PEKERJAAN : LANJUTAN PEMBANGUNAN GEDUNG LINGKUP PU
HARGA SATUAN JUMLAH
Rp. Rp.
1 PEKERJAAN LANTAI 1 I. PEKERJAAN PERSIAPAN :
1 - 1.00 ls 10,000,000.00 10,000,000.00
2 I. 009 768.00 m2 2,085.36 1,601,553.71
3 I. 002 1.00 unit 245,284.79 245,284.79
4 I. 020 768.00 m2 4,346.31 3,337,966.08
5 - 1.00 ls 7,500,000.00 7,500,000.00
22,684,804.58
II, PEKERJAAN TANAH :
1 VI. 001 9.41 m3 238,660.42 2,245,794.55
2 III. 015 431.18 m3 221,907.40 95,682,034.46
97,927,829.01
III. PEK. BETON BERTULANG :
1 XIX. 005 9.41 m3 793,315.71 7,465,100.87
2 XIX. 172 0.36 m3 3,728,192.91 1,342,149.45
8,807,250.32
IV. PEKERJAAN PASANGAN :
1 X. 012 906.80 m2 52,070.36 47,217,400.45
2 XI. 012 141.00 m2 108,780.76 15,338,086.96
3 XI. 012 12.70 m2 108,780.76 1,381,515.63
4 XI. 017 123.00 m2 107,141.88 13,178,451.50
5 XI. 018 55.25 m2 83,613.26 4,619,632.70
6 XI. 018 1.40 m2 83,613.26 117,058.57
7 XVII. 001 16.00 bh 2,203,175.75 35,250,812.00
8 Pas. Wastafel Setara HCG XVII. 005 16.00 bh 488,573.52 7,817,176.34
9 Pas. Urinoir Setara Toto Lengkap XVII. 004 2.00 bh 1,117,470.86 2,234,941.73
10 Pas. Cermin - 16.00 bh 300,000.00 4,800,000.00
11 XVII. 006 1.00 bh 1,581,398.86 1,581,398.86
12 - 16.00 bh 100,000.00 1,600,000.00
135,136,474.74
V. PEK.KUSEN,PINTU, JENDELA, PLAFOND DAN PARTISI :
1 - 5.00 Unit 3,089,992.00 15,449,960.00
2 - 4.00 Unit 2,038,950.00 8,155,800.00
3 - 9.00 Unit 2,105,650.00 18,950,850.00
4 - 8.00 Unit 1,756,050.00 14,048,400.00
5 - 1.00 Unit 2,397,405.00 2,397,405.00
6 Pas. Partisi Gypsum t=9 mm Rangka Hollow XII. 028 292.00 m2 143,770.00 41,980,840.00
7 Pas. Plint Dinding Partisi - 231.00 m2 45,000.00 10,395,000.00
8 - 383.00 m1 27,000.00 10,341,000.00
121,719,255.00
VI. TANGGA :
1 XI. 012 53.33 m2 108,780.76 5,801,277.86
2 110.00 m1 450,000.00 49,500,000.00
3 81.90 m1 125,000.00 10,237,500.00
65,538,777.86
VII. PEKERJAAN INSTALASI LISTRIK & AIR :
1 XXVII. 004 99.00 ttk 348,459.72 34,497,512.53
2 XXVII. 003 13.00 ttk 282,594.91 3,673,733.83
3 XXVII. 004 17.00 ttk 348,459.72 5,923,815.28
4 - 1.00 set 14,500,000.00 14,500,000.00
5 - 53.00 bh 295,000.00 15,635,000.00
6 - 35.00 bh 200,000.00 7,000,000.00
7 - 11.00 bh 100,000.00 1,100,000.00
8
XVII. 016 36.00 m1 17,691.10 636,879.72 XVII. 015 47.50 m1 15,201.67 722,079.30 9
XVII. 019 22.00 m1 42,966.92 945,272.19
10 XVII. 023 25.00 bh 48,652.95 1,216,323.67
11 XVII. 025 16.00 bh 37,922.95 606,767.23
86,457,383.75
VIII. PEKERJAAN LAIN - LAIN
1 XVIII. 012 815.80 m2 28,959.02 23,624,771.78
2 XVIII. 034 615.00 m2 29,904.43 18,391,224.33
3 - 1.00 bh 3,000,000.00 3,000,000.00
4 - 30.00 hrf 150,000.00 4,500,000.00
5 - 30.00 hrf 225,000.00 6,750,000.00
56,265,996.11
