DAFTAR HARGA SATUAN PEKERJAAN

PROYEK : SOLIA BOUTIQUE HOTEL

LOKASI : JL. DR. RAJIMAN 525 LAWEYAN-SURAKARTA PEKERJAAN : STRUKTURE-ARSITEKTURE-MEP

NO URAIAN PEKERJAAN SAT HARGA

SATUAN (Rp)

HARGA SATUAN PEKERJAAN PERSIAPAN LS 480,000,000.00

HARGA SATUAN PEKERJAAN STRUKTURE

1 Pekerjaan balok

beton m³ 965,250.00

besi (Material Besi SBO) kg 1,500.00

m² 115,000.00

2 Pekerjaan kolom

beton m³ 1,015,250.00

besi (Material Besi SBO) kg 1,500.00

bekesting m² 115,000.00

3 Pekerjaan plat

beton m³ 965,250.00

besi (material besi SBO) kg 1,500.00

bekesting m² 115,000.00

4 Pekerjaan tangga

beton m³ 965,250.00

(2)

besi (material besi SBO) kg 1,500.00

bekesting m² 115,000.00

5 Pekerjaan shearwall

beton m³ 1,015,250.00

besi (material besi SBO) kg 1,500.00

bekesting m² 115,000.00

6 Pekerjaan Atap Galvalum

Pekerjaan IWF (Material WF SBO) m2 246,972.00

Penutup Atap Galvalum m2 145,000.00

HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 Pasangan dinding bata trassram m² 120,000.00

2 Pasangan dinding bata m² 105,000.00

HARGA SATUAN PEKERJAAN FINISHING DINDING

1 Plesteran dinding bata trassram m² 47,510.00

2 Plesteran dinding bata m² 38,224.20

3 Acian dinding bata m² 23,153.40

4 Finish Keramik dinding L-1 m² 114,660.00

5 Finishing Keramik dinding toilet m² 154,123.00

6 Keramik dinding Kitchen m² 124,660.00

7 Pekerjaan pengecatan dinding m² 23,746.20

8 Marmer Lift m² 750,000.00

HARGA SATUAN PEKERJAAN PINTU DAN JENDELA

1 D2 unit 2,198,500.00

(3)

2 D7 unit 10,890,700.00

3 D14 unit 4,417,100.00

4 D15 unit 11,843,200.00

5 D16 unit 5,277,100.00

6 W1 unit 3,975,600.00

7 D4 unit 10,052,500.00

8 D6 unit 3,850,800.00

9 D8 unit 3,609,300.00

10 D9 unit 2,724,200.00

11 D10 unit 2,757,700.00

12 D14 unit 4,417,100.00

13 D17 unit 10,890,700.00

14 D18 unit 4,077,300.00

15 D20 unit 2,979,000.00

16 DW1 unit 44,828,900.00

17 DW2 unit 40,727,100.00

18 CW1 m2 1,150,050.00

19 CW2 m2 1,150,050.00

20 CW3 m2 1,150,050.00

21 Pintu & Jendela Kaca Ballroom unit 31,963,400.00

22 Pintu & Jendela Kaca Prefunction unit 27,914,000.00

23 D12 unit 5,949,400.00

24 D18 unit 4,077,300.00

HARGA SATUAN PEKERJAAN PLAFOND

1 Ceiling Gypsum Board 9 mm m² 81,909.00

2 Cat plafond m² 18,150.00

3 Shadow line. m² 16,701.00

(4)

HARGA SATUAN PEKERJAAN LANTAI

1 Keramik Roman 40x40 m² 155,000.00

2 Homogeneus Tile Area Public 60x60 m² 203,500.00

3 Marmer Area Lobby m² 824,700.00

4 Karpet Vynil beserta lantai kerja m² 310,000.00

5 Keramik Kamar Mandi m² 203,500.00

6 Floor Hardener m² 27,500.00

7 Karpet Tile beserta lantai kerja m² 363,774.00

8 Plint m' 40,051.00

9 Waterproofing m² 37,370.00

10 Dek kolam renang beserta lantai kerja m² 874,240.00

HARGA SATUAN PEKERJAAN RAILING

1 Railing m' 513,690.00

HARGA SATUAN PEKERJAAN FASAD

1 GRC Trawangan m² 855,000.00

2 GRC list m² 456,000.00

3 Curtain Wall m² 1,750,000.00

HARGA SATUAN PEKERJAAN BAJA (Material Baja WF , SBO)

1 WF 350.150 KG 7,500.00

2 WF 150.100 KG 7,500.00

3 BASE PLATE 15 MM KG 7,500.00

4 BASE PLATE 10 MM KG 7,500.00

(5)

5 ANGKUR M19 TITIK 159,619.50

6 ANGKUR M16 TITIK 65,175.00

7 MUR BAUT M16 BH 7,702.50

8 PLAT SAMBUNG 10 MM KG 21,330.00

9 CAT ZINCROMATE KG 1,422.00

HARGA SATUAN PEKERJAAN FINISHING

1 ACP M2 744,180.00

2 KACA LAMINATED 2x6 MM TEMPERED M2 1,592,640.00

HARGA SATUAN PEKERJAAN SANITAIR

1 Wastafel ex Toto TOTO TX115LRS+TOTO LW649CJ lengkap dengan meja Unit 1,606,380.00

2 Towel Shelf & Towel Bar TX726AE Unit 57,000.00

3 Paper Holder TX720AB Unit 39,310.00

4 Shoap Holder ex Toto AR15 Unit 39,310.00

5 Closet Jongkok ex Toto CE7 Unit 152,750.00

6 Closet ex Toto CW637J/SW637JP Unit 193,780.00

7 Shower ex Toto TX493SRR Unit 127,230.00

8 Floor Drain ex Toto TX1BV1N Unit 45,170.00

9 Kran Dinding ex Toto Unit 27,580.00

10 Roob Hook ex Toto Unit 27,580.00

HARGA SATUAN PEKERJAAN PENERANGAN & STOP KONTAK

1 Instalasi Penerangan dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 titik 134,550.00 2 Instalasi Kotak kontak Biasa dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20

mm2 titik 134,550.00

3 Balk LED Tube 1 x 20 W bh 473,265.00

4 Kotak Kontak Biasa bh 20,475.00

(6)

5 Saklar Ganda bh 46,215.00

6 Saklar Grid 8 Gang set 119,925.00

7 Saklar Grid 12 Gang set 187,785.00

HARGA SATUAN PEKERJAAN KABEL TRAY & LADDER

1 Kabel Ladder ukuran 300 mm x 100 mm m1 172,500.00

2 Kabel Tray ukuran 300 mm x 100 mm m1 172,500.00

3 Tee Tray ukuran 300 mm x 100 mm bh 172,500.00

4 Elbow ukuran 300 mm x 100 mm bh 172,500.00

HARGA SATUAN PEKERJAAN FIRE ALARM

1 Instalasi ROR Heat Detector & EORL dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 2 Instalasi Smoke detector dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 3 Instalasi Flow & Temper Switch dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 4 Instalasi Manual Push Button dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

5 Instalasi Alarm Bell dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

6 Instalasi Indicating lamp dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

7 ROR Heat Detector bh 253,305.00

8 Smoke Detector bh 194,805.00

9 Flow Switch bh 838,305.00

10 Temper Switch bh 955,305.00

11 Manual Push Button bh 136,305.00

12 Alarm Bell bh 165,555.00

13 Indicating Lamp bh 124,605.00

14 End of line resistor bh 9,009.00

15 Terminal Box Fire Alarm (TB-FA) bh 780,975.00

(7)

16 Kabel Feeder fire alarm m1 22,932.00

HARGA SATUAN PEKERJAAN TATA SUARA/ SOUND SYSTEM 1 Instalasi Ceiling speaker dgn kabel NYMHY 3 x 1,5mm dlm pipa conduit PVC dia. 20

mm2 titik 200,655.00

2 Celling Speaker 3 W bh 177,255.00

3 Horn Speaker 15 W bh 311,805.00

4 Volume Kontrol bh 311,805.00

5 Sound Terminal Box (STB) bh 569,205.00

6 Kabel Feeder sound system m1 26,325.00

HARGA SATUAN PEKERJAAN CCTV

1 Instalasi CCTV dg kabel RG 59 + Power dlm pipa conduit PVC dia. 20 mm2 titik 235,755.00

2 In door Camera CCTV IR type Fixed bh 962,910.00

3 Color Dome type camera bh 669,825.00

4 Box CCD Camera ls 585,000.00

HARGA SATUAN PEKERJAAN INSTALASI AIR KOTOR/ BEKAS DAN VENT

CUP

1 Memasang Pipa PVC dia. 150 mm kelas AW m1 235,755.00

2 Memasang Pipa PVC dia. 100 mm kelas AW m1 118,755.00

3 Memasang Pipa PVC dia. 75 mm kelas AW m1 80,145.00

4 Memasang Pipa PVC dia. 75 mm kelas AW m1 80,145.00

5 Memasang Pipa PVC dia. 50 mm kelas AW m1 49,140.00

6 Memasang Clean Out dia. 150 mm m1 234,819.00

7 Pre Treatment lemak/ grease trap kap. 2 m3 Unit 7,488,000.00

8 Resapan Unit 2,340,000.00

9 Pompa Submersible Sewage Unit 23,400,000.00

(8)

