ANALISA HARGA SATUAN PEKERJAAN MAKASAR

Kota : Makasar

No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)

I PEKERJAAN PERSIAPAN

1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M

a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00

b Semen PC (abu-abu) 0.05 sak 42,000.00 2,100.00

c Seng gelombang 1.20 sak 53,800.00 64,560.00

d Pasir beton 0.01 m3 72,000.00 360.00

e Split (batu pecah) 0.01 m3 210,000.00 1,890.00

f Balok kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00

g Paku 5 - 10 cm 0.06 kg 14,700.00 882.00

h Meni Besi 0.45 kg 20,000.00 9,000.00

i Tukang kayu 0.20 org 55,000.00 11,000.00

j Pembantu tukang 0.10 org 40,000.00 4,000.00

Jumlah 453,792.00

Dibulatkan 453,790.00

2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M

a Tiang kayu borneo 4/6 0.05 m3 3,600,000.00 180,000.00

b Semen PC (abu-abu) 0.04 sak 42,000.00 1,680.00

c Kawat Duri 2.50 kg 166,000.00 415,000.00

d Pasir beton 0.01 m3 72,000.00 360.00

e Split (batu pecah) 0.01 m3 210,000.00 1,890.00

f Paku 5 - 10 cm 0.06 kg 14,700.00 882.00

g Tukang kayu 0.20 org 55,000.00 11,000.00

h Pembantu tukang 0.30 org 40,000.00 12,000.00

Jumlah 622,812.00

(2)

Dibulatkan 622,810.00

3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK

a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00

b Paku 5 - 10 cm 0.02 kg 14,700.00 294.00

c Papan papan kayu terentang 2/20 - m3 1,220,000.00 4,880.00

d Tukang kayu 0.10 org 55,000.00 5,500.00

e Pembantu tukang 0.10 org 40,000.00 4,000.00

Jumlah 86,674.00

Dibulatkan 86,670.00

4 1 M2 PEMBUATAN KANTOR DIREKSI

a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00

b Papan kayu terentang 0.18 m3 1,220,000.00 219,600.00

c Paku semua ukuran 0.85 kg 14,700.00 12,495.00

d Besi strip 1.10 kg 17,500.00 19,250.00 e Semen PC (abu-abu) 35.00 kg 42,000.00 1,470,000.00 f Pasir pasang 0.15 m3 68,000.00 10,200.00 g Pasir beton 0.10 m3 72,000.00 7,200.00 h Split (batu pecah) 0.15 m3 210,000.00 31,500.00

i Bata merah 30.00 bh 600.00 18,000.00 j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00 k Seng Plat BJLS 32 1.00 m2 33,000.00 33,000.00 l Kawat harmonika 2.00 m2 22,000.00 44,000.00 m Kaca polos 3 mm 0.08 m2 63,000.00 5,040.00 n Kunci tanam standart 0.15 bh 55,000.00 8,250.00

o Triplek 120 x 240 x 0,4 cm 0.06 lbr 51,000.00 3,060.00

p Tukang kayu 2.00 org 55,000.00 110,000.00

q Tukang batu 1.00 org 55,000.00 55,000.00

r Pembantu tukang 2.00 org 40,000.00 80,000.00

Jumlah 2,271,315.00

Dibulatkan 2,271,310.00

(3)

5 1 M2 PEMBUATAN GUDANG PROYEK

a Kayu kaso 5/7 borneo 0.02 m3 3,600,000.00 72,000.00

b Papan kayu terentang 0.10 m3 1,220,000.00 122,000.00

c Paku 0.30 kg 14,700.00 4,410.00

d Semen PC (abu-abu) 0.21 sak 42,000.00 8,820.00

e Pasir beton 0.03 m3 72,000.00 2,160.00

f Split (batu pecah) 0.05 m3 210,000.00 10,500.00

g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 60,600.00 72,720.00

h Tukang kayu 1.00 org 55,000.00 55,000.00

i Pembantu tukang 1.00 org 40,000.00 40,000.00

Jumlah 387,610.00

Dibulatkan 387,610.00

6 1 M2 MEMBERSIHKAN LOKASI ROYEK

a Pembantu tukang 0.10 org 40,000.00 4,000.00

Jumlah 4,000.00 Dibulatkan 4,000.00 7 1 M2 MEMBERSIHKAN PUING-PUING a Pembantu tukang 0.20 org 40,000.00 8,000.00

Jumlah 8,000.00

Dibulatkan 8,000.00

8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN

a Pembantu tukang 2.00 org 40,000.00 80,000.00

Jumlah 80,000.00

Dibulatkan 80,000.00

9 1M2 PEMBUATAN JALAN MASUK PROYEK

a Batu belah 15/20 0.10 m3 72,000.00 7,200.00 b Koral 5/7 ( sirtu ) 0.05 m3 122,000.00 6,100.00 c Pasir urug 0.01 m3 66,000.00 660.00 d Pembantu tukang 1.00 org 40,000.00 40,000.00

Jumlah 53,960.00

(4)

