ANALISA HARGA SATUAN PEKERJAAN MAKASAR
Kota : Makasar
No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)
I PEKERJAAN PERSIAPAN
1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M
a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
b Semen PC (abu-abu) 0.05 sak 42,000.00 2,100.00
c Seng gelombang 1.20 sak 53,800.00 64,560.00
d Pasir beton 0.01 m3 72,000.00 360.00
e Split (batu pecah) 0.01 m3 210,000.00 1,890.00
f Balok kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
g Paku 5 - 10 cm 0.06 kg 14,700.00 882.00
h Meni Besi 0.45 kg 20,000.00 9,000.00
i Tukang kayu 0.20 org 55,000.00 11,000.00
j Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 453,792.00
Dibulatkan 453,790.00
2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M
a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00
b Semen PC (abu-abu) 0.04 sak 42,000.00 1,680.00
c Kawat Duri 2.50 kg 166,000.00 415,000.00
d Pasir beton 0.01 m3 72,000.00 360.00
e Split (batu pecah) 0.01 m3 210,000.00 1,890.00
f Paku 5 - 10 cm 0.06 kg 14,700.00 882.00
g Tukang kayu 0.20 org 55,000.00 11,000.00
h Pembantu tukang 0.30 org 40,000.00 12,000.00
Jumlah 622,812.00
Dibulatkan 622,810.00
3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Paku 5 - 10 cm 0.02 kg 14,700.00 294.00
c Papan papan kayu terentang 2/20 - m3 1,220,000.00 4,880.00
d Tukang kayu 0.10 org 55,000.00 5,500.00
e Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 86,674.00
Dibulatkan 86,670.00
4 1 M2 PEMBUATAN KANTOR DIREKSI
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Papan kayu terentang 0.18 m3 1,220,000.00 219,600.00
c Paku semua ukuran 0.85 kg 14,700.00 12,495.00
d Besi strip 1.10 kg 17,500.00 19,250.00 e Semen PC (abu-abu) 35.00 kg 42,000.00 1,470,000.00 f Pasir pasang 0.15 m3 68,000.00 10,200.00 g Pasir beton 0.10 m3 72,000.00 7,200.00 h Split (batu pecah) 0.15 m3 210,000.00 31,500.00
i Bata merah 30.00 bh 600.00 18,000.00 j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00 k Seng Plat BJLS 32 1.00 m2 33,000.00 33,000.00 l Kawat harmonika 2.00 m2 22,000.00 44,000.00 m Kaca polos 3 mm 0.08 m2 63,000.00 5,040.00 n Kunci tanam standart 0.15 bh 55,000.00 8,250.00
o Triplek 120 x 240 x 0,4 cm 0.06 lbr 51,000.00 3,060.00
p Tukang kayu 2.00 org 55,000.00 110,000.00
q Tukang batu 1.00 org 55,000.00 55,000.00
r Pembantu tukang 2.00 org 40,000.00 80,000.00
Jumlah 2,271,315.00
Dibulatkan 2,271,310.00
5 1 M2 PEMBUATAN GUDANG PROYEK
a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00
b Papan kayu terentang 0.10 m3 1,220,000.00 122,000.00
c Paku 0.30 kg 14,700.00 4,410.00
d Semen PC (abu-abu) 0.21 sak 42,000.00 8,820.00
e Pasir beton 0.03 m3 72,000.00 2,160.00
f Split (batu pecah) 0.05 m3 210,000.00 10,500.00
g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00
h Tukang kayu 1.00 org 55,000.00 55,000.00
i Pembantu tukang 1.00 org 40,000.00 40,000.00
Jumlah 387,610.00
Dibulatkan 387,610.00
6 1 M2 MEMBERSIHKAN LOKASI ROYEK
a Pembantu tukang 0.10 org 40,000.00 4,000.00
Jumlah 4,000.00 Dibulatkan 4,000.00 7 1 M2 MEMBERSIHKAN PUING-PUING a Pembantu tukang 0.20 org 40,000.00 8,000.00
Jumlah 8,000.00
Dibulatkan 8,000.00
8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN
a Pembantu tukang 2.00 org 40,000.00 80,000.00
Jumlah 80,000.00
Dibulatkan 80,000.00
9 1M2 PEMBUATAN JALAN MASUK PROYEK
a Batu belah 15/20 0.10 m3 72,000.00 7,200.00 b Koral 5/7 ( sirtu ) 0.05 m3 122,000.00 6,100.00 c Pasir urug 0.01 m3 66,000.00 660.00 d Pembantu tukang 1.00 org 40,000.00 40,000.00
Jumlah 53,960.00
Dibulatkan 53,900.00
10 1 M3 PEMBONGKARAN BETON
a Pembantu tukang 6.20 org 40,000.00 248,000.00
Jumlah 248,000.00
Dibulatkan 248,000.00
11 1 M3 PEMBONGKARAN DINDING BATA
a Pembantu tukang 4.60 org 40,000.00 184,000.00
Jumlah 184,000.00
Dibulatkan 184,000.00
12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK
