PE RUSAHAAN DAE RAH AIR MINUM KOT A MAL ANG
REKAPITULASI RENCANA ANGGARAN BIAYA
NOMOR : RAB/201905/0093
PEKERJAAN : REHAB JARINGAN PIPA DISTRIBUSI PE100-PN 12,5/ GP-MS SEPANJANG 2.510 METER L O K A S I : JL. YOS SUDARSO - JL. TANIMBAR DAN SEKITARNYA
KEC. KLOJEN KOTA MALANG
No. URAIAN PEKERJAAN JUMLAH
1 2 3
I. PEKERJAAN PERSIAPAN : Rp. 1,207,379.69
II. PEKERJAAN TANAH : Rp. 39,054,671.05
III. PEKERJAAN PASANGAN : Rp. 120,024.97
IV. PEKERJAAN PENGEMBALIAN JALAN : Rp. 116,160,531.70
V. PEKERJAAN PIPA 1. BAHAN a. PIPA Rp. 291,953,467.00 b. AKSESORIS JARINGAN Rp. 63,010,330.80 2. UPAH a. PEMASANGAN PIPA Rp. 15,562,784.64
b. BIAYA PEMASANGAN AKSESORIS Rp. 7,278,599.20
c. BIAYA PENGEBORAN Rp. 38,970,391.92
d. BIAYA TAPING Rp. 1,974,120.34
VI. PEMBERSIHAN LOKASI DAN PEMBUANGAN BEKAS GALIAN : Rp. 542,737.86
Jumlah Rp. 575,835,039.18
PPn 10% Rp. 57,583,503.92
Jumlah Total Rp. 633,418,543.09 Dibulatkan Rp. 633,419,000.00 Terbilang : Enam ratus tiga puluh tiga juta empat ratus sembilan belas ribu rupiah
Keterangan :
- Biaya tersebut diatas berdasarkan analisa SNI
Malang, 11 June 2019 dibuat oleh, Manajer Perencanaan Teknik
Hendrik Ribowo, ST NPP. 06090593
Mengetahui,
Direktur Administrasi dan Keuangan
Moch. Syaifudin Zuhri, SE,MM
Mengetahui, Direktur Teknik
Ir. Ari Mukti, MT
Disetujui, Untuk Dilaksanakan
Direktur Utama
PE RUSAHAAN DAE RAH AIR MINUM KOT A MAL ANG
RENCANA ANGGARAN BIAYA
PEKERJAAN : REHAB JARINGAN PIPA DISTRIBUSI PE100-PN 12,5/ GP-MS SEPANJANG 2.510 METER L O K A S I : JL. YOS SUDARSO - JL. TANIMBAR DAN SEKITARNYA
KEC. KLOJEN KOTA MALANG
No. URAIAN PEKERJAAN SATUAN VOLUME ANALISA
HARGA (Rp) SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SELURUH 1 2 3 4 5 6 7 8 I. PEKERJAAN PERSIAPAN
Pengukuran Pipa u/ MC 0 km 2.51 : A.19 481,027.76 1,207,379.69
1,207,379.69
II. PEKERJAAN TANAH
Galian Tanah Keras m3 44.66 : B.04 SP 64,072.00 2,861,263.30 Galian Tanah Biasa m3 267.94 : B.01 SP 48,150.00 12,901,407.30 Urugan Kembali + Pemadatan Tanah m3 299.70 : B.10 + B.11 77,716.60 23,292,000.45
39,054,671.05
III. PEKERJAAN PASANGAN
Pembuatan Thrustblock m3 0.10 : G.07 1,179,979.76 120,024.97
IV. PEKERJAAN PENGEMBALIAN JALAN
Aspal m2 606.19 : S.12-F + S.08.SP 182,833.78 110,832,923.09 Rabat m3 4.52 : G.07 1,179,979.76 5,327,608.61 116,160,531.70 V. PEKERJAAN PIPA 1. BAHAN a. PIPA HDPE 0.50 m 268.00 762 7,107.00 1,904,676.00 HDPE 2 m 676.00 772 64,446.00 43,565,496.00 HDPE 3 m 914.00 776 131,249.50 119,962,043.00 HDPE 4 m 652.00 778 194,051.00 126,521,252.00 291,953,467.00 b. AKSESORIS JARINGAN 1. DETAIL 2
MUR BAUT 5/8'' X 4" buah 16.00 375 7,187.40 114,998.40
2. DETAIL 3
EQUAL TEE 110 X 110 MM 4'' X 4'' buah 1.00 876 2,214,923.00 2,214,923.00
3. DETAIL 4
EQUAL TEE 90 X90 MM 3'' X 3'' buah 1.00 875 973,567.00 973,567.00
4. DETAIL 5
END CUP 110 4' buah 1.00 951 1,497,185.00 1,497,185.00
5. DETAIL 6
UNIVERSAL COUPLING CI 2" buah 1.00 665 673,970.00 673,970.00 REDUCING TEE 110X63 MM 4'' X 2'' buah 2.00 891 3,031,975.00 6,063,950.00
6. DETAIL 7
UNIVERSAL COUPLING CI 2" buah 1.00 665 673,970.00 673,970.00
7. DETAIL 8
REDUCING TEE 110X63 MM 4'' X 2'' buah 2.00 891 3,031,975.00 6,063,950.00
8. DETAIL 9
REDUCING TEE 110X90 MM 4'' X 3'' buah 1.00 892 3,031,975.00 3,031,975.00
9. DETAIL 10
END CUP 90 3 " buah 3.00 1331 317,457.00 952,371.00
10. DETAIL 11
EQUAL TEE 63 X63 MM 2'' X 2'' buah 4.00 873 318,538.50 1,274,154.00
11. DETAIL 12
END CUP 63 2'' buah 2.00 948 104,328.00 208,656.00
12. DETAIL 14
TOPI PELINDUNG (SAFETY HELMET) bh 1.00 SM. 014 115,500.00 115,500.00
13. PINDAH ZADDLE Ø 4"
DOUBLE NEPEL 1/2" buah 36.00 256 5,175.00 186,300.00 ZADEL KLEM DCI 4 X 1/2" stel 36.00 615 155,595.00 5,601,420.00 FEMALE THREAD ELBOW 20 X 1/2" 1/2'' X 1/2" buah 36.00 856 32,510.50 1,170,378.00 SHOCK GALVANIS DIA 1/2 " bh 36.00 M384 6,758.00 243,288.00
14. PINDAH ZADDLE Ø 3"
DOUBLE NEPEL 1/2" buah 128.00 256 5,175.00 662,400.00 ZADEL KLEM DCI 3 X 1/2" stel 128.00 614 124,380.55 15,920,710.40 FEMALE THREAD ELBOW 20 X 1/2" 1/2'' X 1/2" buah 128.00 856 32,510.50 4,161,344.00
SHOCK GALVANIS DIA 1/2 " bh 128.00 M384 6,758.00 865,024.00
15. PINDAH ZADDLE Ø 2"
DOUBLE NEPEL 1/2" buah 97.00 256 5,175.00 501,975.00 ZADEL KLEM DCI 2 X 1/2" stel 97.00 609 62,157.50 6,029,277.50 FEMALE THREAD ELBOW 20 X 1/2" 1/2'' X 1/2" buah 97.00 856 32,510.50 3,153,518.50 SHOCK GALVANIS DIA 1/2 " bh 97.00 M384 6,758.00 655,526.00
63,010,330.80 2. UPAH a. PEMASANGAN PIPA HDPE 0.50 m 268.00 R.21 2,935.20 786,633.60 HDPE 2 m 676.00 R.24 5,781.60 3,908,361.60 HDPE 3 m 914.00 R.25 6,939.84 6,343,013.76 HDPE 4 m 652.00 R.26 6,939.84 4,524,775.68 15,562,784.64 b. UPAH DETAIL 3
EQUAL TEE 110 X 110 MM 4'' X 4'' buah 1.00 : R.133 27,594.00 27,594.00
c. UPAH DETAIL 4
EQUAL TEE 90 X90 MM 3'' X 3'' buah 1.00 : R.132 27,594.00 27,594.00
d. UPAH DETAIL 5
END CUP 110 4' buah 1.00 : R.151 7,633.00 7,633.00
e. UPAH DETAIL 6
UNIVERSAL COUPLING CI 2" buah 1.00 : R.79 26,215.00 26,215.00 REDUCING TEE 110X63 MM 4'' X 2'' buah 2.00 : R.133 27,594.00 55,188.00
f. UPAH DETAIL 7
UNIVERSAL COUPLING CI 2" buah 1.00 : R.79 26,215.00 26,215.00
g. UPAH DETAIL 8
REDUCING TEE 110X63 MM 4'' X 2'' buah 2.00 : R.133 27,594.00 55,188.00
h. UPAH DETAIL 9
REDUCING TEE 110X90 MM 4'' X 3'' buah 1.00 : R.133 27,594.00 27,594.00