Dibulatkan 53,900.00

10 1 M3 PEMBONGKARAN BETON

a Pembantu tukang 6.20 org 40,000.00 248,000.00

Jumlah 248,000.00

Dibulatkan 248,000.00

11 1 M3 PEMBONGKARAN DINDING BATA

a Pembantu tukang 4.60 org 40,000.00 184,000.00

Jumlah 184,000.00

Dibulatkan 184,000.00

12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK

a Papan kayu borneo 0.02 m3 4,000,000.00 80,000.00

b Balok kayu borneo 5/7 0.02 m3 3,600,000.00 72,000.00

c Pasir beton 0.08 m3 72,000.00 5,760.00

d Split (batu pecah) 0.15 m3 210,000.00 31,500.00

e Semen abu - abu 0.50 sak 42,000.00 21,000.00

f Tukang kayu 0.13 org 55,000.00 7,150.00

g Pembantu tukang 0.38 org 40,000.00 15,200.00

Jumlah 232,610.00 Dibulatkan 232,600.00 II PEKERJAAN TANAH

1 1 M3 GALIAN TANAH SEDALAM 1 M

a Pembantu tukang 0.40 org 40,000.00 16,000.00 b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 16,900.00

Dibulatkan 16,900.00

2 1 M3 GALIAN TANAH SEDALAM 2 M

(5)

b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 22,100.00

Dibulatkan 22,100.00

3 1 M3 GALIAN TANAH SEDALAM 3 M

a Pembantu tukang 0.74 org 40,000.00 29,600.00 b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 30,500.00

Dibulatkan 30,500.00

4 1 M3 GALIAN TANAH KERAS SEDALAM 1 M

a Pembantu tukang 0.45 org 40,000.00 18,000.00 b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 18,900.00

Dibulatkan 18,900.00

5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM

a Pembantu tukang 0.05 org 40,000.00 1,000.00 b Tukang gali 0.02 org 45,000.00 675.00

Jumlah 1,675.00

Dibulatkan 1,670.00

6 1 M3 PEMBUANGAN TANAH SEJAUH 150 M

a Pembantu tukang 0.42 org 40,000.00 16,800.00 b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 17,700.00

Dibulatkan 17,700.00

7 1 M3 URUGAN TANAH KEMBALI

a Pembantu tukang 0.19 org 40,000.00 7,600.00 b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 8,500.00

Dibulatkan 8,500.00

8 1 M3 PEMADATAN TANAH

(6)

b Tukang gali 0.02 org 45,000.00 900.00

Jumlah 20,900.00

Dibulatkan 20,900.00

9 1 M3 URUGAN PASIR

a Pasir urug 1.20 m3 66,000.00 79,200.00 b Pembantu tukang 0.30 org 40,000.00 12,000.00 c Tukang gali 0.02 org 45,000.00 900.00

Jumlah 92,100.00

Dibulatkan 92,100.00

10 1 M3 URUGAN TANAH

a Tanah urug 1.20 m3 70,000.00 84,000.00 b Pembantu tukang 0.30 org 40,000.00 12,000.00 c Tukang gali 0.02 org 45,000.00 900.00

Jumlah 96,900.00

Dibulatkan 96,900.00

11 1 M3 URUGAN SIRTU

a Sirtu ( koral ) 1.20 m3 122,000.00 146,400.00 b Pembantu tukang 0.25 org 40,000.00 10,000.00 c Tukang gali 0.02 org 45,000.00 900.00

Jumlah 157,300.00

Dibulatkan 157,300.00

III PEKERJAAN PONDASI

1 1 M3 PASANG PONDASI BT KALI , 1 Pc : 3 Ps

a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00 c Pasir pasang 0.49 m3 68,000.00 32,980.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00

(7)

e Tukang batu 0.60 org 55,000.00 33,000.00

Jumlah 374,860.00

Dibulatkan 374,860.00

2 1 M3 PASANG PONDASI BT KALI , 1 Pc : 4 Ps

a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 3.26 sak 42,000.00 136,920.00 c Pasir pasang 0.52 m3 68,000.00 35,360.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00 e Tukang batu 0.60 org 55,000.00 33,000.00

Jumlah 344,480.00

Dibulatkan 344,480.00

3 1 M3 PASANG PONDASI BT KALI , 1 Pc : 5 Ps

a Batu belah 1.10 m3 72,000.00 79,200.00 b Semen PC (abu-abu) 2.72 sak 42,000.00 114,240.00 c Pasir pasang 0.54 m3 68,000.00 36,992.00 d Pembantu tukang 1.50 org 40,000.00 60,000.00 e Tukang batu 0.60 org 55,000.00 33,000.00

Jumlah 323,432.00

Dibulatkan 323,430.00

4 1 M3 PASANG PONDASI BATU KOSONG ( AANSTAMPING )

a Batu belah 1.20 m3 72,000.00 86,400.00 b Pasir urug 0.30 m3 66,000.00 19,800.00 c Pembantu tukang 0.78 org 40,000.00 31,200.00 d Tukang batu 0.39 org 55,000.00 21,450.00

Jumlah 158,850.00

Dibulatkan 158,800.00

5 1 M3 MEMBUAT BETON BERTULANG UNTUK PONDASI 1 Pc : 2 Ps : 3 Kr

a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00 b Pasir beton 0.54 m3 72,000.00 38,880.00 c Split (batu pecah) 0.81 m3 210,000.00 170,100.00

(8)

d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00

Jumlah 590,470.00

Dibulatkan 590,400.00

6 1 Kg PENULANGAN BETON PONDASI

a Besi beton polos 1.05 kg 8,800.00 9,240.00 b Kawat beton 0.02 kg 19,000.00 285.00 c Pembantu tukang 0.01 org 40,000.00 280.00 d Tukang besi 0.01 org 55,000.00 385.00