10 Fitting + Supporting termasuk hanger dan u-trap ls 1,755,000.00

HARGA SATUAN PEKERJAAN INSTALASI AIR BERSIH DINGIN

1 Memasang Pipa PPR PN 10 dia. 25 mm m1 40,131.00

2 Memasang Pipa PPR PN 10 dia. 20 mm m1 29,103.75

3 Memasang Pipa PPR PN 10 dia. 15 mm m1 21,937.50

4 Memasang Gate Valve dia. 20 mm bh 377,471.25

5 Fitting + Supporting termasuk hanger ls 201,649.50

HARGA SATUAN PEKERJAAN INSTALASI PENGKONDISIAN UDARA

1 Instalasi Power AC dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 titik 346,539.38 2 Kabel Power Kontrol NYM 3 x 2.5 mm2 dari Indoor s/d Outdoor unit m1 20,182.50

3 Air Conditioner Split Wall 18.000 Btu/h Unit 4,387,500.00

4 Air Conditioner Split Wall 5.000 Btu/h Unit 3,925,000.00

5 Instalasi Pipa Refrigerant uk. 1/4" m1 65,000.00

6 Instalasi Pipa Refrigerant uk. 1/2" m1 77,000.00

7 Memasang Pipa PVC dia. 20 mm kelas AW m1 24,716.25

8 Fitting + Supporting dan material bantu ls 64,350.00

HARGA SATUAN PEKERJAAN INSTALASI HYDRANT DAN SPRINKLER

1 Memasang Pipa BS sch-40 dia. 150 mm m1 422,370.00

2 Memasang Pipa BS sch-40 dia. 80 mm m1 202,410.00

3 Memasang Pipa BS sch-40 dia. 50 mm m1 124,546.50

4 Memasang Pipa BS sch-40 dia. 40 mm m1 88,881.39

5 Memasang Pipa BS sch-40 dia. 32 mm m1 77,512.50

6 Memasang Pipa BS sch-40 dia. 25 mm m1 62,595.00

(9)

7 Memasang Pipa BS sch-40 dia. 20 mm m1 50,602.50

8 Memasang Head Sprinkler Tipe Pendant bh 105,300.00

9 Memasang Brach Control Valve dia. 80 mm bh 5,444,010.00

10 Memasang Gate Valve 10 K with Flanges dia. 80 mm bh 2,571,660.00

11 Memasang Gate Valve 10 K with Flanges dia. 50 mm bh 2,135,250.00

12 In door Hydrant Box dgn Hose,Hose Rack, Nozel, Landing Valve dan Gate Valve unit 4,128,579.00 13 Memasang Portable Fire Extinguisher type ABC 3.5 kg unit 438,165.00

14 Fitting dan assesories termasuk hanger ls 772,200.00

15 Instalasi Exshaust FAN dg kabel NYM 2 x 2.5 mm2 dlm Pipa Conduit dia. 20 mm2 titik 141,570.00

16 Memasang Exshaust FAN 12 W bh 409,500.00

HARGA SATUAN PEKERJAAN INSTALASI PENERANGAN DAN KOTAK

KONTAK

1 Instalasi Penerangan dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 titik 134,550.00 2 Instalasi Kotak kontak Biasa dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20

mm2 titik 134,550.00

3 Instalasi Kotak kontak Lantai dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20

mm2 titik 134,550.00

4 Downlight LED 19 W bh 277,875.00

5 Downlight LED 13 W bh 272,025.00

6 Downlight LED 7 W bh 252,135.00

7 RM LED Tube 2 x 10 W bh 90,090.00

8 RM LED Tube 3 x 10 W Arcylic Cover bh 970,515.00

9 Balk LED Tube 1 x 20 W bh 473,265.00

10 Lampu Strip LED 3 m/ 14.4 W/ m set 321,165.00

11 Lampu Strip LED 26.5 m/ 14.4 W/ m set 1,283,490.00

12 Lampu Strip LED 48 m/ 14.4 W/ m set 2,163,915.00

13 Lampu Strip LED 33 m/ 14.4 W/ m set 1,549,665.00

(10)

14 Kotak Kontak Lantai bh 371,475.00

15 Kotak Kontak Biasa bh 20,475.00

16 Saklar Ganda bh 46,215.00

17 Saklar Tunggal bh 39,195.00

18 Saklar Hotel Ganda bh 53,235.00

19 Saklar Grid 14 Gang set 172,575.00

HARGA SATUAN PEKERJAAN INSTALASI KABEL TRAY DAN LADDER

1 Kabel Ladder ukuran 300 mm x 100 mm m1 172,500.00

2 Kabel Tray ukuran 300 mm x 100 mm m1 172,500.00

3 Tee Tray ukuran 300 mm x 100 mm bh 172,500.00

4 Elbow ukuran 300 mm x 100 mm bh 172,500.00

HARGA SATUAN PEKERJAAN INSTALASI TELEPON

1 Instalasi Telephone dg Kabel ITC 2x2x0.6 mm dlm Pipa Conduit 20 mm titik 185,445.00

2 Direct Outlet bh 61,425.00

3 Direct Outlet Lantai bh 374,283.00

4 Direct Outlet Fax bh 61,425.00

5 Operator console bh 1,547,325.00

6 Handset single Telephone unit 1,547,325.00

7 Main Distrubution Fram Telepon (MDF-TP) unit 2,717,325.00

8 Private Automatic Branch eXchange (PABX),10 Co, 140 Ext. unit 64,376,325.00

9 Power Surge Arester 15 KA unit 1,540,305.00

10 Terminal Box Telepon (TTB) unit 435,825.00

11 Kabel Feeder ITC 10 pairs m1 36,270.00

12 Kabel Feeder ITC 150 pairs m1 187,785.00

(11)

HARGA SATUAN PEKERJAAN INSTALASI FIRE ALARM

1 Instalasi ROR Heat Detector & EORL dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 2 Instalasi Smoke detector dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 3 Instalasi Fix detector dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 4 Instalasi Flow & Temper Switch dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00 5 Instalasi Manual Push Button dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

6 Instalasi Alarm Bell dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

7 Instalasi Indicating lamp dgn kabel NYA 2 (1x1.5) mm2 titik 159,705.00

8 ROR Heat Detector bh 253,305.00

9 Smoke Detector bh 194,805.00

10 Fix Temperature Head Detector bh 253,305.00

11 Flow Switch bh 838,305.00

12 Temper Switch bh 955,305.00

13 Manual Push Button bh 136,305.00

14 Alarm Bell bh 165,555.00

15 Indicating Lamp bh 124,605.00

16 End of line resistor bh 9,009.00

17 Terminal Box Fire Alarm (TB-FA) bh 780,975.00

18 Kabel Feeder fire alarm m1 22,932.00

19 Announciator 10 zone Unit 9,380,475.00

20 MC-FA intelegent fire alarm 1 loop 300 device 20 Zone Unit 111,150,000.00

HARGA SATUAN PEKERJAAN INSTALASI TATA SUARA/ SOUND SYSTEM 1 Instalasi Ceiling speaker dgn kabel NYMHY 3 x 1,5mm dlm pipa conduit PVC dia. 20

mm2 titik 200,655.00

2 Celling Speaker 3 W bh 177,255.00

3 Column Speaker 10 W Emergency bh 224,055.00

(12)

4 Volume Kontrol bh 311,805.00

5 Sound Terminal Box (STB) bh 569,205.00

6 Amplifier 240 Watt unit 4,488,705.00

7 Amplifier 60 Watt unit 1,797,705.00

8 Emergency Amplifier 240 Watt unit 4,488,705.00

9 Paging Microphone unit 4,137,705.00

10 Selector Swicth 10 zone unit 4,137,705.00

11 CD/VCD/DVD/MP3+ Radio tuner unit 2,967,705.00

12 Mixer power amplifier 240 Watt unit 2,967,705.00

13 Cabinet Rack w/ Accessories. unit 7,647,705.00

14 Main Distrubution Fram (MDF) Sound System unit 920,205.00

15 Power Surge Arester 15 KA unit 1,540,305.00

16 Kabel Feeder sound system m1 26,325.00

HARGA SATUAN PEKERJAAN INSTALASI CCTV

1 Instalasi CCTV dg kabel RG 59 + Power dlm pipa conduit PVC dia. 20 mm2 titik 235,755.00

2 Color Dome type camera bh 669,825.00

3 In door Camera CCTV IR type Fixed unit 962,910.00

4 DVR kap 32 channel, hardisc 4 T unit 16,423,875.00

5 Monitor LED 32" unit 4,121,325.00

6 Power Surge Arester 15 KA unit 1,755,000.00

7 Box CCD Camera ls 585,000.00

HARGA SATUAN PEKERJAAN INSTALASI DATA KOMPUTER

(13)

