• Tidak ada hasil yang ditemukan

PELAJARI TENTANG HAZOP CASE STUDY

N/A
N/A
Ibu Ardian

Academic year: 2023

Membagikan "PELAJARI TENTANG HAZOP CASE STUDY"

Copied!
22
0
0

Teks penuh

(1)

HAZOP CASE STUDY

(2)

The full HAZOP study requires a committee composed of a cross-section of experienced ' plant, laboratory, technical, and safety professionals. One individual must be a trained HAZOP leader and serves as the committee chair. This person leads the discussion and must be experienced with the HAZOP procedure and the chemical process under review. One individual must also be assigned the task of recording the results, although a number of vendors provide software to perform this function on a

personal computer. The committee meets on a regular basis for a few hours each time. The meeting duration must be short enough to ensure continuing interest and input from all committee

members. A large process might take several months of biweekly

meetings to complete the HAZOP study. Obviously, a complete

HAZOP study requires a large investment in time and effort, but

the value of the result is well worth the effort.

(3)

3

The HAZOP procedure uses the following steps to complete an analysis:

1. Begin with a detailed flow sheet. Break the flow sheet into a number of process units. Thus the reactor area might be one unit, and the storage tank another. Select a unit for study.

2. Choose a study node (vessel, line, operating instruction).

3. Describe the design intent of the study node. For example, vessel V-1 is

designed to store the benzene feedstock and provide it on demand to the reactor.

4. Pick a process parameter: flow, level, temperature, pressure, concentration, pH, viscosity, state (solid, liquid, or gas), agitation, volume, reaction, sample,

component, start, stop, stability, power, inert.

5. Apply a guide word to the process parameter to suggest possible deviations. A list of guide words is shown in Table 10-3. Some of the guide word process

parameter combinations are meaningless, as shown in Tables 10-4 and 10-5 for process lines and vessels.

6. If the deviation is applicable, determine possible causes and note any protective systems.

7. Evaluate the consequences of the deviation (if any).

8. Recommend action (what? by whom? by when?)

9. Record all information.

(4)
(5)

5

(6)

10. Repeat steps 5 through 9 until all applicable guide words have been applied to the chosen process parameter.

11. Repeat steps 4 through 10 until all applicable process parameters have been considered for the given study node.

12. Repeat steps 2 through 11 until all study nodes have been

considered for the given section and proceed to the next section on the

flow sheet.

(7)

The HAZOP procedure to complete an analysis:

5. Apply guide word to the process parameter to suggest possible deviations

(8)

Lembar Kerja Proses HAZOP

Hazards and Operability Review Project

Name:

Date: Page of

Process :

Section: Ref.

Drawing:

Item Study

node

Process Parameter

Deviations (guide words)

Possibl e

causes

Possible consequence s

Action Required

(9)

9

(10)

Kata Panduan/ guide words

Kata panduan dasar pada HAZOP:

Kata Panduan Arti Contoh

No (not, none) None of the design intent is achieved

No flow when production is expected

More (more of, higher)

Quantitative increase in a parameter

Higher temperature than desired

Less (less of, lower) Quantitative decrease in a parameter

Lower pressure than normal As well as (more

than)

An additional activity occurs Other valves closed at the same time (logic fault or human error)

Part of Only some of the design intention is achieved

Only part of the system is shut down

Reverse Logical opposite of the design intention occurs

Back-flow when the system shuts down

Other than (Other) Complete substitution – another activity takes place

Liquids in the gas piping

(11)

11

Kata panduan/guide words …… lanjutan

Guide-word Meaning

Early/ late The timing is different from the intention

Before/ after The step (or part of it) is effected out of sequence

Faster/ slower The step is done/not done with the right timing

Where else Applicable for flows, transfer, sources and destinations

The guide words SOONER THAN, LATER THAN, and WHERE ELSE are

applicable to batch processing.