Jumlah 10,190.00

Dibulatkan 10,100.00

7 1 M2 PEKERJAAN BEKISTING UNTUK PONDASI

a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.30 kg 1,925.00 577.50 c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang kayu 0.26 org 55,000.00 14,300.00

Jumlah 76,677.50

Dibulatkan 76,600.00

8 1 M3 PASANG PONDASI CYCLOOP (60 %BETON : 40% BATU KALI)

a Besi beton polos 50.00 kg 8,800.00 440,000.00 b Semen PC (abu-abu) 4.04 sak 42,000.00 169,680.00 c Pasir beton 0.32 m3 72,000.00 23,040.00 d Split (batu pecah) 0.49 m3 210,000.00 102,900.00 e Kawat beton 0.80 kg 19,000.00 15,200.00 f Batu belah 0.40 m3 72,000.00 28,800.00 g Pembantu tukang 2.00 org 40,000.00 80,000.00 h Tukang batu 0.85 org 55,000.00 46,750.00

Jumlah 906,370.00

(9)

9 1 M3 PASANG PONDASI SUMURAN DIAMETER 100 cm

a Batu belah 0.45 m3 72,000.00 32,400.00 b Semen PC (abu-abu) 5.60 sak 42,000.00 235,200.00 c Pasir beton 0.45 m3 72,000.00 32,400.00 d Split (batu pecah) 0.67 m3 210,000.00 140,700.00 e Pembantu tukang 2.38 org 40,000.00 95,200.00 f Tukang batu 0.30 org 55,000.00 16,500.00

Jumlah 552,400.00

Dibulatkan 552,400.00

10 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm

a Pasir beton 0.10 m3 72,000.00 7,200.00 b Split (batu pecah) 0.15 m3 210,000.00 31,500.00 c Semen PC (abu-abu) 1.21 sak 42,000.00 50,820.00 d Besi beton polos 45.00 kg 8,800.00 396,000.00 e Kawat beton 0.90 kg 19,000.00 17,100.00 f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 115,200.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00 j Plamir tembok 0.24 kg 27,000.00 6,480.00 k Pembantu tukang 1.00 org 40,000.00 40,000.00 l Tukang batu 0.67 org 55,000.00 36,850.00

Jumlah 743,814.00

Dibulatkan 743,800.00

11 1 M¹ PEMBUATAN PONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM

a Pasir beton 0.08 m3 72,000.00 5,760.00 b Split (batu pecah) 0.13 m3 210,000.00 27,300.00 c Semen PC (abu-abu) 0.98 sak 42,000.00 41,160.00 d Besi beton polos 34.50 kg 8,800.00 303,600.00 e Kawat beton 0.70 kg 19,000.00 13,300.00

(10)

f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 108,000.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.12 kg 14,700.00 1,764.00 i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00 900.00 j Plamir tembok 0.20 kg 27,000.00 5,400.00 k Pembantu tukang 0.80 org 40,000.00 32,000.00 l Tukang batu 0.50 org 55,000.00 27,500.00

Jumlah 606,684.00

Dibulatkan 606,600.00

12 1 M3 MEMBUAT PONDASI TIANG PANCANG UKURAN 25 X 25

a Pasir beton 0.06 m3 72,000.00 4,320.00 b Split (batu pecah) 0.11 m3 210,000.00 23,100.00 c Semen PC (abu-abu) 0.82 sak 42,000.00 34,440.00 d Besi beton polos 34.50 kg 8,800.00 303,600.00 e Kawat beton 0.60 kg 19,000.00 11,400.00 f Balok kayu borneo super 5/7 0.03 m3 3,600,000.00 108,000.00 g Papan kayu terentang 0.01 m3 4,000,000.00 40,000.00 h Paku 5 - 12 cm 0.11 kg 14,700.00 1,617.00 i Pelumas begisting (oli/minyak) 0.08 Ltr 10,000.00 800.00 j Plamir tembok 0.20 kg 27,000.00 5,400.00 k Pembantu tukang 0.80 org 40,000.00 32,000.00 l Tukang batu 0.50 org 55,000.00 27,500.00

Jumlah 592,177.00

Dibulatkan 592,100.00

13 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )

a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 Ltr 10,000.00 4,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00

(11)

f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 3.90 org 40,000.00 156,000.00 j Tukang batu 0.35 org 55,000.00 19,250.00 k Tukang kayu 1.04 org 55,000.00 57,200.00 l Tukang besi 1.05 org 55,000.00 57,750.00

Jumlah 2,175,560.00

Dibulatkan 2,175,500.00

14 1 M3 MEMBUAT PONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )

a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos Polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.00 org 40,000.00 160,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00

Jumlah 2,397,360.00

Dibulatkan 2,397,300.00

15 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )

a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos Polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.10 kg 19,000.00 39,900.00

(12)

f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 3.90 org 40,000.00 156,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00

Jumlah 2,170,510.00

Dibulatkan 2,170,500.00

16 1 M3 MEMBUAT PONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )

a Papan kayu terentang 0.20 m3 1,220,000.00 244,000.00 b Paku 5 - 12 cm 1.50 kg 14,700.00 22,050.00 c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00 4,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.46 sak 42,000.00 271,320.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.00 org 40,000.00 160,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.00 org 55,000.00 55,000.00 l Tukang besi 1.00 org 55,000.00 55,000.00

Jumlah 2,397,360.00

Dibulatkan 2,397,300.00

IV PEKERJAAN BETON NON STRUKTUR DAN BETON

STRUKTUR

(13)

