKSI ALAT

3. VIBRATOR ROLLER

Kecepatan alat (V) = 3.00 km/jam

Lebar efektif pemadatan (B) = 1.10 m

Effisiensi (E) = 0.80

Faktor kembang (Fk) = 1.20

Tebal hamparan (t) = 0.30 m

Jumlah lintasan (N) = 10.00

Produksi alat = (V x B x t x E) / (N x Fk) = 66.00 m3/jam

1 m3 tanah diperlukan faktor alat (Vibrator roller) = 0.0152 jam

(38)

KONSULTAN PERENCANA

CV. ZIYAD IDOLA CONSULTANT

KONSULTAN PERENCANAAN UMUM DAN PENGAWASAN

Head Office : Jl. Prada Utama Lr. Delima No. 10 Banda Aceh

A. PEMBANGUNAN JARINGAN AIR

BERSIH MEURANDEH - LANGSA LAMA -

SMA 2 LANGSA

PEMERINTAH ACEH

DINAS BINA MARGA DAN CIPTA KARYA

Jln. Jenderal Sudirman No. 01 Telp. (0651) 46767, 47009, 46915

BIDANG PROGRAM DAN PELAPORAN

PERENCANAAN PENGEMBANGAN INFRASTRUKTUR

(39)

NOMOR KONTRAK

:

07-AC/CTR/BPP.P-OTSUS/DBC/APBA/2010

TANGGAL

:

20 MEI 2010

PEKERJAAN

:

Perencanaan Pengembangan Infrastruktur (KOTA LANGSA)

KODE PAKET

:

PR INFRA 13/2010

NILAI KONTRAK

:

Rp.

162.923.000,-NILAI KONTRAK FISIK

:

Rp.

6.447.585.000,-SUMBER DANA

:

OTSUS

DPA SKPA

:

TAHUN ANGGARAN 2010

KONSULTAN PERENCANA

CV. ZIYAD IDOLA CONSULTANT

KONSULTAN PERENCANAAN UMUM DAN PENGAWASAN

Head Office : Jl. Prada Utama Lr. Delima No. 10 Banda Aceh

PEMERINTAH ACEH

DINAS BINA MARGA DAN CIPTA KARYA

Jln. Jenderal Sudirman No. 01 Telp. (0651) 46767, 47009, 46915

BIDANG PROGRAM DAN PELAPORAN

PERENCANAAN PENGEMBANGAN INFRASTRUKTUR

(40)
(41)

KEGIATAN : PERENCANAAN PENGEMBANGAN INFRASTRUKTUR (KOTA LANGSA)

LOKASI : KOTA LANGSA

TAHUN ANGGARAN : 2010

A. PEMBANGUNAN JARINGAN AIR BERSIH MEURANDEH - LANGSA LAMA-SMA2

LANGSA Rp.

B. SISTEM DRAINASE KOMPLEK PERUMAHAN SUNGAI PAOH KECAMATAN

LANGSA BARAT Rp.

TOTAL Rp.

PPn 10% Rp.

JUMLAH SELURUHNYA Rp.

DIBULATKAN Rp.

Banda Aceh, September 2010 Konsultan Perencana,

CV. ZIYAD IDOLA CONSULTANT

Abdullah, ST

Direktur

REKAPITULASI TOTAL

NO. U R A I A N TOTAL HARGA (Rp.)

Terbilang : Enam Milyar Empat Ratus Empat Puluh Tujuh Juta Lima Ratus Delapan Puluh Lima Ribu

Rupiah,-Disetujui Oleh :

Pejabat Pelaksana Teknis Kegiatan (PPTK) Perencanaan Pengembangan Infrastruktur Dinas Bina Marga dan Cipta Karya Aceh

Mawaddah Noer, ST

Nip. 197404142006042002

Mengetahui ;

Kepala Bidang Program dan Pelaporan

Dinas Bina Marga dan Cipta Karya

Kuasa Pengguna Anggaran / Kuasa Pengguna Barang

Ir. Mohd. Sanusi, M.Si

(42)

2,370,121,110.20 3,491,320,400.74 5,861,441,510.94 586,144,151.09 6,447,585,662.03 6,447,585,000.00

Banda Aceh, September 2010 Konsultan Perencana,

CV. ZIYAD IDOLA CONSULTANT

REKAPITULASI TOTAL

TOTAL HARGA (Rp.)

Terbilang : Enam Milyar Empat Ratus Empat Puluh Tujuh Juta Lima Ratus Delapan Puluh Lima Ribu

Rupiah,-Mengetahui ;

Kepala Bidang Program dan Pelaporan

Dinas Bina Marga dan Cipta Karya

Kuasa Pengguna Anggaran / Kuasa Pengguna Barang

Ir. Mohd. Sanusi, M.Si

(43)

Kegiatan : Sistem Drainase Komplek Perumahan Sei Pauh dan Dusun Makmur Sei Pauh Kec. Langsa Barat Pekerjaan : Pembangunan Tanggul Pengamanan Komplek Perumahan Sei Pauh

Lokasi : Kecamatan Langsa Barat, Kota Langsa Tahun Anggaran : 2010 HARGA JUMLAH SATUAN HARGA (Rp) (Rp) 1 3 4 6 7 = 4 x 6 I. PEKERJAAN PERSIAPAN

1 Mobilisasi dan Demobilisasi Ls 1.00 A.1 21,000,000.00 21,000,000.00 2 Pembersihan Lapangan Ls 1.00 Taksir 2,000,000.00 2,000,000.00

