No. Dok. F/EC/01-02
No. Rev. 00
Tgl. Eff. 06 September 2022
Halaman 1 dari 1
Document Number
Work Request Number Job Location
Drawing Name
Job name Drawing Number
Price/Unit Total Price Price/Unit Total Price
I
1 Soil bearing capacity test
- Test CBR Site 5.00 point
- Test CBR Labolatory 1.00 sample
2 Mob Demob Vibro Roller Capacity 25 Ton 1.00 ls
3 Rental Vibro Roller + fuel + operator 98.00 hours
4 Mob Demob Excavator 1.00 ls
5 Rental Excavator + fuel + operator 98.00 hours
6 Fill side road Sirtu (Sand & Stone) 70.00 m3
7 Fill base road Sirtu (Sand & Stone) 100.00 m3
-
Rp Rp - II
1 Lean Concrete Quality B0 NFA 52.00 m3
2 Concrete Quality K-350 NFA 130.00 m3
3 Wiremesh Size 2.10 m x 5.40 m x M10 / sheet 4827.50 kg
4 Dowel Steel RB Ǿ25 @12 m, include zincromate & anti lengket 836.23 kg
5 RB Ǿ12 @12 m 1324.91 kg
6 Tie Beam DB 16 @12 m 147.55 kg
7 RB Ǿ12 @12 m 818.06 kg
8 Korset for wiremesh / 50 cm2 RB Ǿ10 @12 m 123.50 kg
9 Cutting & Asphal Expanseal 100 @25 kg 226.25 m
10 Treatment conecting existing concrete with new concrete Sika bonding adhesive 100.00 m
11 Plastic Cast 505.00 m2
Preparation Work
Sub Total Preparation Work Rigid Pavement Work
No. Item Name Specification Qty Unit Material Labor Cost
Remarks
: : RMI - Brongkos
Section : IR : Rigid Pavement
: Rigid Pavement - Estimation per 5 m x 100 m :
PT. REJOSO MANIS INDO FORM
BILL OF QUANTITY (BOQ)
:
12 Bekisting / wood formwork Multipleks 12 mm + kayu kelas kuat III*
Termasuk pengecekan level dengan waterpass optic 140.00 m2
-
Rp Rp - -
Rp Rp - - Rp
Inspector
Date :
Name : Mr. Hengki Timatius
Date : Date : Date :
Name : Mr. Fahri Name : Mr. Kasio Name : Mr. Purisup Silanguen
Total material cost, equipment and labor (Rp.)
Engineer Approver Approver
Sub Total Rigid Pavement Work Total
4.00 4.00 4.00
2.502.50 5.00
R D R A D
SKALA 1 : 150
ARS 01-03
Wiremesh M10 - 1 layer Tie Beam
Ruji / Dowel Concrete K-350
0.75 0.75
0.30 0.30
XX-XX
1
XX-XX
1
XX-XX
2
XX-XX
2
SECTION 2-2
S 1 2
S -
C
- T 2 C
2
C 12-
- 12 1 2 -
S 2
- 12 C
12- 1 -
C T 1 C
E S S
2
SECTION 1-1
S 1 2
S 2-
C
- T 2 C
2
1
S 2
- 12 C
12-
1 - C T 1 C
E S
S
2
DETAIL RUJI / DOWEL
S ALA
ARS
RB
W M
A RB
DETAIL TIE BEAM
S ALA
ARS
W M
A DB
RB
L M L M
HAIRA RB
HAIRA RB
L L L
/ L
L L
/ A
A L
D D
W M
RB
DETAILS UPHILL ROAD
S ALA
ARS
RB
L T
E S
RB
E R
R P L M
B T
Actual Design : Next Work : Casting Lean Concrete 10 cm
Quality Control : Check list
1 Already compact per layer 2 No have protruding surfaces 3 No have deflection surface 4 Size area already same with road plan 5 Casting plastic ready
6 Tool work ready - (Vibrator, Backet, Gutter, Beam, etc) 7 Man power, Supervisor & Safety already complete
8 -
Noted :
1 …...