1 1 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt

a Semen PC (abu-abu) 4.36 sak 42,000.00 183,120.00 b Pasir beton 0.52 m3 72,000.00 37,440.00 c Split (batu pecah) 0.87 m3 210,000.00 182,700.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00

Jumlah 502,510.00

Dibulatkan 502,500.00

2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt

a Semen PC (abu-abu) 4.64 sak 42,000.00 194,880.00 b Pasir beton 0.52 m3 72,000.00 37,440.00 c Split (batu pecah) 0.78 m3 210,000.00 163,800.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00

Jumlah 495,370.00

Dibulatkan 495,300.00

3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt

a Semen PC (abu-abu) 6.72 sak 42,000.00 282,240.00 b Pasir beton 0.54 m3 72,000.00 38,880.00 c Split (batu pecah) 0.81 m3 210,000.00 170,100.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00

Jumlah 590,470.00

Dibulatkan 590,400.00

4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225

a Semen PC (abu-abu) 7.76 sak 42,000.00 325,920.00 b Pasir beton 0.65 m3 72,000.00 46,800.00 c Split (batu pecah) 0.65 m3 210,000.00 136,500.00 d Pembantu tukang 2.00 org 40,000.00 80,000.00 e Tukang batu 0.35 org 55,000.00 19,250.00

(14)

Jumlah 608,470.00

Dibulatkan 608,400.00

5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275

a Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 b Pasir beton 0.55 m3 72,000.00 39,600.00 c Split (batu pecah) 0.70 m3 210,000.00 147,000.00 d Pembantu tukang 2.02 org 40,000.00 80,800.00 e Tukang batu 0.40 org 55,000.00 22,000.00

Jumlah 625,400.00

Dibulatkan 625,400.00

B PEKERJAAN PEMBESIAN

1 1 KG PENULANGAN BETON/BESI BETON POLOS

a Besi beton polos 1.05 kg 8,800.00 9,240.00 b Kawat beton 0.02 kg 19,000.00 380.00 c Pembantu tukang 0.01 org 40,000.00 400.00 d Tukang besi 0.01 org 55,000.00 550.00

Jumlah 10,570.00

Dibulatkan 10,500.00

2 1 KG PENULANGAN BETON/BESI BETON ULIR

a Besi Beton Ulir 1.10 kg 16,300.00 17,930.00 b Kawat beton 0.02 kg 19,000.00 285.00 c Pembantu tukang 0.01 org 40,000.00 400.00 d Tukang besi 0.02 org 55,000.00 1,100.00

Jumlah 19,715.00

Dibulatkan 19,700.00

C PEKERJAAN BEGISTING

1 1 M2 PASANG BEKISTING UNTUK SLOOF

a Papan kayu terentang 0.05 m3 1,220,000.00 54,900.00 b Paku 5 - 12 cm 0.30 kg 14,700.00 4,410.00 c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00 1,000.00

(15)

d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang kayu 0.26 org 55,000.00 14,300.00

Jumlah 86,610.00

Dibulatkan 86,600.00

2 1 M2 PASANG BEKISTING UNTUK KOLOM

a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.30 org 40,000.00 12,000.00 g Tukang kayu 0.33 org 55,000.00 18,150.00

Jumlah 267,580.00

Dibulatkan 267,500.00

3 1M2 PASANG BEKISTING UNTUK BALOK

a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00

Jumlah 268,380.00

Dibulatkan 268,300.00

4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI

a Papan kayu terentang 0.04 m3 1,220,000.00 48,800.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00 2,000.00 d Balok Kayu Borneo 0.04 m3 3,600,000.00 144,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00

(16)

f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00

Jumlah 268,380.00

Dibulatkan 268,300.00

5 1 M2 PASANG BEKISTING UNTUK TANGGA

a Papan kayu terentang 0.03 m3 1,220,000.00 36,600.00 b Paku 5 - 12 cm 0.40 kg 14,700.00 5,880.00 c Pelumas begisting (oli/minyak) 0.15 Ltr 10,000.00 1,500.00 d Balok kayu borneo 0.02 m3 3,600,000.00 72,000.00 e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00 36,750.00 f Pembantu tukang 0.32 org 40,000.00 12,800.00 g Tukang kayu 0.33 org 55,000.00 18,150.00

Jumlah 183,680.00

Dibulatkan 183,600.00

D PEKERJAAN BETON BERTULANG

1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225

a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00 b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.50 org 40,000.00 180,000.00 j Tukang batu 0.35 org 55,000.00 19,250.00 k Tukang kayu 1.56 org 55,000.00 85,800.00 l Tukang besi 1.40 org 55,000.00 77,000.00

Jumlah 3,081,090.00

(17)

2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 4,280,190.00

Dibulatkan 4,280,100.00

3 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 kg BESI + BEKISTING)

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00

(18)

m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 4,500,190.00

Dibulatkan 4,500,100.00

4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 160.00 kg 8,800.00 1,408,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 4,588,190.00

Dibulatkan 4,588,100.00

5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 175.00 kg 8,800.00 1,540,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00

(19)

i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 4,720,190.00

Dibulatkan 4,720,100.00

6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 4,940,190.00

Dibulatkan 4,940,100.00

7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 250.00 kg 8,800.00 2,200,000.00