1 Instalasi Data komputer dg kabel UTP Cath 6 dlm pipa conduit PVC dia. 20 mm2 titik 219,726.00

2 Outlet Data bh 99,333.00

3 Outlet Data Lantai bh 99,333.00

4 Outlet Wifi/ Acces Point bh 99,333.00

5 Antena Wiffi/ Acces Point bh 99,333.00

6 Switch hub 24 port unit 1,129,050.00

7 19" Close Rack 42U Depth 1100mm unit 1,404,000.00

8 Fitting & Supporting ls 175,500.00

HARGA SATUAN PEKERJAAN INSTALASI MATV

1 Instalasi MATV dg kabel Coaxial RG 6 dlm pipa conduit PVC dia. 20 mm2 titik 209,430.00

2 Outlet Antena TV bh 73,125.00

3 Splitter 2 Way bh 163,800.00

4 Indoortap 4 Way bh 146,250.00

5 Kabel feeder coaxcial RG 11 m1 16,965.00

6 Kabel feeder coaxcial RG 11 m1 16,965.00

7 Combiner 16 chanel unit 2,925,000.00

8 Modulator unit 1,053,000.00

9 Splitter 6 way unit 193,050.00

10 Boster unit 187,200.00

11 VCD/ DVD Player unit 877,500.00

12 Power Suplay 12 VDC unit 292,500.00

13 Antenna UHF/VHF unit 175,500.00

14 Antenna Parabola 6 Feet unit 2,925,000.00

15 TV Monitor unit 4,095,000.00

16 Rack Mounting unit 1,755,000.00

17 Pengkabelan di Head End MATV ls 585,000.00

(14)

HARGA SATUAN PEKERJAAN INSTALASI PENGKONDISIAN UDARA

1 Instalasi Power AC dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 titik 346,539.38

2 kabel NYY 4 x 16 mm2 m1 141,570.00

3 Out Door Unit kap. 311.620 BTU/h Unit 153,036,000.00

4 Air Conditioner Ceiling Mounted Duct 100.000 BTU/h Unit 30,069,000.00 5 Air Conditioner Ceiling Mounted Duct 80.000 BTU/h Unit 24,219,000.00

6 Indoor Ceiling Wall Mounted 9.000 BTU/h Unit 5,150,000.00

7 Air Conditioner Ceiling Wall Mounted 5.000 BTU/h Unit 4,592,250.00

8 Instalasi Pipa Refrigerant uk. 1 3/8" m1 115,830.00

9 Instalasi Pipa Refrigerant uk. 7/8" m1 98,280.00

10 Instalasi Pipa Refrigerant uk. 3/4" m1 90,090.00

11 Instalasi Pipa Refrigerant uk. 3/8" m1 87,000.00

12 Instalasi Pipa Refrigerant uk. 1/2" m1 83,655.00

13 Instalasi Pipa Refrigerant uk. 1/4" m1 70,200.00

14 Memasang Pipa PVC dia. 50 mm kelas AW m1 49,140.00

15 Memasang Pipa PVC dia. 32 mm kelas AW m1 35,538.75

16 Memasang Pipa PVC dia. 25 mm kelas AW m1 28,080.00

17 Memasang Pipa PVC dia. 20 mm kelas AW m1 24,716.25

18 Fitting + Supporting dan material bantu ls 64,350.00

19 Pekerjaan Ducting

20 Ducting PU uk. 750 x 200 mm m2 146,250.00

21 Ducting PU uk. 600 x 250 mm m2 146,250.00

22 Ducting PU uk. 550 x 200 mm m2 146,250.00

(15)

23 Ducting PU uk. 350 x 200 mm m2 146,250.00

24 Ducting PU uk. 300 x 200 mm m2 146,250.00

25 Round Ducting dia. 200 mm m2 146,250.00

26 Memasang Grill

27 Linear Air Diffuser 508 cfm bh 292,500.00

28 Suplay Air Grill uk. 500 x 500/ 1060 cfm bh 292,500.00

29 Return Air Grill uk. 650 x 650/ 2033 cfm bh 146,250.00

30 Return Air Grill uk. 650 x 650/ 1700 cfm bh 292,500.00

31 Louvre Air Grill 300 x 300 bh 146,250.00

HARGA SATUAN PEKERJAAN INSTALASI AIR KOTOR/ BEKAS DAN VENT

CUP

1 Memasang Pipa PVC dia. 100 mm kelas AW m1 118,755.00

2 Memasang Pipa PVC dia. 75 mm kelas AW m1 80,145.00

3 Memasang Pipa PVC dia. 50 mm kelas AW m1 49,140.00

4 Memasang Pipa PVC dia. 32 mm kelas AW m1 35,538.75

5 Memasang Clean Out dia. 80 mm m1 152,100.00

6 Fitting + Supporting termasuk hanger dan u-trap ls 526,500.00

7 Memasang Pipa PPR PN 10 dia. 32 mm m1 53,966.25

8 Memasang Pipa PPR PN 10 dia. 25 mm m1 40,131.00

9 Memasang Pipa PPR PN 10 dia. 20 mm m1 29,103.75

10 Memasang Pipa PPR PN 10 dia. 15 mm m1 21,937.50

11 Memasang Gate Valve dia. 15 mm bh 267,637.50

12 Memasang Gate Valve dia. 25 mm bh 467,415.00

13 Memasang Gate Valve dia. 32 mm bh 471,948.75

14 Fitting + Supporting termasuk hanger ls 345,094.43

HARGA SATUANPEKERJAAN INSTALASI HYDRANT DAN SPRINKLER

(16)

1 Memasang Pipa BS sch-40 dia. 150 mm m1 422,370.00

2 Memasang Pipa BS sch-40 dia. 80 mm m1 202,410.00

3 Memasang Pipa BS sch-40 dia. 50 mm m1 124,546.50

4 Memasang Pipa BS sch-40 dia. 40 mm m1 88,881.39

5 Memasang Pipa BS sch-40 dia. 32 mm m1 77,512.50

6 Memasang Pipa BS sch-40 dia. 25 mm m1 62,595.00

7 Memasang Pipa BS sch-40 dia. 20 mm bh 50,602.50

8 Memasang Head Sprinkler Tipe Pendant bh 105,300.00

9 Memasang Brach Control Valve dia. 80 mm bh 5,444,010.00

10 Memasang Gate Valve 10 K with Flanges dia. 150 mm bh 2,571,660.00

11 Memasang Gate Valve 10 K with Flanges dia. 50 mm bh 2,135,250.00

12 In door Hydrant Box dgn Hose,Hose Rack, Nozel, Landing Valve dan Gate Valve unit 4,128,579.00 13 Memasang Portable Fire Extinguisher type ABC 3.5 kg unit 438,165.00 14 Out door Hydrant Box dgn Hose,Hose Rack, Nozel, Landing Valve dan Gate Valve unit 4,062,825.00

15 Memasang Pillar hydrant unit 3,551,652.00

16 Memasang Seamese connection 100 mm unit 2,894,580.00

17 Fitting dan assesories termasuk hanger ls 912,600.00

HARGA SATUAN PEKERJAAN INSTALASI GAS KITCHEN

1 Memasang Pipa Galvanis medium dia. 20 mm m1 71,077.50

2 Memasang Selenoid valve dia. 20 mm bh 456,592.50

3 Memasang Pressure Gauge bh 793,552.50

4 Memasang Pressure Switch bh 1,144,552.50

5 Memasang Regulator Yamato bh 877,500.00

6 Memasang Ball Valve dia. 20 mm bh 328,331.25

7 Memasang Check Valve dia. 20 mm bh 439,042.50

(17)

