Ground Improvement by Consolidation
Methods of application:
Preloading with or without vertical drains
Electro-osmosis
Vacuum consolidation
Preloading with or without vertical drains
Preloading is usually accomplished by placing surcharge fills
To accelerate consolidation, vertical (sand or prefabricated wick) drains are often used with preloading
Principle and Mechanism
Coefficient of Surcharge: Ratio of weight used in preloading and wt.
of the final structure to be
constructed on the improved soil
Using a surcharge higher than
work load, soil always remains in an overconsolidated state
secondary compression for overconsolidated soil is much smaller than that of normally consolidated soil
Increasing the time of temporary overloading or size of the
overload, secondary settlement can be reduced /eliminated.
Preloading
• Simply place a surcharge fill on top of the soil that requires consolidation
• Once sufficient consolidation has taken place, the fill can be removed and construction takes place
• Surcharge fills are typically 10-25 feet thick and generally produces settlement of 1 to 3 feet.
• Most effective in clay soil
Advantages of preloading
• Requires only conventional earthmoving equipment
• Any grading contractor can perform the work
• Long track record of success
Disadvantages of preloading
• Surcharge fill must extend horizontally at least 10 m beyond the perimeter of the planned
construction, which may not be possible at confined sites
• Transport of large quantities of soil required
• Surcharge must remain in place for months or
years, thus delaying construction
8
Preloading
Preloading at West Kowloon Expressway, Hong Kong.
(5-10 m embankments for 2-5 months)
Vertical Drains
• Vertical drains are installed under a surcharge load to accelerate the drainage of impervious soils and thus speed up consolidation
• These drains provide a shorter path for the water to flow through to get away from the soil
• Time to drain clay layers can be reduced from
years to a couple of months
Vertical Drains
Sand drains
• sand drain is basically a hole drilled in a cohesive soil and filled with sand.
• Since the sand has larger particle size, its permeability is much higher, thus water will flow through it much more easily.
• The excess water is collected at the top and directed away from the jobsite.
• Simply drill the holes and fill them with sand, but if the soil is soft (which is frequently the case,) the holes will collapse.
Sand drains
Typically 200-500 mm in dia.
Formed by infilling sand in to a hole in the ground.
Hole formed by driving ,jetting or augering.
Typical spacing 1.5 - 6.0 m.
PVD (Prefabricated Vertical Drain)
• Geosynthetics used as a substitute to sand drain
• Installed by being pushed or vibrated into the ground
• Most are about 100
mm wide and 5 mm
thick
EQUIPMENT
PVD installation equipment can be developed to suit the soil condition, installation depth, specified scope of work and re- quired production rate. Technical data of typical medium-sized PVD installation equipment and accessories are shown below.
Installation Rig
Type of Base Machine : Excavator of suitable model CAT EL200B or larger model Size (CAT EL200B) : 3.18m x 4.45m
Weight (CAT EL200B) : 20 ton
Pushing Force : 5.5 – 20 ton
Mandrel Lifting and Pushing : Hydraulic gear drive
Mast Height : 8m
Typical Mandrel Dimensions
Weight of Guide and Mandrel : 1.5 to 4 ton Length of Mandrel : 12 to 20m Cross-sectional Area of Mandrel : 60 to 70 cm2
Maximum Installation Depth : 11 to 19m
INSTALLATION METHODS OF VERTICAL DRAINS
GROUP DESCRIPTION
PARTICULAR METHODS
REMARKS
DISPLACEMNT METHODS
Driving Vibration
Pull Down(static Force)
Washing
Combinations Of Above
A mandrel with or without a disposal shoe is used in each case
GROUP DESCRIPTION
PARTICULAR METHODS
REMARKS
DRILLING METHODS
Rotary drill, with or without a casing
Rotary anger, including continuous standard and hollow fight augers
Percussive(shell and auger) methods, with or
without casing Hand auger
A mandrel with or without a disposal shoe is used in each case.