(20)

e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 5,380,190.00

Dibulatkan 5,380,100.00

8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )

a Papan kayu terentang 0.40 m3 1,220,000.00 488,000.00 b Paku 5 - 12 cm 4.00 kg 14,700.00 58,800.00 c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00 20,000.00 d Besi beton polos 300.00 kg 8,800.00 2,640,000.00 e Kawat beton 4.50 kg 19,000.00 85,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00 367,500.00 k Pembantu tukang 7.30 org 40,000.00 292,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 3.30 org 55,000.00 181,500.00 n Tukang besi 2.10 org 55,000.00 115,500.00

Jumlah 5,820,190.00

Dibulatkan 5,820,100.00

(21)

a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 125.00 kg 8,800.00 1,100,000.00 e Kawat beton 2.25 kg 19,000.00 42,750.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00 l Pembantu tukang 5.80 org 40,000.00 232,000.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.05 org 55,000.00 57,750.00

Jumlah 3,529,330.00

Dibulatkan 3,529,300.00

10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 150.00 kg 8,800.00 1,320,000.00 e Kawat beton 2.25 kg 10,000.00 22,500.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 10,000.00 7,800.00 i Balok kayu Borneo Super 0.12 m3 3,600,000.00 432,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 32.00 btg 8,500.00 272,000.00 l Pembantu tukang 5.80 org 40,000.00 232,000.00

(22)

m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.05 org 55,000.00 57,750.00

Jumlah 3,573,080.00

Dibulatkan 3,573,000.00

11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00

h Split (batu pecah) 0.78 m3 140,000.00 109200

i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 18,000.00 288,000.00 l Pembantu tukang 5.96 org 27,500.00 163,900.00 m Tukang batu 0.35 org 42,000.00 14,700.00 n Tukang kayu 2.80 org 42,000.00 117,600.00 o Tukang besi 1.40 org 42,000.00 58,800.00

Jumlah 4,184,980.00

Dibulatkan 4,184,900.00

12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)

a Papan kayu terentang 0.32 m3 1,750,000.00 560,000.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 225.00 kg 8,750.00 1,968,750.00 e Kawat beton 4.00 kg 15,000.00 60,000.00 f Semen PC (abu-abu) 6.45 sak 49,500.00 319,275.00

(23)

g Pasir beton 0.52 m3 140,000.00 72,800.00 h Split (batu pecah) 0.78 m3 140,000.00 109,200.00 i Balok kayu Borneo Super 0.14 m3 4,000,000.00 560,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00 l Pembantu tukang 5.96 org 40,000.00 238,400.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.40 org 55,000.00 77,000.00

Jumlah 4,631,715.00

Dibulatkan 4,631,700.00

13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )

a Papan kayu terentang 0.32 m3 1,220,000.00 390,400.00 b Paku 5 - 12 cm 3.20 kg 14,700.00 47,040.00 c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00 16,000.00 d Besi beton polos 250.00 kg 8,800.00 2,200,000.00 e Kawat beton 6.00 kg 19,000.00 114,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.14 m3 3,600,000.00 504,000.00 j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00 294,000.00 k Dolken Ø-8 Cm atau kayu 4 x 6 cm / 4m 16.00 btg 8,500.00 136,000.00 l Pembantu tukang 5.96 org 40,000.00 238,400.00 m Tukang batu 0.35 org 55,000.00 19,250.00 n Tukang kayu 2.80 org 55,000.00 154,000.00 o Tukang besi 1.40 org 55,000.00 77,000.00

Jumlah 4,662,230.00

Dibulatkan 4,662,200.00

(24)

a Papan kayu terentang 0.25 m3 1,220,000.00 305,000.00 b Paku 5 - 12 cm 3.00 kg 14,700.00 44,100.00 c Pelumas begisting (oli/minyak) 1.20 Ltr 10,000.00 12,000.00 d Besi beton polos 200.00 kg 8,800.00 1,760,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 6.45 sak 42,000.00 270,900.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Balok kayu Borneo Super 0.30 m3 3,600,000.00 1,080,000.00 j Multiplex 120 x 240 x 9 mm 2.50 lbr 105,000.00 262,500.00 k Pembantu tukang 5.60 org 40,000.00 224,000.00 l Tukang batu 0.35 org 55,000.00 19,250.00 m Tukang kayu 2.30 org 55,000.00 126,500.00 n Tukang besi 1.40 org 55,000.00 77,000.00

Jumlah 4,439,490.00

Dibulatkan 4,439,400.00

15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 10.00 m2 268,300.00 2,683,000.00 c Besi Beton rakit 100.00 kg 8,800.00 880,000.00

Jumlah 4,153,400.00

Dibulatkan 4,153,400.00

16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00 c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00

Jumlah 4,032,839.00

Dibulatkan 4,032,800.00

17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00

(25)

b Pasang Bekisting untuk lantai 8.33 m2 268,300.00 2,234,939.00 c Besi Beton rakit 125.00 kg 10,500.00 1,312,500.00

Jumlah 4,137,839.00

Dibulatkan 4,137,800.00

18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 6.67 m2 268,300.00 1,789,561.00 c Besi Beton rakit 100.00 kg 10,500.00 1,050,000.00

Jumlah 3,429,961.00

Dibulatkan 3,429,900.00

19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

a Beton bertulang camp. 1Pc : 2 Ps : 3 Kr 1.00 m3 590,400.00 590,400.00 b Pasang Bekisting untuk lantai 7.50 m2 268,300.00 2,012,250.00 c Besi Beton rakit 115.00 kg 10,500.00 1,207,500.00