8 Memasang Pipa Fleksibel GAS m1 29,250.00

9 Tabung Gas LPG 50 kg set 1,696,500.00

10 Fitting + Supporting termasuk hanger ls 5,850,000.00

11 Instalasi Exshaust FAN dg kabel NYM 2 x 2.5 mm2 dlm Pipa Conduit dia. 20 mm2 titik 424,710.00

12 Memasang Exshaust FAN 12 W bh 1,228,500.00

HARGA SATUAN PEKERJAAN INSTALASI PENERANGAN DAN KOTAK

KONTAK

1 Instalasi Penerangan dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 titik 134,550.00 2 Instalasi Kotak kontak Biasa dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20

mm2 titik 134,550.00

3 Downlight LED 13 W bh 272,025.00

4 Downlight LED 7 W bh 252,135.00

5 RM LED Tube 2 x 10 W bh 90,090.00

6 RM LED Tube 2 x 20 W bh 853,515.00

7 RM LED Tube 3 x 10 W bh 912,015.00

8 Barret LED 16 W bh 490,815.00

9 Emergency Exit LED 8 W bh 760,500.00

10 Kotak Kontak Biasa bh 20,475.00

11 Saklar Ganda bh 46,215.00

12 Saklar Tunggal bh 39,195.00

13 Saklar Hotel Ganda bh 53,235.00

HARGA SATUAN PEKERJAAN INSTALASI KABEL TOUVUR DAN PANEL

DAYA

1 BUSDUCT 1.000 A ( 3P + N + E) m1 172,500.00

2 A. Busduct Riser 1.000 A, 3P + 100% N + 50% IGB/ BM/ IP54/ 50 KA m1 172,500.00

3 1. Total Length/ Panjang bh 172,500.00

4 2. Flatewise Elbow bh 172,500.00

(18)

5 3. Joint titik 185,445.00 6 4. Hanger Vertical (spring - w/o additional support) bh 61,425.00

7 5. Hanger horizontal unit 201,825.00

8 B. TAP OFF BOX c/w MCCB unit 435,825.00

9 1. TOB 160 A m1 36,270.00

10 C. Reduser Busduct 1.000 A s/d 800 A titik 159,705.00

11 BUSDUCT 8.000 A ( 3P + N + E) titik 159,705.00

12 A. Busduct Riser 8.00 A, 3P + 100% N + 50% IGB/ BM/ IP54/ 50 KA titik 159,705.00

13 1. Total Length/ Panjang titik 159,705.00

14 2. Joint titik 159,705.00

15 5. Hanger Vertical (spring - w/o additional support) titik 159,705.00

16 B. TAP OFF BOX c/w MCCB bh 253,305.00

17 1. TOB 160 A bh 194,805.00

18 Kabel NYY 4 x 50 mm2 bh 838,305.00

19 Kabel NYY 4 x 50 mm2 bh 955,305.00

20 Kabel NYY 4 x 16 mm2 bh 136,305.00

21 Kabel NYY 4 x 25 mm2 bh 165,555.00

22 Kabel NYY 4 x 50 mm2 bh 124,605.00

23 Kabel NYY 4 x 16 mm2 bh 9,009.00

24 Kabel NYY 4 x 25 mm2 bh 780,975.00

25 Kabel NYY 4 x 16 mm2 titik 200,655.00

26 Kabel NYY 4 x 25 mm2 bh 177,255.00

27 Kabel NYY 4 x 10 mm2 bh 224,055.00

28 Kabel NYY 4 x 50 mm2 bh 311,805.00

29 Kabel NYY 4 x 16 mm2 bh 569,205.00

30 Kabel NYY 4 x 25 mm2 m1 26,325.00

(19)

31 Kabel NYY 4 x 50 mm2 titik 235,755.00

32 Kabel NYY 4 x 16 mm2 bh 669,825.00

33 Kabel NYY 4 x 25 mm2 ls 585,000.00

34 Kabel NYM 3 x 4 mm2

35 Kabel NYY 4 x 50 mm2 titik 219,726.00

36 Kabel NYY 4 x 16 mm2 bh 99,333.00

37 Kabel NYY 4 x 25 mm2 unit 1,017,900.00

38 Kabel NYM 3 x 4 mm2 ls 117,000.00

39 Kabel NYY 4 x 25 mm2 titik 141,570.00

40 Kabel NYM 3 x 4 mm2 bh 409,500.00

41 Kabel NYY 4 x 50 mm2 titik 693,078.75

42 Kabel NYY 4 x 16 mm2 m1 85,410.00

43 Kabel NYY 4 x 25 mm2 Unit 71,019,000.00

44 Kabel NYM 3 x 4 mm2 Unit 21,206,250.00

45 Kabel NYY 4 x 50 mm2 Unit 15,122,250.00

46 Kabel NYY 4 x 16 mm2 Unit 6,084,000.00

47 Kabel NYY 4 x 25 mm2 Unit 5,791,500.00

48 Kabel NYY 4 x 50 mm2 m1 76,050.00

49 Kabel NYY 4 x 16 mm2 m1 70,200.00

50 Kabel NYY 4 x 25 mm2 m1 83,655.00

51 Kabel NYY 4 x 16 mm2 m1 90,090.00

52 Kabel NYY 4 x 10 mm2 m1 91,260.00

53 Kabel NYY 4 x 10 mm2 m1 106,470.00

54 Kabel NYY 4 x 16 mm2 m1 112,320.00

55 Memasang Panel Penerangan Lantai Basement set 1,593,000.00

56 Memasang Panel Penerangan Lantai 1 m1 35,538.75

57 Memasang Panel AC Lantai 1 m1 28,080.00

58 Memasang Panel Elektronik m1 24,716.25

(20)

59 Memasang Panel SDP Mezzanin ls 39,487.50

60 Memasang Panel SDP 2 m1 118,755.00

61 Memasang Panel Penerangan Lantai 2 m1 80,145.00

62 Memasang Panel AC Lantai 2 m1 49,140.00

63 Memasang PP- Kitchen lantai 2 m1 190,125.00

64 Memasang Panel SDP 3 m1 152,100.00

65 Memasang Panel Penerangan Lantai 3 ls 526,500.00

66 Memasang Panel SDP 4 m1 53,966.25

67 Memasang Panel Penerangan Lantai 4 m1 29,103.75

68 Memasang Panel AC Lantai 4 m1 21,937.50

69 Memasang Panel SDP 5 bh 377,471.25

70 Memasang Panel Penerangan Lantai 5 bh 471,948.75

71 Memasang Panel AC Lantai 5 ls 541,812.38

72 Memasang Panel AC Lantai 6 m1 202,410.00

73 Memasang Panel SDP 7 m1 124,546.50

74 Memasang Panel Penerangan Lantai 7 m1 88,881.39

75 Memasang Panel AC Lantai 7 m1 77,512.50

76 Memasang Panel SDP 8 m1 62,595.00

77 Memasang Panel Penerangan Lantai 8 m1 50,602.50

78 Memasang Panel AC Lantai 8 bh 105,300.00

79 Memasang Panel SDP 9 bh 5,444,010.00

80 Memasang Panel Penerangan Lantai 9 bh 2,571,660.00

81 Memasang Panel AC Lantai 9 bh 2,135,250.00

82 Memasang PP- Kitchen lantai 9 unit 4,128,579.00

83 Memasang DP- Heat Pump unit 438,165.00

84 Memasang PP- Boster Pump ls 323,700.00

(21)

85 Memasang DP- Pessurized Fan

86 Memasang DP- Lift

87 Grounding System titik 134,550.00

88 Sumuran Grounding Arus Lemah tahanan max. 1 ohm c/w peralatan titik 134,550.00 89 Sumuran Grounding Arus Kuat tahanan max. 5 ohm c/w SDP s/d Panel sub distribusi bh 277,875.00

90 Kabel NYA 2 x 150 mm2 bh 272,025.00

91 Kabel BC 50 mm2 bh 252,135.00

92 Kabel BC 16 mm2 bh 90,090.00

93 Kabel NYA 25 mm2 bh 853,515.00

94 Kabel NYA 16 mm2 bh 1,116,765.00

95 Kabel NYA 10 mm2 set 853,515.00

HARGA SATUAN PEKERJAAN INSTALASI PENYALUR PETIR

1 Head terminal type KURN Radius proteksi 120-150 meter set 996,840.00 2 Tiang penyangga penangkal petir 5 meter lengkap terpasang dg obstruction lamp set 1,385,865.00

3 Kabel NYY 1x70 mm2 set 1,406,340.00

4 Kabel BC 1x50 mm2 set 1,508,715.00

5 Instalasi Pentanahan/ grounding lengkap dengan baut Coupling/Join Conector set 1,590,615.00 6 Bak Kontrol Uk. 40x40 Cm lengkap dengan elektroda tanah set 1,836,315.00

7 Fitting + Supporting bh 490,815.00

HARGA SATUAN PEKERJAAN INSTALASI KABEL TRAY DAN LADDER

1 Kabel Ladder ukuran 300 mm x 100 mm bh 20,475.00

2 Kabel Tray ukuran 300 mm x 100 mm bh 46,215.00

3 Tee Tray ukuran 300 mm x 100 mm bh 39,195.00

4 Elbow ukuran 300 mm x 100 mm bh 53,235.00

HARGA SATUAN PEKERJAAN INSTALASI TELEPON

(22)

