Information Systems Major Sarjana Komputer Thesis Semester Even year 2006/2007
ANALYSIS AND DESIGN OF PROJECT MANAGEMENT INFORMATION SYSTEMS THROUGH SMS APPLICATION FOR PT XYZ
Yenny Novianty Buntarto 0700675791
Abstract
PT XYZ is having problem in managing their project status reporting due to the lack of integration and communication problem between all the stakeholders involve in the current business process. In order to solve the current problem, IT-based solution that relies on Short Message Service application is proposed. The objective of implementing PMIS through SMS application is to support the company to reach automated and highly- integrated business process in order to help the company to better track their project progress.
The method used for the project is, first, by analyzing the current business process and identifying the company problems. Based on the problem analysis and associated theories that are useful to build the new system, the solution is designed as a base for the system implementation. Prior to the implementation, a strategic system implementation plan is developed in order to assure that the system is delivered successfully as required.
Based on the client’s feedback, PMIS through SMS application is the appropriate media that can solve their current problem and increase the overall business performance effectively and efficiently. PMIS through SMS application will be implemented and actively used by the company to support their project reporting management.
Keywords
v
PREFACE
First and above all, I thanked my almighty Father for all the blessings and strengths that He had given to me throughout my university years and the completion of this final thesis. Secondly, for my beloved parents thank you for all the loves and supports. Mommy, thank you for always accompanying me in doing all the projects, exams, and finally my thesis until the crack of dawn.
Next, to all my lecturers, especially Mr Abubakar Siddiq and Mr Mohammad Ichsan, I am very grateful for the precious time spent to share your knowledge and to give your guidance, advises, and supports for me.
Lastly, for all of my friends from all majors and batches, I’ve been very lucky to know you all and thank you for creating such a fun experience studying here. Especially for Information Systems 2007, we’ve been through tough yet exciting years together and for sure I will treasure those beautiful memories.
vi
TABLE OF CONTENTS
COVER PAGE... i
TITLE PAGE...ii
CERTIFICATE OF APPROVAL...iii
ABSTRACT... iv
PREFACE... v
TABLE OF CONTENTS... vi
LIST OF TABLES...xiii
LIST OF FIGURES...xvii
CHAPTER 1 INTRODUCTION...1
1.1 Background ...1
1.2 Thesis Project Team ...2
1.3 Scope ...3
1.4 Aims and Benefits ...8
1.5 Structures...9
CHAPTER 2 THEORETICAL FOUNDATION...11
2.1 Theoretical Foundation ...11
2.1.1 Project Management Information System (PMIS)...12
2.1.2 Short Message Services (SMS)...12
2.1.3 Project Management...13
vii
2.1.3.2 Gantt Chart ...14
2.1.3.3 Schedule Development...15
2.1.3.4 Cost Budgeting...15
2.1.3.5 Earned Value Management (EVM)...16
2.1.4 Project Financial Analysis...18
2.1.4.1 Net Present Value ...18
2.1.4.2 Payback Period ...18
2.1.4.3 Return on Investment (ROI)...18
2.1.5 System Analysis – Traditional Approach...19
2.1.5.1 Functional Hierarchy Diagram...19
2.1.5.2 Flowchart...20
2.1.5.3 Entity Relationship Diagram (ERD) ...21
2.1.5.4 Data Flow Diagram (DFD) ...23
2.1.6 System Analysis – Object Oriented Approach...24
2.1.6.1 Use Case Diagram...24
