1. OVERVIEW OF THE SYSTEM
2. INTRODUCTION OF THE MAIN EQUIPMENT
‐ YARD LIGHTING SYSTEM
‐ OUTDOOR STREET LIGHT
‐ BUILDING LIGHTING
3. OPERATING THE EQUIPMENT
‐ OPERATING THE HIGH MAST LIGHTING SYSTEM
‐ OPERATING OUTDOOR STREET LIGHT
‐ OPERATING THE BUILDING LIGHTING
LEGEND:
: High Mast Lighting System : Outdoor Street Light
: Building Lighting
RMU‐AD MV‐SWGR
TR 1250KVA
LVSB‐AD (LVMDB)
G GENSET650KVA,
0.4KV
A T S P
L N N
P C
A P
E P
MDB‐LT.2 MDB‐LT.3
MDB‐LT.1
HMP 1.2 HMP 1.1
HMP 2.1
HMP 3.1
HMP 3.2
ADMIN AREA STREET LIGHTS
(8 NOS)
LVSB‐XR
HMP 5.1 HMP 5.2 HMP 5.3 HMP 5.4
HMP 2.3 HMP 2.3 HMP 4.1 HMP 4.2
UTILITY AREA STREET LIGHTS
LVDB A
LVDB B
LVDB CD
LVDB EF
LP‐
OM
LP‐
FEG
LIGHTING SYSTEM POWER SUPPLY
1. HIGH MAST LIGHTING SYSTEM
High Mast lighting system are ports main lighting system. It placed all over the port with determined number of lights and direction to cover the whole area. It has 35m height and numerous lighting fixtures installed on top of the high mast pole.
1. HIGH MAST LIGHTING SYSTEM
2. OUTDOOR STREET LIGHT
To illuminate the area around admin landscape and utility landscape, general outdoor street lights is used. With height around 12m, the area were illuminated with 120W LED lighting fixtures.
3. BUILDING LIGHTING FIXTURES
To illuminate the area inside building, various lighting fixtures is used.
OPERATING THE HIGH MAST POLE 1. Power ON Automatic Operation
To Perform automatic operation:
1. Ensure the selector is in “AUTO” position 2. Check if the lighting works automatically.
NOTE: High mast lighting pole will automatically turned on at around 6 pm (ON by timer) or if
there are not enough illumination (ON by photocell)
OPERATING THE HIGH MAST POLE 2. Power ON Manual Operation
To Perform normal operation:
1. Switch selector to “MAN” position
2. Push “ON” Button, Lighting Fixtures will ON 3. To go back, simply Switch the selector to
“AUTO” and it will back to automatic operation.
Turn Selector to “MAN” Push ON Button
OPERATING THE HIGH MAST POLE 3. Lowering the Carriage Rings
Install Ring Support Turn OFF all sub mcb except for motor Turn off mcb inside HMP
Take off socket plug inside HMP
Clear Surround Area before lowering Lower the ring using provided remote
OPERATING THE HIGH MAST POLE 3. Lowering the Carriage Rings
Ensure to Check all the locking
Lower the ring carefully while arranging the cable so it will not entangled Lower until all support
holds the ring safely
OPERATING THE HIGH MAST POLE 4. Raising the Carriage Rings
Raise the ring using provided remote Check surrounding, ensure
No obstruction
While Raising, cable is also pulled down, Arrange so it wont entangled
Guide the sling to avoid bad rolling and friction
OPERATING THE HIGH MAST POLE 4. Raising the Carriage Rings
When ring arrived on top, Ensure to lock the locking
Plug back the socket Turn ON the lighting fixtures MCB
Do not forget to set operation on “AUTO” mode
OPERATING THE HIGH MAST POLE WARNING:
Prior to Operate the High Mast (Lowering/Raising), the wind velocity must be checked to avoid
accident (ring crashing, cable entangling, etc.). The allowable wind velocity to perform the operation is no more than 10 knots or 18.52 km/h.
To check the wind velocity, a simple way is by using windsock. And the following condition of windsock can be used as reference to get the approximate of wind velocity:
OPERATING THE OUTDOOR STREET LIGHT
1. Automatic / Manual Operation for ADMIN AREA Street Lighting
When the selector is in “MAN”
Position, the Panel will directly sent the power and turn the Lights ON When the selectr is in “AUTO”
position, the panel will sent the
power via timer, and will turned on around 6 pm.
The Panel In Charge for Admin Area Street lights is MDB‐LT.1 Which is located near the guard house building EF.
OPERATING THE OUTDOOR STREET LIGHT
2. Automatic / Manual Operation for UTILITY AREA Street Lighting
When the selector is in “MAN”
Position, the Panel will directly sent the power and turn the Lights ON When the selectr is in “AUTO”
position, the panel will sent the
power via timer, and will turned on around 6 pm.
The Panel In Charge for Utility Area Street lights is MDB‐LT.3 Which is located Inside O&M Building
OPERATING THE BUILDING LIGHTING
Operating the lighting fixtures inside building can be done by simply
turned ON/OFF the switch which are installed in every room.