a Papan kayu borneo 0.02 m3 4,000,000.00 80,000.00
b Balok kayu borneo 5/7 0.02 m3 3,600,000.00 72,000.00
c Pasir beton 0.08 m3 72,000.00 5,760.00
d Split (batu pecah) 0.15 m3 210,000.00 31,500.00
e Semen abu - abu 0.50 sak 42,000.00 21,000.00
f Tukang kayu 0.13 org 55,000.00 7,150.00
g Pembantu tukang 0.38 org 40,000.00 15,200.00
Jumlah 232,610.00 Dibulatkan 232,600.00 II PEKERJAAN TANAH
1 1 M3 GALIAN TANAH SEDALAM 1 M
a Pembantu tukang 0.40 org 40,000.00 16,000.00 b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 16,900.00
Dibulatkan 16,900.00
2 1 M3 GALIAN TANAH SEDALAM 2 M
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 22,100.00
Dibulatkan 22,100.00
3 1 M3 GALIAN TANAH SEDALAM 3 M
a Pembantu tukang 0.74 org 40,000.00 29,600.00 b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 30,500.00
Dibulatkan 30,500.00
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M
a Pembantu tukang 0.45 org 40,000.00 18,000.00 b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 18,900.00
Dibulatkan 18,900.00
5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM
a Pembantu tukang 0.05 org 40,000.00 1,000.00 b Tukang gali 0.02 org 45,000.00 675.00
Jumlah 1,675.00
Dibulatkan 1,670.00
6 1 M3 PEMBUANGAN TANAH SEJAUH 150 M
a Pembantu tukang 0.42 org 40,000.00 16,800.00 b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 17,700.00
Dibulatkan 17,700.00
7 1 M3 URUGAN TANAH KEMBALI
a Pembantu tukang 0.19 org 40,000.00 7,600.00 b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 8,500.00
Dibulatkan 8,500.00
8 1 M3 PEMADATAN TANAH
b Tukang gali 0.02 org 45,000.00 900.00
Jumlah 20,900.00
Dibulatkan 20,900.00
9 1 M3 URUGAN PASIR
a Pasir urug 1.20 m3 66,000.00 79,200.00 b Pembantu tukang 0.30 org 40,000.00 12,000.00 c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 92,100.00
Dibulatkan 92,100.00
10 1 M3 URUGAN TANAH
a Tanah urug 1.20 m3 70,000.00 84,000.00 b Pembantu tukang 0.30 org 40,000.00 12,000.00 c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 96,900.00
Dibulatkan 96,900.00
11 1 M3 URUGAN SIRTU
a Sirtu ( koral ) 1.20 m3 122,000.00 146,400.00 b Pembantu tukang 0.25 org 40,000.00 10,000.00 c Tukang gali 0.02 org 45,000.00 900.00
Jumlah 157,300.00
Dibulatkan 157,300.00
III PEKERJAAN PONDASI
1 1 M3 PASANG PONDASI BT KALI , 1 Pc : 3 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00 c Pasir pasang 0.49 m3 68,000.00 32,980.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00
e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 374,860.00
Dibulatkan 374,860.00
2 1 M3 PASANG PONDASI BT KALI , 1 Pc : 4 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 3.26 sak 42,000.00 136,920.00 c Pasir pasang 0.52 m3 68,000.00 35,360.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00 e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 344,480.00
Dibulatkan 344,480.00
3 1 M3 PASANG PONDASI BT KALI , 1 Pc : 5 Ps
a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 2.72 sak 42,000.00 114,240.00 c Pasir pasang 0.54 m3 68,000.00 36,992.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00 e Tukang batu 0.60 org 55,000.00 33,000.00
Jumlah 323,432.00
Dibulatkan 323,430.00
4 1 M3 PASANG PONDASI BATU KOSONG ( AANSTAMPING )
a Batu belah 1.20 m3 72,000.00 86,400.00 b Pasir urug 0.30 m3 66,000.00 19,800.00 c Pembantu tukang 0.78 org 40,000.00 31,200.00 d Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 158,850.00
Dibulatkan 158,800.00
5 1 M3 MEMBUAT BETON BERTULANG UNTUK PONDASI 1 Pc : 2 Ps : 3 Kr
a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00 b Pasir beton 0.54 m3 72,000.00 38,880.00 c Split (batu pecah) 0.81 m3 210,000.00 170,100.00
d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 590,470.00
Dibulatkan 590,400.00
6 1 Kg PENULANGAN BETON PONDASI
a Besi beton polos 1.05 kg 8,800.00 9,240.00 b Kawat beton 0.02 kg 19,000.00 285.00 c Pembantu tukang 0.01 org 40,000.00 280.00 d Tukang besi 0.01 org 55,000.00 385.00