i. UPAH DETAIL 11
EQUAL TEE 63 X63 MM 2'' X 2'' buah 4.00 : R.131 23,303.00 93,212.00
j. UPAH DETAIL 12
END CUP 63 2'' buah 2.00 : R.149 7,633.00 15,266.00
k. UPAH PENYAMBUNGAN PIPA HDPE Ø 3"
PENYAMBUNGAN PIPA HDPE 3" (BUTTFUSION) 3'' buah 9.00 : R.47 44,726.05 402,534.45
l. UPAH PENYAMBUNGAN PIPA HDPE Ø 2"
PENYAMBUNGAN PIPA HDPE 2" (BUTTFUSION) 2'' buah 6.00 : R.46.SP 33,994.05 203,964.30
m. UPAH PENYAMBUNGAN PIPA HDPE Ø 4"
PENYAMBUNGAN PIPA HDPE 4" (BUTTFUSION) 4'' buah 13.00 : R.48 66,190.05 860,470.65
n. UPAH PINDAH ZADDLE Ø 4"
DOUBLE NEPEL 1/2" buah 36.00 : R.244 1,120.00 40,320.00 ZADEL KLEM DCI 4 X 1/2" stel 36.00 : R.114 25,220.10 907,923.60
o. UPAH PINDAH ZADDLE Ø 3"
DOUBLE NEPEL 1/2" buah 128.00 : R.244 1,120.00 143,360.00 ZADEL KLEM DCI 3 X 1/2" stel 128.00 : R.113 22,057.20 2,823,321.60
p. UPAH PINDAH ZADDLE Ø 2"
DOUBLE NEPEL 1/2" buah 97.00 : R.244 1,120.00 108,640.00 ZADEL KLEM DCI 2 X 1/2" stel 97.00 : R.112 14,704.80 1,426,365.60
7,278,599.20 q. BIAYA PENGEBORAN HDPE 0.50 m 8.00 : B.18.B 41,076.49 328,611.92 HDPE 2 m 22.00 : B.18 164,305.00 3,614,710.00 HDPE 3 m 12.00 : B.19 209,235.00 2,510,820.00 HDPE 4 m 115.00 : B.20 282,750.00 32,516,250.00 38,970,391.92 r. BIAYA TAPING PVC 3 titik 1.00 : R.36 269,076.69 269,076.69 PVC 2 titik 6.00 : R.35 224,943.09 1,349,658.52 PVC 4 titik 1.00 : R.37 355,385.14 355,385.14 1,974,120.34
VI. PEMBERSIHAN LOKASI DAN PEMBUANGAN BEKAS GALIAN m3 12.89 : B.09 SP 42,090.00 542,737.86
PE RUSAHAAN DAE RAH AIR MINUM KOT A MAL ANG
VOLUME PEKERJAAN
PEKERJAAN : REHAB JARINGAN PIPA DISTRIBUSI PE100-PN 12,5/ GP-MS SEPANJANG 2.510 METER L O K A S I : JL. YOS SUDARSO - JL. TANIMBAR DAN SEKITARNYA KEC. KLOJEN KOTA MALANG
No. JENIS PEKERJAAN PERHITUNGAN VOLUME
1 Galian Tanah Keras Galian PIPA
(ASPAL) HDPE 2 0.10000 x 0.20000 x 439.00000 m = 8.78000 m3 (RABAT) HDPE 2 0.10000 x 0.20000 x 215.00000 m = 4.30000 m3 (ASPAL) HDPE 3 0.10000 x 0.20000 x 902.00000 m = 18.04000 m3 (ASPAL) HDPE 4 0.10000 x 0.25000 x 537.00000 m = 13.42500 m3 44.54500 m3 Titik TAPING (ASPAL) PVC 3 0.10000 x 0.40000 x 0.40000 x 1 titik = 0.01600 m3 (ASPAL) PVC 2 0.10000 x 0.40000 x 0.40000 x 6 titik = 0.09600 m3 (ASPAL) PVC 4 0.00000 x 0.00000 x 0.00000 x 1 titik = 0.00000 m3 0.11200 m3
Total Galian Tanah Keras = 44.65700 m3
2 Galian Tanah Biasa Galian PIPA
(ASPAL) HDPE 2 0.60000 x 0.20000 x 439.00000 = 52.68000 m3 (RABAT) HDPE 2 0.60000 x 0.20000 x 215.00000 = 25.80000 m3 (ASPAL) HDPE 3 0.60000 x 0.20000 x 902.00000 = 108.24000 m3 (ASPAL) HDPE 4 0.60000 x 0.25000 x 537.00000 = 80.55000 m3 267.27000 m3 Titik TAPING (ASPAL) PVC 3 0.60000 x 0.40000 x 0.40000 x 1 titik = 0.09600 m3 (ASPAL) PVC 2 0.60000 x 0.40000 x 0.40000 x 6 titik = 0.57600 m3 (ASPAL) PVC 4 0.00000 x 0.00000 x 0.00000 x 1 titik = 0.00000 m3 0.67200 m3
Total Galian Tanah Biasa = 267.94200 m3
3 Urugan Tanah Kembali + Pemadatan Galian PIPA
(ASPAL) HDPE 2 ( ( 0.70000 x 0.20000 - ¼π x 0.063002 ) x 439.00000 ) = 60.09100 m3 (RABAT) HDPE 2 ( ( 0.70000 x 0.20000 - ¼π x 0.063002 ) x 215.00000 ) = 29.43000 m3 (ASPAL) HDPE 3 ( ( 0.70000 x 0.20000 - ¼π x 0.090002 ) x 902.00000 ) = 120.53900 m3 (ASPAL) HDPE 4 ( ( 0.70000 x 0.25000 - ¼π x 0.110002 ) x 537.00000 ) = 88.87000 m3 298.93000 m3 Titik TAPING (ASPAL) PVC 3 ( 0.70000 x 0.40000 - ¼π x 0.089002 ) x 0.40000 x 1 titik = 0.11000 m3 (ASPAL) PVC 2 ( 0.70000 x 0.40000 - ¼π x 0.060002 ) x 0.40000 x 6 titik = 0.66500 m3 (ASPAL) PVC 4 ( 0.00000 x 0.00000 - ¼π x 0.114002 ) x 0.00000 x 1 titik = 0.00000 m3 0.77500 m3
Total Urugan Kembali = 299.70400 m3
4 Buangan Tanah Galian Tanah Keras + Galian Tanah Biasa - Urugan Tanah Kembali =
44.65700 + 267.94200 - 299.70400 = 12.89500 m3
5 Pembuatan Thrust Block Tee / Valve / Dop
HDPE 4 ( ( (0.20000 x 0.36500) + (0.20000 x 0.32000) ) / 2 ) x 0.12500 x 1.00000 titik = 0.00900 m3 HDPE 3 ( ( (0.20000 x 0.24500) + (0.20000 x 0.28000) ) / 2 ) x 0.10000 x 1.00000 titik = 0.00500 m3 HDPE 4 ( ( (0.20000 x 0.36500) + (0.20000 x 0.32000) ) / 2 ) x 0.12500 x 1.00000 titik = 0.00900 m3 HDPE 4 ( ( (0.20000 x 0.36500) + (0.20000 x 0.32000) ) / 2 ) x 0.12500 x 2.00000 titik = 0.01700 m3 HDPE 4 ( ( (0.20000 x 0.36500) + (0.20000 x 0.32000) ) / 2 ) x 0.12500 x 2.00000 titik = 0.01700 m3 HDPE 4 ( ( (0.20000 x 0.36500) + (0.20000 x 0.32000) ) / 2 ) x 0.12500 x 1.00000 titik = 0.00900 m3 HDPE 3 ( ( (0.20000 x 0.24500) + (0.20000 x 0.28000) ) / 2 ) x 0.10000 x 3.00000 titik = 0.01600 m3 HDPE 2 ( ( (0.20000 x 0.12000) + (0.20000 x 0.22600) ) / 2 ) x 0.10000 x 4.00000 titik = 0.01400 m3 HDPE 2 ( ( (0.20000 x 0.12000) + (0.20000 x 0.22600) ) / 2 ) x 0.10000 x 2.00000 titik = 0.00700 m3 0.10200 m3
6 Rekondisi Jalan Aspal Galian PIPA
HDPE 2 0.30000 x 439.00000 m = 131.70000 m2 HDPE 3 0.30000 x 902.00000 m = 270.60000 m2 HDPE 4 0.37500 x 537.00000 m = 201.37500 m2
603.67500 m2 Titik TAPING PVC 3 0.60000 x 0.60000 x 1 titik = 0.36000 m2 PVC 2 0.60000 x 0.60000 x 6 titik = 2.16000 m2 PVC 4 0.00000 x 0.00000 x 1 titik = 0.00000 m2 2.52000 m2
Total Rekondisi Jalan Aspal = 606.19500 m2
7 Rekondisi Jalan Macadam Titik TAPING
0.00000 m2
-8 Rekondisi Jalan Rabat Galian PIPA
HDPE 2 0.30000 x 215.00000 m x 0.07000 = 4.51500 m3
4.51500 m3
Total Rekondisi Jalan Rabat = 4.51500 m3
