Dr. Ir. Pintor T. Simatupang, MT.
Sekjen Himpunan Ahli Teknik Tanah Indonesia (HATTI)
Pengurus Lembaga Pengembangan Jasa Konstruksi Nasional (LPJKN)
OJT Terowongan, 5 - 8 Maret 2018 Balai Diklat III, JAKARTA
SNI 8460 : 2017
Outline
ü Historical Background of Tunnel ü The Need of Shield Tunnel
ü Tunnel Boring Machine (TBM) ü Geologic Condition
ü Settlement on Ground Surface ü Lining
Historical Background
1,036 m
(3,399 ft)
length in
Samos, Greece,
built in the 6th
century BC
Historical Background
Historical Background
Historical Background
Historical Background
Historical Background
Historical Background
The Need of Shield Tunnel
The Need of Shield Tunnel
The Need of Shield Tunnel
The Need of Shield Tunnel
Membangun terowongan di daerah perkotaan
Bangunan di atas tanah
tidak boleh terganggu
Shield Tunnel (Terowongan Perisai)
Tunnel Boring Machine (TBM)
Shield Tunnel (Terowongan Perisai)
Thames River in London
Marc Brunel
Dibangun tahun 1825
Soft Soil
Geologic Condition Geometri Terowongan
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Tunnel Boring Machine (TBM)
Cutterhead
Segmental Lining
• Type of Machine
• TBM design conditions
• Design Basis
• TBM Components
• Manufacturing of TBM
• Maintenance of TBM
Tunnel Boring Machine (TBM)
Face system Type of TBM
Closed Earth Pressure Balanced (EPB) Slurry
Open
Mechanical Semi-mechanical Manual excavation
Tunnel Boring Machine (TBM)
Slurry TBM
Applicability of machine type
Soil type TBM type
Open type Closed type
Classification SPT
blow Semi-
mechanical mechanical EPB
Slurry W/o injection With injection
Alluvial clay
Humus 0 NA NA NA AC AC
Clay, silt 0 - 2 NA NA A A A
Sandy silt Sandy clay
0 - 5 NA NA A A A
5 - 10 AC AC A A A
Diluvial clay
Loam, clay 10 - 20 A AC AC A A
Sandy loam Sandy clay
15 - 25 A A AC A A
25 - A A AC A A
Softrock Mudstone 50 - AC AC AC AC AC
Sandy soil
Sand w/ clay 10 - 15 AC AC A A A
Loose sand 10 - 30 NA AC AC A A
Stiff sand 30 - AC AC AC A A
Gravel,
Loose gravel 10 - 40 AC AC AC A A
Stiff gravel 40 - AC AC AC A A
Gravel with
Major TBM design conditions
Items Remarks
Ground conditions Special care for very soft clay, high water pressure, soil with boulders, and combination of soft and stiff.
Tunnel length The abrasion and durability of each machine component become more important.
Tunnel alignment Articulation jacks are needed and copy cutter needs to be check for extra excavation in case of curve.
Tunnel depth Special care for higher pressure
Sealing capacity needs to be paid attention where water pressure is high
TBM Design Basis
Ø For the initial planning
Ø Closed-type machine weight
Ø For single track approx. 200 ton Ø For double track approx. 1000 ton.
Ø Machine length (no articulation jacks )
Ø For single track approx. 5 to 6 m
Ø For double track approx. 6 to 8 m.
