ESTIMATION – CASE estimate at this point,” Carl said.
“that’s not going to work,”Bill said. “I was hoping you’d say 3 or 4 months. We absolutely need to bring that system in within 6 months. Can you do it in 6?”
“I’m not sure,”Carl said honestly.”I’d have to look the project more carefully, but I can try to find a way to get it done in 6.”
“Treat 6 months as a goal then, “Bill said. “That’s what it’s got to be, anyway.” The rest of committee agreed.
ESTIMATION – CASE STUDY
STUDI KASUS (lanjutan):
Carl’s team made steady progress, but requirements analysis took longer than they had hoped. “They were now almost 4 months into what was supposed to be a 6-month project. “there’s no way we can do the rest of the work we have to do in 3 months, “he told Bill. He told Bill he needed a 2-month schedule slip and rescheduled the project to take 8-months.
A few weeks later, Carl realized that design wasn’t proceeding as quickly as he had hoped either. “Implement the parts you can do easily,” he told the team. “We’ll worry about the rest of the parts when get to them.”
Carl met with the oversight committee. “We’re now 7 months into our 8-month project. Detailed design is almost complete, and we’re making good progress. But we can’t complete the project in 8 months.” Carl announced his second schedule slip, this time to 10 months. Bill grumbled and asked Carl to look for ways to bring the schedule back to around 8 months.
ESTIMATION – CASE STUDY
STUDI KASUS (lanjutan):
Coding proceeded fairly well, but a few areas needed redesign and reimplementation. The team hadn’t coordinated design details in those areas well, and some of their implementation conflicted. At the 11-month oversight committee meeting, Carl announced the fourth schedule slip – to 13 months . Bill became livid, “Do you have any idea what you’re doing? He yelled. “You obviously don’t have any idea! You obviously don’t have any idea when the project is going to be done! I’ll tell you when it’s going to be done! It’s going to be done by the 13-month mark, or you’re going to be out of a job! I’m tired of being jerked around by you software guys! You and your team are going to work 60 hours a week until you deliver! Carl felt his blood pressure rise, especially since Bill had backed him into an unrealistic schedule in the first place. But he knew that with four schedule slips under his belt, he had no credibility left. He felt that he had to knuckle under to mandatory overtime or he would lose his job.
ESTIMATION – CASE STUDY
STUDI KASUS (PERTANYAAN):
1.Apa masalah utama yang ada pada kasus di atas?
2.Identifikasi kelemahan-kelemahan manajemen (Perencanaan, Pengorganisasian, Kepemimpinan, Pengendalian) yang timbul pada saat Carl menangani proyek tersebut!
ESTIMATION – FUZZYNESS
ESTIMASI ADALAH PEKERJAAN YANG SULIT, KARENA MENGANDUNG KETIDAKPASTIAN.
KITA HARUS MEMASTIKAN BAHWA SELURUH LEVEL MANAJEMEN TELAH MENGETAHUI DENGAN PASTI MENGENAI PROYEK YANG AKAN KITA LAKSANAKAN.
"A whole year to build
a house here? No problem
"Good. Let's get
ESTIMATION – SAY
“It is the mark of an
instructed mind
to rest satisfied
with the degree of
precision •which the
nature of a subject
admits, and not to
seek exactness when
only an approximation
of the truth
is possible...”
ESTIMATION – REFINEMENT
PENGEMBANGAN SOFTWARE ADALAH PROSES PENGHALUSAN • TINGKAT AKURASI YANG BIASA DAPAT DITERIMA OLEH PIHAK MANAJEMEN ADALAH 10% DARI ESTIMASI
ANGGARAN.
ESTIMATION – REFINEMENT
BEBERAPA HAL YANG HARUS DIPERHATIKAN DALAM PROSES PENGHALUSAN
• APAKAH PELANGGAN BUTUH FUNGSI “X” ?
• APAKAH HARGA FUNGSI YANG DIBUTUHKAN MURAH ATAU MAHAL ?
• BILA SEKARANG DIBUTUHKAN, APAKAH NANTINYA MAU YANG MAHAL UNTUK VERSI BERIKUTNYA?
• BAGAIMANA FUNGSI TERSEBUT DIRANCANG ?
• SAMPAI TINGKATAN MANA KUALITAS FUNGSI TERSEBUT ? • BERAPA LAMA UNTUK MEN-DEBUG DAN MENGKOREKSI ERROR ?
ESTIMATION – GRAPH
INITIAL PRODUCT DEFINITION
APPROVED PRODUCT DEFINITION
REQUIREMENT SPECIFICATION
PRODUCT DESIGN SPECIFICATION
DETAIL DESIGN SPECIFICATION
ESTIMATION – CONTROL
HUBUNGAN ESTIMASI DENGAN KENDALI
• KEBANYAKAN PELANGGAN PERANGKAT LUNAK AWALNYA MEMBUTUHKAN SESUATU LEBIH DARI YANG SEBENARNYA
MEREKA BUTUHKAN.