9 Pengeboran HDPE 0.50 8.00000 m
HDPE 2 22.00000 m
HDPE 3 12.00000 m
PE RUSAHAAN DAE RAH AIR MINUM KOT A MAL ANG
L17 L08 M409 M061 L17 L07 L02 L01 L17 L07 L02 L01 L17 L07 L02 L01 ANALISA PEKERJAAN
PEKERJAAN : REHAB JARINGAN PIPA DISTRIBUSI PE100-PN 12,5/ GP-MS SEPANJANG 2.510 METER L O K A S I : JL. YOS SUDARSO - JL. TANIMBAR DAN SEKITARNYA
KEC. KLOJEN KOTA MALANG
KODE ANALISA : A.19
JENIS PEKERJAAN : PENGUKURAN JARINGAN PIPA UNTUK MC 0
SATUAN PEMBAYARAN : KM1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.00000 61,000.00 61,000.00
2 TUKANG KAYU ORG/HR 0.33333 76,000.00 25,333.33
JUMLAH HARGA TENAGA 86,333.33
B BAHAN
1 CAT MENI KAYU KG 0.24000 48,796.00 11,711.04
2 USUK : 5/7 (KAYU MERANTI) M3 0.05400 7,092,285.00 382,983.39
JUMLAH HARGA BAHAN 394,694.43
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 481,027.76
KODE ANALISA : B.04 SP
JENIS PEKERJAAN : GALIAN TANAH KERAS SEDALAM 1 M
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.00000 61,000.00 61,000.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.03200 96,000.00 3,072.00
JUMLAH HARGA TENAGA 64,072.00
B JUMLAH HARGA TENAGA ( A ) 64,072.00
KODE ANALISA : B.01 SP
JENIS PEKERJAAN : GALIAN TANAH BIASA SEDALAM 1 M
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.75000 61,000.00 45,750.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 48,150.00
B JUMLAH HARGA TENAGA ( A ) 48,150.00
KODE ANALISA : B.10
JENIS PEKERJAAN : URUGAN KEMBALI
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.49250 61,000.00 30,042.50
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.02083 96,000.00 2,000.00
JUMLAH HARGA TENAGA 32,042.50
L17 L07 L02 L01 E64 L17 L07 L02 L01 E85 L17 L07 L02 L01 M037 M004 M019 M486 KODE ANALISA : B.11
JENIS PEKERJAAN : PEMADATAN TANAH DENGAN MESIN PEMADAT TUMBUK (PER 20 CM)
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.50000 61,000.00 30,500.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.05000 96,000.00 4,800.00
JUMLAH HARGA TENAGA 35,300.00
B PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02282 454,620.00 10,374.10
JUMLAH HARGA PERLENGKAPAN 10,374.10
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 45,674.10
KODE ANALISA : B.09 SP
JENIS PEKERJAAN : PEMBUANGAN TANAH DENGAN MOBILISASI
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.33000 61,000.00 20,130.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 21,090.00
B PERLENGKAPAN
1 MOBILISASI BUANGAN TANAH M3 1.00000 21,000.00 21,000.00
JUMLAH HARGA PERLENGKAPAN 21,000.00
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 42,090.00
KODE ANALISA : G.07
JENIS PEKERJAAN : BETON MUTU FC=19,3 MPA (K225) SLUMP (12 +- 2) CM, W/C = 0,58
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.65000 61,000.00 100,650.00
2 TUKANG BATU ORG/HR 0.27500 76,000.00 20,900.00
3 KEPALA TUKANG BATU ORG/HR 0.02800 90,000.00 2,520.00
4 MANDOR ORG/HR 0.08300 96,000.00 7,968.00
JUMLAH HARGA TENAGA 132,038.00
B BAHAN
1 PORTLAND CEMENT (PC) KG 371.00000 1,926.00 714,546.00
2 PASIR COR M3 0.49857 206,267.00 102,838.83
3 BATU PECAH MESIN 2/3 M3 0.77556 285,082.00 221,096.93
4 AIR BERSIH LTR 215.00000 44.00 9,460.00
JUMLAH HARGA BAHAN 1,047,941.76
L17 L01 M001 M016 M014 E64 E87 L17 L01 M021 M003 M498 M487. A M487 E64 E87 L17 L12 L06A L01 KODE ANALISA : S.12-F
JENIS PEKERJAAN : WATERBOUND MACADAM UTK. PEK. MINOR ( TEBAL 12 CM )
SATUAN PEMBAYARAN : M2
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.08889 61,000.00 5,422.22
2 MANDOR ORG/HR 0.02222 96,000.00 2,133.33
JUMLAH HARGA TENAGA 7,555.56
B BAHAN
1 PASIR URUG M3 0.05000 126,788.00 6,339.40
2 STENSLAH/BATU PECAH TANGAN 4/6 - 5/7 M3 0.05000 205,050.00 10,252.50
3 STENSLAH/BATU PECAH TANGAN 2/3 M3 0.02000 287,503.00 5,750.06
JUMLAH HARGA BAHAN 22,341.96
C PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02860 454,620.00 13,000.00
2 ALAT BANTU (1 SET; 3 ALAT) M2 1.00000 6,000.00 6,000.00
JUMLAH HARGA PERLENGKAPAN 19,000.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 48,897.52
KODE ANALISA : S. 08.SP
JENIS PEKERJAAN : ASPAL GORENG MANUAL (TEBAL 5 CM)
SATUAN PEMBAYARAN : M2
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.00310 61,000.00 189.10
2 MANDOR ORG/HR 0.00060 96,000.00 57.60
JUMLAH HARGA TENAGA 246.70
B BAHAN
1 BATU PECAH MESIN 4/6 - 5/7 M3 0.03030 238,167.00 7,216.46
2 PASIR HITAM M3 0.01980 199,103.00 3,942.24
3 KAYU BAKAR M3 0.10000 90,000.00 9,000.00
4 ASPAL PENGIKAT KG 0.20000 13,871.00 2,774.20
5 ASPAL KG 6.61500 13,871.00 91,756.67
JUMLAH HARGA BAHAN 114,689.56
C PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02860 454,620.00 13,000.00
2 ALAT BANTU (1 SET; 3 ALAT) M2 1.00000 6,000.00 6,000.00
JUMLAH HARGA PERLENGKAPAN 19,000.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 133,936.26
KODE ANALISA : R.21
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 1/2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.01080 61,000.00 658.80
2 TUKANG PIPA ORG/HR 0.02400 80,000.00 1,920.00
3 KEPALA TUKANG PIPA ORG/HR 0.00300 90,000.00 270.00
4 MANDOR ORG/HR 0.00090 96,000.00 86.40
JUMLAH HARGA TENAGA 2,935.20
L17 L07 L02 L01 L17 L12 L06A L01 L17 L07 L02 L01 L17 L12 L06A L01 KODE ANALISA : B.18.B
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 1/2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.53125 61,000.00 32,406.25