Jumlah 3,810,150.00

Dibulatkan 3,810,100.00

20 1M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225

a Papan kayu terentang 0.27 m3 1,220,000.00 329,400.00 b Paku 5 - 12 cm 2.00 kg 14,700.00 29,400.00 c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00 6,000.00 d Besi beton polos 175.00 kg 8,800.00 1,540,000.00 e Kawat beton 3.00 kg 19,000.00 57,000.00 f Semen PC (abu-abu) 8.00 sak 42,000.00 336,000.00 g Pasir beton 0.52 m3 72,000.00 37,440.00 h Split (batu pecah) 0.78 m3 210,000.00 163,800.00 i Pembantu tukang 4.85 org 40,000.00 194,000.00 j Tukang batu 0.40 org 55,000.00 22,000.00 k Tukang kayu 1.75 org 55,000.00 96,250.00 l Tukang besi 1.45 org 55,000.00 79,750.00

(26)

Dibulatkan 2,891,000.00

V PEKERJAAN DINDING

1 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps

a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.65 sak 42,000.00 27,300.00 c Pasir pasang 0.09 m3 68,000.00 6,120.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 154,420.00

Dibulatkan 154,400.00

2 1 M2 PASANGAN Bata merah TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps

a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.55 sak 42,000.00 23,100.00 c Pasir pasang 0.09 m3 68,000.00 6,120.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 150,220.00

Dibulatkan 150,200.00

3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps

a Bata merah 140.00 bh 600.00 84,000.00 b Semen PC (abu-abu) 0.45 sak 42,000.00 18,900.00 c Pasir pasang 0.10 m3 68,000.00 6,800.00 d Pembantu tukang 0.65 org 40,000.00 26,000.00 e Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 146,700.00

Dibulatkan 146,700.00

4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps

(27)

b Semen PC (abu-abu) 0.29 sak 42,000.00 12,180.00 c Pasir pasang 0.04 m3 68,000.00 2,720.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00

Jumlah 75,200.00

Dibulatkan 75,200.00

5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps

a Bata merah 70.00 bh 600.00 42,000.00 b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.05 m3 68,000.00 3,400.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00

Jumlah 74,200.00

Dibulatkan 74,200.00

6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps

a Bata merah 70.00 bh 600.00 42,000.00 b Semen PC (abu-abu) 0.22 sak 42,000.00 9,240.00 c Pasir pasang 0.05 m3 68,000.00 3,400.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.10 org 55,000.00 5,500.00

Jumlah 72,940.00

Dibulatkan 72,900.00

7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG

a Rooster / Terawang ukuran 12 x 11 x 24 37.00 bh 4,100.00 151,700.00 b Semen PC (abu-abu) 0.27 sak 42,000.00 11,340.00 c Pasir pasang 0.04 m3 68,000.00 2,720.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.10 org 55,000.00 5,500.00

Jumlah 183,260.00

(28)

8 1 M2 PASANG DINDING GLASSBLOCK

a Glassblock ukuran 18 x 18 cm 30.00 bh 20,000.00 600,000.00 b Semen putih 0.27 sak 12,700.00 3,429.00 c Pembantu tukang 0.30 org 40,000.00 12,000.00 d Tukang batu 0.10 org 55,000.00 5,500.00

Jumlah 620,929.00

Dibulatkan 620,900.00

9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps

a Bataco putih 15.00 bh 4,200.00 63,000.00 b Semen PC (abu-abu) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.03 m3 68,000.00 2,040.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 95,790.00

Dibulatkan 95,700.00

10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps

a Bataco press semen 15.00 bh 4,300.00 64,500.00 b Semen PC (abu-abu) 0.20 sak 42,000.00 8,400.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Pembantu tukang 0.30 org 40,000.00 12,000.00 e Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 94,510.00

Dibulatkan 94,500.00

11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON ).

a Bata Ringan ( hebel/celcon ) 8.00 bh 3,800.00 30,400.00 b Semen Instan 11.45 kg 2,450.00 28,052.50 c Pembantu tukang 0.30 org 40,000.00 12,000.00 d Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 81,452.50

(29)

VI PEKERJAAN PLESTERAN/ACCI

1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.14 sak 42,000.00 5,880.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 23,490.00

Dibulatkan 23,400.00

2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.13 sak 42,000.00 5,460.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 23,070.00

Dibulatkan 23,000.00

3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.10 sak 42,000.00 4,200.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 21,810.00

Dibulatkan 21,800.00

4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.20 org 40,000.00 8,000.00 d Tukang batu 0.15 org 55,000.00 8,250.00

(30)

Dibulatkan 21,300.00 5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm

a Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 b Pasir pasang 0.03 m3 68,000.00 2,040.00 c Pembantu tukang 0.22 org 40,000.00 8,800.00 d Tukang batu 0.16 org 55,000.00 8,800.00

Jumlah 26,780.00

Dibulatkan 26,700.00

6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm

a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00 b Pasir pasang 0.03 m3 68,000.00 2,040.00 c Pembantu tukang 0.25 org 40,000.00 10,000.00 d Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 29,340.00

Dibulatkan 29,300.00

7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.11 sak 42,000.00 4,620.00 b Pasir pasang 0.03 m3 68,000.00 1,700.00 c Pembantu tukang 0.15 org 40,000.00 6,000.00 d Tukang batu 0.07 org 55,000.00 3,850.00