3 Dewatering Ls 1.00 Taksir 6,500,000.00 6,500,000.00

4 Sewa Direksi Keet Unit 1.00 Taksir 2,000,000.00 2,000,000.00 5 Papan Nama Proyek Unit 1.00 Taksir 750,000.00 750,000.00 6 Adm. / Gbr. Lap / Dok. / Pas. Profil Ls 1.00 Taksir 4,500,000.00 4,500,000.00

36,750,000.00

II. PEKERJAAN TANGGUL BANJIR

1 Timbunan Tanah Didatangkan dan

dipadatkan dengan Alat Berat M3 3,099.57 B.6 156,697.00 485,693,320.29 2 Pasangan Gebalan Rumput M2 3,334.38 B.8 42,535.00 141,827,853.30

627,521,173.59

III. PEKERJAAN SALURAN DRAINASE

1 Galian Tanah Biasa M3 2,057.62 B.2 48,434.00 99,658,767.08

2 Timbunan Tanah Hasil Galian M3 685.87 1/3 x B.2 16,144.67 11,073,196.34

3 Urugan Pasir M3 62.16 B.7 150,733.00 9,369,563.28

4 Pasangan Batu Kosong (aanstamping) M3 248.65 D.2 364,629.00 90,665,000.85 5 Beton Tumbuk Lantai Kerja K.100 M3 62.16 C.1 598,775.00 37,219,854.00 6 Beton Struktur K.225 M3 420.43 C.3 1,184,505.00 498,001,437.15

7 Pekerjaan Besi Kg 44,035.67 C.4 18,165.00 799,907,945.55

8 Bekisting M2 2,179.31 C.7 511,321.00 1,114,326,968.51

9 Pipa Drain Hole PVC dia. 1 1/2" Bh 457.00 D.5 22,501.00 10,282,957.00

2,670,505,689.76

IV. PEKERJAAN PINTU AIR (1 UNIT)

1 Galian Tanah Biasa M3 19.78 B.2 48,434.00 958,024.52 2 Timbunan Tanah Hasil Galian M3 4.95 1/3 x B.2 16,144.67 79,835.38

3 Urugan Pasir M3 8.71

B.7 150,733.00 1,312,884.43 4 Pasangan Batu Kosong (aanstamping) M3 17.42 D.2 364,629.00 6,351,837.18 5 Beton Tumbuk Lantai Kerja K.100 M3 8.35 C.1 598,775.00 4,999,771.25

6 Beton Cor K.175 M3 15.68 C.2 739,466.00 11,594,826.88

7 Beton Struktur K.225 M3 31.02 C.3 1,184,505.00 36,743,345.10

8 Pekerjaan Besi Kg 842.66 C.4 18,165.00 15,306,918.90

9 Bekisting M2 123.75 C.7 511,321.00 63,275,973.75

10 Pipa Sandaran Galvanis Ø3" M' 20.00 M49 96,006.00 1,920,120.00 11 Pintu Air Sorong (B = 0,7 H = 1,0) Set 2.00 M47 3,000,000.00 6,000,000.00 12 Pintu Air Koklep (B = 0,7 H = 1,25) Set 2.00 M48 4,000,000.00 8,000,000.00

156,543,537.39

DAFTAR KUANTITAS DAN HARGA

NO. URAIAN PEKERJAAN SAT KUANTITAS

2

KODE ANALISA

Jumlah Harga Pekerjaan I (dipindah ke lembar Rekapitulasi)

Jumlah Harga Pekerjaan II (dipindah ke lembar Rekapitulasi)

Jumlah Harga Pekerjaan III (dipindah ke lembar Rekapitulasi)

(44)

Kegiatan : Sistem Drainase Komplek Perumahan Sei Pauh dan Dusun Makmur Sei Pauh Kec. Langsa Barat Pekerjaan : Pembangunan Tanggul Pengamanan Komplek Perumahan Sei Pauh

Lokasi : Kecamatan Langsa Barat, Kota Langsa Tahun Anggaran : 2010 JUMLAH HARGA KET. (Rp) 1 3 4 I. PEKERJAAN PERSIAPAN 36,750,000.00

II. PEKERJAAN TANGGUL BANJIR 627,521,173.59

III. PEKERJAAN SALURAN DRAINASE 2,670,505,689.76

IV. PEKERJAAN PINTU AIR (1 UNIT) 156,543,537.39

A. Jumlah Harga 3,491,320,400.74

B. Pajak Pertambahan Nilai (PPn) = 10 % (A) 349,132,040.07

C. Jumlah (A) + (B) 3,840,452,440.81

D. DIBULATKAN 3,840,452,000.00

REKAPITULASI

DAFTAR KUANTITAS DAN HARGA

NO. URAIAN PEKERJAAN

2

(45)

Rupiah,-ENGINEER'S ESTIMATE

KEGIATAN : PEMBANGUNAN JARINGAN AIR BERSIH MEURANDEH - LANGSA LAMA - SMA 2 LANGSA PEKERJAAN : INSTALASI JARINGAN PIPA TRANSMISI PDAM TIRTA KEUMUNENG - LANGSA LOKASI : KOTA LANGSA

TAHUN ANGGARAN : 2010

HARGA JUMLAH SATUAN HARGA

(Rp) (Rp)