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.09032 96,000.00 8,670.24
JUMLAH HARGA TENAGA 41,076.49
B JUMLAH HARGA TENAGA ( A ) 41,076.49
KODE ANALISA : R.24
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.02700 61,000.00 1,647.00
2 TUKANG PIPA ORG/HR 0.04500 80,000.00 3,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.00450 90,000.00 405.00
4 MANDOR ORG/HR 0.00135 96,000.00 129.60
JUMLAH HARGA TENAGA 5,781.60
B JUMLAH HARGA TENAGA ( A ) 5,781.60
KODE ANALISA : B.18
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 2.12500 61,000.00 129,625.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.36125 96,000.00 34,680.00
JUMLAH HARGA TENAGA 164,305.00
B JUMLAH HARGA TENAGA ( A ) 164,305.00
KODE ANALISA : R.25
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 3"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.03240 61,000.00 1,976.40
2 TUKANG PIPA ORG/HR 0.05400 80,000.00 4,320.00
3 KEPALA TUKANG PIPA ORG/HR 0.00540 90,000.00 486.00
4 MANDOR ORG/HR 0.00164 96,000.00 157.44
JUMLAH HARGA TENAGA 6,939.84
L17 L07 L02 L01 L17 L12 L06A L01 L17 L07 L02 L01 L17 L12 L06A L01 E03 E19 E24 KODE ANALISA : B.19
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 3"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 2.77500 61,000.00 169,275.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.41625 96,000.00 39,960.00
JUMLAH HARGA TENAGA 209,235.00
B JUMLAH HARGA TENAGA ( A ) 209,235.00
KODE ANALISA : R.26
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 4"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.03240 61,000.00 1,976.40
2 TUKANG PIPA ORG/HR 0.05400 80,000.00 4,320.00
3 KEPALA TUKANG PIPA ORG/HR 0.00540 90,000.00 486.00
4 MANDOR ORG/HR 0.00164 96,000.00 157.44
JUMLAH HARGA TENAGA 6,939.84
B JUMLAH HARGA TENAGA ( A ) 6,939.84
KODE ANALISA : B.20
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 4"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 3.75000 61,000.00 228,750.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.56250 96,000.00 54,000.00
JUMLAH HARGA TENAGA 282,750.00
B JUMLAH HARGA TENAGA ( A ) 282,750.00
KODE ANALISA : R.36
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 3"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.64800 61,000.00 39,528.00
2 TUKANG PIPA ORG/HR 1.08000 80,000.00 86,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.05400 90,000.00 4,860.00
4 MANDOR ORG/HR 0.01640 96,000.00 1,574.40
JUMLAH HARGA TENAGA 132,362.40
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.28571 330,000.00 94,285.71
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 136,714.29
L17 L12 L06A L01 E03 E19 E24 L17 L12 L06A L01 E03 E19 E24 L12 L17 L12 L06A L01 KODE ANALISA : R.35
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 2"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.43200 61,000.00 26,352.00
2 TUKANG PIPA ORG/HR 0.72000 80,000.00 57,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.03600 90,000.00 3,240.00
4 MANDOR ORG/HR 0.01080 96,000.00 1,036.80
JUMLAH HARGA TENAGA 88,228.80
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.28571 330,000.00 94,285.71
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 136,714.29
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 224,943.09
KODE ANALISA : R.37
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 4"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.81000 61,000.00 49,410.00
2 TUKANG PIPA ORG/HR 1.35000 80,000.00 108,000.00
3 KEPALA TUKANG PIPA ORG/HR 0.13500 90,000.00 12,150.00
4 MANDOR ORG/HR 0.02050 96,000.00 1,968.00
JUMLAH HARGA TENAGA 171,528.00
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.42857 330,000.00 141,428.57
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 183,857.14
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 355,385.14
KODE ANALISA : R.244
JENIS PEKERJAAN : PEMASANGAN DOUBLE NEPEL GP O.1/2''
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 TUKANG PIPA ORG/HR 0.01400 80,000.00 1,120.00
JUMLAH HARGA TENAGA 1,120.00
B JUMLAH HARGA TENAGA ( A ) 1,120.00
KODE ANALISA : R.112
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.07200 61,000.00 4,392.00
2 TUKANG PIPA ORG/HR 0.12000 80,000.00 9,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.00600 90,000.00 540.00
4 MANDOR ORG/HR 0.00180 96,000.00 172.80
JUMLAH HARGA TENAGA 14,704.80
L17 L12 L06A L01 L17 L12 L06A L01 L17 L12 L06A L01 L17 L12 L06A L01 KODE ANALISA : R.113
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 3"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.10800 61,000.00 6,588.00
2 TUKANG PIPA ORG/HR 0.18000 80,000.00 14,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.00900 90,000.00 810.00
4 MANDOR ORG/HR 0.00270 96,000.00 259.20
JUMLAH HARGA TENAGA 22,057.20
B JUMLAH HARGA TENAGA ( A ) 22,057.20
KODE ANALISA : R.114
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.12150 61,000.00 7,411.50
2 TUKANG PIPA ORG/HR 0.20250 80,000.00 16,200.00
3 KEPALA TUKANG PIPA ORG/HR 0.01350 90,000.00 1,215.00
4 MANDOR ORG/HR 0.00410 96,000.00 393.60
JUMLAH HARGA TENAGA 25,220.10
B JUMLAH HARGA TENAGA ( A ) 25,220.10
KODE ANALISA : R.79