Jumlah 16,170.00

Dibulatkan 16,100.00

8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm

a Semen PC (abu-abu) 0.19 sak 42,000.00 7,980.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.26 org 40,000.00 10,400.00 d Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 30,740.00

Dibulatkan 30,700.00

(31)

a Semen PC (abu-abu) 0.15 sak 42,000.00 6,300.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.26 org 40,000.00 10,400.00 d Tukang batu 0.20 org 55,000.00 11,000.00

Jumlah 29,060.00

Dibulatkan 29,000.00

10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps

a Semen PC (abu-abu) 0.01 sak 42,000.00 420.00 b Pasir pasang 0.01 m3 68,000.00 680.00 c Pembantu tukang 0.06 org 40,000.00 2,400.00 d Tukang batu 0.04 org 55,000.00 2,200.00

Jumlah 5,700.00

Dibulatkan 5,700.00

11 1 M2 ACCIAN PLESTERAN

a Semen PC (abu-abu) 0.08 sak 42,000.00 3,360.00 b Pembantu tukang 0.14 org 40,000.00 5,600.00 c Tukang batu 0.11 org 55,000.00 6,050.00

Jumlah 15,010.00

Dibulatkan 15,000.00

12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps

a Semen PC (abu-abu) 0.09 sak 42,000.00 3,780.00 b Pasir pasang 0.02 m3 68,000.00 1,360.00 c Pembantu tukang 0.15 org 40,000.00 6,000.00 d Tukang batu 0.07 org 55,000.00 3,850.00

Jumlah 14,990.00

Dibulatkan 14,900.00

VII PEKERJAAN PELAPIS LANTAI

(32)

a Keramik ukuran 40 x 40 cm 1.00 m2 246,000.00 246,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00

Jumlah 271,036.00

Dibulatkan 271,030.00

2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH

a Keramik ukuran 40 x 40 cm 1.00 m2 205,000.00 205,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 40,000.00 10,400.00 f Tukang batu 0.13 org 55,000.00 6,875.00

Jumlah 230,609.00

Dibulatkan 230,600.00

3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm

a Keramik ukuran 60 x 60 cm 1.00 m2 290,000.00 290,000.00 b Semen PC (abu-abu) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00

Jumlah 315,787.10

Dibulatkan 315,780.00

4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm

a Keramik ukuran 60 x 90 cm 1.00 m2 336,000.00 336,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00

(33)

d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.26 org 40,000.00 10,400.00 f Tukang batu 0.14 org 55,000.00 7,700.00

Jumlah 362,956.00

Dibulatkan 362,950.00

5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm

a Keramik lantai 10 x 20 cm 1.00 m2 32,000.00 32,000.00 b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00

Jumlah 71,974.00

Dibulatkan 71,970.00

6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm

a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 40,000.00 12,000.00 f Tukang batu 0.15 org 55,000.00 8,250.00

Jumlah 67,106.00

Dibulatkan 67,100.00

7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm

a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC (abu-abu) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,462.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.30 org 40,000.00 12,000.00 f Tukang batu 0.15 org 55,000.00 8,250.00

(34)

Jumlah 67,106.00

Dibulatkan 67,100.00

8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm

a Keramik polos 30 x 30 cm 1.00 m2 38,500.00 38,500.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00

Jumlah 63,434.00

Dibulatkan 63,430.00

9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm

a Keramik motif 30 x 30 cm 1.00 m2 41,000.00 41,000.00 b Semen PC (abu-abu) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.25 org 40,000.00 10,000.00 f Tukang batu 0.12 org 55,000.00 6,600.00

Jumlah 65,934.00

Dibulatkan 65,930.00

10 1 M2 PASANG LANTAI MARMER

a marmer standar 1.00 m2 200,000.00 200,000.00 b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00 c Pasir pasang 0.10 m3 68,000.00 6,800.00 d Semen warna 0.20 sak 12,700.00 2,540.00 e Pembantu tukang 0.62 org 40,000.00 24,800.00 f Tukang batu 0.35 org 55,000.00 19,250.00

Jumlah 273,550.00

Dibulatkan 273,550.00

(35)

a Parquet jati 1.05 m2 278,000.00 291,900.00 b Lem vinyl 0.60 kg 35,000.00 21,000.00 c Pembantu tukang 0.65 org 40,000.00 26,000.00 d Tukang 0.35 org 55,000.00 19,250.00

Jumlah 358,150.00

Dibulatkan 358,150.00

12 1 M2 PASANG LANTAI GRANIT

a Granit standar 1.00 m2 750,000.00 750,000.00 b Semen PC (abu-abu) 0.48 sak 42,000.00 20,160.00 c Pasir pasang 0.08 m3 68,000.00 5,440.00 d Semen warna 0.10 sak 12,700.00 1,270.00 e Pembantu tukang 0.60 org 40,000.00 24,000.00 f Tukang batu 0.48 org 55,000.00 26,400.00

Jumlah 827,270.00

Dibulatkan 827,270.00

VIII PEKERJAAN PELAPIS DINDING

1 1 M2 PASANG DINDING KERAMIK MOTIF 10 x 20 cm

a Keramik motif 10 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00

Jumlah 77,974.00

Dibulatkan 77,970.00

2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm

(36)

b Semen PC ( abu-abu ) 0.18 sak 42,000.00 7,560.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.22 org 40,000.00 8,800.00 f Tukang batu 0.40 org 55,000.00 22,000.00

Jumlah 73,974.00

Dibulatkan 73,970.00

3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm

a Keramik motif 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 40,000.00 8,000.00 f Tukang batu 0.39 org 55,000.00 21,450.00