1 3 4 5 6 7

A. PEMBANGUNAN JARINGAN AIR BERSIH MEURANDEH - LANGSA LAMA - SMA 2 LANGSA

I. PEKERJAAN PERSIAPAN

1 Direksi keet (sewa) 1.000 Ls Ditaksir 3,000,000.00 3,000,000.00 2 Pembersihan Lokasi Pekerjaan 1.000 Ls Ditaksir 1,700,000.00 1,700,000.00 3 Pematokan/Pengukuran (setting out) 1.000 Ls Ditaksir 4,850,000.00 4,850,000.00 4 Mobilisasi dan Demobilisasi 1.000 Ls Ditaksir 5,000,000.00 5,000,000.00 5 Administrasi, Dokumentasi dan Pelaporan 1.000 Ls Ditaksir 2,500,000.00 2,500,000.00 6 Papan Nama Proyek 1.000 Ls Ditaksir 750,000.00 750,000.00 7 Gambar Pekerjaan Selesai (As Built Drawing) 1.000 Ls Ditaksir 3,000,000.00 3,000,000.00

20,800,000.00

II. PENGADAAN PIPA

1 Pengadaan Pipa GIP Panjang efektif 6 m'/batang

- Pipa GIP dia. 150 mm 27.000 M' M51 272,689.50 7,362,616.50 - Pipa GIP dia. 200 mm 202.000 M' M52 344,433.00 69,575,466.00

2 Pipa PVC lengkap dengan Rubber Ring Joint Panjang efektif 6 m'/batang (seri S-12,5)

- Pipa PVC dia. 200 mm 4,002.000 M' M116 195,370.00 781,870,740.00 - Pipa PVC dia. 150 mm 515.000 M' M115 132,932.50 68,460,237.50 - Pipa PVC dia. 100 mm 95.000 M' M114 70,495.00 6,697,025.00

933,966,085.00

III. PENGADAAN ASESORIES

(Lengkap dengan Baut, Mur, Rubber Ring dan Gasket)

1 Tee RRJ GIP dia. 150 mm 1.00 Bh M104 972,162.00 972,162.00 2 Bend GIP dia. 200 mm x 90 1.00 Bh M67 708,768.00 708,768.00 3 Bend PVC dia. 200 mm x 90º 5.00 Bh M128 390,532.00 1,952,660.00 4 Bend PVC dia. 200 mm x 45º 8.00 Bh M127 335,333.00 2,682,664.00 5 Bend PVC dia. 200 mm x 22.5º 3.00 Bh M126 290,533.00 871,599.00 6 Gate Valve GIP dia. 200 mm 1.00 Bh M94 2,822,393.00 2,822,393.00 7 Gate Valve GIP dia. 150 mm 2.00 Bh M93 1,702,905.00 3,405,810.00 8 Flange Socket PVC dia. 200 mm 11.00 Bh M140 466,520.00 5,131,720.00 9 Flange Socket PVC dia. 150 mm 9.00 Bh M139 294,691.50 2,652,223.50 10 Flange Socket GIP dia. 200 mm 8.00 Bh M84 590,392.00 4,723,136.00 11 Flange Socket GIP dia. 150 mm 10.00 Bh M85 419,400.00 4,194,000.00 12 Loos Flange GIP dia. 200 mm 10.00 Bh M89 164,500.00 1,645,000.00 13 Loos Flange GIP dia. 150 mm 10.00 Bh M88 110,700.00 1,107,000.00 14 Dop PVC dia. 150 mm 1.000 Bh M135 199,675.00 199,675.00

33,068,810.50 IV. PEMASANGAN PIPA

1 Pekerjaan Tanah

a. Galian Tanah 2,523.760 M³ B.3 52,334.00 132,078,455.84 b. Urugan Kembali 2,092.685 M³ 1/3 x B3 17,444.67 36,506,192.26 c. Urugan Pasir 258.180 M³ B.7 150,733.00 38,916,245.94

2 Pekerjaan Beton

- Beton Cor K175 (trust block) 2.400 M³ C.2 739,466.00 1,774,718.40

3 Pipa PVC lengkap dengan Rubber Ring Joint Panjang efektif 6 m'/batang (seri S-12,5)

a - Pipa PVC dia. 200 mm 4,002.000 M' E.4 23,413.00 93,698,826.00 b - Pipa PVC dia. 150 mm 515.000 M' E.3 19,514.00 10,049,710.00

4 Pengetesan Aliran Pipa 4,517.000 Ls (E.12+E.13)/2 5,623.50 25,401,349.50

338,425,497.94

No URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA

2

Jumlah (I)

Jumlah (II)

Jumlah (III)

(46)

HARGA JUMLAH SATUAN HARGA

(Rp) (Rp)

1 3 4 5 6 7

V. PERLINTASAN PIPA

1 Perlintasan Pipa dia. 200 mm (5 unit)

- Pipa GIP dia. 200 mm 32.000 M' M52 344,433.00 11,021,856.00

Asesories :