JENIS PEKERJAAN : PEMASANGAN UNIVERSAL COUPLING DIAMETER 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.16500 61,000.00 10,065.00
2 TUKANG PIPA ORG/HR 0.11000 80,000.00 8,800.00
3 KEPALA TUKANG PIPA ORG/HR 0.05500 90,000.00 4,950.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 26,215.00
B JUMLAH HARGA TENAGA ( A ) 26,215.00
KODE ANALISA : R.131
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.17300 61,000.00 10,553.00
2 TUKANG PIPA ORG/HR 0.08700 80,000.00 6,960.00
3 KEPALA TUKANG PIPA ORG/HR 0.04300 90,000.00 3,870.00
4 MANDOR ORG/HR 0.02000 96,000.00 1,920.00
JUMLAH HARGA TENAGA 23,303.00
L17 L12 L06A L01 L17 L12 L06A L01 M483 M484 E26 E03 L17 L12 L06A L01 KODE ANALISA : R.149
JENIS PEKERJAAN : PEMASANGAN COMPRESSION END CUP PIPA HDPE 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.05600 61,000.00 3,416.00
2 TUKANG PIPA ORG/HR 0.02800 80,000.00 2,240.00
3 KEPALA TUKANG PIPA ORG/HR 0.01450 90,000.00 1,305.00
4 MANDOR ORG/HR 0.00700 96,000.00 672.00
JUMLAH HARGA TENAGA 7,633.00
B JUMLAH HARGA TENAGA ( A ) 7,633.00
KODE ANALISA : R.46.SP
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 2" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.06000 61,000.00 3,660.00
2 TUKANG PIPA ORG/HR 0.03000 80,000.00 2,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.03000 90,000.00 2,700.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 9,720.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.30000 10,120.00 3,036.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 3,874.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.03000 350,000.00 10,500.00
2 SEWA MESIN GENSET HARI 0.03000 330,000.00 9,900.00
JUMLAH HARGA PERLENGKAPAN 20,400.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 33,994.05
KODE ANALISA : R.132
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 3"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.20400 61,000.00 12,444.00
2 TUKANG PIPA ORG/HR 0.10200 80,000.00 8,160.00
3 KEPALA TUKANG PIPA ORG/HR 0.05100 90,000.00 4,590.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 27,594.00
L17 L12 L06A L01 M483 M484 E26 E03 L17 L12 L06A L01 L17 L12 L06A L01 KODE ANALISA : R.47
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 3" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.08000 61,000.00 4,880.00
2 TUKANG PIPA ORG/HR 0.04000 80,000.00 3,200.00
3 KEPALA TUKANG PIPA ORG/HR 0.04000 90,000.00 3,600.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 12,640.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.40000 10,120.00 4,048.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 4,886.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.04000 350,000.00 14,000.00
2 SEWA MESIN GENSET HARI 0.04000 330,000.00 13,200.00
JUMLAH HARGA PERLENGKAPAN 27,200.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 44,726.05
KODE ANALISA : R.133
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.20400 61,000.00 12,444.00
2 TUKANG PIPA ORG/HR 0.10200 80,000.00 8,160.00
3 KEPALA TUKANG PIPA ORG/HR 0.05100 90,000.00 4,590.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 27,594.00
B JUMLAH HARGA TENAGA ( A ) 27,594.00
KODE ANALISA : R.151
JENIS PEKERJAAN : PEMASANGAN COMPRESSION END CUP PIPA HDPE 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.05600 61,000.00 3,416.00
2 TUKANG PIPA ORG/HR 0.02800 80,000.00 2,240.00
3 KEPALA TUKANG PIPA ORG/HR 0.01450 90,000.00 1,305.00
4 MANDOR ORG/HR 0.00700 96,000.00 672.00
JUMLAH HARGA TENAGA 7,633.00
L17 L12 L06A L01 M483 M484 E26 E03 KODE ANALISA : R.48
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 4" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.12000 61,000.00 7,320.00
2 TUKANG PIPA ORG/HR 0.06000 80,000.00 4,800.00
3 KEPALA TUKANG PIPA ORG/HR 0.06000 90,000.00 5,400.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 18,480.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.60000 10,120.00 6,072.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 6,910.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.06000 350,000.00 21,000.00
2 SEWA MESIN GENSET HARI 0.06000 330,000.00 19,800.00
JUMLAH HARGA PERLENGKAPAN 40,800.00
PE RUSAHAAN DAE RAH AIR MINUM KOT A MAL ANG
L17 L08 M409 M061 L17 L07 L02 L01 L17 L07 L02 L01 L17 L07 L02 L01 ANALISA PEKERJAAN
PEKERJAAN : REHAB JARINGAN PIPA DISTRIBUSI PE100-PN 12,5/ GP-MS SEPANJANG 2.510 METER L O K A S I : JL. YOS SUDARSO - JL. TANIMBAR DAN SEKITARNYA
KEC. KLOJEN KOTA MALANG
KODE ANALISA : A.19
JENIS PEKERJAAN : PENGUKURAN JARINGAN PIPA UNTUK MC 0
SATUAN PEMBAYARAN : KM1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.00000 61,000.00 61,000.00
2 TUKANG KAYU ORG/HR 0.33333 76,000.00 25,333.33
JUMLAH HARGA TENAGA 86,333.33
B BAHAN
1 CAT MENI KAYU KG 0.24000 48,796.00 11,711.04
2 USUK : 5/7 (KAYU MERANTI) M3 0.05400 7,092,285.00 382,983.39
JUMLAH HARGA BAHAN 394,694.43
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 481,027.76
KODE ANALISA : B.04 SP
JENIS PEKERJAAN : GALIAN TANAH KERAS SEDALAM 1 M
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.00000 61,000.00 61,000.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.03200 96,000.00 3,072.00
JUMLAH HARGA TENAGA 64,072.00
B JUMLAH HARGA TENAGA ( A ) 64,072.00
KODE ANALISA : B.01 SP
JENIS PEKERJAAN : GALIAN TANAH BIASA SEDALAM 1 M