Continued…
GROUP DESCRIPTION
PARTICULAR METHODS
REMARKS
WASHING METHODS
Rotary wash jet Washed open
ended case Weighted wash jet
head on flexible hose
Methods in which sand is washed in via the jet pipe are not suitable for
prefabricated drains
Continued…
Vertical Drain
Installation of drains on a barge
Typical installation of PVD
• Typically spaced 3 m on centers
Prefabricated Vertical Drains Available in US
•Alidrain
•Aliwick
•Ameridrain
•Colbond Drain
•Mebradrain
The drain which is
placed inside the
mandrel with tip
anchor
The details of PVD and tip anchor.
Horizontal Stripdrain
Instrumentation of Vertical Drains
Settlement Platform Permanent Fill
Soft Clay Vertical Drain
Firm Soil
Piezometers
Surcharge
Drainage Blanket
Not to Scale
How are PVD designed?
• The vertical wick drains are usually placed in a triangular configuration of 3 to 12 feet (1 to 4
meters) - depending on the desired consolidation time. As a result of this method of accelerating the consolidation process, uneven post-
construction settlements can be virtually
eliminated.
LAYOUT CONFIGURATION AND DRAIN INFLUENCE ZONE
PVDs are installed in either square or triangular patterns. A square pattern is more simple for setting out in the field. Triangular pattern however provides more uniform consolidation between drains.
Relationship of drain influence zone (D) to drain spacing (S) can be expressed by;
For square pattern D = 1.13 S For triangular pattern D = 1.05 S
TYPICAL APPLICATIONS
PVDs with surcharge as pre-loading method has been successfully appplied in various projects.
PVDs are typically used as ground improve- ment system in -
• Construction of road, railway, embankment, airport and ports
• Industrial projects
• Land reclamation projects
Case history – EADS Airbus Plant, Hamburg General overview of Airbus site
• Settlement ≥ 2,0 – 5,5 m
• Dyke construction to +6.5 in 8.5 month and to + 9.00 in 16 month
• Columns GCC Settlement 0,7 – 1.84 m
Temporary sheet pile wall – in 5 month – dyke construction in 3 years
Dyke construction to +6.5 in 8.5 month and to + 9.00 in 16 month
Columns GCC Settlement 0,7– 1.84 m
Settlement≥ 2,0 – 5,5 m
Basic design and alternate concept of Moebius–Menard
Subsoil characteristics
How to move on the mud !
Case history – EADS Airbus Plant, Hamburg
Case history – EADS Airbus Plant, Hamburg
Case history – EADS Airbus Plant, Hamburg
Case Study For Ground Improvement Using PVD With Preloading For Coal & Iron
Ore Stackyard
Project Details
Development of New Port at Gangavaram at 15 km south of Visakhapatnam Port , AP Development of Port Facilities included development of backup facility for coal and iron ore storage and stacking and handling
The Proposed Heights were – Coal Stacks : 12.00 m
Iron Stacks : 10.00 m
Sub-soil stratification
• Ascertain Design
Parameters
• 8 Nos Boreholes
Geotechnical Investigation
• Dredged Sand: 0.20~0.30 m thick
• Marine Clay with Shells:
1.00~3.00 m thick
• Soft Marine Clay:
7.00~15.00 m thick
• Below 12- 18m N values increased to a tune of 30 Stratification
Improvement Required
Natural Moisture content
12 - 81 %
Specific Gravity 2.52 – 2.65 Bulk Density 1.24 –
1.52 g/cc
Gravel 00 %
Sand 2 – 31 %
Silt + Clay 7 – 63 %
Liquid Limit 21 – 102 %
Plastic Limit 15 – 47 %
Initial Void Ratio, e0 0.627 – 2.249 Compression Index, Cc 0.38 –
0.92 Coefficient of
Consolidation, Cv
0.72 –
1.95 m²/y r
Cohesion, Ccu 0.19 –
1.05 kg/
c m² Angle of Friction, Φcu 18 – 29 Deg Shear Strength from
VST 0.095 –
0.991 kg/
c m²
Ground Improvement Scheme
Depth of
PVD 10.00 m to 18.00 m below OGL
Spacing of (TriangularPVD
)
1.00 m c/c below stacker reclaimers
1.50 m c/c in other area
Consolidati For
on Period
1.00 m spacing:
65 days
For 1.50 m spacing:
174 days
Thickness of Sand
Mat 300 mm
Horizontal Drainage
System
Geotextile pipes filled by boulders / gravels;
PVD laid horizontally
Machinery
Used Hydraulic Stitchers
Post treatment Assessment & Analysis
Ana
Readings every 4 days when loading started.