Jumlah 10,190.00
Dibulatkan 10,100.00
7 1 M2 PEKERJAAN BEKISTING UNTUK PONDASI
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.30 kg 1,925.00 577.50 c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang kayu 0.26 org 55,000.00 14,300.00
Jumlah 76,677.50
Dibulatkan 76,600.00
8 1 M3 PASANG PONDASI CYCLOOP (60 %BETON : 40% BATU KALI)
a Besi beton polos 50.00 kg 8,800.00 440,000.00 b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00 c Pasir beton 0.32 m3 72,000.00 23,040.00 d Split (batu pecah) 0.49 m3 210,000.00 102,900.00 e Kawat beton 0.80 kg 19,000.00 15,200.00 f Batu belah 0.40 m3 72,000.00 28,800.00 g Pembantu tukang 2.00 org 40,000.00 80,000.00 h Tukang batu 0.85 org 55,000.00 46,750.00
Jumlah 906,370.00
9 1 M3 PASANG PONDASI SUMURAN DIAMETER 100 cm
a Batu belah 0.45 m3 72,000.00 32,400.00 b Semen PC (abu-abu) 5.60 sak 42,000.00 235,200.00 c Pasir beton 0.45 m3 72,000.00 32,400.00 d Split (batu pecah) 0.67 m3 210,000.00 140,700.00 e Pembantu tukang 2.38 org 40,000.00 95,200.00 f Tukang batu 0.30 org 55,000.00 16,500.00
Jumlah 552,400.00
Dibulatkan 552,400.00
10 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm
a Pasir beton 0.10 m3 72,000.00 7,200.00 b Split (batu pecah) 0.15 m3 210,000.00 31,500.00 c Semen PC (abu-abu) 1.21 sak 42,000.00 50,820.00 d Besi beton polos 45.00 kg 8,800.00 396,000.00 e Kawat beton 0.90 kg 19,000.00 17,100.00 f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 115,200.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00 j Plamir tembok 0.24 kg 27,000.00 6,480.00 k Pembantu tukang 1.00 org 40,000.00 40,000.00 l Tukang batu 0.67 org 55,000.00 36,850.00
Jumlah 743,814.00
Dibulatkan 743,800.00
11 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM
a Pasir beton 0.08 m3 72,000.00 5,760.00 b Split (batu pecah) 0.13 m3 210,000.00 27,300.00 c Semen PC (abu-abu) 0.98 sak 42,000.00 41,160.00 d Besi beton polos 34.50 kg 8,800.00 303,600.00 e Kawat beton 0.70 kg 19,000.00 13,300.00
f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 108,000.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00 j Plamir tembok 0.20 kg 27,000.00 5,400.00 k Pembantu tukang 0.80 org 40,000.00 32,000.00 l Tukang batu 0.50 org 55,000.00 27,500.00
Jumlah 606,684.00
Dibulatkan 606,600.00
12 1 M3 MEMBUAT PONDASI TIANG PANCANG UKURAN 25 X 25
a Pasir beton 0.06 m3 72,000.00 4,320.00 b Split (batu pecah) 0.11 m3 210,000.00 23,100.00 c Semen PC (abu-abu) 0.82 sak 42,000.00 34,440.00 d Besi beton polos 34.50 kg 8,800.00 303,600.00 e Kawat beton 0.60 kg 19,000.00 11,400.00 f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 108,000.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.11 kg 14,700.00 1,617.00 i Pelumas begisting (oli/minyak) 0.08 Ltr 10,000.00 800.00 j Plamir tembok 0.20 kg 27,000.00 5,400.00 k Pembantu tukang 0.80 org 40,000.00 32,000.00 l Tukang batu 0.50 org 55,000.00 27,500.00
Jumlah 592,177.00
Dibulatkan 592,100.00
13 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 Ltr 10,000.00 4,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 3.90 org 40,000.00 156,000.00 j Tukang batu 0.35 org 55,000.00 19,250.00 k Tukang kayu 1.04 org 55,000.00 57,200.00 l Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 2,175,560.00
Dibulatkan 2,175,500.00
14 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos Polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.00 org 40,000.00 160,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,397,360.00
Dibulatkan 2,397,300.00
15 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos Polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.10 kg 19,000.00 39,900.00
f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 3.90 org 40,000.00 156,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,170,510.00