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.75000 61,000.00 45,750.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 48,150.00
B JUMLAH HARGA TENAGA ( A ) 48,150.00
KODE ANALISA : B.10
JENIS PEKERJAAN : URUGAN KEMBALI
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.49250 61,000.00 30,042.50
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.02083 96,000.00 2,000.00
JUMLAH HARGA TENAGA 32,042.50
L17 L07 L02 L01 E64 L17 L07 L02 L01 E85 L17 L07 L02 L01 M037 M004 M019 M486 KODE ANALISA : B.11
JENIS PEKERJAAN : PEMADATAN TANAH DENGAN MESIN PEMADAT TUMBUK (PER 20 CM)
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.50000 61,000.00 30,500.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.05000 96,000.00 4,800.00
JUMLAH HARGA TENAGA 35,300.00
B PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02282 454,620.00 10,374.10
JUMLAH HARGA PERLENGKAPAN 10,374.10
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 45,674.10
KODE ANALISA : B.09 SP
JENIS PEKERJAAN : PEMBUANGAN TANAH DENGAN MOBILISASI
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.33000 61,000.00 20,130.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 21,090.00
B PERLENGKAPAN
1 MOBILISASI BUANGAN TANAH M3 1.00000 21,000.00 21,000.00
JUMLAH HARGA PERLENGKAPAN 21,000.00
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 42,090.00
KODE ANALISA : G.07
JENIS PEKERJAAN : BETON MUTU FC=19,3 MPA (K225) SLUMP (12 +- 2) CM, W/C = 0,58
SATUAN PEMBAYARAN : M3
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 1.65000 61,000.00 100,650.00
2 TUKANG BATU ORG/HR 0.27500 76,000.00 20,900.00
3 KEPALA TUKANG BATU ORG/HR 0.02800 90,000.00 2,520.00
4 MANDOR ORG/HR 0.08300 96,000.00 7,968.00
JUMLAH HARGA TENAGA 132,038.00
B BAHAN
1 PORTLAND CEMENT (PC) KG 371.00000 1,926.00 714,546.00
2 PASIR COR M3 0.49857 206,267.00 102,838.83
3 BATU PECAH MESIN 2/3 M3 0.77556 285,082.00 221,096.93
4 AIR BERSIH LTR 215.00000 44.00 9,460.00
JUMLAH HARGA BAHAN 1,047,941.76
L17 L01 M001 M016 M014 E64 E87 L17 L01 M021 M003 M498 M487. A M487 E64 E87 L17 L12 L06A L01 KODE ANALISA : S.12-F
JENIS PEKERJAAN : WATERBOUND MACADAM UTK. PEK. MINOR ( TEBAL 12 CM )
SATUAN PEMBAYARAN : M2
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.08889 61,000.00 5,422.22
2 MANDOR ORG/HR 0.02222 96,000.00 2,133.33
JUMLAH HARGA TENAGA 7,555.56
B BAHAN
1 PASIR URUG M3 0.05000 126,788.00 6,339.40
2 STENSLAH/BATU PECAH TANGAN 4/6 - 5/7 M3 0.05000 205,050.00 10,252.50
3 STENSLAH/BATU PECAH TANGAN 2/3 M3 0.02000 287,503.00 5,750.06
JUMLAH HARGA BAHAN 22,341.96
C PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02860 454,620.00 13,000.00
2 ALAT BANTU (1 SET; 3 ALAT) M2 1.00000 6,000.00 6,000.00
JUMLAH HARGA PERLENGKAPAN 19,000.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 48,897.52
KODE ANALISA : S. 08.SP
JENIS PEKERJAAN : ASPAL GORENG MANUAL (TEBAL 5 CM)
SATUAN PEMBAYARAN : M2
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.00310 61,000.00 189.10
2 MANDOR ORG/HR 0.00060 96,000.00 57.60
JUMLAH HARGA TENAGA 246.70
B BAHAN
1 BATU PECAH MESIN 4/6 - 5/7 M3 0.03030 238,167.00 7,216.46
2 PASIR HITAM M3 0.01980 199,103.00 3,942.24
3 KAYU BAKAR M3 0.10000 90,000.00 9,000.00
4 ASPAL PENGIKAT KG 0.20000 13,871.00 2,774.20
5 ASPAL KG 6.61500 13,871.00 91,756.67
JUMLAH HARGA BAHAN 114,689.56
C PERLENGKAPAN
1 SEWA TAMPING RAMMER HARI 0.02860 454,620.00 13,000.00
2 ALAT BANTU (1 SET; 3 ALAT) M2 1.00000 6,000.00 6,000.00
JUMLAH HARGA PERLENGKAPAN 19,000.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 133,936.26
KODE ANALISA : R.21
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 1/2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.01080 61,000.00 658.80
2 TUKANG PIPA ORG/HR 0.02400 80,000.00 1,920.00
3 KEPALA TUKANG PIPA ORG/HR 0.00300 90,000.00 270.00
4 MANDOR ORG/HR 0.00090 96,000.00 86.40
JUMLAH HARGA TENAGA 2,935.20
L17 L07 L02 L01 L17 L12 L06A L01 L17 L07 L02 L01 L17 L12 L06A L01 KODE ANALISA : B.18.B
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 1/2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.53125 61,000.00 32,406.25
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.09032 96,000.00 8,670.24
JUMLAH HARGA TENAGA 41,076.49
B JUMLAH HARGA TENAGA ( A ) 41,076.49
KODE ANALISA : R.24
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.02700 61,000.00 1,647.00
2 TUKANG PIPA ORG/HR 0.04500 80,000.00 3,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.00450 90,000.00 405.00
4 MANDOR ORG/HR 0.00135 96,000.00 129.60
JUMLAH HARGA TENAGA 5,781.60
B JUMLAH HARGA TENAGA ( A ) 5,781.60
KODE ANALISA : B.18
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 2"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 2.12500 61,000.00 129,625.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.36125 96,000.00 34,680.00
JUMLAH HARGA TENAGA 164,305.00
B JUMLAH HARGA TENAGA ( A ) 164,305.00
KODE ANALISA : R.25
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 3"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.03240 61,000.00 1,976.40
2 TUKANG PIPA ORG/HR 0.05400 80,000.00 4,320.00
3 KEPALA TUKANG PIPA ORG/HR 0.00540 90,000.00 486.00
4 MANDOR ORG/HR 0.00164 96,000.00 157.44
JUMLAH HARGA TENAGA 6,939.84