Pengecatan Dinding setara ICI/Dulux Warna Biasa Pengecatan Plafon Setara Metrolith
Lambang Daerah Tangerang Selatan Huruf Stainless Steel t=20 cm Huruf Stainless Steel t=30 cm Pipa PVC 3/4"
Pipa PVC 1/2"
Instalasi Air Kotor & Air Hujan Pipa PVC 2 "
Pas. Kran Air
Pas. Floor Drain Ø 3" Lokal
Pek. Instalasi Stop Kontak AC 3x2.5 mm Eterna Pas. Box Panel Groub
Pas. Lampu RM 2 x 18
Pas. Lampu Down Light PL 20 Watt Pas. Lampu Neon Phillips PL 20 Watt Instalasi Air Bersih
Pas. Keramik 40/40 Setara Masterina Warna KWI Pas.Hand Railling Tangga Pipa Stainless Steel Ø 2.5" Pas. Step Nosing
Pek. Instalasi Titik Lampu 2x1.5 mm Eterna Pek. Instalasi Stop Kontak 2x2.5 mm Eterna Kusen pintu P 2
Kusen pintu P 4 Kusen pintu P 5 Kusen Jendela P T Kusen Jendela P T 2
Pas. List Profil Plafond Gypsum 7 CM
Pas. Keramik Lantai 20/20 Corak/Warna Setara Masterina KW I Pas. Keramik Meja Pantry 20/20 Corak/Warna Setara Masterina KW I Pas. Closet Duduk Setara HCG
Pas. Kitchen Zink lengkap Accessories Pas. Jet Washer
Pek. Meja Pantry, Beton Ready Mix K-225, Besi = 88kg/m3,
Pas. Plesteran Biasa 1:5 + Acian
Pas. Lantai Keramik 40/40 warna setara Masterina KW I Pas. Plint Lantai 20/40 warna setara Masterina KW I
Pas. Keramik Dinding 20/25 Corak/Warna setara Masterina KW II Urugan Pasir Bawah Lantai
Urugan Tanah Merah dipadatkan tiap 20 Cm
Pek. Beton Tumbuk Lantai Kerja 1:3:5 Papan Nama Proyek Uk. 60x90 cm Pembersihan Lokasi/Perataan Tanah Pengadaan Air Kerja dan Listrik Kerja Mobilisasi dan Demobilisasi Alat Bantu Pek. Pengukuran kembali / Pematokan
NO. URAIAN PEKERJAAN ANA- VOLUME
LISA
DAFTAR KUANTITAS DAN HARGA
PEMERINTAH KOTA TANGERANG SELATAN DINAS TATA KOTA, BANGUNAN DAN PEMUKIMAN
HARGA SATUAN JUMLAH
Rp. Rp.
2 PEKERJAAN LANTAI 2
I. PEK. BETON BERTULANG :
1 XIX. 172 0.36 m3 3,728,192.91 1,342,149.45
1,342,149.45
II. PEKERJAAN PASANGAN :
1 X. 012 893.80 m2 52,070.36 46,540,485.80
2 XI. 012 25.40 m2 108,780.76 2,763,031.27
3 XI. 017 123.00 m2 107,141.88 13,178,451.50
4 XI. 018 53.00 m2 83,613.26 4,431,502.87
5 XI. 018 3.00 m2 83,613.26 250,839.78
6 XVII. 001 15.00 bh 2,203,175.75 33,047,636.25
7 Pas. Wastafel Setara HCG XVII. 005 13.00 bh 488,573.52 6,351,455.77
8 Pas. Urinoir Setara Toto Lengkap XVII. 004 4.00 bh 1,117,470.86 4,469,883.46
9 Pas. Cermin - 13.00 bh 300,000.00 3,900,000.00
10 XVII. 006 1.00 bh 1,581,398.86 1,581,398.86
11 - 13.00 bh 100,000.00 1,300,000.00
117,814,685.55
III. PEK.KUSEN,PINTU & JENDELA+PLAFOND :
1 - 7.00 Unit 3,089,992.00 21,629,944.00
2 - 4.00 Unit 2,038,950.00 8,155,800.00
3 - 8.00 Unit 2,105,650.00 16,845,200.00
4 - 8.00 Unit 1,756,050.00 14,048,400.00
5 - 1.00 Unit 4,339,237.00 4,339,237.00