Dibulatkan 2,170,500.00
16 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )
a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.00 org 40,000.00 160,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00
Jumlah 2,397,360.00
Dibulatkan 2,397,300.00
IV PEKERJAAN BETON NON STRUKTUR DAN BETON
STRUKTUR
1 1 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt
a Semen PC (abu-abu) 4.36 sak 42,000.00 183,120.00 b Pasir beton 0.52 m3 72,000.00 37,440.00 c Split (batu pecah) 0.87 m3 210,000.00 182,700.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 502,510.00
Dibulatkan 502,500.00
2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt
a Semen PC (abu-abu) 4.64 sak 42,000.00 194,880.00 b Pasir beton 0.52 m3 72,000.00 37,440.00 c Split (batu pecah) 0.78 m3 210,000.00 163,800.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 495,370.00
Dibulatkan 495,300.00
3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt
a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00 b Pasir beton 0.54 m3 72,000.00 38,880.00 c Split (batu pecah) 0.81 m3 210,000.00 170,100.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 590,470.00
Dibulatkan 590,400.00
4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225
a Semen PC (abu-abu) 7.76 sak 42,000.00 325,920.00 b Pasir beton 0.65 m3 72,000.00 46,800.00 c Split (batu pecah) 0.65 m3 210,000.00 136,500.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 608,470.00
Dibulatkan 608,400.00
5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275
a Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 b Pasir beton 0.55 m3 72,000.00 39,600.00 c Split (batu pecah) 0.70 m3 210,000.00 147,000.00 d Pembantu tukang 2.02 org 40,000.00 80,800.00 e Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 625,400.00
Dibulatkan 625,400.00
B PEKERJAAN PEMBESIAN
1 1 KG PENULANGAN BETON/BESI BETON POLOS
a Besi beton polos 1.05 kg 8,800.00 9,240.00 b Kawat beton 0.02 kg 19,000.00 380.00 c Pembantu tukang 0.01 org 40,000.00 400.00 d Tukang besi 0.01 org 55,000.00 550.00
Jumlah 10,570.00
Dibulatkan 10,500.00
2 1 KG PENULANGAN BETON/BESI BETON ULIR
a Besi Beton Ulir 1.10 kg 16,300.00 17,930.00 b Kawat beton 0.02 kg 19,000.00 285.00 c Pembantu tukang 0.01 org 40,000.00 400.00 d Tukang besi 0.02 org 55,000.00 1,100.00
Jumlah 19,715.00
Dibulatkan 19,700.00
C PEKERJAAN BEGISTING
1 1 M2 PASANG BEKISTING UNTUK SLOOF
a Papan kayu terentang 0.05 m3 1,220,000.00 54,900.00 b Paku 5 - 12 cm 0.30 kg 14,700.00 4,410.00 c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00
d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang kayu 0.26 org 55,000.00 14,300.00
Jumlah 86,610.00
Dibulatkan 86,600.00
2 1 M2 PASANG BEKISTING UNTUK KOLOM
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.30 org 40,000.00 12,000.00 g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 267,580.00
Dibulatkan 267,500.00
3 1M2 PASANG BEKISTING UNTUK BALOK
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 268,380.00
Dibulatkan 268,300.00
4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI
a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00
f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 268,380.00
Dibulatkan 268,300.00
5 1 M2 PASANG BEKISTING UNTUK TANGGA
a Papan kayu terentang 0.03 m3 1,220,000.00 36,600.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.15 Ltr 10,000.00 1,500.00 d Balok kayu borneo 0.02 m3 3,600,000.00 72,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00
Jumlah 183,680.00
Dibulatkan 183,600.00
D PEKERJAAN BETON BERTULANG
1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00 b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.50 org 40,000.00 180,000.00 j Tukang batu 0.35 org 55,000.00 19,250.00 k Tukang kayu 1.56 org 55,000.00 85,800.00 l Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 3,081,090.00