Geologic Condition
Preliminary
Investigation Basic
Investigation Detail Investigation
Purpose
1. Understanding general
conditions of topography, soil and geological structures 2. Predicting
problematic soil and obtaining following investigation data
1. Understanding soil and geological structures along the entire route 2. Understanding
soil properties 3. Preparation of
geological profile
1. Supplemental soil
investigation 2. Detailed soil
investigation on critical elements for design and construction 3. Design
information for special conditions, such as earthquakes
Geologic Condition
Method 1. Collecting and compiling existing information 2. Collecting and
compiling information on similar and nearby projects
3. Document investigation 4. Observation during a
site survey
1. Borings 2. Standard
penetration tests 3. Core sampling 4. Groundwater level
survey
5. Porewater pressures measurement 6. Laboratory soil tests
1. Borings 2. Standard
penetration tests 3. Core sampling 4. Porewater pressures
measurement 5. Permeability tests 6. Laboratory soil tests 7. Pressuremeter test 8. Survey on oxygen
deficient air, hazardous and flammable gases 9. Deep foundation
excavation
Soil Investigation Item
1. Various maps (topographical and geological maps) 2. Existing soil investigation reports
3. Construction reports on previously built structures in the vicinity
4. Wells and groundwater
5. Observation of topography, soil conditions and surrounding areas
6. Ground settlement
Preliminary Investigation
Soil Investigation Item
Basic Investigation
- Stratum composition - SPT blows
- Coefficient of permeability
- Groundwater level and porewater pressure - Core samples
- Particle size distribution - Moisture content
- Soil particle specific gravity - Unit weight
- Unconfined compressive strength - Liquid and plastic limits
- Cohesion
- Angle of internal friction
- Properties of consolidation
Soil Investigation Item
Detailed Investigation
1. SPT blows
2. Coefficient of permeability 3. Groundwater level and
porewater pressures 4. Core samples
5. Particle size distribution 6. Moisture content
7. Soil particle specific gravity 8. Unit weight
9. Unconfined compressive strength
10.Liquid and plastic limits
Soil Investigation Item
Detailed Investigation
1. Cohesion
2. Angle of internal friction 3. Properties of consolidation
4. Speed and direction of groundwater flow 5. Size of cobbles and boulders
6. Modulus of subgrade reaction 7. Seismic velocity
8. Apparent resistivity
9. Rock layer for seismic design
Settlement on Ground Surface
Settlement on Ground Surface
Settlement on Ground Surface
Lining
1. Load
2. Segmental lining
3. Shape and dimension of segment
4. Key segment
Load
Earth Pressure
Design
method Ground condition λ Approx. SPT blow
Effective stress method
Very dense sandy soil 0.45 30 ≤ N
Medium dense sandy soil 0.45-0.50 15 ≤ N< 30
Loose sandy soil 0.50-0.60 N < 15
Total stress Method
Stiff cohesive soil 0.40-0.50 8 ≤ N < 25 Medium cohesive soil 0.50-0.60 4 ≤ N < 8
Soft cohesive soil 0.60-0.70 2 ≤ N< 4
Very soft cohesive soil 0.70-0.80 N < 2
Water pressure
Pw1=γw∙Hw
Hw
Dc
Self weight
A uniformly distributed load in vertical direction.
Surcharge loads
Ø Surface traffic 10 kN/m².
Ø Existing or known future buildings 20 kN/floor/m² unless clearly known
The coefficient of ground reaction times tunnel radius, kN/m
21) Ground condition During hardening process
of tail void grouting *1 After hardening of tail
void grouting *2 Approx. SPT blow
Very dense sandy soil 35.0 – 47.0 55.0 – 90.0 30 ≤ N< 50
Medium dense sandy soil 21.5 – 35.0 28.0 – 55.0 15 ≤ N< 30
Loose sandy soil – 21.5 – 28.0 N< 15
Solid cohesive soil 31.5 – 46.0 – 25 ≤ N
Stiff cohesive soil 13.0 – 31.5 15.0 –46.0 8 ≤ N < 25
Medium cohesive soil 7.0 –13.0 7.5 – 15.0 4 ≤ N < 8
Soft cohesive soil 3.5 – 7.0 3.8 – 7.5 2 ≤ N< 4
Very soft cohesive soil – 3.5 – 3.8 N<2
*1 For design by primary loads or construction load Unit: kN/m2
Ground Reaction
Spring model
B
B B
K
K
K B B
A A A K
K B B
B
K B B
A
A A
α α