- Flange GIP dia. 200 mm 8.000 Bh M83 200,000.00 1,600,000.00 - Flange GIP dia. 150 mm 8.000 Bh M82 165,000.00 1,320,000.00 - Tee GIP dia. 150 x 150 x 150 mm 1.000 Bh M104 972,162.00 972,162.00 - Gate Valve CI dia. 200 mm x 90º 1.000 Bh M94 2,822,393.00 2,822,393.00 - Gate Valve CI dia. 150 mm x 90º 1.000 Bh M93 1,702,905.00 1,702,905.00 - Bend CI dia. 200 mm x 45º 8.000 Bh M66 626,325.00 5,010,600.00 - Los Flange GIP dia. 200 mm 12.000 Bh M89 164,500.00 1,974,000.00 - Flange Socket PVC RRJ dia. 200 mm 4.000 Bh M140 466,520.00 1,866,080.00 - Baut dan Mur Ring Flange dia. 200 mm 2.000 Set M97 137,500.00 275,000.00 - Trust Block 0.600 M³ C.2 739,466.00 443,679.60 - Clamp dia. 200 mm dan Angker Bolt+Mur+Ring 10.000 Set M74 250,098.00 2,500,980.00 - Pabrikasi dan Pemasangan Perlintasan Jalan Pipa 5.000 Unit Ditaksir 8,500,000.00 42,500,000.00 (termasuk galian dan urugan)

2 Perlintasan Pipa dia. 150 mm (4 unit)

- Pipa GIP dia. 150 mm 27.000 M' M51 272,689.50 7,362,616.50

Asesories :

- Bend CI dia. 150 mm x 45º 12.000 Bh M64 442,349.00 5,308,188.00 - Los Flange GIP dia. 150 mm 6.000 Bh M88 110,700.00 664,200.00 - Flange Socket PVC RRJ dia. 150 mm 2.000 Bh M139 294,691.50 589,383.00 - Baut dan Mur Ring Flange dia. 150 mm 1.000 Set M96 127,600.00 127,600.00 - Trust Block 0.480 M³ C.2 739,466.00 354,943.68 - Clamp dia. 150 mm dan Angker Bolt+Mur+Ring 8.000 Set M75 131,276.00 1,050,208.00 - Pabrikasi dan Pemasangan Perlintasan Jalan Pipa 4.000 Unit Ditaksir 7,000,000.00 28,000,000.00 (termasuk galian dan urugan)

117,466,794.78

Jumlah (V)

No URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA

(47)

HARGA JUMLAH SATUAN HARGA

(Rp) (Rp)

1 3 4 5 6 7

VI. PEMBUATAN JEMBATAN PIPA (3 UNIT) + PERLINTASAN (1 UNIT)

1 Pekerjaan Tanah

- Galian Tanah 50.655 M³ B.3 52,334.00 2,650,978.77 - Urugan Kembali 12.664 M³ 1/3 x B3 17,444.67 220,914.90 - Urugan Pasir 1.620 M³ B.7 150,733.00 244,187.46

2 Pekerjaan Pasangan/Beton

- Pasangan Batu Kosong 1.620 M³ D.2 364,629.00 590,698.98 - Beton Cor Lantai K100 0.810 M³ C.1 598,775.00 485,007.75 - Beton Bertulang K225 24.696 M³ C.3 1,184,505.00 29,252,535.48 - Pembesian 798.360 Kg C.4 18,165.00 14,502,209.40 - Bekisting Pondasi 31.740 M2 C.6 194,462.00 6,172,223.88

3 Pemasangan Pipa dan Asesories A. Pemasangan Pipa Jembatan

- Pipa PVC dia. 100 mm 144.000 M' M114 70,495.00 10,151,280.00 - Pipa GIP dia. 200 mm 92.000 M' M52 344,433.00 31,687,836.00 - Pipa GIP dia. 150 mm 102.000 M'

B. Asesories

- Flange Socket GIP dia. 200 mm 3.000 Bh M84 590,392.00 1,771,176.00 - Flange Socket GIP dia. 150 mm 5.000 Bh M85 419,400.00 2,097,000.00 - Flange Socket GIP dia. 100 mm 4.000 Bh M86 248,408.00 993,632.00 - Gate Valve CI dia. 200 mm 2.000 Bh M94 2,822,393.00 5,644,786.00 - Gate Valve CI dia. 150 mm 3.000 Bh M93 1,702,905.00 5,108,715.00 - Gate Valve CI dia. 100 mm 4.000 Bh M92 855,754.00 3,423,016.00 - Street Block 4.000 Bh M150 225,000.00 900,000.00 - Tee GIP dia. 200 - 100 - 200 mm 2.000 Bh M106 1,069,378.00 2,138,756.00 - Tee GIP dia. 150 - 100 - 150 mm 3.000 Bh M107 972,162.00 2,916,486.00 - Angker Bolt D22+Mur+Ring 36.000 Bh M02 42,000.00 1,512,000.00 - Bar Pengaman 8.000 Set M03 1,200,000.00 9,600,000.00 - Bend CI dia. 200 mm x 45º 5.000 Bh M66 626,325.00 3,131,625.00 - Bend CI dia. 150 mm x 45º 9.000 Bh M64 442,349.00 3,981,141.00 - Bend CI dia. 100 mm x 45º 4.000 Bh M63 258,373.00 1,033,492.00 - Air Realease CI Ø 50 mm 2.000 Bh M54 1,854,412.00 3,708,824.00 - Air Realease CI Ø 100 mm 3.000 Bh M56 3,384,171.00 10,152,513.00 - Base Plat 16 mm 6.000 Bh M12 170,000.00 1,020,000.00 - Baja Profil H.70.30.1,3.2,4 15,540.000 Kg M04 28,300.00 439,782,000.00 - Baut dan Mur Steel 1 1/2" 42.000 Set M10 22,000.00 924,000.00 - Los Flange GIP dia. 200 mm 10.000 Bh M89 164,500.000 1,645,000.00 - Los Flange GIP dia. 150 mm 19.000 Bh M88 110,700.000 2,103,300.00 - Los Flange GIP dia. 100 mm 7.000 Bh M87 56,900.000 398,300.00 - Trust Block 0.960 M³ C.2 739,466.00 709,887.36 - Pabrikasi dan Pemasangan Perlintasan Pipa Jembatan 4.000 Unit Ditaksir 12,000,000.00 48,000,000.00