ESTIMATION – COOPERATION
KERJASAMA
• PERLU DISAMPAIKAN KEPADA PEMAKAI DI TAHAP MANA SAJA PENGEMBANG DAPAT MELAKUKAN ESTIMASI
DENGAN CUKUP AKURAT.
• PEMAKAI PERLU DIBERITAHUKAN TINDAKAN / KEGIATAN SELANJUTNYA
• STRATEGI YANG AKAN DIPAKAI UNTUK MELAKSANAKAN KEGIATAN TERSEBUT.
• BILA ADA PERUBAHAN DARI KEBUTUHAN, RANCANGAN AWAL RINCI, TERMASUK PERUBAHAN ANGGARAN.
ESTIMATION – REALITY APPROACH
DEKATKAN ESTIMASI DENGAN KENYATAAN
• BILA PEMAKAI INGIN MEMPERCEPAT, HINDARKAN PENGEMBANG DARI KESALAHAN ESTIMASI YANG
TERLALU RENDAH ATAU MEMBERIKAN ESTIMASI YANG MENYESATKAN.
• TARGET PIMPINAN PROYEK ADALAH MENCOBA
MELAKUKAN ESTIMASI YANG TEPAT DAN SESUAI DENGAN
ESTIMATION – ACTUAL VS ESTIMATION
Estimated Schedule
ESTIMATION – POINT HAL YANG HARUS DIPERHATIKAN DALAM MELAKUKAN ESTIMASI
• TIDAK ADA YANG DAPAT MENENTUKAN DENGAN TEPAT BERAPA BIAYA YANG AKAN DIKELUARKAN KECUALI DAPAT TEPAT
MENGETAHUI APA YANG DIKEHENDAKI.
• BILA INGIN BUAT ANGGARAN, BUATLAH KARAKTERISTIK PRODUK YANG LENTUR
• PROSES PENGEMBANGAN ADALAH PENGHALUSAN BERTAHAP • ESTIMASI DAPAT DIPERHALUS SEIRING DENGAN PELAKSANAAN PROYEK
• BEDAKAN PENGERTIAN AKURASI DENGAN PRESISI AKURASI : SEBERAPA DEKAT DENGAN TETAPAN TERTENTU
PRESISI : SEBERAPA SIGNIFIKAN ANGKA DIGIT SEBUAH PENGUKURAN
PADA ESTIMASI PERANGKAT LUNAK, KESALAHAN PRESISI MERUPAKAN MUSUH DARI AKURASI.
ESTIMATION – PROCESS
PROSES ESTIMASI
PROSES UNTUK MENCAPAI KEAKURATAN DALAM MENJADWAL PENGEMBANGAN :
1. ESTIMASIKAN UKURAN DARI PRODUK (SEBERAPA BESAR FUNGSI YANG HARUS ADA)
2. ESTIMASIKAN EFFORTS (YANG PERNAH DILAKUKAN) 3. ESTIMASI JADWAL
4. SAJIKAN ESTIMASI YANG DIDAPAT DALAM RUANG LINGKUP
ESTIMATION – SIZE
MENGHITUNG ESTIMASI
DAPAT DILAKUKAN MELALUI BEBERAPA CARA :
1. MENGGUNAKAN PENDEKATAN ALGORITMA (BESARNYA PROGRAM ATAU FUNGSI YANG AKAN DIBUAT)
2. BERDASARKAN DESKRIPSI PROGRAM (SCREENS, DIALOGS, FILES, DATABASE TABLES)
ESTIMATION – FUNCTION POINT
ESTIMASI MENGGUNAKAN FUNCTION POINT • DIGUNAKAN PADA AWAL PROYEK
• LEBIH MUDAH MENDASARKAN DARI SPESIFIKASI KEBUTUHAN • JUMLAH FUNCTION POINT SEBUAH PROGRAM DILIHAT DARI JUMLAH DAN KOMPLEKSITAS SETIAP ITEM BERIKUT :
1. • INPUT 2. • OUTPUT 3. • INQUIRIES
4. • LOGICAL INTERNAL FILES 5. • EXTERNAL INTERFACE FILES
ESTIMATION – TIPS TIPS UNTUK MEMBUAT ESTIMASI
• AVOID OFF-THE-CUFF ESTIMATES.
• ALLOW TIME FOR THE ESTIMATE, AND PLAN IT.
• USE DATA FROM PREVIOUS PROJECTS.
• USE DEVELOPER-BASED ESTIMATES
• ESTIMATE BY WALK-THROUGH
• ESTIMATE BY CATEGORIES
• ESTIMATE AT A LOW LEVEL OF DETAIL
• DON'T OMIT COMMON TASKS
• USE SOFTWARE ESTIMATION TOOLS
• USE SEVERAL DIFFERENT ESTIMATION TECHNIQUES, AND COMPARE THE RESULTS.