Later at every 7 days Settlement Recorders
Plate Type: 13
Nos Magnetic: 7 Nos
Piezometers
Casagrande : 5
Nos Vibrating Wire : 14 Nos
Post Treatment Assessment
SECTION - C-C'
Hard / Stiff Strata
PreloadAsPerDesign
GL
Soft Clay 6m
9m 9m 3mMS 6m CP PS
VWP
AREA - B
AREA - A Section 3
IN 8
Section 2 Section 1
CP2(9m) VWP4(6m)
CP3(6m) CP1(9m)
CP4(9m) MS6
VWP5(6m)
VWP6(9m)
Vwp8(9m) VWP7(6m)
VWP9(6m)
VWP10(6m) VWP11(9m)
VWP3(6m) VWP2(6m) VWP1(9m)
MS3
MS4
MS5
MS1
MS2 PS3
PS4
PS5
PS6
PS7 PS10
PS9
PS8 PS1
PS2 IN 3
IN 6 IN 9
)
PS13 C'
C IN 4 IN 2
Section 4
IN 7 IN 1
IN 5
Section 5
IN 10 CP 5 (6m )
VWP13(6m) VWP12(9m
MS7 VWP14 (9m) PS12 PS11
Analysis of Data
Excess Pore Pressure Settlement
%U UmaxUt UtUi x100
x100
%U S100
St
Asaoka Method
Settlement at equal time intervalΔ t
Points (Si, Si-1) are plotted
Interception of this line with line having slope = 1
Settlement S100
Hyperbolic Method Graph of Time
/ settlement Vs Settlement Graph in the
form of Hyperbole Inverse of
slope of Hyperbola Settlement
S100
800 700 600 500 400 300 200 100 0
0 100 200 300 400 500 600 700 800 Settlements (Si-1)
Settlements(Si)
Asaoka Method - PS2
1.0 0 0.9 0 0.8 0 0.7 0 0.6 0 0.5 0 0.4 0 0.3 0 0.2 0 0.1 0 0.0 0
0 5 0 1 0 0 1 5 0 2 0 0 2 5 0 3 0 0 3 5 0 4 0 0 4 5 0 5 0 0
T i m e ( D a y s ) Time /Settlements
H y p e r b o l i c M e t h o d - P S 2
Analysis of Data – Pore Pressure
1.40 1.30 1.20 1.10 1.00 0.90 0.80 0.70 0.60 0.50 0.40
0 25 50 75 100 125 150 175 200 225 250 275 300
CP 1 CP 2 CP 3 CP 4
1.40 1.30 1.20 1.10 1.00 0.90 0.80 0.70 0.60 0.50 0.40
0 25 50 75 100125150175200225250275300 VP 2 VP 11 VP 10 VP 9 VP 8 VP 5
Piezome
t er Ui Umax Ut % U
CP 1 0.543 0.884 0.665 64.22
CP 3 0.579 0.981 0.688 72.89
CP 4 0.843 1.035 0.889 76.04
VP 2 0.597 1.062 0.753 66.45
CP 2 0.807 1.189 1.039 39.27
VP 5 0.534 0.918 0.793 32.55
VP 8 0.621 0.961 0.835 37.06
VP 10 0.567 1.004 0.833 39.13
VP 11 0.920 1.226 1.070 50.98
VP 9 0.610 1.222 0.894 53.59
Analysis of Data
0
100
200
300
400
500
600
0 25 50 75 100 125 150 175 200 225 250 275 300
Settlement(mm)
No of Days
Settlement PS1 PS2 PS4 PS6 PS9 PS10
Settleme
nt Marker Observed Settleme nt
Asaoka Method Hyperbolic Method
S100 % U S100 % U
PS 1 532 460 115.65 833 63.87
PS 2 385 380 101.32 556 69.24
PS 4 261 335 77.91 500 52.20
PS 10 390 450 86.67 732 53.28
PS 6 239 260 91.92 735 32.52
PS 9 289 340 85.00 667 43.33
Conclusions
• Plate Settlement Recorders are more reliable than the Magnetic Settlement Recorders for marine clays.