1 Instalasi Telephone dg Kabel ITC 2x2x0.6 mm dlm Pipa Conduit 20 mm set 166,725.00

2 Direct Outlet

3 Handset single Telephone m1 172,500.00

HARGA SATUAN PEKERJAAN INSTALASI CARD LOCK

1 Card Lock magnetik bh 172,500.00

2 System Soft Ware + RF Encoding bh 172,500.00

HARGA SATUAN PEKERJAAN INSTALASI TATA SUARA/ SOUND SYSTEM 1 Instalasi Ceiling speaker dgn kabel NYMHY 3 x 1,5mm dlm pipa conduit PVC dia. 20

mm2 bh 61,425.00

2 Celling Speaker 3 W unit 201,825.00

3 Volume Kontrol unit 435,825.00

4 Column Speaker 10 W Emergency m1 36,270.00

5 Kabel Feeder sound system titik 159,705.00

HARGA SATUAN PEKERJAAN INSTALASI CCTV

1 Instalasi CCTV dg kabel RG 59 + Power dlm pipa conduit PVC dia. 20 mm2 titik 159,705.00

2 Color Dome type camera titik 159,705.00

3 Fitting & Supporting titik 159,705.00

HARGA SATUAN PEKERJAAN INSTALASI DATA KOMPUTER

1 Instalasi Data komputer dg kabel UTP Cath 6 dlm pipa conduit PVC dia. 20 mm2 titik 159,705.00

2 Outlet Wifi/ Acces Point bh 253,305.00

3 Antena Wiffi/ Acces Point bh 194,805.00

4 Switch hub 4 port bh 253,305.00

(23)

5 Fitting & Supporting bh 838,305.00

HARGA SATUAN PEKERJAAN INSTALASI AIR KOTOR/ BEKAS DAN VENT

CUP

1 Memasang Pipa PVC dia. 100 mm kelas AW bh 165,555.00

2 Memasang Pipa PVC dia. 75 mm kelas AW bh 124,605.00

3 Memasang Pipa PVC dia. 50 mm kelas AW bh 9,009.00

4 Memasang Pipa PVC dia. 32 mm kelas AW bh 780,975.00

5 Memasang Clean Out dia. 100 mm m1 22,932.00

6 Fitting + Supporting termasuk hanger dan u-trap titik 200,655.00

7 Pipa Riser bh 177,255.00

8 Memasang Pipa PVC dia. 150 mm kelas AW bh 224,055.00

9 Memasang Pipa PVC dia. 100 mm kelas AW bh 311,805.00

10 Memasang Pipa PVC dia. 50 mm kelas AW bh 569,205.00

11 Fitting + Supporting termasuk hanger dan u-trap m1 26,325.00

HARGA SATUAN PEKERJAAN INSTALASI AIR BERSIH DINGIN

1 Memasang Pipa PPR PN 10 dia. 32 mm titik 235,755.00

2 Memasang Pipa PPR PN 10 dia. 25 mm bh 669,825.00

3 Memasang Pipa PPR PN 10 dia. 20 mm ls 585,000.00

4 Memasang Gate Valve dia. 25 mm titik 219,726.00

5 Memasang Gate Valve dia. 20 mm bh 99,333.00

6 Fitting + Supporting termasuk hanger bh 99,333.00

7 Lantai Atap bh 99,333.00

8 Memasang Pipa PPR PN 10 dia. 50 mm unit 1,129,050.00

9 Memasang Rooftank FRP kap 12 m3 ls 117,000.00

10 Pengkabelan dari panel kontrol s/d unit pompa titik 693,078.75

11 Memasang Gate Valve dia. 100 mm m1 85,410.00

(24)

12 Memasang Gate Valve dia. 50 mm Unit 235,462,500.00

13 Memasang Header dia. 100 mm Unit 30,069,000.00

14 Fitting + Supporting termasuk hanger Unit 21,206,250.00

15 Memasang Pipa PPR PN 10 dia. 50 mm m1 141,570.00

16 Fitting + Supporting termasuk hanger m1 129,870.00

HARGA SATUAN PEKERJAAN INSTALASI AIR BERSIH PANAS

1 Lantai Atap m1 98,280.00

2 Memasang Heat Pump Kap. 2000 liter m1 91,260.00

3 Fitting + Supporting termasuk hanger m1 90,090.00

4 Memasang Header 4" (Air Panas) m1 83,655.00

5 Memasang Selenoid valve dia. 50 mm m1 70,200.00

6 Memasang Selenoid valve dia. 40 mm m1 76,050.00

7 Memasang Gate valve dia. 50 mm set 1,593,000.00

9 Memasang Strainer dia. 50 mm m1 35,538.75

10 Memasang Strainer dia. 40 mm m1 28,080.00

11 Fitting + Supporting termasuk hanger ls 39,487.50

13 Fitting + Supporting termasuk hanger m2 146,250.00

HARGA SATUAN PEKERJAAN INSTALASI AIR HUJAN m2 146,250.00

1 Memasang Roofdrain dia. 100 mm m2 146,250.00

2 Memasang Pipa PVC dia. 100 mm kelas AW m2 146,250.00

3 Memasang Pipa PVC dia. 50 mm kelas AW m2 146,250.00

4 Bak Kontrol Air Hujan m2 146,250.00

5 Sumur Peresapan Air Hujan (SPAH) m2 146,250.00

6 Bak Sumpit m2 146,250.00

(25)

7 Fitting dan assesories termasuk hanger bh 146,250.00

HARGA SATUAN PEKERJAAN INSTALASI HYDRANT DAN SPRINKLER

1 Memasang Pipa BS sch-40 dia. 80 mm bh 146,250.00

2 Memasang Pipa BS sch-40 dia. 50 mm bh 146,250.00

3 Memasang Pipa BS sch-40 dia. 40 mm bh 146,250.00

4 Memasang Pipa BS sch-40 dia. 25 mm titik 141,570.00

5 Memasang Pipa BS sch-40 dia. 20 mm bh 409,500.00

6 Memasang Head Sprinkler Tipe Pendant m1 118,755.00

7 Memasang Brach Control Valve dia. 80 mm m1 80,145.00

8 Memasang Gate Valve 10 K with Flanges dia. 80 mm m1 49,140.00

9 Memasang Gate Valve 10 K with Flanges dia. 50 mm m1 190,125.00

10 In door Hydrant Box dgn Hose,Hose Rack, Nozel, Landing Valve dan Gate Valve m1 152,100.00

11 Memasang Portable Fire Extinguisher type ABC 3.5 kg ls 409,500.00

12 Fitting dan assesories termasuk hanger m1 53,966.25

13 RISER m1 29,103.75

14 Memasang Pipa BS sch-40 dia. 150 mm m1 21,937.50

15 Memasang Pipa BS sch-40 dia. 100 mm bh 377,471.25

16 Memasang Pipa BS sch-40 dia. 50 mm bh 471,948.75

17 Fitting dan assesories termasuk hanger ls 541,812.38

HARGA SATUAN PEKERJAAN INSTALASI PENGKONDISIAN UDARA

1 Instalasi Power AC dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 m1 202,410.00

2 Kabel NYY 4 x 16 mm2 m1 124,546.50

3 Out Door Unit kap. 300.000 BTU/h m1 88,881.39

4 Air Conditioner Ceiling Mounted Duct 100.000 BTU/h m1 77,512.50

5 Air Conditioner Ceiling Mounted Duct 45.000 BTU/h m1 62,595.00

6 Pekerjaan Instalasi Pipa Refrigerant lengkap dgn material bantu dan accessories m1 50,602.50

(26)

7 Instalasi Pipa Refrigerant uk. 1 3/8" bh 105,300.00

8 Instalasi Pipa Refrigerant uk. 7/8" bh 5,444,010.00

9 Instalasi Pipa Refrigerant uk. 3/4" bh 2,571,660.00

10 Instalasi Pipa Refrigerant uk. 3/8" bh 2,135,250.00

11 Instalasi Ref net unit 4,128,579.00

12 Pekerjaan Instalasi Pipa U-Drain lengkap dengan material bantu dan accessories unit 438,165.00

13 Memasang Pipa PVC dia. 32 mm kelas AW ls 393,900.00

14 Pekerjaan Ducting m1 71,077.50

15 Ducting PU uk. 900 x 200 mm m1 29,250.00

16 Ducting PU uk. 750 x 200 mm bh 793,552.50

17 Ducting PU uk. 450 x 200 mm bh 328,331.25

18 Ducting PU uk. 200 x 200 mm bh 439,042.50

19 Round Ducting dia. 200 mm ls 5,850,000.00

20 Memasang Grill m1 71,077.50

21 Suplay Air Grill uk. 400 x 400/ 635 cfm ls 1,755,000.00

22 Suplay Air Grill uk. 250 x 250/ 318 cfm ls 1,755,000.00

23 Return Air Grill uk. 650 x 650/ 2033 cfm titik 134,550.00

24 Louvre Air Grill 300 x 300 titik 134,550.00

25 ACCESSORIES bh 277,875.00

26 Wired Remocom bh 272,025.00

27 Wireless Remocom bh 272,025.00

28 Riser U-Drain bh 473,265.00

29 Memasang Pipa PVC dia. 50 mm kelas AW bh 490,815.00

30 Fitting + Supporting dan material bantu set 760,500.00

31 Ruang Lift set 894,465.00

32 Instalasi Power AC dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 bh 20,475.00

(27)