648,653,521.98

VII. PEKERJAAN LAIN-LAIN

1 Pengadaan dan Pemasangan Pompa Centrifugal (termasuk panel, Instalasi dan Asesories) dengan spesifikasi :

a. Pompa kapasitas 60 ltr/det, Head = 40 meter/37,5 kw/2900-3000 rpm 1.000 Unit Ditaksir 78,000,000.00 78,000,000.00 b. Pompa kapasitas 50 ltr/det, Head = 40 meter/30 kw/2900-3000 rpm 1.000 Unit Ditaksir 64,000,000.00 64,000,000.00 c. Pompa kapasitas 20 ltr/det, Head = 40 meter/18,5 kw/2900-3000 rpm 2.000 Unit Ditaksir 46,000,000.00 92,000,000.00 2 Pengadaan dan Pemasangan Meter air :

a. Meter air Ø 300 mm 1.000 Unit M152 28,269,400.00 28,269,400.00 b. Meter air Ø 300 mm 1.000 Unit M153 15,471,000.00 15,471,000.00

277,740,400.00

Jumlah (VII) Jumlah (VI)

No URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA

(48)

KEGIATAN : PEMBANGUNAN JARINGAN AIR BERSIH MEURANDEH - LANGSA LAMA - SMA 2 LANGSA PEKERJAAN : INSTALASI JARINGAN PIPA TRANSMISI PDAM TIRTA KEUMUNENG - LANGSA

LOKASI : KOTA LANGSA

TAHUN ANGGARAN : 2010

1

A.

PEMBANGUNAN JARINGAN AIR BERSIH MEURANDEH -

LANGSA LAMA - SMA 2 LANGSA

I.

PEKERJAAN PERSIAPAN

20,800,000.00

II.

PENGADAAN PIPA

933,966,085.00

III.

PENGADAAN ASESORIES

33,068,810.50

IV.

PEMASANGAN PIPA

338,425,497.94

V.

PERLINTASAN PIPA

117,466,794.78

VI.

PEMBUATAN JEMBATAN PIPA (3 UNIT) + PERLINTASAN (1 UNIT)

648,653,521.98

VII.

PEKERJAAN LAIN-LAIN

277,740,400.00

A. Jumlah Harga

2,370,121,110.20

B. Pajak Pertambahan Nilai (PPn) = 10 % (A)

237,012,111.02

C. Jumlah (A) + (B)

2,607,133,221.22

D. DIBULATKAN

2,607,133,000.00

REKAPITULASI

DAFTAR KUANTITAS DAN HARGA

2

Terbilang : Dua Milyar Enam Ratus Tujuh Juta Seratus Tiga Puluh Tiga Ribu

Rupiah,-NO.

URAIAN PEKERJAAN

JUMLAH HARGA

(49)

JENIS PEKERJAAN

: MOBILISASI/DEMOBILISASI

SATUAN PEKERJAAN

: LS

KODE ANALISA

: A.1

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

MOBILISASI ALAT & PERSONIL

1

Excavator

bh

1.000

3,500,000.00

3,500,000.00

2

Buldozer

bh

1.000

3,500,000.00

3,500,000.00

3

Vibro roller

bh

1.000

3,500,000.00

3,500,000.00

4

5

B

DEMOBILISASI ALAT & PERSONIL

1

Excavator

bh

1.000

3,500,000.00

3,500,000.00

2

Buldozer

bh

1.000

3,500,000.00

3,500,000.00

3

Vibro roller

bh

1.000

3,500,000.00

3,500,000.00

4

5

Jumlah (termasuk biaya umum dan keuntungan)

21,000,000.00

Harga pekerjaan (diluar PPN)

21,000,000.00

Jumlah dibulatkan

21,000,000.00

(50)

JENIS PEKERJAAN

: PASANGAN BATU 1 : 4 (TERMASUK SIAR 1 : 3)

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

1.5000

49,700.00

74,550.00

2

Tukang

OH

0.6000

78,700.00

47,220.00

3

Kepala Tukang

OH

0.0600

94,500.00

4

Mandor

OH

0.0750

82,300.00

6,172.50

B

B A H A N

1

PC

kg

163.0000

1,257.50

204,972.50

2

Batu Kali

m3

1.2000

202,800.00

243,360.00

3

Pasir Pasang

m3

0.5200

129,600.00

67,392.00

C

PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan)

643,667.00

Harga pekerjaan (diluar PPN)

643,667.00

Jumlah dibulatkan

643,667.00

JENIS PEKERJAAN

: PASANGAN BATU KOSONG (AANSTAMPING)

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.7800

49,700.00

38,766.00

2

Tukang

OH

0.3900

78,700.00

30,693.00

3

Kepala Tukang

OH

0.0390

94,500.00

4

Mandor

OH

0.0390

82,300.00

3,209.70

B

B A H A N

1

Batu Kali

m3

1.2000

202,800.00

243,360.00

2

Pasir Urug

m3

0.4320

112,500.00

48,600.00

C

PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan)

364,628.70

Harga pekerjaan (diluar PPN)

364,628.70

(51)

JENIS PEKERJAAN

:

PLESTERAN 1 : 3

SATUAN PEKERJAAN

:

M2

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.2000

49,700.00

9,940.00

2

Tukang

OH

0.1500

78,700.00

11,805.00

3

Kepala Tukang

OH

0.0150

94,500.00

4

Mandor

OH

0.0100

82,300.00

823.00

B

B A H A N

1

PC

kg

7.7760

1,257.50

9,778.32

2

Pasir Pasang

m3

0.0230

129,600.00

2,980.80

3

C

PERALATAN

1

-Jumlah (termasuk biaya umum dan keuntungan)

35,327.12

Harga pekerjaan (diluar PPN)

35,327.12

Jumlah dibulatkan

35,327.00

JENIS PEKERJAAN

:

PLESTERAN 1 : 4

SATUAN PEKERJAAN

:

M2

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.2000

49,700.00

9,940.00

2

Tukang

OH

0.1500

78,700.00

11,805.00

3

Kepala Tukang

OH

0.0150

94,500.00

4

Mandor

OH

0.0100

82,300.00

823.00

B

B A H A N

1

PC

kg

6.2400

1,257.50

7,846.80

2

Pasir Pasang

m3

0.0240

129,600.00

3,110.40

3

C

PERALATAN

1

-Jumlah (termasuk biaya umum dan keuntungan)

33,525.20

Harga pekerjaan (diluar PPN)

33,525.20

(52)
(53)

NO

A

1

2

3

B

1

C

1

2

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

B

1

C

1

(54)

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

B

1

C

1

2

3

4

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

1

C

1

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

1

(55)

C

1

2

3

(56)

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

B

1

C

1

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

B

1

(57)

JENIS PEKERJAAN

:

GALIAN TANAH BIASA SEDALAM 1 METER

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.7500

49,700.00

37,275.00

2

Mandor

OH

0.0250

82,300.00

2,057.50

3

B

B A H A N

1

C

PERALATAN

1

2

Jumlah (termasuk biaya umum dan keuntungan)

39,332.50

Harga pekerjaan (diluar PPN)

39,332.50

Jumlah dibulatkan

39,333.00

(58)

JENIS PEKERJAAN

:

GALIAN TANAH BIASA SEDALAM 2 METER

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.9000

49,700.00

44,730.00

2

Mandor

OH

0.0450

82,300.00

3,703.50

3

B

B A H A N

1

C

PERALATAN

1

2

Jumlah (termasuk biaya umum dan keuntungan)

48,433.50

Harga pekerjaan (diluar PPN)

48,433.50

Jumlah dibulatkan

48,434.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

:

GALIAN TANAH KERAS SEDALAM 1 METER

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

1.0000

49,700.00

49,700.00

2

Mandor

OH

0.0320

82,300.00

2,633.60

3

B

B A H A N

1

C

PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan)

52,333.60

Harga pekerjaan (diluar PPN)

52,333.60

Jumlah dibulatkan

52,334.00

(59)

JENIS PEKERJAAN

:

GALIAN TANAH LUMPUR SEDALAM 1 METER

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

1.2000

49,700.00

59,640.00

2

Mandor

OH

0.0450

82,300.00

3,703.50

3

B

B A H A N

1

C

PERALATAN

1

2

3

4

Jumlah (termasuk biaya umum dan keuntungan)

63,343.50

Harga pekerjaan (diluar PPN)

63,343.50

Jumlah dibulatkan

63,344.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

:

MEMADATKAN TANAH (PER 20 CM)

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.5000

49,700.00

24,850.00

2

Mandor

OH

0.0500

82,300.00

4,115.00

3

4

B

B A H A N

1

C

PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan)

28,965.00

Harga pekerjaan (diluar PPN)

28,965.00

Jumlah dibulatkan

28,965.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

: TIMBUNAN TANAH DIDATANGKAN & PEMADATAN DENGAN ALAT BERAT

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.3000

49,700.00

14,910.00

2

Mandor

OH

0.0100

82,300.00

823.00

3

Operator

OH

0.2905

122,300.00

35,528.15

4

Pembantu Operator

OH

0.2905

75,000.00

21,787.50

B

B A H A N

1

Tanah Timbun

m3

1.2000

51,700.00

62,040.00

(60)

C

PERALATAN

1

Excavator

Jam

0.0250

343,208.28

8,580.21

2

Buldozer

Jam

0.0164

547,125.46

8,969.27

3

Vibro roller

Jam

0.0152

267,913.36

4,059.29

Jumlah (termasuk biaya umum dan keuntungan)

156,697.42

Harga pekerjaan (diluar PPN)

156,697.42

Jumlah dibulatkan

156,697.00

(61)

JENIS PEKERJAAN

:

TIMBUNAN PASIR URUG

SATUAN PEKERJAAN

:

M3

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.3000

49,700.00

14,910.00

2

Mandor

OH

0.0100

82,300.00

823.00

B

B A H A N

1

Pasir urug

m3

1.2000

112,500.00

135,000.00

C

PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan)

150,733.00

Harga pekerjaan (diluar PPN)

150,733.00

Jumlah dibulatkan

150,733.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN

:

PEKERJAAN GEBALAN RUMPUT

SATUAN PEKERJAAN

:

M2

NO

URAIAN

SATUAN

KUANTITAS

HARGA SATUAN

JUMLAH

Rp.

Rp.