With the application of the load the pore pressure increased and dropped down slowly with time. The pore pressure variation indicated about 55 - 60 % dissipation i.e. degree of consolidation.
Hyperbolic Method is more comparable with the Pore Pressure Dissipation Results. Further the results obtained with theoretical slope of hyperbola as 1.00 are more closer to the predicted by pore water pressure analysis.
The consolidation settlements worked out theoretically from laboratory test results were much higher than that predicted by Asaoka and Hyperbolic Method
Electro-osmosis
The process of dewatering assisted by the application of a direct electric current is known as electro-
osmosis thus resulting in consolidation
soft clays whose moisture content cannot be reduced by conventional dewatering methods.
In Electro-osmosis method, Electrodes are installed in the soil and a DC current supplied which results water movement from anode to the cathode
A wellpoint system or ejector well system used as
cathode which collects and removes the water from the
ground.
Mechanism
Electro-osmosis transports water of the clay pore space to the cathodically charged electrode
When these cations move toward the cathode, they also bring water molecules along with them
These water molecules clump around the cations as a consequence of their dipolar nature
Macroscopic effect of this process is reduction of water content at anode and an increase in water content at the cathode
Free water appears at the interface between the clay and the cathode surface
Molybdenum Electrodes
Graphite Electrode
Shapes of Electrodes Metallic Electrodes
Electrodes Before Installation
Connecting Wires
DC Current Source
Flow of Water under Electro-osmosis
Advantages and Limitations
Advantages
Can be used for dewatering of silty and clayey soils which are difficult to drain by gravity.
Method is fast and instantaneous.
Environment-friendly method
Equipments required are few in number and easy to carry to the site.
Method useful for all types of soils.
Efficiency of this method is very high.
Less man-power required to implement this method.
Limitations
• Practical application limited since very costly.
• Before actual application on site Laboratory tests and site tests are imperative.
• Huge amount of electricity.
needed
• Highly skilled labour needed
• Electrodes replacement needed from time to time.