(12)

Deviation

12

Deviation Column Tank/Vessel Line

Heat

Exchanger Pump

High Flow X

Low/no Flow X

High Level X X

Low Level X X

High Pressure X X X

Low Pressure X X X

High Temp. X X X

Low Temp. X X X

High Concen. X X X

Low Concen. X X X

Reverse Flow X

Tube Leak X

Tube Rupture X

Leak X X X X X

Rupture X X X X X

(13)

Parameters

13

Flow Frequency Pressure Viscosity Temperature Voltage

Level Information Time Mixing

Composition Addition

pH Separation

Speed Reaction

(14)

Studi kasus – Shell & Tube Heat Exchanger

Gunakan petunjuk kerja yang relevan, lakukan studi HAZOP study pada shell & tube heat exchanger

Process fluid

Cooling water

(15)

15

HAZOP on Heat Exchanger – Answer 1

Guide Word Deviation Causes Consequences Action

Less Less flow of

cooling water

Pipe blockage

Temperature of process fluid remains constant

High

Temperature Alarm

More More

cooling flow

Failure of cooling water valve

Temperature of process fluid decrease

Low

Temperature Alarm

More of More

pressure on tube side

Failure of process fluid valve

Bursting of tube Install high pressure alarm Contamination Contaminati

on of process fluid line

Leakage of tube and

cooling water goes in

Contamination of process fluid

Proper

maintainance and operator alert

Corrosion Corrosion of tube

Hardness of cooling water

Less cooling and crack of tube

Proper

maintainence

(16)

HAZOP on Heat Exchanger – Answer 2

Guide Word Deviation Cause Consequences Action

NONE No cooling

water flow

Failure of inlet cooling water valve to open

Process fluid temperature is not lowered accordingly

Install Temperature indicator before and after the process fluid line Install TAH

MORE More cooling

water flow

Failure of inlet cooling water valve to close

Output of Process fluid temperature too low

Install Temperature indicator before and after process fluid line

Install TAL

LESS Less cooling

water

Pipe leakage Process fluid temperature too low

Installation of flow meter

REVERSE Reverse

process fluid flow

Failure of process fluid inlet valve

Product off set Install check valve (whether it is

crucial have to check?)

CONTAMINATIO N

Process fluid contaminatio n

Contamination in cooling

water

Outlet

temperature too low

Proper

maintenance and operator alert

(17)

Hazard & Operability Studies

Example

Consider the simple process diagram below. It represents a plant where substances A and B

react with each other to form a new substance C.

If there is more B than A there may be an explosion.

A

B

V1

V2 V3

V4

V5

A < B = Explosion C

(18)

Guide Word

Deviation Possible Causes Consequences Proposed Measures NO, NOT No A Tank containing A is empty.

V1 or V2 closed.

Pump does not work.

Pipe broken

Not enough A = Explosion

Indicator for low level.

Monitoring of flow

MORE Too much

A

Pump too high capacity Opening of V1 or V2 is too large.

C contaminated by A. Tank overfilled.

Indicator for high level.

Monitoring of flow

LESS Not enough

A

V1,V2 or pipe are partially blocked. Pump gives low flow or runs for too short a time.

Not enough A = Explosion

See above

AS WELL AS Other substance

V3 open – air sucked in Not enough A = Explosion

Flow monitoring based on weight REVERSE Liquid

pumped backwards

Wrong connector to motor Not enough A = Explosion

A is contaminated

Flow monitoring

OTHER THAN

A boils in pump

Temperature too high Not enough A = Explosion

Temperature (and flow) monitoring.

(19)

Preliminary HAZOP Example

Refer to reactor system shown.

The reaction is exothermic. A cooling system is provided to remove the excess energy of reaction. In the event of cooling function is lost, the temperature of reactor would increase.

This would lead to an increase in reaction rate leading to additional energy release.

The result could be a runaway reaction with pressures exceeding the bursting pressure of the reactor. The temperature within the reactor is measured and is used to control the cooling water flow rate by a valve.

Perform HAZOP Study

19 T

C

Cooling Coils Monomer

Feed

Cooling Water to Sewer

Cooling Water In

Thermocouple

(20)
(21)

21

(22)

install a high-temperature alarm to alert the operator in the even of cooling function loss

install a high-temperature shutdown system (this system would automatically shut down the process in the event of a high reactor temperature; the shutdown temperature would be higher than the alarm temperature to provide the operator with the opportunity to restore cooling before the reactor is shutdown),

install a check valve in the cooling line to prevent reverse flow (a check valve could be installed both before and after the reactor to prevent the reactor contents from flowing upstream and to prevent the backflow in the event of a leak in the coils),

periodically inspect the cooling coil to ensure its integrity,

study the cooling water source to consider possible contamination and interruption of supply,

install a cooling water flow meter and low-flow alarm

(which will provide an immediate indication of cooling

Referensi

Dokumen terkait