Jumlah 76,204.00

Dibulatkan 76,200.00

4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm

a Keramik polos 20 x 20 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.17 sak 42,000.00 7,140.00 c Pasir pasang 0.02 m3 68,000.00 1,360.00 d Semen warna 0.02 kg 12,700.00 254.00 e Pembantu tukang 0.20 org 40,000.00 8,000.00 f Tukang batu 0.39 org 55,000.00 21,450.00

Jumlah 76,204.00

Dibulatkan 76,200.00

5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm

a Keramik polos 20 x 25 cm 1.00 m2 38,000.00 38,000.00 b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,224.00 d Semen warna 0.01 kg 12,700.00 165.10

(37)

e Pembantu tukang 0.19 org 40,000.00 7,500.00 f Tukang batu 0.38 org 55,000.00 20,625.00

Jumlah 74,234.10

Dibulatkan 74,230.00

6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm

a Keramik motif 20 x 25 cm 1.00 m2 39,000.00 39,000.00 b Semen PC ( abu-abu ) 0.16 sak 42,000.00 6,720.00 c Pasir pasang 0.02 m3 68,000.00 1,224.00 d Semen warna 0.01 kg 12,700.00 165.10 e Pembantu tukang 0.19 org 40,000.00 7,500.00 f Tukang batu 0.38 org 55,000.00 20,625.00

Jumlah 75,234.10

Dibulatkan 75,230.00

7 1 M2 PASANG DINDING MARMER

a Marmer standar 1.00 m2 200,000.00 200,000.00 b Paku sekrup 4.00 bh 750.00 3,000.00 c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00

d Pasir pasang 0.03 m3 68,000.00 1,700.00 e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 19,000.00 475.00 g Paku 0.03 kg 14,700.00 367.50 h Pembantu tukang 0.72 org 40,000.00 28,800.00 i Tukang batu 0.65 org 55,000.00 35,750.00

Jumlah 299,642.50

Dibulatkan 299,640.00

8 1 M2 PASANG DINDING GRANIT

a Granit standar 1.00 m2 750,000.00 750,000.00 b Paku sekrup 2.00 bh 750.00 1,500.00 c Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00 d Pasir pasang 0.03 m3 68,000.00 1,700.00

(38)

e Semen warna 1.50 kg 12,700.00 19,050.00 f Kawat ikat 0.03 kg 19,000.00 475.00 g Paku 0.03 kg 14,700.00 367.50 h Pembantu tukang 0.72 org 40,000.00 28,800.00 i Tukang batu 0.65 org 55,000.00 35,750.00

Jumlah 848,142.50

Dibulatkan 848,140.00

9 1 M2 PASANG DINDING BATU TEMPEL HITAM

a Batu tempel hitam 1.00 m2 140,000.00 140,000.00 b Semen PC ( abu-abu ) 0.24 sak 42,000.00 10,080.00 c Pasir pasang 0.04 m3 68,000.00 2,380.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.25 org 55,000.00 13,750.00

Jumlah 179,010.00

Dibulatkan 179,010.00

10 1 M2 PASANG DINDING BATU ALAM

a Batu alam 1.00 m2 185,000.00 185,000.00 b Semen PC ( abu-abu ) 0.25 sak 42,000.00 10,500.00 c Pasir pasang 0.04 m3 68,000.00 2,380.00 d Pembantu tukang 0.32 org 40,000.00 12,800.00 e Tukang batu 0.25 org 55,000.00 13,750.00

Jumlah 224,430.00

Dibulatkan 224,430.00

11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm

a Plint Keramik ukuran 10 x 40 cm 2.65 bh 9,000.00 23,850.00 b Semen PC (abu-abu) 0.02 sak 42,000.00 840.00 c Pasir pasang 0.01 m3 68,000.00 680.00 d Semen warna 0.10 kg 12,700.00 1,270.00 e Pembantu tukang 0.06 org 40,000.00 2,400.00 f Tukang batu 0.03 org 55,000.00 1,650.00

Referensi

Dokumen terkait

LOKASI : EKS KANTOR CAMAT PURWANTORO. TAHUN : TAHUN

LOKASI : PASAR SIDOREJO KECAMATAN WONOGIRI. TAHUN : TAHUN

No Uraian Pekerjaan Sat Material Spek.Ringkas Harga Satuan Halaman

dilakukan di lapangan, terutama untuk analisa cetakan (bekisting) pracetak baik untuk komponen kolom, balok dan pelat.. Apabila ada tambahan peralatan yang digunakan,

Untuk mengetahui harga satuan pekerjaan paving block dan kansteen, berikut ini kami coba sampaikan Analisa Harga Satuan Pekerjaan Paving Block menurut versi kami sendiri yang telah kami sesuaikan, bukan versi SNI, jadi mungkin ada perbedaan koefisien dengan analisa harga satuan versi

Menyamakan persepsi tentang acuan harga sewa Biaya satuan per item pekerjaan Mempermudah pemahaman peneliti maupun pakar yang melakukan validasi mengingat konsep

TOTAL BIAYA BAHAN TOTAL BIAYA PERALATAN Total upah tenaga, biaya material dan peralatan Overhead + profit Harga satuan pekerjaan Downloaded by Priangga Ma’ri prianggamakri@gmail.com

PASANG BEKISTING UNTUK PLAT LANTAI SNI.. PASANG BEKISTING UNTUK DINDING