2.1.6.2 Class Diagram ...26
2.1.6.3 Sequence Diagram...28
2.1.7 Implementation Tools and Technologies ...30
2.1.7.1 SMS Server Tools ...30
2.1.7.2 GSM Modem...31
2.1.7.3 Hypertext Markup Language (HTML) ...31
2.1.7.4 Relational Database Management System (RDBMS) using My SQL32 2.1.7.5 Python...32
viii
2.1.8 Human-Computer Interaction (HCI) ...34
2.1.9 User Acceptance Testing...40
2.2 Theoretical Framework ...41
2.2.1 System Development Life Cycle (SDLC)...41
2.2.2 Joint Application Design (JAD) ...43
CHAPTER 3 ANALYSIS OF THE EXISTING SYSTEM...44
3.1 Company Overview...44
3.1.1 Company History ...44
3.1.2 The Leading Telecom Supplier...44
3.1.3 Vision and Core Values...45
3.1.4 Policy and Procedure...46
3.2 PT XYZ Project Management Office Organizational Chart ...49
3.3 Current NRO Project Structure ...49
3.4 Current NRO Project Reporting Format ...51
3.5 Existing System...54
3.5.1 Functional Hierarchy Diagram...54
3.5.2 Data Flow Diagram...56
3.5.2.1 Context Diagram ...56
3.5.2.2 Data Flow Diagram Level 0 ...57
3.5.2.3 Manual Transaction Handling Subsystem Data Flow Diagram...58
3.5.2.4 Manual Weekly Report Generation Subsystem Data Flow Diagram ..61
3.5.2.5 Current System Flow Chart...66
ix
3.5.4 Proposed System ...74
3.5.4.1 GSM Modems Comparison...75
CHAPTER 4 DESIGN OF THE NEW SYSTEM...77
4.1 Functional Hierarchy Diagram...77
4.2 New Policy and Procedures...80
4.3 Data Flow Diagram...86
4.3.1 Context Diagram ...86
4.3.2 Data Flow Diagram Level 0 ...87
4.3.3 Transaction Handling Subsystem Data Flow Diagram...88
4.3.4 Weekly Report Management Subsystem Data Flow Diagram...96
4.3.5 Project Record Management Subsystem Data Flow Diagram...102
4.3.6 New System Flowchart ...106
4.4 System Data...116
4.4.1 Data Normalization...116
4.4.2 Table Instance Chart...117
4.4.3 Entity Relationship Diagram...124
4.5 Use Case Diagram...125
4.5.1 Users Description...125
4.5.2 Data Update Subsystem Use Case Description...127
4.5.2.1 Data Update Subsystem Use Case Scenario ...130
4.5.3 Data Retrieval Subsystem Use Case Description...136
4.5.3.1 Data Retrieval Subsystem Use Case Scenario ...139
x
4.5.4.1 Transaction Log Subsystem Use Case Scenario ...144
4.5.5 Weekly Project Report Generation Subsystem Use Case Description ...146
4.5.5.1 Weekly Project Report Generation Subsystem Use Case Scenario ...148
4.5.6 Weekly Business Performance Report Generation Subsystem Use Case Description...153
4.5.6.1 Weekly Business Performance Report Generation Subsystem Use Case Scenario ...155
4.5.7 Weekly Implementation Performance Report Generation Subsystem Use Case Description...157
4.5.7.1 Weekly Implementation Performance Report Generation Subsystem Use Case Scenario ...159
4.5.8 Weekly Project Report Summary Generatio n Subsystem Use Case Description...161
4.5.8.1 Weekly Project Report Summary Generation Subsystem Use Case Scenario ...163
4.5.9 Project Record Management Subsystem Use Case Description...165
4.5.9.1 Project Record Management Subsystem Use Case Scenario...167
4.6 Class Diagram ...170
4.7 Sequence Diagram...171
4.7.1 Transaction Handling Subsystem Sequence Diagram ...171
4.7.2 Weekly Project Report Generation Subsystem Sequence Diagram...178
4.7.3 Project Record Management Subsystem Sequence Diagram ...183
4.8 User Interface Design...187
xi
4.8.2 Input Design ...189
4.8.3 Output Design ...202
4.9 Architecture Design...211
4.10 Cost Benefit Analysis...212
CHAPTER 5 SYSTEM IMPLEMENTATION PLAN...216
5.1 Implementation Strategy ...216
5.1.1 System Specifications ...216
5.1.1.1 Hardware ...216
