• Tidak ada hasil yang ditemukan

Analysis of Value Engineering in the Joint Lecture Building, Airlangga University Campus-C Surabaya

N/A
N/A
Nguyễn Gia Hào

Academic year: 2023

Membagikan "Analysis of Value Engineering in the Joint Lecture Building, Airlangga University Campus-C Surabaya "

Copied!
6
0
0

Teks penuh

(1)

Analysis of Value Engineering in the Joint Lecture Building, Airlangga University Campus-C Surabaya

Leli Puniyawanti, Fredy Kurniawan, Diah Ayu Restuti Wulandari Departement of Civil lEngineering, Faculty of Engineering

Narotama University Surabaya

[email protected] , [email protected], [email protected]

Abstract

The GKB (Gedung Kuliah Bersama) building project is a concept of sharing resorts by integrating student facilities from several faculty levels. The building has 10 floors, with a total area of 20,130 m (2,930 ft), a considerable financing of the building requires optimization and effective financing to avoid having to waste funds for unnecessary expenses. Efforts to optimize cost spending without eliminating the building's function value. By using value engineering analysis. Value engine analysis work using the method analysis life cycle cost (LCC) covering all the costs required in a building starting from the execution stage, maintenance based on building materials according to costing specifications from the university of University C. Based on analysis of the job identification done on aluminum interior of the building's interior, stainless floor work on tile tile tile floor, wood wall acoustic ceiling, heradesign acoustic wall, heradesign acoustic wall, From the initial design reimbursement with the recommendation design, the total cost of the construction cost was 5,508,514,957.29 with a percentage of the total physical cost of construction at 3.5%.

Keywords:

Value Enginering Analysis, Life Cycle Cost (LCC)Analysis, RAB

1. Introduction

Construction would require cost or cost, and of course, the owner or owner of the building would want a minimum cost but with a maximum output or output of the building's quality. Project cost control is a key in the process of project cost management because the activities of the project may occur there are less than optimal use of materials, less skilled labour, irregular use of time will cause increased costs over initial planning. On the architectural job (wall work, a plafond job, floor work, window work, rail work, sanitary work, and so on), it is generally used to make a considerable portion of the budget compared with the rest of the work, hence whether the design is used optimally. This could be done by reviewing the design of the project without correcting the errors made by the planner or correcting its calculations but, rather, leading to the cost savings to be obtained by identifying and reducing unnecessary costs without reducing the quality, reliability, and function of the project.

Hence, some austerity is known in the engineer branch of the study of cost-saving or manufacturing costs called value engineering

Along with the number of students at Airlangga University which continues to grow from year to year, Airlangga University is included as a World Class University which is included in the 465 world rankings, so it will encourage to rebuild lecture buildings for all faculties. One of them is the Gedung kuliah Bersama which is a resort sharing concept by combining various student facilities from several faculties in one place which was built on an area of 2013 m2 which is located on Jalan Mulyorejo Campus C, Universitas Airlangga. This building has 10 floors with a total building area of 20,130 m2, which costs Rp. 156.332,400,000. With such a large amount of funding, optimization efforts and funding effectiveness are needed so as not to experience wasting funds for things that are not needed. Efforts to optimize the cost budget without eliminating the value of the function can be done by applying the Value Engineering method. If viewed from the price per m2, with the building area of the Joint Lecture Building, then the price per m2 is Rp. 7,781,602.78 with a nominal value of that size indicates that the building has a high cost so that cost efficiency is needed. This study aims to determine the total cost savings that can be obtained after applying the Value Engineering method to the work carried out by value engineering, only architectural work for project Gedung Kuliah Bersama

Based on the problems above, the formulation of the problem can be formulated as follows:

1. What finishing work items will Value Engineering do?

2. How much is the value of the alternative material and design work through value engineering analysis (Value Engineering) for building finishing / architectural work?

3. How much cost savings are obtained after implementing Value Engineering?

(2)

2. Method

2.1. Location

This research was carried out in the construction project of the Airlangga University Joint Lecture Building.

2.2. Data Collection Techniques

The data collection technique used in this research is data collection which is divided into two, namely primary data and secondary data.

Primary data is original data that is in the field and only researchers have it, primary data is obtained by direct observation in the field (observation), asking directly to related parties or it can be by way of interviews (interviews).