6 Pas. Partisi Gypsum t=9 mm Rangka Hollow XII. 028 292.00 m2 143,770.00 41,980,840.00
7 Pas. Plint Dinding Partisi - 584.00 m2 45,000.00 26,280,000.00
8 - 502.00 m1 27,000.00 13,554,000.00
146,833,421.00
IV. PEKERJAAN INSTALASI LISTRIK & AIR :
1 XXVII. 004 97.00 ttk 348,459.72 33,800,593.09
2 XXVII. 003 30.00 ttk 282,594.91 8,477,847.30
3 XXVII. 004 18.00 ttk 348,459.72 6,272,275.01
4 - 48.00 bh 295,000.00 14,160,000.00
5 - 38.00 bh 200,000.00 7,600,000.00
6 - 11.00 bh 100,000.00 1,100,000.00
7
-XVII. 016 22.00 m1 17,691.10 389,204.27 XVII. 017 23.00 m1 22,172.08 509,957.93
8
-XVII. 019 20.00 m1 42,966.92 859,338.35
9 XVII. 023 15.00 bh 48,652.95 729,794.20
10 XVII. 025 13.00 bh 37,922.95 492,998.38
74,392,008.53
V. PEKERJAAN LAIN - LAIN
1 XVIII. 012 1,337.00 m2 28,959.02 38,718,215.09
2 XVIII. 034 600.00 m2 29,904.43 17,942,657.88
3 XVIII. 034 35.14 m2 29,904.43 1,050,841.66
4 - 259.37 m2 46,000.00 11,931,020.00
5 - 1.00 ls 5,000,000.00 5,000,000.00
6 - 1.00 ls 5,000,000.00 5,000,000.00
7 - 1.00 ls 15,000,000.00 15,000,000.00
8 Instalasi Penangkal Petir + Grounding - 1.00 ls 14,000,000.00 14,000,000.00
108,642,734.63
HARGA SATUAN JUMLAH
Rp. Rp.
1 PEKERJAAN LUAR
I. PEKERJAAN TANAH :
-1 III. 003 118.00 m3 30,170.48 3,560,116.64
2 VI. 001 1.40 m3 238,660.42 334,124.59
3 VI. 001 11.00 m3 238,660.42 2,625,264.62
4 III. 013 39.45 m3 14,458.83 570,400.86
7,089,906.71
II. PEK. BETON BERTULANG :
-1 XIX. 005 1.70 m3 793,315.71 1,348,636.71
2 XIX. 171 1.20 m3 4,331,560.21 5,197,872.25
6,546,508.96
III. PEKERJAAN SALURAN :
-1 VIII. 005 189.00 m2 94,247.76 17,812,826.51
2 X. 012 283.50 m2 52,070.36 14,761,946.44
3 XVII. 045 158.00 m1 236,563.87 37,377,091.01
4 XVII. 037 8.00 bh 602,327.66 4,818,621.25
74,770,485.22
IV. BAK BUNGA :
-1 III. 003 118.00 m3 30,170.48 3,560,116.64
2 VI. 001 11.00 m3 238,660.42 2,625,264.62
3 VIII. 005 189.00 m2 94,247.76 17,812,826.51
4 XI. 047 70.00 m2 176,413.26 12,348,928.08
5 - 70.00 m2 42,000.00 2,940,000.00
39,287,135.86
Pengecatan Batu Alam Dengan Vernis
Pas. Bak Kontrol 60 x 60
Galian Tanah Saluran
Urugan Pasir Bawah Pondasi Ralag Pas. Dinding Bata a.d 1:5 Pas. Batu Alam Andesit
Urugan Tanah Kembali Bekas galian
Pek. Beton Tumbuk Lantai Kerja RAM 1:3:5
Pek. Cor Beton Ram, Beton Ready Mix K-225, Besi = 160kg/m3,
Pas. Dinding Bata a.d 1:5 Pas. Plesteran Biasa 1:5 + Acian
Pek. Terbuka U-Ditch, type U-20, uk. 20 x 20 cm, tebal 6 cm,
ANA-VOLUME LISA
Galian Tanah Saluran Urugan Pasir Bawah Ram Urugan Pasir Bawah Pondasi Ralag Pengecatan List Plafon Setara Metrolith Water Profing Atap dan Canopy
Pelaporan , As-Build Drawing dan Dokumentasi Pek. Perapihan & Pembersihan.