5.1.1.2 Software ...217
5.1.2 Stakeholders Communication Plan ...217
5.1.3 Implementation Schedule Plan...218
5.1.4 Data Migration ...219
5.1.5 System Rollout ...219
5.1.6 Quality Assurance ...220
5.1.7 Training ...220
5.2 User Acceptance Test Plan...221
5.2.1 Login Page ...222
5.2.2 Project Page ...224
5.2.3 Stakeholders Page ...235
5.2.4 Report Page ...248
5.2.5 Transaction Log Page ...255
5.2.6 Project Status Update (SMS)...258
xii
CHAPTER 6 DISCUSSION...267
6.1 Factors Affecting System Performance...267
6.2 User Resistance to Change ...269
6.3 Result...270
CHAPTER 7 CONCLUSION AND RECOMMENDATION...271
7.1 Conclusion...271
7.2 Recommendation...271
7.2.1 User Resistance Management ...272
7.2.2 System Scalability Plan...272
7.2.3 Value-Added Service ...274
REFERENCE...276
CURRICULUM VITAE...279
APPENDIX A: Sample Weekly Progress Report ...280
APPENDIX B: Sample Customer Requirement Analysis Log...281
xiii
LIST OF TABLES
Table 1 Project Scope...6
Table 2 Earned Value Formula ...17
Table 3 Table Instance Chart (TIC) for Project ...117
Table 4 Table Instance Chart (TIC) for Project Work ...118
Table 5 Table Instance Chart (TIC) for Work Task ...118
Table 6 Table Instance Chart (TIC) for Employee ...119
Table 7 Table Instance Chart (TIC) for Project Remarks ...119
Table 8 Table Instance Chart (TIC) for Work Report...120
Table 9 Table Instance Chart (TIC) for Business Report...121
Table 10 Table Instance Chart (TIC) for Sponsor...121
Table 11 Table Instance Chart (TIC) for Incoming Message ...122
Table 12 Table Instance Chart (TIC) for Outgoing Message ...122
Table 13 Table Instance Chart (TIC) for Cut Off Date ...123
Table 14 Table Instance Chart (TIC) for Project Manager, Sub-Project Manager...123
Table 15 Table Instance Chart (TIC) for Program Controller, Head of PMO, and Top Management ...123
Table 16 Users Description...125
Table 17 Data Update Subsystem Use Case Description...128
Table 18 Send Weekly Project Update by SMS Use Case Scenario ...130
Table 19 Check Received SMS Use Case Scenario ...131
xiv
Table 21 Data Retrieval Subsystem Use Case Description...137
Table 22 Send Weekly Status Request by SMS Use Case Scenario ...139
Table 23 Send Requested Project Status Use Case Scenario ...140
Table 24 Transaction Log Subsystem Use Case Description ...143
Table 25 Display Transaction log Use Case Scenario ...144
Table 26 Weekly Project Report Generation Subsystem Use Case Description ...147
Table 27 Generate Weekly Project Report Use Case Scenario...148
Table 28 Update Project Status Use Case Scenario ...150
Table 29 Weekly Business Performance Report Generation Subsystem Use Case Description...154
Table 30 Generate Weekly Business Performance Report Use Case Scenario ...155
Table 31 Weekly Implementation Performance Report Generation Subsystem Use Case Description...158
Table 32 Generate Weekly Implementation Performance Report Use Case Scenario ..159
Table 33 Weekly Project Report Summary Generation Subsystem Use Case Description ...162
Table 34 Generate Weekly Project Report Summary Use Case Scenario ...163
Table 35 Project Record Management Subsystem Use Case Description...166
Table 36 Display Stakeholders Information Use Case Scenario ...167
Table 37 Display Project Information Use Case Scenario ...168
Table 38 Capital Expenditure Analysis...212
Table 39 Monthly Operational Cost Analysis...212
Table 40 Tangible Benefit Analysis ...213
xv
Table 42 Successful User Login Test Case ...222
Table 43 Unsuccessful User Login Test Case...223