Secondary data is supporting data in this study. Secondary data were obtained from literature books, reports, documentation, libraries, or previous research reports.

The data collection method is in the form of data collection on the Budget Plan for the construction of the Joint Lecture Building. From the data, the costs incurred during the life of the plan are determined and re- analyzed to obtain cost efficiency in order to save development costs on the project. The author uses secondary data, namely RAB and some existing literature to complete this final project. Secondary data, namely data that is not obtained directly from the data source but is obtained directly from related companies related to the research carried out.

This secondary data is in the form of technical drawings from projects such as project plan drawings in the form of AutoCAD and hardcopy taken from Airlangga University

The data collection technique used in this study is data retrieval is divided into two, namely primary data and secondary data.

Primary data is the original data in the field and only researchers have it, primary data is obtained by way of direct observation on the ground (observation), ask directly to the relevant party or can be by interview (interview).

2.3. Method

The research method for this final project contains the steps for solving a problem using the application of Value Engineering. For this project, the analysis stage is used which consists of the information stage, creative stage, analysis stage, and recommendation stage. (Dell'Isola, 1973)

The information stage is the stage of collecting as much data about the project as possible. This study uses the structural components of the building as a study that will be carried out by Value Engineering. This analysis intends to find high-cost work items, which can be done with several techniques including Cost Model, Breakdown, Pareto Analysis.

Pareto analysis is carried out to determine the highest cost on a project that has the potential to be used for Value Engineering analysis. Pareto's law applies: that is, 80% of the total cost is contained by 20% of its components. The following are the steps in testing Pareto's law:

a. Sorting costs from largest to smallest b. Summing up the cumulative total work costs c. Calculate the percentage of the cost of each job.

d. Calculate the cumulative percentage e. Plot cumulative percentage

Functional Analysis Functional analysis aims to:

a. Classify the main functions (basic function) and supporting functions (secondary function)

b. Obtain a comparison between the costs and the value of the benefits needed to produce the function.

The creative stage of value engineering is exploring alternative ideas and ideas. The method used at this stage is the brainstorming technique. That is one technique of solving problems by discussing together in a team.

The basic principles of this theory are:

a. The quantity of ideas is preferred.

b. Do a combination and improvisation of ideas.

c. All ideas are accommodated without any criticism or evaluation of existing ideas

The analysis stage is carried out with an analysis of advantages and disadvantages which at this stage of analysis has the aim of obtaining and obtaining the best alternative from the ideas or ideas that arise in the creative stage.

(3)

a. Analysis of Advantages and Disadvantages

Profit and loss analysis is the most crude screening stage among the valuation methods used in the valuation stage

b. Life Cycle Cost Analysis

Life Cost Cost of the item that is calculated during the investment period with all costs relevant to the item based on consideration of the Time value of money. Relevant costs or costs incurred during the investment period include:

1. Initial cost which is the initial cost incurred at the time of construction. The initial cost is taken from the initial design cost analysis with unit prices according to local government regulations.

2. Operational are costs incurred due to the use of labor

3. Maintenance are costs incurred according to a certain time interval plan for item replacement. Maintenance costs are specific but not the highest priority.

4. Replacement is the cost of replacing an item which is beyond what we planned to be replaced. During the investment period, it is assumed that replacements are not reported

5. The residual value is the price that exists at the end of the investment period (including the cost of moving).

It is assumed that after the end of the investment period there is no residual value because the items analyzed are assumed not to be sold again.

6. Energy cost is the cost that comes out due to the use of power / energy

The recommendation stage is carried out by recommending the selected alternatives. This study only recommends in tabular form and includes a comparison between the old design and the proposed design and the amount of savings.

At the conclusion stage, a summary of the results of the analysis is presented and answers to the formulation of the problem that underlies the purpose of this research, namely mentioning the work items that need to be value engineering, explaining the best design alternatives, and explaining the amount of savings obtained from value engineering on the selected work items

3. Results And Discussion

3.1. Information Stage

The principle at this stage is the identification of high costs and the identification of high costs and the identification of unnecessary costs. In identifying high costs, the first thing that needs to be done is to create a cost model. Breakdown After the cost model chart is made, a breakdown analysis is carried out to identify which work items have the potential to be carried out by Value Engineering, the costs of these work items are compared with the total cost of the entire project.