• Method becomes ineffective If the moisture content of the soil is extremely low
Vacuum consolidation
Vacuum consolidation
,Both liquid and gas (water and air) are extracted from the ground by suction
This Suction is induced by the creation of vacuum on the ground surface and assisted by a system of vertical and horizontal drains
Vacuum is applied to the pore phase in a sealed membrane system
The vacuum causes water to drain out from the soil and creates negative pore water pressure in the soil
This leads to an increase in effective stress to the magnitude of the induced negative pore water pressure, without the
increase of total stress
•For rapid pre-consolidation, vertical drains (Prefabricated Vertical Drains) along with the vacuum preloading are used
•Vertical drains helps to distribute the vacuum pressures to the deeper layers and drain out water from the sub soil
•Vacuum preloading with PVD substantially reduces the lateral displacement and potential shear failure
•Maximum achievable
vacuum pressure in the field
is only about 80kPa Schematic view vacuum consolidation technique
VACUUM (J.M. COGNON PATENT)
Vacuum Consolidation (high fines contents soils)
CONCEPT
-Soil is too soft for surcharge
-Time does not allow for step loading -Surcharge soil not available
-Available area does not allow for berns
• PARAMETERS
1 – Depth
2 – Drainage path
3 – Condition of impervious soil 4 – Watertable near surface
• 5 - Absence of pervious continuous layer 6 – Cohesion
7 - Consolidation
parameters (oedometer, CPT)
• eO, CC, CV, CR, Cα, t,
• CPT dissipation test
8 – Theoretical depression value 9 – Field coefficient vacuum
10 – Reach consolidation to
effective pressure in every layer 11 – Target approach
Vacuum Consolidation
Advantages of Vacuum preloading technique over the Surcharge preloading technique
•Ground improvement with vacuum preloading does not require any fill material and there is no need of heavy machinery
•Construction period is generally shorter
•The increase in effective stress under vacuum preloading is isotropic. Therefore, the corresponding lateral displacement is in the inward direction and there is no risk of shear failure
•Application of Vacuum Preloading improves Bearing capacity of soil by 100% in the case of soft clays and eliminates 70% of the total estimated settlement of design load
•The overall cost of vacuum preloading is only about 2/3rd of that with surcharge preloading
VACUUM CONSOLIDATION IN PEAT
CASE STUDTY IN DUBLIN
0.85m sq.
spacing
1.2m sq.
spacing
TCD/NRA VACUUM CONSOLIDATION FIELD TRIAL
TCD/NRA VACUUM CONSOLIDATION
FIELD TRIAL - INSTRUMENTATION
Pumping system: 30
thNov 2009 – 23
rdJun 2010
• 1.5kW Centrifugal pump
• 38mm diameter jet pump
Pumping system: 29
thJul 2010 – 29
thOct 2010
• 2.2kW Liquid ring pump
• 1.5kW Centrifugal pump
• 38mm diameter jet pump
• Prior to starting the TCD/NRA vacuum
consolidation field trial, four months of baseline monitoring were conducted.
• The vacuum consolidation trial was run from 30
thNovember 2009 and was terminated on 29
thOctober 2010
MONITORING BEFORE PUMPING
Flooding in August 2009
• The TCD/NRA vacuum preloading field
trial commenced on the 30th November 2009.
• The results for the eleven months of pumping presented here.
• Rain, water table, vacuum, settlement and pore water pressure are presented.
MONITORING DURING PUMPING
Visual 1 st June 2010
CRACKS AT EDGE
Ground Improvement by Consolidation
Key Issues associated with consolidation:
Stability during surcharge placement,
Clogging of vertical drains, and
Maintenance of the vacuum.
System Stability
To safeguard against stability problems, the surcharge loads are often placed in stages
Each stage of loading is added only after the soil has acquired sufficient strength under the influence of the previous stage to support the new load
Build up and dissipation of the excess pore water pressure and the accompanying soil deformations are monitored to pinpoint the time for stage placement
In case of electro-osmosis or vacuum consolidation no stability problem is anticipated
Clogging of Drains
•Clogging of the vertical drain is a key issue affecting the feasibility of the system of ground improvement
•Major advantage of the plastic wick drains over sand drains is their flexibility and ability to sustain large deformations of the consolidating cohesive soil, which may otherwise shear and clog the sand drains, rendering them ineffective
•The hydraulic conductivity of the wick drains is influenced by the potential crimping of the material when large deformations take place or clogging of the drainage channels due to an
ineffective filter jacket
•A non-wooven geotextile fabric is usually used to provide filtering and ensure the hydraulic conductivity of the
prefabricated drains
Maintenance of the Vacuum
• Maintaining the vacuum by providing an all-around seal is
critical for the successful application of vacuum consolidation
• Resistance of the membrane to tear during and after placement is an important factor
• Membrane is covered by a layer of soil or by water ponding to prevent its tear by vehicles, animals or birds attacks, or
vandalism
• Vacuum is generated by circulation of air through a series of specially designed drains, installed to the depth of the layer to be consolidated (new system developed recently in France eliminated the need for the membrane)