33 Air Conditioner Split Wall 18.000 Btu/h bh 46,215.00

34 Instalasi Pipa Refrigerant uk. 1/4" bh 39,195.00

35 Instalasi Pipa Refrigerant uk. 1/2" bh 53,235.00

36 Memasang Pipa PVC dia. 20 mm kelas AW titik 134,550.00

37 Fitting + Supporting dan material bantu titik 134,550.00

38 Exshaust FAN bh 272,025.00

39 Instalasi Exshaust FAN dg kabel NYM 2 x 2.5 mm2 dlm Pipa Conduit dia. 20 mm2 bh 252,135.00

40 Memasang Exshaust FAN 12 W bh 272,025.00

41 Lantai Roof top set 362,115.00

42 Memasang Pressurized Air Fan 10.428 CMH bh 20,475.00

43 Memasang Suplay Air Grill 500 mm x 500 mm bh 73,125.00

bh 59,085.00

HARGA SATUASN PEKERJAAN PUMP ROOM

1 Pompa lengkap terkopel dengan diesel engine diatas baseplate, lengkap dgn Radiator, bh 97,695.00 2 Electric Fire Pump (EFP) Lengkap dengan panel kontrol comply NFPA bh 318,825.00 3 Diesel Fire Pump (DFP) Lengkap dengan panel kontrol comply NFPA bh 39,195.00 4 Jockey Pump (JP) Lengkap dengan panel kontrol comply NFPA bh 53,235.00 5 yang diperlukan sesuai dengan gambar perencanaan dan spesifikasi teknis Unit 573,300.00

6 Memasang Gate Valve 10 K with Flanges dia. 150 mm m1 172,500.00

7 Memasang Gate Valve 10 K with Flanges dia. 50 mm m1 172,500.00

8 Memasang Strainer dia. 100 mm bh 172,500.00

9 Memasang Strainer dia. 50 mm bh 172,500.00

10 Memasang Check Valve dia. 100 mm titik 185,445.00

11 Memasang Flexible Joint dia. 100 mm bh 61,425.00

12 Memasang Flexible Joint dia. 50 mm unit 201,825.00

13 Memasang Foot Valve dia. 100 mm unit 435,825.00

14 Memasang Foot Valve dia. 50 mm m1 36,270.00

15 Pipa Black Stell Medium A dia. 50 mm titik 159,705.00

(28)

16 Memasang Header dia. 200 mm titik 159,705.00

17 Memasang Pressure Gauge titik 159,705.00

18 Memasang Pressure Switch titik 159,705.00

19 Memasang Pressure Tank kap 500 L titik 159,705.00

20 Sumur bor kedalaman 120 meter Lengkap dengan pompa Deep weel, pemipaan titik 159,705.00

21 Pompa Transfer titik 111,150.00

22 Centrifugal pump bh 253,305.00

23 Dosing Pump bh 194,805.00

24 Sand Filter bh 838,305.00

25 Carbon Filter bh 955,305.00

26 Memasang Gate Valve 10 K Drat dia. 32 mm bh 136,305.00

27 Memasang Gate Valve dia. 50 mm bh 165,555.00

28 Memasang Check Valve dia. 32 mm bh 124,605.00

29 Memasang Foot Valve dia. 32 mm bh 545,805.00

30 Memasang Flexible Joint dia. 32 mm bh 9,009.00

31 Memasang Pipa PPR PN 10 dia. 20 mm bh 780,975.00

32 Memasang Pipa PPR PN 10 dia. 32 mm m1 22,932.00

33 Memasang Pipa PPR PN 10 dia. 50 mm titik 200,655.00

34 Memasang Header dia. 100 mm bh 177,255.00

35 Memasang Pressure Gauge bh 224,055.00

36 Memasang Pressure Switch bh 569,205.00

37 Memasang Automatic Air Vant 25 GV m1 26,325.00

38 Fitting + Supporting titik 235,755.00

39 - System Filterasi Kolam Renang bh 669,825.00

40 - Pemipaan Kolam Renang ls 585,000.00

41 - Accessories titik 219,726.00

(29)

42 Perijinan, Testing dan Commissioning bh 99,333.00

HARGA SATUAN PEKERJAAN POWER HOUSE

1 PEKERJAAN PASANG DAYA LISTRIK 690 KVA

Transformator 800 KVA , 20/ 11.55 KV-400/ 231 V, 3 Phasa, 50 HZ, indoor type bh 99,333.00

2 PEKERJAAN PANEL MVMDP

Incoming LBS, 24kV, busbar 630A, 16kA unit 783,900.00

- Casing Cubicle 24 kV ls 117,000.00

Trafo Protection, tipe QM- SM6 titik 209,430.00

3 PEKERJAAN PANEL DAN KABEL TOUVUR

Kabel N2XSEFGbY 3 x 70 mm2 bh 73,125.00

Kabel N2XSY 3 x 1 x 70 mm2 bh 193,050.00

1. BUSDUCT 1.350 A bh 146,250.00

2. BUSDUCT 1.350 A ( 3P + N + E) m1 16,965.00

Kabel NYY 2 (4 x 1c x 150 mm2) m1 16,965.00

Kabel NYY 2 (4 x 1c x 150 mm2) m1 235,755.00

Kabel FRC 4 x 35 mm2 m1 118,755.00

Kabel FRC 4 x 70 mm2 m1 49,140.00

Kabel FRC 4 x 6 mm2 m1 35,538.75

Kabel FRC 4 x 25 mm2 m1 234,819.00

Kabel NYY 4 x 10 mm2 m1 190,125.00

Kabel NYY 4 x 6 mm2 m1 119,925.00

Memasang Panel In-Trafo ls 803,873.36

Memasang Panel Genset Synhcron 350 KVA m1 21,937.50

Memasang Kapasitor Bank 193 KVAR/ 415 V bh 267,637.50

Memasang Panel LVMDP ls 244,032.75

Memasang DP. Pompa Air kotor m1 131,040.00

Memasang DP- Hydrant bh 35,743.50

(30)

Memasang Pipa PVC dia. 150 mm kelas AW bh 267,637.50 Checkered Plate penutup pit kabel di Power House 0,8 x 15 m ls 151,725.60

4 GROUNDING SYSTEM

Sumuran Grounding Arus Kuat tahanan max. 5 ohm c/w TM, LVMDP, Travo, genset m1 202,410.00

Kabel NYA 150 mm2 m1 124,546.50

Kabel NYA 2 x (1c x 150 mm2) m1 88,881.39

Kabel BC 2 x (1c x 150 mm2) m1 77,512.50

Kabel BC 70 mm2 m1 62,595.00

Kabel BC 16 mm2 m1 50,602.50

Grounding CU BAR uk. 20 x 5 mm2 bh 105,300.00

Rekolit (dudukan CU BAR Grounding) bh 117,000.00

PEKERJAAN INSTALASI GENSET 2 x 350 KVA

5 Intake Louvre sound attenuator bh 5,444,010.00

Tanki bahan bakar mingguan bh 2,571,660.00

Tanki bahan bakar bulanan bh 2,135,250.00

Pompa Bahan bakar 10 LPM ( Pompa Elektrik ) unit 4,128,579.00

Pemipaan Bahan Bakar lengkap dengan Gate Valve unit 438,165.00

Instalasi Cerobong Asap dari Genset ke area luar /pembuangan dan Silincer ls 429,000.00

Instalasi Pengedap/ Peredam Suara Ruangan Genset titik 141,570.00

Testing & Commisioning dan Perijinan bh 409,500.00

(31)