2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,280,190.00
Dibulatkan 4,280,100.00
3 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 kg BESI + BEKISTING)
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00
m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,500,190.00
Dibulatkan 4,500,100.00
4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 160.00 kg 8,800.00 1,408,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,588,190.00
Dibulatkan 4,588,100.00
5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 175.00 kg 8,800.00 1,540,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00
i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,720,190.00
Dibulatkan 4,720,100.00
6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 4,940,190.00
Dibulatkan 4,940,100.00
7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 250.00 kg 8,800.00 2,200,000.00
e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 5,380,190.00
Dibulatkan 5,380,100.00
8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )
a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 300.00 kg 8,800.00 2,640,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00
Jumlah 5,820,190.00
Dibulatkan 5,820,100.00
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00 l Pembantu tukang 5.80 org 40,000.00 232,000.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 3,529,330.00
Dibulatkan 3,529,300.00
10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 10,000.00 22,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 10,000.00 7,800.00 i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00 l Pembantu tukang 5.80 org 40,000.00 232,000.00
m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.05 org 55,000.00 57,750.00
Jumlah 3,573,080.00
Dibulatkan 3,573,000.00
11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00
h Split (batu pecah) 0.78 m3 140,000.00 109200
i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 18,000.00 288,000.00 l Pembantu tukang 5.96 org 27,500.00 163,900.00 m Tukang batu 0.35 org 42,000.00 14,700.00 n Tukang kayu 2.80 org 42,000.00 117,600.00 o Tukang besi 1.40 org 42,000.00 58,800.00
Jumlah 4,184,980.00
Dibulatkan 4,184,900.00
12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)
a Papan kayu terentang 0.32 m3 1,750,000.00 560,000.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 225.00 kg 8,750.00 1,968,750.00 e Kawat beton 4.00 kg 15,000.00 60,000.00 f Semen PC (abu-abu) 6.45 sak 49,500.00 319,275.00
g Pasir beton 0.52 m3 140,000.00 72,800.00 h Split (batu pecah) 0.78 m3 140,000.00 109,200.00 i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00 l Pembantu tukang 5.96 org 40,000.00 238,400.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,631,715.00
Dibulatkan 4,631,700.00
13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )
a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 250.00 kg 8,800.00 2,200,000.00 e Kawat beton 6.00 kg 19,000.00 114,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.14 m3 3,600,000.00 504,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00 l Pembantu tukang 5.96 org 40,000.00 238,400.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,662,230.00
Dibulatkan 4,662,200.00
a Papan kayu terentang 0.25 m3 1,220,000.00 305,000.00 b Paku 5 - 12 cm 3.00 kg 14,700.00 44,100.00 c Pelumas begisting (oli/minyak) 1.20 Ltr 10,000.00 12,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 2.50 lbr 105,000.00 262,500.00 k Pembantu tukang 5.60 org 40,000.00 224,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 2.30 org 55,000.00 126,500.00 n Tukang besi 1.40 org 55,000.00 77,000.00
Jumlah 4,439,490.00
Dibulatkan 4,439,400.00
15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 10.00 m2 268,300.00 2,683,000.00 c Besi Beton rakit 100.00 kg 8,800.00 880,000.00
Jumlah 4,153,400.00