L17 L07 L02 L01 L17 L12 L06A L01 L17 L07 L02 L01 L17 L12 L06A L01 E03 E19 E24 KODE ANALISA : B.19
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 3"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 2.77500 61,000.00 169,275.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.41625 96,000.00 39,960.00
JUMLAH HARGA TENAGA 209,235.00
B JUMLAH HARGA TENAGA ( A ) 209,235.00
KODE ANALISA : R.26
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE DIAMETER 4"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.03240 61,000.00 1,976.40
2 TUKANG PIPA ORG/HR 0.05400 80,000.00 4,320.00
3 KEPALA TUKANG PIPA ORG/HR 0.00540 90,000.00 486.00
4 MANDOR ORG/HR 0.00164 96,000.00 157.44
JUMLAH HARGA TENAGA 6,939.84
B JUMLAH HARGA TENAGA ( A ) 6,939.84
KODE ANALISA : B.20
JENIS PEKERJAAN : BOR CROSSING JALAN DIAMETER 4"
SATUAN PEMBAYARAN : M1
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 3.75000 61,000.00 228,750.00
2 TUKANG BATU ORG/HR 0.00000 76,000.00 0.00
3 KEPALA TUKANG BATU ORG/HR 0.00000 90,000.00 0.00
4 MANDOR ORG/HR 0.56250 96,000.00 54,000.00
JUMLAH HARGA TENAGA 282,750.00
B JUMLAH HARGA TENAGA ( A ) 282,750.00
KODE ANALISA : R.36
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 3"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.64800 61,000.00 39,528.00
2 TUKANG PIPA ORG/HR 1.08000 80,000.00 86,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.05400 90,000.00 4,860.00
4 MANDOR ORG/HR 0.01640 96,000.00 1,574.40
JUMLAH HARGA TENAGA 132,362.40
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.28571 330,000.00 94,285.71
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 136,714.29
L17 L12 L06A L01 E03 E19 E24 L17 L12 L06A L01 E03 E19 E24 L12 L17 L12 L06A L01 KODE ANALISA : R.35
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 2"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.43200 61,000.00 26,352.00
2 TUKANG PIPA ORG/HR 0.72000 80,000.00 57,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.03600 90,000.00 3,240.00
4 MANDOR ORG/HR 0.01080 96,000.00 1,036.80
JUMLAH HARGA TENAGA 88,228.80
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.28571 330,000.00 94,285.71
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 136,714.29
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 224,943.09
KODE ANALISA : R.37
JENIS PEKERJAAN : TAPPING PIPA DIAMETER 4"
SATUAN PEMBAYARAN : UNIT
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.81000 61,000.00 49,410.00
2 TUKANG PIPA ORG/HR 1.35000 80,000.00 108,000.00
3 KEPALA TUKANG PIPA ORG/HR 0.13500 90,000.00 12,150.00
4 MANDOR ORG/HR 0.02050 96,000.00 1,968.00
JUMLAH HARGA TENAGA 171,528.00
B PERLENGKAPAN
1 SEWA MESIN GENSET HARI 0.42857 330,000.00 141,428.57
2 SEWA ALAT BERAT KHUSUS SEWA WATER PUMP HARI 0.14286 165,000.00 23,571.43
3 SEWA JACK HAMMER HARI 0.14286 132,000.00 18,857.14
JUMLAH HARGA PERLENGKAPAN 183,857.14
C JUMLAH HARGA TENAGA DAN BAHAN ( A + B ) 355,385.14
KODE ANALISA : R.244
JENIS PEKERJAAN : PEMASANGAN DOUBLE NEPEL GP O.1/2''
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 TUKANG PIPA ORG/HR 0.01400 80,000.00 1,120.00
JUMLAH HARGA TENAGA 1,120.00
B JUMLAH HARGA TENAGA ( A ) 1,120.00
KODE ANALISA : R.112
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.07200 61,000.00 4,392.00
2 TUKANG PIPA ORG/HR 0.12000 80,000.00 9,600.00
3 KEPALA TUKANG PIPA ORG/HR 0.00600 90,000.00 540.00
4 MANDOR ORG/HR 0.00180 96,000.00 172.80
JUMLAH HARGA TENAGA 14,704.80
L17 L12 L06A L01 L17 L12 L06A L01 L17 L12 L06A L01 L17 L12 L06A L01 KODE ANALISA : R.113
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 3"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.10800 61,000.00 6,588.00
2 TUKANG PIPA ORG/HR 0.18000 80,000.00 14,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.00900 90,000.00 810.00
4 MANDOR ORG/HR 0.00270 96,000.00 259.20
JUMLAH HARGA TENAGA 22,057.20
B JUMLAH HARGA TENAGA ( A ) 22,057.20
KODE ANALISA : R.114
JENIS PEKERJAAN : PEMASANGAN ZADEL KLEM BESI DIAMETER 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.12150 61,000.00 7,411.50
2 TUKANG PIPA ORG/HR 0.20250 80,000.00 16,200.00
3 KEPALA TUKANG PIPA ORG/HR 0.01350 90,000.00 1,215.00
4 MANDOR ORG/HR 0.00410 96,000.00 393.60
JUMLAH HARGA TENAGA 25,220.10
B JUMLAH HARGA TENAGA ( A ) 25,220.10
KODE ANALISA : R.79
JENIS PEKERJAAN : PEMASANGAN UNIVERSAL COUPLING DIAMETER 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.16500 61,000.00 10,065.00
2 TUKANG PIPA ORG/HR 0.11000 80,000.00 8,800.00
3 KEPALA TUKANG PIPA ORG/HR 0.05500 90,000.00 4,950.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 26,215.00
B JUMLAH HARGA TENAGA ( A ) 26,215.00
KODE ANALISA : R.131
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.17300 61,000.00 10,553.00
2 TUKANG PIPA ORG/HR 0.08700 80,000.00 6,960.00
3 KEPALA TUKANG PIPA ORG/HR 0.04300 90,000.00 3,870.00
4 MANDOR ORG/HR 0.02000 96,000.00 1,920.00
JUMLAH HARGA TENAGA 23,303.00
L17 L12 L06A L01 L17 L12 L06A L01 M483 M484 E26 E03 L17 L12 L06A L01 KODE ANALISA : R.149
JENIS PEKERJAAN : PEMASANGAN COMPRESSION END CUP PIPA HDPE 2"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.05600 61,000.00 3,416.00
2 TUKANG PIPA ORG/HR 0.02800 80,000.00 2,240.00
3 KEPALA TUKANG PIPA ORG/HR 0.01450 90,000.00 1,305.00