Table.1 Breakdown The Budget Plan

Job Description Cost

I. Preparatory Work 21.142.228

Ii. Structure Work

Ii.1. Substructure Work 13.095.250.417

Ii.2 Upper Structure Work 41.465.595.272

Ii. Architect Job 44.853.336.998

Iv. Mechanical Electrical And Plumbing Works 42.341.303.213 V. Occupational Safety And Health 343.780.000

Sub Total Cost 142.120.408.128

Ppn 10% 14.212.040.813

Total Cost 156.332.448.941

Rounded Up Cost 156.332.400.000

The results of the processing of the data above, the work items of the Architectural Pek. work, the Upper Structure work, and the Mechanical Electrical and Plumbing work are the work items that consume the largest cost among other work costs as a whole, which is Rp. 41,465,595,272,-, Rp. 13,095,250,417,- and Rp.

44,853,336,998. From this fact, we will re-do a breakdown analysis on the Architectural work items, to see which jobs cost a lot of money in the construction of the Airlangga University Joint Lecture building project.

From the results of data processing above, it is found that architectural work is the largest contributor to costs. For this reason, a more detailed breakdown of architectural work items will be carried out to see which part contributes the most funds. The following is a presentation of architectural work data.

(4)

The job analysis reviewed is:

1. Aluminum Composite Cover Column, Beam and Finish Guard Lift Works 2. Floor carpet tile work for multi-story classrooms

3. Heradesign wood wool acoustic ceiling + Complete frame with grass will 4. Heradesign wood wool acoustic wall + Complete frame with grass will 5. Bathroom granite wall work

6. Granite floor work 7. Gypsum tile ceiling

8. Installing waterproofing coating

The data processing process used Life Cycle Cost (LCC) analysis in this study at the Joint Lecture building. The calculation of Life Cycle Cost (LCC) is only for wall, floor, and ceiling building elements. Based on Government Regulation no. 36 of 2005, the estimated design life used in this analysis is 20 years.

Table 2 Perbandingan Biaya Desain Awal dan Pemeliharaan N

o Item Job Description First Cost

maintenan ce coefficient

Cost Maintenance A Interior

Wallcoverin g

Alumunium Composite interior work 815.386.528 2,00 1.630.773.05 A

1

Wall painting work/emultion paint 33.486.305 2,86 95.675.158

A Granite installation work 493.876.362 2,00 987.752.723

B Floor

coating

Tile carpet floor work 1.660.787.30 2,86 4.745.106.57 B

1

Ceramic installation work 737.031.243 2,00 1.474.062.48 7 B

2

Granite installation work 1.345.158.91 2

2,00 2.690.317.82 5

C Room

soundproofi ng ceiling

Heradesign woodwoll and grasswoll acoustic 697.683.324 2,00 1.395.366.64 C Acoustic ceiling installation 60x120 cm 83.887.055 2,86 239.677.300 C

2

Gypsum Perforated Ceiling Installation + Grasswoll

155.790.245 2,86 445.114.986

D Room

soundproofi ng wall

Heradesign woodwoll acoustic wall with 532.060.689 2,00 1.064.121.37

D Gypsum Perforated Wall Mounting with 163.896.400 2,00 327.792.800

D 2

Grasswool carpet installation 151.502.389 2,86 432.863.970 E

0

Bathroom granite wall

work

Installation of homogeneous granite tiles 60x60cm

873.632.371 2,00 1.747.264.74 2 E Ceramic Tile installation work uk. 40x40 478.675.305 2,00 957.350.610

E Marble Installation 2.337.003.15 2,00 4.674.006.29

F

0 Granite floor work

Installation of homogeneous granite tile floor 60x60cm

4.136.101.73 9

2,00 8.272.203.47 7 F Ceramic Tile installation work uk. 40x40 2.266.227.56 2,00 4.532.455.13

F Marble Installation 11.064.245.2 2,00 22.128.490.4

G 0

Gypsum tile ceiling

work

Gypsum tile ceiling installation 188.964.636 2,86 539.898.959 G Installation of 9 mm thick gypsum ceiling + 89.672.582 2,86 256.207.377 G Installation of 6 mm thick GRC ceiling + 111.120.066 2,86 317.485.904

H Floor

coating is not

Installation of multiguard waterproofing 511.951.860 4,00 2.047.807.44 H

1

Installation of waterproofing coating ex. Sika 55.177.034 6,67 367.846.892 H Installation of waterproofing membrane ex. 568.835.400 4,00 2.275.341.60 3.2. Recommendation Stage

The recommendation stage is the stage of submitting recommendations and the reasons why the chosen alternative is feasible to replace the initial design.