A

TENAGA

1

Pekerja

OH

0.1500

49,700.00

7,455.00

2

Mandor

OH

0.0150

82,300.00

1,234.50

3

Alat bantu

set

0.0125

10,000.00

125.00

B

B A H A N

1

Lempengan Rumput

m2

1.2000

28,100.00

33,720.00

Jumlah (termasuk biaya umum dan keuntungan)

42,534.50

Harga pekerjaan (diluar PPN)

42,534.50

Jumlah dibulatkan

( B )

42,535.00

(62)

JENIS PEKERJAAN : BETON K.175 (TANPA ACUAN)

SATUAN PEKERJAAN : M3

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 1.6500 49,700.00 82,005.00 2 Tukang OH 0.2750 78,700.00 21,642.50 3 Kepala Tukang OH 0.0280 94,500.00 2,646.00 4 Mandor OH 0.0830 82,300.00 6,830.90 5 6 B B A H A N 1 Pasir Beton kg 760.00 100.79 76,597.14 2 Kerikil kg 1,029.00 104.52 107,549.56 3 PC kg 326.00 1,257.50 409,945.00 4 Air Liter 215.00 150.00 32,250.00 5 6 C PERALATAN 1 2 3

Jumlah (termasuk biaya umum dan keuntungan 739,466.10

Harga pekerjaan (diluar PPN) 739,466.10

Jumlah dibulatkan 739,466.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN : BETON STRUKTUR K.225 (TANPA ACUAN)

SATUAN PEKERJAAN : M3

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 1.6500 49,700.00 82,005.00 2 Tukang OH 0.2750 78,700.00 21,642.50 3 Kepala Tukang OH 0.0280 94,500.00 2,646.00 4 Mandor OH 0.0830 82,300.00 6,830.90 5 B B A H A N

1 Kerikil (batu pecah 2-3 cm) kg 1,047.00 479.70 502,249.78

2 Pasir Beton kg 698.00 100.79 70,348.43 3 PC kg 371.00 1,257.50 466,532.50 4 Air Liter 215.00 150.00 32,250.00 C PERALATAN 1 2

Jumlah (termasuk biaya umum dan keuntungan 1,184,505.11

Harga pekerjaan (diluar PPN) 1,184,505.11

Jumlah dibulatkan 1,184,505.00

(63)

JENIS PEKERJAAN : BESI TULANGAN POLOS

SATUAN PEKERJAAN : 10 KG

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 0.0700 49,700.00 3,479.00 2 Tukang OH 0.0700 78,700.00 5,509.00 Kepala Tukang OH 0.0070 94,500.00 661.50 3 Mandor OH 0.0040 82,300.00 329.20 B B A H A N

1 Besi beton polos kg 10.5000 16,200.00 170,100.00

2 Kawat Beton kg 0.1500 10,500.00 1,575.00

C PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan 181,653.70

Harga pekerjaan (diluar PPN) 181,653.70

Jumlah untuk 1 Kg Besi 18,165.37

Jumlah dibulatkan 18,165.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN : BESI TULANGAN ULIR

SATUAN PEKERJAAN : 10 KG

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 0.0700 49,700.00 3,479.00 2 Tukang OH 0.0700 78,700.00 5,509.00 Kepala Tukang OH 0.0070 94,500.00 661.50 3 Mandor OH 0.0040 82,300.00 329.20 B B A H A N

1 Besi beton ulir kg 10.5000 24,800.00 260,400.00

2 Kawat Beton kg 0.1500 10,500.00 1,575.00

C PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan 271,953.70

Harga pekerjaan (diluar PPN) 271,953.70

Jumlah untuk 1 Kg Besi 27,195.37

Jumlah dibulatkan 27,195.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN : ACUAN BETON/BEKISTING UNTUK PONDASI

SATUAN PEKERJAAN : M2

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 0.5200 49,700.00 25,844.00 2 Tukang OH 0.2600 78,700.00 20,462.00 3 Kepala Tukang OH 0.0260 94,500.00 4 Mandor OH 0.0260 82,300.00 2,139.80 B B A H A N 1 Paku kg 0.3000 11,600.00 3,480.00

2 Kayu kelas III m3 0.0400 3,553,900.00 142,156.00

3 Minyak bekisting liter 0.1000 3,800.00 380.00

C PERALATAN

1

(64)

Harga pekerjaan (diluar PPN) 194,461.80

Jumlah dibulatkan 194,462.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN : ACUAN BETON/BEKISTING UNTUK DINDING

SATUAN PEKERJAAN : M2

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 0.6600 49,700.00 32,802.00 2 Tukang OH 0.3300 78,700.00 25,971.00 3 Kepala Tukang OH 0.0330 94,500.00 3,118.50 4 Mandor OH 0.0330 82,300.00 2,715.90 B B A H A N 1 Paku kg 0.4000 11,600.00 4,640.00

2 Kayu kelas III m3 0.0300 3,553,900.00 106,617.00

3 Balok kayu kelas II m3 0.0200 3,926,100.00 78,522.00

4 Minyak bekisting liter 0.2000 3,800.00 760.00

5 Plywood tebal 9 mm lembar 0.3500 150,500.00 52,675.00

6 Kayu dolken batang 3.0000 62,500.00 187,500.00

7 Formite/penjaga jarak bekisting/spacer buah 4.0000 4,000.00 16,000.00

C PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan) 511,321.40

Harga pekerjaan (diluar PPN) 511,321.40

Jumlah dibulatkan 511,321.00

Sumber : Analisa SNI 2007

JENIS PEKERJAAN : ACUAN BETON/BEKISTING UNTUK LANTAI

SATUAN PEKERJAAN : M2

NO URAIAN SATUAN KUANTITAS HARGA SATUAN JUMLAH

Rp. Rp. A TENAGA 1 Pekerja OH 0.6600 49,700.00 32,802.00 2 Tukang OH 0.3300 78,700.00 25,971.00 3 Kepala Tukang OH 0.0330 94,500.00 3,118.50 4 Mandor OH 0.0330 82,300.00 2,715.90 B B A H A N 1 Paku kg 0.4000 11,600.00 4,640.00