Table 44 Successful Add New Project Test Case ...224
Table 45 Unsuccessful Add New Project Test Case ...226
Table 46 View Project Information Test Case ...228
Table 47 Successful Search Project Test Case ...229
Table 48 Unsuccessful Search Project Test Case...230
Table 49 Successful Update Project Information Test Case ...232
Table 50 Uns uccessful Update Project Information Test Case...233
Table 51 Successful Add New Employee Test Case ...235
Table 52 Unsuccessful Add New Employee Test Case ...236
Table 53 Successful Add New Sponsor Test Case ...238
Table 54 Unsuccessful Add New Sponsor Test Case ...239
Table 55 View Stakeholders Information Test Case...240
Table 56 Successful Search Stakeholders Test Case ...241
Table 57 Unsuccessful Search Stakeholders Test Case ...243
Table 58 Successful Update Employee Information Test Case ...244
Table 59 Unsuccessful Update Employee Information Test Case ...246
Table 60 Successful Search Project Report Test Case ...248
Table 61 Unsuccessful Search Project Report Test Case...249
Table 62 Generate Weekly Project Report Test Case...251
Table 63 Successful Update Project Status Test Case ...252
Table 64 Unsuccessful Update Project Status Test Case ...254
xvi
Table 66 View Transaction Log Details Test Case...256
Table 67 Resend Transaction Test Case ...257
Table 68 Successful Update Project Status (SMS) Test Case...258
Table 69 Unsuccessful Update Project Status (SMS) Test Case ...259
Table 70 Successful Request Project Status Test Case ...262
Table 71 Unsuccessful Request Project Status Test Case...263
Table 72 Successful Request Project Report Summary Test Case ...264
xvii
LIST OF FIGURES
Figure 1 Work Breakdown Structure ...7
Figure 2 Gantt Chart...15
Figure 3 Cash Flows...19
Figure 4 Sample Flowchart ...21
Figure 5 Sample One-to-Many (Mandatory) ERD ...22
Figure 6 Sample DFD ...24
Figure 7 Sample Use Case Diagram ...26
Figure 8 Sample Class Diagram...28
Figure 9 Sample Sequence Diagram...29
Figure 10 PT XYZ Project Management Office Organization Chart ...49
Figure 11 Sample Business Performance Report ...51
Figure 12 Sample Implementation Performance Report...52
Figure 13 Sample Project Remarks ...53
Figure 14 FHD - Current System...54
Figure 15 Context Diagram - Current System ...56
Figure 16 DFD Current System - Level 0 ...57
Figure 17 DFD Current System Process 1 – Level 1 ...58
Figure 18 DFD Current System Process 1.1 – Level 2 ...59
Figure 19 DFD Current System Process 1.2 – Level 2 ...60
Figure 20 DFD Current System Process 2 – Level 1 ...61
Figure 21 DFD Current System Process 2.1 – Level 2 ...62
xviii
Figure 23 Current Data Retrieval Flowchart (Project Sponsor)...66
Figure 24 Current Project Status Update Flowchart ...68
Figure 25 Current Weekly Report Generation Flowchart ...70
Figure 26 FHD – New System...77
Figure 27 Context Diagram - New System...86
Figure 28 DFD New System - Level 0...87
Figure 29 DFD New System Process 1 - Level 1 ...88
Figure 30 DFD New System Process 1.1 - Level 2 ...89
Figure 31 DFD New System Process 1.2 - Level 2 ...90
Figure 32 DFD New System Process 1.3 - Level 2 ...91
Figure 33 DFD New System Process 1.4 - Level 2 ...92
Figure 34 DFD New System Process 1.5 - Level 2 ...93
Figure 35 DFD New System Process 2 - Level 1 ...96
Figure 36 DFD New System Process 2.1 - Level 2 ...97
Figure 37 DFD New System Process 2.2 - Level 2 ...98
Figure 38 DFD New System Process 2.3 - Level 2 ...99
Figure 39 DFD New System Process 3 - Level 1 ...102
Figure 40 DFD New System Process 3.1 - Level 2 ...103