Dibulatkan 4,153,400.00
16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00 c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00
Jumlah 4,032,839.00
Dibulatkan 4,032,800.00
17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00
b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00 c Besi Beton rakit 125.00 kg 10,500.00 1,312,500.00
Jumlah 4,137,839.00
Dibulatkan 4,137,800.00
18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 6.67 m2 268,300.00 1,789,561.00 c Besi Beton rakit 100.00 kg 10,500.00 1,050,000.00
Jumlah 3,429,961.00
Dibulatkan 3,429,900.00
19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )
a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 7.50 m2 268,300.00 2,012,250.00 c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00
Jumlah 3,810,150.00
Dibulatkan 3,810,100.00
20 1M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225
a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00 b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00 d Besi beton polos 175.00 kg 8,800.00 1,540,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.85 org 40,000.00 194,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.75 org 55,000.00 96,250.00 l Tukang besi 1.45 org 55,000.00 79,750.00
Dibulatkan 2,891,000.00
V PEKERJAAN DINDING
1 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps
a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.65 sak 42,000.00 27,300.00 c Pasir pasang 0.09 m3 68,000.00 6,120.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 154,420.00
Dibulatkan 154,400.00
2 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.55 sak 42,000.00 23,100.00 c Pasir pasang 0.09 m3 68,000.00 6,120.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 150,220.00
Dibulatkan 150,200.00
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.45 sak 42,000.00 18,900.00 c Pasir pasang 0.10 m3 68,000.00 6,800.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 146,700.00
Dibulatkan 146,700.00
4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps
b Semen PC (abu-abu) 0.29 sak 42,000.00 12,180.00 c Pasir pasang 0.04 m3 68,000.00 2,720.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 75,200.00
Dibulatkan 75,200.00
5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps
a Bata merah 70.00 bh 600.00 42,000.00 b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.05 m3 68,000.00 3,400.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 74,200.00
Dibulatkan 74,200.00
6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps
a Bata merah 70.00 bh 600.00 42,000.00 b Semen PC (abu-abu) 0.22 sak 42,000.00 9,240.00 c Pasir pasang 0.05 m3 68,000.00 3,400.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 72,940.00
Dibulatkan 72,900.00
7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG
a Rooster / Terawang ukuran 12 x 11 x 24 37.00 bh 4,100.00 151,700.00 b Semen PC (abu-abu) 0.27 sak 42,000.00 11,340.00 c Pasir pasang 0.04 m3 68,000.00 2,720.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 183,260.00
8 1 M2 PASANG DINDING GLASSBLOCK
a Glassblock ukuran 18 x 18 cm 30.00 bh 20,000.00 600,000.00 b Semen putih 0.27 sak 12,700.00 3,429.00 c Pembantu tukang 0.30 org 40,000.00 12,000.00 d Tukang batu 0.10 org 55,000.00 5,500.00
Jumlah 620,929.00
Dibulatkan 620,900.00
9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps
a Bataco putih 15.00 bh 4,200.00 63,000.00 b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.03 m3 68,000.00 2,040.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 95,790.00
Dibulatkan 95,700.00
10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps
a Bataco press semen 15.00 bh 4,300.00 64,500.00 b Semen PC (abu-abu) 0.20 sak 42,000.00 8,400.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 94,510.00
Dibulatkan 94,500.00
11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON ).