Profil Ornamen Betawi
NO. URAIAN PEKERJAAN
Instalasi Air Kotor & Air Hujan Pipa PVC 2 "
Pas. Kran Air
Pas. Floor Drain Ø 3" Lokal
Pengecatan Dinding setara ICI/Dulux Warna Biasa Pengecatan Plafon Setara Metrolith
Pas. Lampu RM 2 X 18
Pas. Lampu Down Light PL 20 Watt Pas. Lampu Neon Phillips PL 20 Watt Instalasi Air Bersih
Pipa PVC 3/4" Pipa PVC 1" Kusen pintu PT Kusen Pintu jendela J 4
Pas. List Profil Plafond Gypsum 7 CM
Pek. Instalasi Titik Lampu 3x2.5 mm Eterna Pek. Instalasi Stop Kontak 2x2.5 mm Eterna Pek. Instalasi Stop Kontak AC 3x2.5 mm Eterna Pas. Closet Duduk Setara HCG
Pas. Kitchen Zink lengkap Accessories Pas. Jet Washer
Kusen pintu P 2 Kusen pintu P 4 Kusen pintu P 5
Pek. Meja Pantry, Beton Ready Mix K-225, Besi = 88kg/m3, Bekisting Multip
Pas. Plesteran Biasa 1:5 + Acian
Pas. Plint Lantai 20/40 warna setara Masterina KW I
Pas. Keramik Dinding 20/25 Corak/Warna setara Masterina KW II Pas. Keramik Lantai 20/20 Corak/Warna Setara Masterina KW I Pas. Keramik Meja Pantry 20/20 Corak/Warna Setara Masterina KW I
NO. URAIAN PEKERJAAN ANA- VOLUME
REKAPITULASI TOTAL : LANTAI 1
I. PEKERJAAN PERSIAPAN Rp. 22,684,804.58
II. PEKERJAAN TANAH Rp. 97,927,829.01
III. PEKERJAAN BETON Rp. 8,807,250.32
IV. PEKERJAAN PASANGAN Rp. 135,136,474.74
V. PEK.KUSEN,PINTU & JENDELA + PLAFOND Rp. 121,719,255.00
VI. PEKERJAAN TANGGA Rp. 65,538,777.86
VII. PEKERJAAN INSTALASI LISTRIK Rp. 86,457,383.75
VIII. PEKERJAAN LAIN-LAIN : Rp. 56,265,996.11
JUMLAH. Rp. 594,537,771.36
LANTAI 2
I. PEK. BETON BERTULANG Rp. 1,342,149.45
II. PEKERJAAN PASANGAN Rp. 117,814,685.55
III. PEKERJAAN KUSEN,PINTU & JENDELA+PLAFOND : Rp. 146,833,421.00
IV. PEKERJAAN INSTALASI LISTRIK & AIR : Rp. 74,392,008.53
V. PEKERJAAN LAIN-LAIN : Rp. 108,642,734.63
JUMLAH. Rp. 449,024,999.16
REKAPITULASI TOTAL : LANTAI LUAR
I. PEKERJAAN TANAH Rp. 7,089,906.71
II. PEKERJAAN BETON Rp. 6,546,508.96
III. PEKERJAAN SALURAN Rp. 74,770,485.22
IV. PEK.BAK BUNGA Rp. 39,287,135.86
JUMLAH. Rp. 127,694,036.74
REKAPITULASI : LANTAI 1 + LANTAI 2 + LUAR
REKAPITULASI LANTAI 1 Rp. 594,537,771.36
REKAPITULASI LANTAI 2 Rp. 449,024,999.16
REKAPITULASI LUAR Rp. 127,694,036.74
JUMLAH TOTAL Rp. 1,171,256,807.27
PPN 10 % Rp. 117,125,680.73
JUMLAH TOTAL Rp. 1,288,382,487.99 1,292,750,000.00
DIBULATKAN. Rp. 1,288,382,000.00 4,368,000.00
(DOMISILI PERUSAHAAN,TANGGAL BULAN TAHUN) PENAWAR,
CV/PT.
NAMA PEMIMPIN PERUSAHAAN JABATAN
KEPALA SEKSI PERENCANAAN DINAS TATA KOTA, BANGUNAN DAN PEMUKIMAN
KOTA TANGERANG SELATAN SELAKU PEJABAT PELAKSANA TEKNIS KEGIATAN
RADITYA SUKMA UTAMA, ST, MT.
NIP. 19790116 200212 1 003