Bill Of Quantity Rebuild Floor WH-DC PT PARDIC JAYA CHEMICAL
13/PJC-BPP/QUOT-WH-DC/7.1/2024
No SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
A PEKERJAAN PERSIAPAN
1 Mobilisasi demobilisasi Manpower dan tools Ls 1.00 1,750,000.00 1,750,000.00
2 Safety dan K3 Ls 1.00 1,500,000.00 1,500,000.00
3 Mess Karyawan Bln 2.00 750,000.00 1,500,000.00
4 Pembersihan Ahir Ls 1.00 2,750,000.00 2,750,000.00
SUB TOTAL 7,500,000.00 B PEKERJAAN PERBAIKAN LANTAI BETON ELEVASI LANTAI YANG DIPERBAIKI TIDAK MENGIKUTI ELEVASI LANTAI EXISTING COR BARU
1 Screding Lantai Beton 7cm M3 40.50 336,740.68 13,637,492.43
2 Cutting crak floor dan injection SIKA Crack Seal (perbaikan lantai
retak) M2 64.00 225,000.00
14,400,000.00
3
Leveling lantai DTA tebal 8cm (12.6m x 6.5m) menggunakan material bonding adhesive, perekat beton lama dan beton baru , pasir ayak, semen dan Addictive floor (readymix) tebal 7Cm
M3 40.50 1,871,825.20 75,806,112.86
4 Wiremesh 1 Layer M 8 (seting overlaping antar wiremesh 30cm) M2 578.55 132,500.00
76,657,875.00
5 Pek. Finsih Lantai Trowel, 5kg/M2 (20.3 m x 28.5 m) M2 578.55 83,000.00 48,019,650.00 SUB TOTAL 228,521,130.29 C
1 Perapihan Pedestal Tiang WF Ls 1.00 787,562.30 787,562.30 2 Pengecatan grill gutter (digerinda amplas lalu finishing cat Spray) Ls 1.00 646,820.40 646,820.40 3 Perbaikan kebocoran atap GD-DC dengan metode
sealent/plincoating Ls 1.00 1,846,236.20 1,846,236.20
4 Pengecatan Strucktur BAJA WF untuk GD-DC Ls 1.00 6,846,236.20 6,846,236.20 5 Pengecatan marka Lantai Termoplastic 1.5mm M2 98.56 62,800.00 6,189,568.00 SUB TOTAL 16,316,423.10 268,363,944.52
Tangerang 17 Januari 2024 PT BUMI PALAPA PERKASA
Agus Wiyono ST 100%
Direktur 100.00%
PEKERJAAN LAIN LAIN
GRAND TOTAL (A+B+ C) JENIS PEKERJAAN
Bill Of Quantity Utility WH- DC
PT PARDIC JAYA CHEMICAL
14/PJC-BPP/QUOT-WH-DC/7.1/2024 D
1 Pek. Galian dan bobokan lantai t 20 cm M3 2.16 560,000.00 1,209,600.00
2 Pek. Pembesian M8 2 layer kg 153.00 19,186.44 2,935,525.32
3 Pek. Pengecoran Lantai K-350 t 20 cm M3 2.16 1,856,262.68 4,009,527.38 SUB TOTAL 8,154,652.70 E PERBAIKAN OPRITAN RAMP AKSES SISI KANAN (1.5 x16.2)
1 Pek. Galian dan bobokan lantai t 20 cm M3 7.29 560,000.00 4,082,400.00
2 Pek. Pembesian M8 1 layer kg 171.72 19,186.44 3,294,695.48
3 Pek. Pengecoran Lantai K-250 t 20 cm (site mix) M3 4.86 1,681,262.68 8,170,936.61 SUB TOTAL 15,548,032.08 F PERBAIKAN OPRITAN RAMP AKSES SISI Kiri (2.4 x 31.2)
1 Pek. Galian dan bobokan lantai t 20 cm (2.4 x 31.2 x 0.2) M3 14.98 560,000.00 8,386,560.00
2 Pek. Pembesian M8 1 layer kg 529.15 19,186.44 10,152,543.10
3 Pek. Pengecoran Lantai K-250 t 20 cm (site mix) M3 14.98 1,681,262.68 25,178,589.84 SUB TOTAL 43,717,692.94 67,420,377.72
Tangerang 17Januari 2024 PT BUMI PALAPA PERKASA
Agus Wiyono ST 100%
Direktur 100.00%