a Bata Ringan ( hebel/celcon ) 8.00 bh 3,800.00 30,400.00 b Semen Instan 11.45 kg 2,450.00 28,052.50 c Pembantu tukang 0.30 org 40,000.00 12,000.00 d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 81,452.50
VI PEKERJAAN PLESTERAN/ACCI
1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.14 sak 42,000.00 5,880.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 23,490.00
Dibulatkan 23,400.00
2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.13 sak 42,000.00 5,460.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 23,070.00
Dibulatkan 23,000.00
3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.10 sak 42,000.00 4,200.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 21,810.00
Dibulatkan 21,800.00
4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00
Dibulatkan 21,300.00 5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 b Pasir pasang 0.03 m3 68,000.00 2,040.00 c Pembantu tukang 0.22 org 40,000.00 8,800.00 d Tukang batu 0.16 org 55,000.00 8,800.00
Jumlah 26,780.00
Dibulatkan 26,700.00
6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm
a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00 b Pasir pasang 0.03 m3 68,000.00 2,040.00 c Pembantu tukang 0.25 org 40,000.00 10,000.00 d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 29,340.00
Dibulatkan 29,300.00
7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.11 sak 42,000.00 4,620.00 b Pasir pasang 0.03 m3 68,000.00 1,700.00 c Pembantu tukang 0.15 org 40,000.00 6,000.00 d Tukang batu 0.07 org 55,000.00 3,850.00
Jumlah 16,170.00
Dibulatkan 16,100.00
8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm
a Semen PC (abu-abu) 0.19 sak 42,000.00 7,980.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.26 org 40,000.00 10,400.00 d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 30,740.00
Dibulatkan 30,700.00
a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.26 org 40,000.00 10,400.00 d Tukang batu 0.20 org 55,000.00 11,000.00
Jumlah 29,060.00
Dibulatkan 29,000.00
10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.01 sak 42,000.00 420.00 b Pasir pasang 0.01 m3 68,000.00 680.00 c Pembantu tukang 0.06 org 40,000.00 2,400.00 d Tukang batu 0.04 org 55,000.00 2,200.00
Jumlah 5,700.00
Dibulatkan 5,700.00
11 1 M2 ACCIAN PLESTERAN
a Semen PC (abu-abu) 0.08 sak 42,000.00 3,360.00 b Pembantu tukang 0.14 org 40,000.00 5,600.00 c Tukang batu 0.11 org 55,000.00 6,050.00
Jumlah 15,010.00
Dibulatkan 15,000.00
12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps
a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.15 org 40,000.00 6,000.00 d Tukang batu 0.07 org 55,000.00 3,850.00
Jumlah 14,990.00
Dibulatkan 14,900.00
VII PEKERJAAN PELAPIS LANTAI
a Keramik ukuran 40 x 40 cm 1.00 m2 246,000.00 246,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 271,036.00
Dibulatkan 271,030.00
2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH
a Keramik ukuran 40 x 40 cm 1.00 m2 205,000.00 205,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 40,000.00 10,400.00 f Tukang batu 0.13 org 55,000.00 6,875.00
Jumlah 230,609.00
Dibulatkan 230,600.00
3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm
a Keramik ukuran 60 x 60 cm 1.00 m2 290,000.00 290,000.00 b Semen PC (abu-abu) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 315,787.10
Dibulatkan 315,780.00
4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm
a Keramik ukuran 60 x 90 cm 1.00 m2 336,000.00 336,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00
d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 40,000.00 10,400.00 f Tukang batu 0.14 org 55,000.00 7,700.00
Jumlah 362,956.00
Dibulatkan 362,950.00
5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm
a Keramik lantai 10 x 20 cm 1.00 m2 32,000.00 32,000.00 b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 71,974.00
Dibulatkan 71,970.00
6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 40,000.00 12,000.00 f Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 67,106.00
Dibulatkan 67,100.00
7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 40,000.00 12,000.00 f Tukang batu 0.15 org 55,000.00 8,250.00
Jumlah 67,106.00
Dibulatkan 67,100.00
8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm
a Keramik polos 30 x 30 cm 1.00 m2 38,500.00 38,500.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 63,434.00
