Plan today, Wednesday June 04, 2025 (E) MCC#2
Supervisor : Reno, Manpower Total : 18 Cable Room
- Install Arm
- Install Cable tray dll - Install Joint support MCC room
- Continue Fullweld base frame - Cleaning, Painting base frame
- Continue Fabrikasi base frame stand alone - Repair base frame line 20
Trafo Room
- Install Trafo TR024 ( Waiting info)
Trafo Room MCC4
Supervisor : Nelson Purba, Manpower Total : 15 Panel room
Instal UNP for base frame Transformer room
Install tray outgoing from Transformer Plan today, Wednesday June 04, 2025 (IA)
Chipping Line 20; Screening Line 20; Panel Room MCC4; Conveyor 4013 Supervisor : Ishak , Manpower Total : 20
Conveyor 4013; Manpower 6 - Install 2nd tray
- Install Field Device - Fabrikasi suport
Screening line 20, Manpower 4 - Install Frame JB
- Install JB Digital - Install suport 2nd tray Chiping Line 20, Manpower 7 - Install Frame JB
- Install JB analog
- Install support, cable tray Panel Room MCC4, Manpower 3 - Touchup painting
- Drilling Frame automation panel