PEKERJAAN STRUKTUR

1 1M3 Pekerjaan Balok beton K 300 TENAGA

pekerja oh 0.6100 80,000.00 48,800.00

tukang batu oh 0.1800 95,000.00 17,100.00

kepala tukang oh 0.3400 110,000.00 37,400.00

mandor oh 0.3400 150,000.00 51,000.00

154,300.00

bahan

beton redy mik k 300 m3 1.0250 760,000.00 779,000.00 beton decking bh 15.0000 1,500.00 22,500.00 curing beton m3 1.0000 9,450.00 9,450.00 810,950.00

harga satuan m3 beton 965,250.00

2 1 kg pekerjaan besi (material sbo ) TENAGA

pekerja oh 0.0040 80,000.00 320.00

tukang besi oh 0.0080 95,000.00 760.00 kepala tukang oh 0.0020 110,000.00 220.00

mandor oh 0.0010 150,000.00 150.00

alat ls 0.0010 50,000.00 50.00

1,500.00

3 1 m2 pekerjaan begesteng TENAGA

pekerja oh 0.0400 80,000.00 3,200.00

tukang besi oh 0.0700 95,000.00 6,650.00

kepala tukang oh 0.0200 110,000.00 2,200.00

mandor oh 0.0100 150,000.00 1,500.00

alat ls 0.1000 50,000.00 5,000.00

18,550.00

bahan

multiplek 18 mm m2 1.0000 80,250.00 80,250.00

skrup bh 30.0000 150.00 4,500.00

alat bantu ls 1.0000 11,700.00 11,700.00

96,450.00

jumlah harga tenaga

jumlah harga bahan

jumlah harga tenaga

jumlah harga tenaga

jumlah harga bahan

(32)

4 1M3 Pekerjaan plat tangga beton K 300 TENAGA

pekerja oh 0.6100 80,000.00 48,800.00

tukang batu oh 0.1800 95,000.00 17,100.00

kepala tukang oh 0.3400 110,000.00 37,400.00

mandor oh 0.3400 150,000.00 51,000.00

154,300.00

bahan

beton redy mik k 300 m3 1.0250 760,000.00 779,000.00 beton decking bh 15.0000 1,500.00 22,500.00 curing beton m3 1.0000 9,450.00 9,450.00 810,950.00

harga satuan m3 beton 965,250.00

PEKERJAAN PASANGAN DINDING

1M2 PEKERJAAN PASANG BATA TRASRAM TENAGA

pekerja oh 0.0200 80,000.00 1,600.00

tukang batu oh 0.0900 95,000.00 8,550.00

kepala tukang oh 0.0300 110,000.00 3,300.00

mandor oh 0.0250 150,000.00 3,750.00

17,200.00

bahan

bata bh 97.0000 750.00 72,750.00

pasir m3 0.1000 135,000.00 13,500.00

semen zak 0.3000 55,000.00 16,500.00

102,750.00

harga 1m2 pasangan bata dibulatkan 120,000.00

PASANGAN DINDING BATA 1m2 pangan bata

TENAGA

pekerja oh 0.0200 80,000.00 1,600.00

tukang batu oh 0.0900 95,000.00 8,550.00

kepala tukang oh 0.0300 110,000.00 3,300.00

mandor oh 0.0200 150,000.00 3,000.00

16,450.00

jumlah harga bahan

jumlah harga tenaga jumlah harga tenaga

jumlah harga bahan

jumlah harga tenaga

(33)

semen zak 0.0900 55,000.00 4,950.00 88,350.00

harga 1m2 pasangan bata dibulatkan 105,000.00

PEKERJAAN PLESTERAN 1m2 PLESTERAN TRASRAM TENAGA

pekerja oh 0.0200 80,000.00 1,600.00

tukang batu oh 0.0900 95,000.00 8,550.00

kepala tukang oh 0.0210 110,000.00 2,310.00

mandor oh 0.0200 150,000.00 3,000.00

15,460.00

bahan

pasir m3 0.2000 135,000.00 27,000.00

semen zak 0.1000 55,000.00 5,500.00

32,500.00

harga 1m2 pasangan bata dibulatkan 47,500.00

PEKERJAAN PLESTERAN 1m2 PLESTERAN TENAGA

pekerja oh 0.0200 80,000.00 1,600.00

tukang batu oh 0.0900 95,000.00 8,550.00

kepala tukang oh 0.0210 110,000.00 2,310.00

mandor oh 0.0200 150,000.00 3,000.00

15,460.00

bahan

pasir m3 0.0800 135,000.00 10,800.00

semen zak 0.2000 55,000.00 11,000.00

21,800.00

harga 1m2 pasangan bata dibulatkan 38,224.00

PEKERJAAN KERAMIK DINDING 1m2 KERAMIK

jumlah harga bahan

jumlah harga tenaga

jumlah harga bahan

jumlah harga tenaga

jumlah harga bahan

(34)

kepala tukang oh 0.0200 110,000.00 2,200.00

mandor oh 0.0200 150,000.00 3,000.00

31,350.00

bahan

pasir m3 0.0800 135,000.00 10,800.00

semen zak 0.3000 55,000.00 16,500.00

KERAMIK DOS 1.0000 95,440.00 95,440.00

SEMEN WARNA KG 1.3000 25.0000 32.5000 122,772.50

154,122.50

PEKERJAAN MARMER 1m2 KERAMIK TENAGA

pekerja oh 0.2500 80,000.00 20,000.00

tukang batu oh 0.0900 95,000.00 8,550.00

kepala tukang oh 0.0200 110,000.00 2,200.00

mandor oh 0.0200 150,000.00 3,000.00

33,750.00

bahan

pasir m3 0.2000 135,000.00 27,000.00

semen zak 0.3000 55,000.00 16,500.00

SEMEN WARNA KG 1.3000 25.0000 32.5000 43,532.50

77,282.50

jumlah harga tenaga

jumlah harga bahan jumlah harga tenaga

jumlah harga bahan

(35)

1500 -

(36)

1,015,000.00

#REF!

(37)

38,224.20

0.20

(38)

154,123.00

0.50

750,000.00

672,717.50

(39)

PEKERJAAN PASANGAN DINDING

1M2 PEKERJAAN PASANG BATA TRASRAM TENAGA

pekerja oh 0.0200 80,000.00

tukang batu oh 0.0900 95,000.00

kepala tukang oh 0.0300 110,000.00

mandor oh 0.0250 150,000.00

bahan

bata bh 97.0000 750.00

pasir m3 0.1000 135,000.00

semen zak 0.3000 55,000.00

harga 1m2 pasangan bata dibulatkan

PASANGAN DINDING BATA 1m2 pangan bata

TENAGA

pekerja oh 0.0200 80,000.00

tukang batu oh 0.0900 95,000.00

kepala tukang oh 0.0300 110,000.00

mandor oh 0.0200 150,000.00

bahan

bata bh 95.0000 750.00

pasir m3 0.0900 135,000.00

semen zak 0.0900 55,000.00

harga 1m2 pasangan bata dibulatkan

jumlah harga tenaga

jumlah harga bahan

jumlah harga tenaga

jumlah harga bahan

(40)
(41)
(42)
(43)

1,600.00

8,550.00

3,300.00

3,750.00

17,200.00

72,750.00

13,500.00

16,500.00

102,750.00

120,000.00

1,600.00

8,550.00

3,300.00

3,000.00

16,450.00

71,250.00

12,150.00

4,950.00

88,350.00

105,000.00

(44)
(45)
(46)
(47)

pekerja OH 0.0100

tukang listrik OH 0.0100

kepala tukang OH 0.0020

mandor OH 0.0002

B bahan

kabel tray 300 x 100 mm M1 1.0000

C

(48)

3 Tukang Batu Orang/Hari Rp95,000 3

4 Tukang Besi Orang/Hari Rp95,000 4

5 Kepala Tukang Orang/Hari Rp110,000 5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47

48

49

(49)

53

54

55

56

57

58

59

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

94

95

96

97

98

99

(50)

103

104

105

106

107

108

109

110

111

112

113

114

115

116

117

118

119

120

(51)

curing beton multiplek 18 mm skrup

alat bantu bata pasir semen WF 350.150 WF 150.100

BASE PLATE 15 MM BASE PLATE 10 MM ANGKUR M19 ANGKUR M16 MUR BAUT M16

PLAT SAMBUNG 10 MM CAT ZINCROMATE

Wastafel ex Toto TOTO TX115LRS+TOTO LW649CJ lengkap dengan meja Towel Shelf & Towel Bar TX726AE

Paper Holder TX720AB Shoap Holder ex Toto AR15 Closet Jongkok ex Toto CE7 Closet ex Toto CW637J/SW637JP Shower ex Toto TX493SRR Floor Drain ex Toto TX1BV1N Kran Dinding ex Toto

Roob Hook ex Toto

Instalasi Penerangan dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 Instalasi Kotak kontak Biasa dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 Balk LED Tube 1 x 20 W