Figure 41 DFD New System Process 3.2 - Level 2 ...104
Figure 42 New Project Status Update Flowchart...106
Figure 43 New Project Status Update Flowchart (Contd.)...107
Figure 44 New Weekly Project Report Generation Flowchart ...109
Figure 45 New Weekly Project Report Generation Flowchart (Contd.)...110
xix
Figure 47 New Project Status Request Flowchart (Contd.) ...114
Figure 48 Entity Relationship Diagram ...124
Figure 49 Data Update Subsystem Use Case Diagram...127
Figure 50 Data Retrieval Subsystem Use Case Diagram...136
Figure 51 Transaction Log Subsystem Use Case Diagram...142
Figure 52 Weekly Project Report Generation Subsystem Use Case Diagram...146
Figure 53 Weekly Business Performance Report Generation Subsystem Use Case Diagram...153
Figure 54 Weekly Implementation Performance Report Generation Subsystem ...157
Figure 55 Weekly Project Report Summary Generation Subsystem Use Case Diagram...161
Figure 56 Project Record Management Subsystem Use Case Diagram ...165
Figure 57 Class Diagram...170
Figure 58 Data Update Subsystem Sequence Diagram...171
Figure 59 Data Update Subsystem Sequence Diagram (Contd.) ...172
Figure 60 Data Retrieval Subsystem (Project Status Request) Sequence Diagram...173
Figure 61 Data Retrieval Subsystem (Project Status Request) Sequence Diagram (Contd.) ...174
Figure 62 Data Retrieval Subsystem (Project Report Summary Request) Sequence Diagram...175
Figure 63 Data Retrieval Subsystem (Project Report Summary Request) Sequence Diagram (Contd.) ...176
Figure 64 Transaction Log Subsystem Sequence Diagram ...177
xx
Figure 66 Business Performance Report Generation Subsystem Sequence Diagram ...179
Figure 67 Implementation Performance Report Generation Subsystem Sequence Diagram...180
Figure 68 Weekly Project Report Generation Subsystem (Project Status Update) Sequence Diagram...181
Figure 69 Weekly Project Report Summary Generation Subsystem Sequence Diagram...182
Figure 70 Stakeholders Information Subsystem Sequence Diagram...183
Figure 71 Stakeholders Information Subsystem Sequence Diagram (Contd.)...184
Figure 72 Project Information Subsystem Sequence Diagram ...185
Figure 73 Project Information Subsystem Sequence Diagram (Contd.) ...186
Figure 74 Menu Structure ...187
Figure 75 Login Page ...189
Figure 76 Login Error 1 ...189
Figure 77 Login Error 2 ...190
Figure 78 Report Page ...191
Figure 79 Search Report Page ...192
Figure 80 Search Report Error 1 ...192
Figure 81 Search Report Error 2 ...193
Figure 82 Project Page ...193
Figure 83 Search Project Error ...194
Figure 84 Add New Project Page ...195
Figure 85 Add Project Success...196
xxi
Figure 87 Change Project Information Page ...197
Figure 88 Change Project Confirmation ...197
Figure 89 Stakeholders Page ...198
Figure 90 Add New Sponsor Page ...199
Figure 91 Add New Employee Page ...199
Figure 92 Change Stakeholders Information ...200
Figure 93 Log Out Warning ...201
Figure 94 Transaction Log Page ...201
Figure 95 View Project Information Page ...202
Figure 96 Delete Confirmation ...202
Figure 97 View Stakeholders Information Page ...203
Figure 98 Weekly Project Report ...204
Figure 99 View Project Status ...205
Figure 100 Search Report...206
Figure 101 Weekly Project Report Summary...207
Figure 102 Previous Year Project Report ...208
Figure 103 Received Transaction Details Page ...209
Figure 104 Sent Transaction Details Page ...209
Figure 105 Failed Transaction Details Page ...210
Figure 106 Resend Transaction Confirmation...210
Figure 107 New System Architecture Design...211