4 MANDOR ORG/HR 0.00700 96,000.00 672.00
JUMLAH HARGA TENAGA 7,633.00
B JUMLAH HARGA TENAGA ( A ) 7,633.00
KODE ANALISA : R.46.SP
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 2" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.06000 61,000.00 3,660.00
2 TUKANG PIPA ORG/HR 0.03000 80,000.00 2,400.00
3 KEPALA TUKANG PIPA ORG/HR 0.03000 90,000.00 2,700.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 9,720.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.30000 10,120.00 3,036.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 3,874.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.03000 350,000.00 10,500.00
2 SEWA MESIN GENSET HARI 0.03000 330,000.00 9,900.00
JUMLAH HARGA PERLENGKAPAN 20,400.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 33,994.05
KODE ANALISA : R.132
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 3"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.20400 61,000.00 12,444.00
2 TUKANG PIPA ORG/HR 0.10200 80,000.00 8,160.00
3 KEPALA TUKANG PIPA ORG/HR 0.05100 90,000.00 4,590.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 27,594.00
L17 L12 L06A L01 M483 M484 E26 E03 L17 L12 L06A L01 L17 L12 L06A L01 KODE ANALISA : R.47
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 3" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.08000 61,000.00 4,880.00
2 TUKANG PIPA ORG/HR 0.04000 80,000.00 3,200.00
3 KEPALA TUKANG PIPA ORG/HR 0.04000 90,000.00 3,600.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 12,640.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.40000 10,120.00 4,048.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 4,886.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.04000 350,000.00 14,000.00
2 SEWA MESIN GENSET HARI 0.04000 330,000.00 13,200.00
JUMLAH HARGA PERLENGKAPAN 27,200.00
D JUMLAH HARGA TENAGA DAN BAHAN DAN PERLENGKAPAN ( A + B + C ) 44,726.05
KODE ANALISA : R.133
JENIS PEKERJAAN : PEMASANGAN COMPRESSION TEE PIPA HDPE 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.20400 61,000.00 12,444.00
2 TUKANG PIPA ORG/HR 0.10200 80,000.00 8,160.00
3 KEPALA TUKANG PIPA ORG/HR 0.05100 90,000.00 4,590.00
4 MANDOR ORG/HR 0.02500 96,000.00 2,400.00
JUMLAH HARGA TENAGA 27,594.00
B JUMLAH HARGA TENAGA ( A ) 27,594.00
KODE ANALISA : R.151
JENIS PEKERJAAN : PEMASANGAN COMPRESSION END CUP PIPA HDPE 4"
SATUAN PEMBAYARAN : BUAH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.05600 61,000.00 3,416.00
2 TUKANG PIPA ORG/HR 0.02800 80,000.00 2,240.00
3 KEPALA TUKANG PIPA ORG/HR 0.01450 90,000.00 1,305.00
4 MANDOR ORG/HR 0.00700 96,000.00 672.00
JUMLAH HARGA TENAGA 7,633.00
L17 L12 L06A L01 M483 M484 E26 E03 KODE ANALISA : R.48
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE DIAMETER 4" (BUTT FUSSION)
SATUAN PEMBAYARAN : BH
No. KOMPONEN SATUAN PERKIRAAN
KUANTITAS HARGA SATUAN (Rp) JUMLAH HARGA (Rp) A TENAGA
1 PEKERJA BIASA ORG/HR 0.12000 61,000.00 7,320.00
2 TUKANG PIPA ORG/HR 0.06000 80,000.00 4,800.00
3 KEPALA TUKANG PIPA ORG/HR 0.06000 90,000.00 5,400.00
4 MANDOR ORG/HR 0.01000 96,000.00 960.00
JUMLAH HARGA TENAGA 18,480.00
B BAHAN
1 SOLAR INDUSTRI LTR 0.60000 10,120.00 6,072.00
2 MINYAK PELUMAS LTR 0.01250 67,044.00 838.05
JUMLAH HARGA BAHAN 6,910.05
C PERLENGKAPAN
1 SEWA BUTT WELDING MACHINE KL 250 (63 - 250 ) HARI 0.06000 350,000.00 21,000.00
2 SEWA MESIN GENSET HARI 0.06000 330,000.00 19,800.00
JUMLAH HARGA PERLENGKAPAN 40,800.00
JL. NIAGA JL. TERSUSAN HALMAHERA JL. SINGKEP JL. BENGKALIS JL. RUPAT JL. RUPAT JL. MALAKA JL. MALAKA JL. BENGKALIS JL. PULAU SERIBU JL. KARIMATA JL. MENARI JL. TAMAN BUNGA JL. MENTAWAI JL. TAMAN RIAU JL. TANIMBAR JL. TANIMBAR JL. RAAS JL. PUTERAN JL. GENTENG JL. MADURA JL. SAPU LIDI JL. BAWEAN JL. KALIMANTAN JL. SEMPU JL. YOS SUDARSO JL. BELITUNG JL. PULAU BURU JL. NIAS JL.SAPARUA JL. NATUNA JL. MENARI JL. KALIMANTAN JL. SANGIR JL. OBI JL. BANDA JL. AMBON JL. BALI JL. KALIMANTAN JL. SERAM JL. TIMOR 407 m 407 m 271 m 271 m 140 m 140 m 50 m 232 m 232 m 144 m 144 m 71 m 71 m 207 m 207 m 245 m 245 m 265 m 265 m 210 m 210 m TGL/BLN/THN :
Lay Out Jaringan
JL. YOS SUDARSO - JL. TANIMBAR
DAN SEKITARNYA
KEC. KLOJEN
KOTA MALANG
MEI 2019
REHAB JARINGAN PIPA DISTRIBUSI PE100-PN12.5 / GP-MS
: 652 Meter : 914 Meter : 676 Meter : 268 Meter
TOTAL PANJANG PIPA : 2.510 Meter
PERUSAHAAN DAERAH AIR MINUM
KOTA MALANG
JUDUL GAMBAR :GAMBAR RENCANA : KETERANGAN :
MANAJER PERENCANAAN TEKNIK
DIREKTUR TEKNIK DIREKTUR UTAMA LOKASI UTARA
TNI AL
NEGERI 4
SMU NEGERI 5
SMK
JL. YOS SUDARSO REKONDISI JALAN :SEMUA REKONDISI ASPAL DIKURANGI PANJANG BORING SETIAP DIAMETER PIPA.
BORING = 30 meter = 22 meter
1
2
3
4
5
6
7a
7b
8
9a
9b
14
9c
10a
10b
10c
10d
10e
11a
11b
13
12a
12b
12c
1
2
3
4
5
6
7
8
a-b
9 a-c
10 a-d
11 a-b
TGL/BLN/THN :Detail Jaringan
JL. YOS SUDARSO - JL. TANIMBAR
DAN SEKITARNYA
KEC. KLOJEN
KOTA MALANG
MEI 2019
REHAB JARINGAN PIPA DISTRIBUSI PE100-PN12.5 / GP-MS
: 652 Meter : 914 Meter : 676 Meter : 268 Meter
TOTAL PANJANG PIPA : 2.510 Meter
PERUSAHAAN DAERAH AIR MINUM
KOTA MALANG
JUDUL GAMBAR :GAMBAR RENCANA : KETERANGAN :
MANAJER PERENCANAAN TEKNIK
DIREKTUR TEKNIK
DIREKTUR UTAMA
LOKASI UTARA
REKONDISI JALAN :
SEMUA REKONDISI ASPAL DIKURANGI PANJANG BORING SETIAP DIAMETER PIPA.
BORING = 30 meter = 22 meter