Kotak Kontak Biasa Saklar Ganda Saklar Grid 8 Gang Saklar Grid 12 Gang

Kabel Ladder ukuran 300 mm x 100 mm Kabel Tray ukuran 300 mm x 100 mm Tee Tray ukuran 300 mm x 100 mm Elbow ukuran 300 mm x 100 mm

Instalasi ROR Heat Detector & EORL dgn kabel NYA 2 (1x1.5) mm2 Instalasi Smoke detector dgn kabel NYA 2 (1x1.5) mm2

Instalasi Flow & Temper Switch dgn kabel NYA 2 (1x1.5) mm2 Instalasi Manual Push Button dgn kabel NYA 2 (1x1.5) mm2 Instalasi Alarm Bell dgn kabel NYA 2 (1x1.5) mm2

Instalasi Indicating lamp dgn kabel NYA 2 (1x1.5) mm2 ROR Heat Detector

Smoke Detector

Flow Switch

Temper Switch

(52)

End of line resistor

Terminal Box Fire Alarm (TB-FA) Kabel Feeder fire alarm

Instalasi Ceiling speaker dgn kabel NYMHY 3 x 1,5mm dlm pipa conduit PVC dia. 20 mm2 Celling Speaker 3 W

Horn Speaker 15 W Volume Kontrol

Sound Terminal Box (STB) Kabel Feeder sound system

Instalasi CCTV dg kabel RG 59 + Power dlm pipa conduit PVC dia. 20 mm2 In door Camera CCTV IR type Fixed

Color Dome type camera Box CCD Camera

Memasang Pipa PVC dia. 150 mm kelas AW Memasang Pipa PVC dia. 100 mm kelas AW Memasang Pipa PVC dia. 75 mm kelas AW Memasang Pipa PVC dia. 75 mm kelas AW Memasang Pipa PVC dia. 50 mm kelas AW Memasang Clean Out dia. 150 mm

Pre Treatment lemak/ grease trap kap. 2 m3 Resapan

Pompa Submersible Sewage

Fitting + Supporting termasuk hanger dan u-trap Memasang Pipa PPR PN 10 dia. 25 mm

Memasang Pipa PPR PN 10 dia. 20 mm Memasang Pipa PPR PN 10 dia. 15 mm Memasang Gate Valve dia. 20 mm Fitting + Supporting termasuk hanger

Instalasi Power AC dg Kabel NYM 3 x 2.5 mm dlm Pipa Conduit dia. 20 mm2 Kabel Power Kontrol NYM 3 x 2.5 mm2 dari Indoor s/d Outdoor unit

Air Conditioner Split Wall 18.000 Btu/h Air Conditioner Split Wall 5.000 Btu/h Instalasi Pipa Refrigerant uk. 1/4"

Instalasi Pipa Refrigerant uk. 1/2"

Memasang Pipa PVC dia. 20 mm kelas AW Fitting + Supporting dan material bantu Memasang Pipa BS sch-40 dia. 150 mm Memasang Pipa BS sch-40 dia. 80 mm Memasang Pipa BS sch-40 dia. 50 mm Memasang Pipa BS sch-40 dia. 40 mm Memasang Pipa BS sch-40 dia. 32 mm Memasang Pipa BS sch-40 dia. 25 mm Memasang Pipa BS sch-40 dia. 20 mm Memasang Head Sprinkler Tipe Pendant Memasang Brach Control Valve dia. 80 mm

Memasang Gate Valve 10 K with Flanges dia. 80 mm

Memasang Gate Valve 10 K with Flanges dia. 50 mm

(53)

Instalasi Exshaust FAN dg kabel NYM 2 x 2.5 mm2 dlm Pipa Conduit dia. 20 mm2 Memasang Exshaust FAN 12 W

Downlight LED 19 W Downlight LED 13 W Downlight LED 7 W RM LED Tube 2 x 10 W

RM LED Tube 3 x 10 W Arcylic Cover Balk LED Tube 1 x 20 W

Lampu Strip LED 3 m/ 14.4 W/ m Lampu Strip LED 26.5 m/ 14.4 W/ m Lampu Strip LED 48 m/ 14.4 W/ m Lampu Strip LED 33 m/ 14.4 W/ m Kotak Kontak Lantai

Kotak Kontak Biasa

Saklar Ganda

Saklar Tunggal

Saklar Hotel Ganda

Saklar Grid 14 Gang

(54)

m3 9,450.00

m2 80,250.00

bh 150.00

ls 11,700.00

bh 750.00

m3 135,000.00

zak 55,000.00

KG 7,500.00

KG 7,500.00

KG 7,500.00

KG 7,500.00

TITIK 159,619.50

TITIK 65,175.00

BH 7,702.50

KG 21,330.00

KG 1,422.00

Unit 1,606,380.00

Unit 57,000.00

Unit 39,310.00

Unit 39,310.00

Unit 152,750.00

Unit 193,780.00

Unit 127,230.00

Unit 45,170.00

Unit 27,580.00

Unit 27,580.00

titik 134,550.00

titik 134,550.00

bh 473,265.00

bh 20,475.00

bh 46,215.00

set 119,925.00

set 187,785.00

m1 172,500.00

m1 172,500.00

bh 172,500.00

bh 172,500.00

titik 159,705.00

titik 159,705.00

titik 159,705.00

titik 159,705.00

titik 159,705.00

titik 159,705.00

bh 253,305.00

bh 194,805.00

bh 838,305.00

bh 955,305.00

(55)

bh 9,009.00

bh 780,975.00

m1 22,932.00

titik 200,655.00

bh 177,255.00

bh 311,805.00

bh 311,805.00

bh 569,205.00

m1 26,325.00

titik 235,755.00

bh 962,910.00

bh 669,825.00

ls 585,000.00

m1 235,755.00

m1 118,755.00

m1 80,145.00

m1 80,145.00

m1 49,140.00

m1 234,819.00

Unit 7,488,000.00

Unit 2,340,000.00

Unit 23,400,000.00

ls 1,755,000.00

m1 40,131.00

m1 29,103.75

m1 21,937.50

bh 377,471.25

ls 201,649.50

titik 346,539.38

m1 20,182.50

Unit 4,387,500.00

Unit 3,925,000.00

m1 65,000.00

m1 77,000.00

m1 24,716.25

ls 64,350.00

m1 422,370.00

m1 202,410.00

m1 124,546.50

m1 88,881.39

m1 77,512.50

m1 62,595.00

m1 50,602.50

bh 105,300.00

bh 5,444,010.00

bh 2,571,660.00

bh 2,135,250.00

(56)

titik 141,570.00

bh 409,500.00

bh 277,875.00

bh 272,025.00

bh 252,135.00

bh 90,090.00

bh 970,515.00

bh 473,265.00

set 321,165.00

set 1,283,490.00

set 2,163,915.00

set 1,549,665.00

bh 371,475.00

bh 20,475.00

bh 46,215.00

bh 39,195.00

bh 53,235.00

set 172,575.00

(57)

MASTER TIME SCHEDULE

PROYEK PEMBANGUNAN HOTEL "SOLIA BOUTIQUE "

Jl. Dr. Radjiman-Surakarta

8sd13 14sd20 21sd 27 28sd4 5sd11 12sd18 19sd25 26sd31 1sd8 9sd15 16sd22 23sd29 31sd6 7sd13 14sd20 21sd27 28sd3 4sd10 11sd16 18sd24 25sd31 1sd7 8sd14 15sd21 22sd28

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

II III IV I II III IV V I II III IV I II III IV I II III IV V I II III IV

LI B U R H A R I R

I PEKERJAAN PERSIAPAN 1,184 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028 0,028

II PEKERJAAN STRUKTURE

1 LANTAI 1 0,333 0,167 0,167

2 LANTAI MEZANINE 0,228 0,114 0,114

3 LANTAI-2 0,814 0,271 0,271 0,271

4 LANTAI-3 1,353 0,451 0,451 0,451

5 LANTAI-4 1,253 0,418 0,418 0,418

6 LANTAI-5 1,249 0,416 0,416 0,416

7 LANTAI-6 1,251 0,417 0,417 0,417

8 LANTAI-7 1,243 0,414 0,414 0,414

9 LANTAI-8 1,180 0,393 0,393 0,393

10 LANTAI-9 1,161 0,387 0,387 0,387

11 LANTAI ATAP 0,918 0,306 0,306 0,306

III PEKERJAAN ARSITEKTURE

1 BATA & KOLOM PRAKTIS 6,700 0,064 0,258 0,348 0,498 0,498 0,583 0,540 0,450 0,450 0,600 0,450 0,450 0,537 0,387 0,243

2 PLESTERAN & ACIAN 5,942 0,277 0,277 0,486 0,486 0,418 0,461 0,461 0,252 0,504 0,504 0,252 0,460

3 KERAMIK