2 …...
3 …...
4 …...
5 …...
6 …...
DETAIL
FORM APPROVAL WORK
ENGINEERING CENTER
PROJECT : RIGID PAVEMENT
Location Work : Zone 1
VIEW ALL WORK
Rejoso, 01 Januari 2023
(Mr. Fahri) Date : .../.../...
Civil Engineer
(Mr. L. Hengky Timatius) Date : .../.../...
Engineering Assistance Manager
(Mr. Purisup Silanguen) Date : .../.../...
Engineering Manager (Mr. Zainuri)
Date : .../.../...
Project Supervisor (Mr...)
Date : .../.../...
Supplier
Actual Design : Next Work : Install Dowel, Tiebars, Wiremesh & Formwork
Quality Control : Check list
1 Lean concrete finish 2 Level already good
3 The age of the lean concrete is sufficient 4 Surface lean concrete already clean
5 Tool work ready - (Vibrator, Backet, Gutter, Beam, etc) 6 Man power, Supervisor & Safety already complete
7 -
8 -
Noted :
1 …...
2 …...
3 …...
4 …...
5 …...
6 …...
DETAIL
FORM APPROVAL WORK
ENGINEERING CENTER
PROJECT : RIGID PAVEMENT
Location Work : Zone 1
VIEW ALL WORK
Rejoso, 01 Januari 2023
(Mr. Fahri) Date : .../.../...
Civil Engineer
(Mr. L. Hengky Timatius) Date : .../.../...
Engineering Assistance Manager
(Mr. Purisup Silanguen) Date : .../.../...
Engineering Manager (Mr. Zainuri)
Date : .../.../...
Project Supervisor (Mr...)
Date : .../.../...
Supplier
Actual Design : Next Work : Casting Concrete K-350
Quality Control : Check list
1 Formwork already good
2 Relat already on check level 3 Tie bars already same drawing 4 Dowel have protection 5 Wiremesh have behel per 1 m2
6 Tool work ready - (Vibrator, Backet, Gutter, Beam, etc) 7 Support material ready - (Concrete Glue)
8 Man power, Supervisor & Safety already complete
Noted :
1 …...
2 …...
3 …...
4 …...
5 …...
6 …...
DETAIL
Rejoso, 01 Januari 2023
VIEW ALL WORK
FORM APPROVAL WORK
ENGINEERING CENTER
PROJECT : RIGID PAVEMENT
Location Work : Zone 1
(Mr. Fahri) Date : .../.../...
Civil Engineer
(Mr. L. Hengky Timatius) Date : .../.../...
Engineering Assistance Manager
(Mr. Purisup Silanguen) Date : .../.../...
Engineering Manager (Mr. Zainuri)
Date : .../.../...
Project Supervisor (Mr...)
Date : .../.../...
Supplier
Actual Design : Next Work : Unlock traffic
Quality Control : Check list
1 Minimum age of concrete 2 weeks
2 Design strength of the concrete has been achieved 3 Concrete surface has been cut according to the drawing 4 Installation of asphalt / sealant finish
5 The side of the road has been filled with stone 6 The road is clear
7 -
8 -
Noted :
1 …...
2 …...
3 …...
4 …...
5 …...
6 …...
DETAIL
FORM APPROVAL WORK
ENGINEERING CENTER
PROJECT : RIGID PAVEMENT
Location Work : Zone 1
VIEW ALL WORK
Rejoso, 01 Januari 2023
(Mr. Fahri) Date : .../.../...
Civil Engineer
(Mr. L. Hengky Timatius) Date : .../.../...
Engineering Assistance Manager
(Mr. Purisup Silanguen) Date : .../.../...
Engineering Manager (Mr. Zainuri)
Date : .../.../...
Project Supervisor (Mr...)
Date : .../.../...