2 Kayu kelas III m3 0.0400 3,553,900.00 142,156.00

3 Balok kayu kelas II m3 0.0150 3,926,100.00 58,891.50

4 Minyak bekisting liter 0.2000 3,800.00 760.00

5 Plywood tebal 9 mm lembar 0.3500 150,500.00 52,675.00

6 Kayu dolken batang 6.0000 62,500.00 375,000.00

C PERALATAN

1

Jumlah (termasuk biaya umum dan keuntungan) 698,729.90

Harga pekerjaan (diluar PPN) 698,729.90

Jumlah dibulatkan 698,730.00

(65)

Kebutuhan Waktu dan Tenaga untuk Pemasangan Tulangan Pengelak

Tukangjam 0.27

Besi Beton Ulirkg 1.10

produksi 1jam tukangkg 4.12

Satu hari (8 jam)kg/hari 32.96

Vol. baja yang akan dikerjakankg #REF!

waktu yang dibutuhkanjam #REF!

jika dikerjakan 60 oranghari #REF!

Pekerja jam 0.13

Besi Beton Ulir kg 1.10

produksi 1jam tukang kg 8.27

Satu hari (8 jam) kg/hari 66.17

Vol. baja yang akan dikerjakan kg #REF!

waktu yang dibutuhkan jam #REF!

jika dikerjakan 50 orang hari #REF!

Kebutuhan Waktu dan Tenaga untuk Pemasangan Bekisting dan Perancah Pengelak

Pekerja jam 2.45

Kayu acuan dan perancah m3 0.52

produksi 1 jam pekerja m3/jam 0.21

Satu hari (8 jam) m3/hari 1.68

Vol. Bekisting dan perancah m3 #REF!

waktu yang dibutuhkan jam #REF!

jika dikerjakan 1 orang hari #REF!

Kebutuhan Waktu dan Tenaga untuk Pemasangan Tulangan Peimpah

Tukangjam 0.27

Besi Beton Ulirkg 1.10

produksi 1jam tukangkg 4.12

Satu hari (8 jam)kg/hari 32.96

Vol. baja yang akan dikerjakankg #REF!

waktu yang dibutuhkanjam #REF!

jika dikerjakan 60 oranghari #REF!

Pekerja jam 0.13

Besi Beton Ulir kg 1.10

produksi 1jam tukang kg 8.27

Satu hari (8 jam) kg/hari 66.17

Vol. baja yang akan dikerjakan kg #REF!

waktu yang dibutuhkan jam #REF!

jika dikerjakan 50 orang hari #REF!

Kebutuhan Waktu dan Tenaga untuk Pemasangan Bekisting dan Perancah Pelimpah

Pekerja jam 2.45

Kayu acuan dan perancah m3 0.52

produksi 1 jam pekerja m3/jam 0.21

Satu hari (8 jam) m3/hari 1.68

Vol. Bekisting dan perancah m3 #REF!

waktu yang dibutuhkan jam #REF!

(66)
(67)

NO

A

1

2

3

4

B

1

C

1

2

Sumber : Hasil Perhitungan

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

1

C

1

(68)

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

1

C

1

2

3

4

Sumber : Hasil Perhitungan

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

1

C

1

Sumber : Hasil Perhitungan

JENIS PEKERJAAN

SATUAN PEKERJAAN

NO

A

1

2

3

4

B

Referensi

Dokumen terkait

PEKERJAAN PEMBERSIHAN LOKASI DAN PERSIAPAN Rp.. PEKERJAAN

Gambar 8.2 Timbunan tanah pada Saluran Pengambilan Galian tanah diatas saluran intake adalah sebesar 1372.79 m 3.. Dari gambar diatas diketahui volume timbunan tanah diatas

Rencana Anggaran Biaya merupakan perkiraan biaya yang diperlukan dalam suatu pekerjaan konstruksi. Didalam menentukan Rencana Anggaran Biaya dibutuhkan perhitungan volume galian

2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran. 3 Biaya satuan untuk peralatan sudah termasuk bahan

PASANGAN PONDASI • Hitung luas penampang galian luas trapesium • Hitung panjang galian • Hitung volume galian luas penampang x panjang galian VOLUME PASANGAN PODASI Perhitungan

PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL SEDERHANA LOKASI : 0 KABUPATEN : PURWOKERTO TAHUN ANGGARAN : 2023 RENCANA ANGGARAN BIAYA RAB NO URAIAN PEKERJAAN HARGA SATUAN Rp JUMLAH

Galian Tanah Untuk Pile Cap Volume = 201,60 m3 Dengan menggunakan analisa SNI Standard Nasional Indonesia yang berlaku di wilayah kabupaten Pengumpulan Data : Biaya Satuan Pekerjaan

Hasil penelitian rencana anggaran biaya dengan metode Analisa harga satuan pekerjaan 2016 adalah 12.294.200.000 dengan rincian pelaksanaan galian perkerasan berbutir, timbunan