Dibulatkan 63,430.00
9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm
a Keramik motif 30 x 30 cm 1.00 m2 41,000.00 41,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00
Jumlah 65,934.00
Dibulatkan 65,930.00
10 1 M2 PASANG LANTAI MARMER
a marmer standar 1.00 m2 200,000.00 200,000.00 b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00 c Pasir pasang 0.10 m3 68,000.00 6,800.00 d Semen warna 0.20 sak 12,700.00 2,540.00 e Pembantu tukang 0.62 org 40,000.00 24,800.00 f Tukang batu 0.35 org 55,000.00 19,250.00
Jumlah 273,550.00
Dibulatkan 273,550.00
a Parquet jati 1.05 m2 278,000.00 291,900.00 b Lem vinyl 0.60 kg 35,000.00 21,000.00 c Pembantu tukang 0.65 org 40,000.00 26,000.00 d Tukang 0.35 org 55,000.00 19,250.00
Jumlah 358,150.00
Dibulatkan 358,150.00
12 1 M2 PASANG LANTAI GRANIT
a Granit standar 1.00 m2 750,000.00 750,000.00 b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00 c Pasir pasang 0.08 m3 68,000.00 5,440.00 d Semen warna 0.10 sak 12,700.00 1,270.00 e Pembantu tukang 0.60 org 40,000.00 24,000.00 f Tukang batu 0.48 org 55,000.00 26,400.00
Jumlah 827,270.00
Dibulatkan 827,270.00
VIII PEKERJAAN PELAPIS DINDING
1 1 M2 PASANG DINDING KERAMIK MOTIF 10 x 20 cm
a Keramik motif 10 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 77,974.00
Dibulatkan 77,970.00
2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm
b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00
Jumlah 73,974.00
Dibulatkan 73,970.00
3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm
a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 40,000.00 8,000.00 f Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 76,204.00
Dibulatkan 76,200.00
4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm
a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 40,000.00 8,000.00 f Tukang batu 0.39 org 55,000.00 21,450.00
Jumlah 76,204.00
Dibulatkan 76,200.00
5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm
a Keramik polos 20 x 25 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,224.00 d Semen warna 0.01 kg 12,700.00 165.10
e Pembantu tukang 0.19 org 40,000.00 7,500.00 f Tukang batu 0.38 org 55,000.00 20,625.00
Jumlah 74,234.10
Dibulatkan 74,230.00
6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm
a Keramik motif 20 x 25 cm 1.00 m2 39,000.00 39,000.00 b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,224.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.19 org 40,000.00 7,500.00 f Tukang batu 0.38 org 55,000.00 20,625.00
Jumlah 75,234.10
Dibulatkan 75,230.00
7 1 M2 PASANG DINDING MARMER
a Marmer standar 1.00 m2 200,000.00 200,000.00 b Paku sekrup 4.00 bh 750.00 3,000.00 c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00
d Pasir pasang 0.03 m3 68,000.00 1,700.00 e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 19,000.00 475.00 g Paku 0.03 kg 14,700.00 367.50 h Pembantu tukang 0.72 org 40,000.00 28,800.00 i Tukang batu 0.65 org 55,000.00 35,750.00
Jumlah 299,642.50
Dibulatkan 299,640.00
8 1 M2 PASANG DINDING GRANIT
a Granit standar 1.00 m2 750,000.00 750,000.00 b Paku sekrup 2.00 bh 750.00 1,500.00 c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00 d Pasir pasang 0.03 m3 68,000.00 1,700.00
e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 19,000.00 475.00 g Paku 0.03 kg 14,700.00 367.50 h Pembantu tukang 0.72 org 40,000.00 28,800.00 i Tukang batu 0.65 org 55,000.00 35,750.00
Jumlah 848,142.50
Dibulatkan 848,140.00
9 1 M2 PASANG DINDING BATU TEMPEL HITAM
a Batu tempel hitam 1.00 m2 140,000.00 140,000.00 b Semen PC ( abu-abu ) 0.24 sak 42,000.00 10,080.00 c Pasir pasang 0.04 m3 68,000.00 2,380.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.25 org 55,000.00 13,750.00
Jumlah 179,010.00
Dibulatkan 179,010.00
10 1 M2 PASANG DINDING BATU ALAM
a Batu alam 1.00 m2 185,000.00 185,000.00 b Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.04 m3 68,000.00 2,380.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.25 org 55,000.00 13,750.00
Jumlah 224,430.00
Dibulatkan 224,430.00
11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm
a Plint Keramik ukuran 10 x 40 cm 2.65 bh 9,000.00 23,850.00 b Semen PC (abu-abu) 0.02 sak 42,000.00 840.00 c Pasir pasang 0.01 m3 68,000.00 680.00 d Semen warna 0.10 kg 12,700.00 1,270.00 e Pembantu tukang 0.06 org 40,000.00 2,400.00 f Tukang batu 0.03 org 55,000.00 1,650.00