From the results of replacing the initial design with the recommended design, the total construction cost savings was Rp. 12,604,925.490.68. of the total cost of architectural work of Rp. 44,853,336,998. While the life cycle cost savings (LCC) is Rp. 27,281,353,006.72.

Table 3 Cost Saving

No Type Contruction's Cost (Rp) LCC's Cost (Rp)

First Design First Design First Design First Design 1 Interior wall cladding 815.386.528 33.486.305 1.630.773.057 95.675.158 2 Floor coating 1.660.787.300 737.031.243 4.745.106.572 1.474.062.487 3 Room soundproofing 697.683.324 83.887.055 1.395.366.648 239.677.300 4 Room soundproofing 532.060.689 163.896.400 1.064.121.379 327.792.800 5 Bathroom granite 873.632.371 478.675.305 1.747.264.742 957.350.610 6 Granite floor work 4.136.101.739 2.266.227.566 8.272.203.477 4.532.455.131

(5)

7 Gypsum tile ceiling 188.964.636 89.672.582 539.898.959 256.207.377 8 Floor coating is not 511.951.860 55.177.034 2.047.807.440 367.846.892 TOTAL 9.416.568.447 3.908.053.490 21.442.542.274 8.251.067.755 SAVING 5.508.514.957 13.191.474.519 From the results of cost savings, several materials from the initial design and design recommendations from several items installed in the building appear a comparison of cost values which will be explained in the table below.

Table 4 Preliminary Design and Cost Saving Recommendation Design

No Material Cost

1

Interior Wall Cladding (Columns, Beams And Elevator Axles) First Design Aluminum Composite Cover Columns, Beams And Lift

Guards

815.386.528

Recommendation Wall Painting/ Emultion Paint 33.486.305

2

Floor Coating

First Design Tile Carpet Installation Pekerjaan 1.660.787.300

Recommendation Ceramic Installation Work 737.031.243

3

Room Soundproofing Ceiling Cladding

First Design Heradesign Woodwoll Acoustic Ceiling + Frame And Grasswoll

697.683.324 Recommendation Acoustic Ceiling Installation 60x120 Cm + Concealed Grid

Type Frame

83.887.055 4

Room Soundproofing Wall Cladding

First Design Heradesign Woodwoll Acoustic Wall + Complete Frame With Grasswoll

532.060.689 Recommendation Installation Of Ceiling-High Perforated Gypsum Walls

Complete With Grasswoll

163.896.400 5

Bathroom Granite Wall Work

First Design Installation Of Homogeneous Granite Tiles 60x60cm 873.632.371 Recommendation Ceramic Tile Installation Work Uk. 40x40 478.675.305 6

Granite Floor Work

First Design Installation Of Homogeneous Granite Tile Floor 60x60cm 4.136.101.739 Recommendation Ceramic Tile Installation Work Uk. 40x40 2.266.227.566 7

Pekerjaan Plafon Gypsum Tile

First Design Gypsum Tile Ceiling Installation 188.964.636

Recommendation Installation Of 9 Mm Thick Gypsum Ceiling And Frame 89.672.582 8

Floor Coating Is Not Waterproof

First Design Installation Of Multiguard Waterproofing 511.951.860 Recommendation Installation Of Waterproofing Coating Ex. Sika 55.177.034

4. Conclusions and Suggestions

4.1. Conclusion

Based on the results of the analysis of the application of the Value Engineering method in the Construction of the Joint Lecture Building, it can be concluded that:

1. Some finishing work items that Value Engineering can do are

a. Aluminum Composite Cover Column, Beam and Finish Guard Lift Jobs b. Multi-story classroom carpet tile floor work

c. Heradesign woodwoll acoustic ceiling work complete with grasswoll d. Heradesign woodwoll acoustic wall work complete frame with grasswoll e. Building exterior facade work

f. Granite wall work g. Granite floor work h. Gypsum tile ceiling work i. Installer of waterproofing coating

2. The cost and value of the initial design of the architectural project for the construction of the Joint Lecture Building with the planned materials is Rp. 9,416,568,447,-

(6)

3. The cost and value of the recommended alternative designs for the architectural work of the Joint Lecture Building is Rp. 3,908.053,489,-

4. While the cost savings by using multiple analysis methods is Rp. 5,508,514,957,- with a percentage of the total physical construction cost of 3.5%

4.2. Suggestion

1. In planning a project, the owner needs to know the choice of materials and installed materials so that they get high savings in budgeting.

2. In planning a building construction work, several comparisons of alternative designs are needed, both in terms of alternative designs and materials so that the most economical planning is obtained.

3. For further research, creative ideas can be developed by engineering the value of the lower structure of the building while still paying attention to its function

References

A. J. Dell’Isola, Value Engineering : Practical Applications --for Design, Construction, Maintenance &

Operations. Kingston, Mass. : R. S. Means Company, 1973

Adisaputro, Gunawan dan Marwan Asri (1992) Anggaran Perusahaan. Edisi ketiga Cetakan Kelima, BPFE Yogyakarta. Anthony dan Govindarajan (2004) Manajemen Control System, Editon New York, Richard D.

Irwin. Mc. Grawhill.

Gorinson dan Noreen (2000) dalam Anggraeni (2003). Manajerial Accounting. Terjemahan Budi Santoso, Penerbit Salemba Empat Jakarta.

Hidayat, Rachmad., dkk. 2014. Pengembangan Mesin Fermentasi Roti Menggunakan Pendekatan Value Engineering (VE). Spektrum Industri 12(1): 1-14.

Hutabarat, J., 1995, (Jurnal Sumiati., 2006). Penerapan Rekayasa Nilai Untuk Mendapatkan Nilai Tambah Pada Perusahaan Sandal Wanita, diakses dari http://eprints.upnjatim.ac.id/124/1/210107-47-54.pdf

Latifah, N. L., & Rahadian, E. Y. (2018). Strategi Green Building untuk Optimalisasi Penghematan Energi Operasional Bangunan terkait Rancangan Ventilasi dan Pengkondisian Udara pada Gedung Kantor Pengelola Bendungan Sei Gong - Batam. Jurnal Institut Teknologi Nasional, 2, 7–12.

Nuruddin, M., & Andesta, D. 2008. Pemilihan Mesin Welding Otomatis dengan Penerapan Value Engineering dan Analitical Hierarchy Process. Jurnal Ilmiah Semesta Teknika, 11(1), 74-85.

Park, Richard J. 1999. Value Engineering: A Plan for Invention. CRC Press LLC. Florida

Reqsi Setiawan, dan Wahyu Widiyantoro. (2014). Penerapan Value Engineering Pada Proyek Perumahan Kalipepe Semarang, Skripsi, Fakultas Teknik Unissula, Semarang

Rumintang, A. (2008). Analisa Rekayasa Nilai Pekerjaan Struktur Gedung Teknik Informatika U P N “ Veteran

” JATIM Surabaya adalah pusat pemerintahan propinsi Jawa Timur dan sekaligus pusat perdagangan dan bisnis untuk kawasan Oleh karena itu Surabaya dituntut untuk dapat memen. Jurnal Rekayasa Perencanaan, 4(2), 1–16.

Susilo, E. (2018). Analisis Life Cycle Cost Pada Bangunan Rumah Susun Sederhana Sewa di Daerah Istimewa Yogyakarta. Jurnal Ekonomi Volume 18, Nomor 1 Maret201, 2(1), 41–49.

Biography

Leli Puniyawanti, Born in Surabaya April 21, 1985. Students of the civil engineering faculty of Narotama University Surabaya, with a school history from SDN Keputih 245 Surabaya then continued to SLTP Negeri 19 Surabaya and continued school at SMU Negeri 3 Surabaya and then continued to Diploma III majoring in Civil Engineering Building ITS Surabaya. The author is currently working at Airlannga University Surabaya as a planning staff at the Sub-directorate of Facilities and Infrastructure for the Management Office building.

Referensi

Dokumen terkait

First name Surname/family name Salutation Mr Ms Miss Mrs Other please specify Position title Email Telephone Mobile By signing this form you are declaring: • that the statements