MUHAMMAD AL FARISY 20/463181/TK/51173

ID Budget ($000) 1 2 3 4 5 6 7 8 9 10 11 12

A 40 10 10 10 10

B 32 8 4 8 4 8

C 48 12 12 12 12

D 18 6 2 2 2 6

E 28 8 8 12

F 40 20 20

Total 206 18 14 18 14 20 26 22 26 2 6 20 20

Cumulative 18 32 50 64 84 110 132 158 160 166 186 206

(2)

MUHAMMAD AL FARISY 20/463181/TK/51173

Task % Complete EV AC PV CV = EV-AC SV = EV-PV $

A 75 30 25 20 5 10

B 50 16 12 12 4 4

Cummulative Totals 46 37 32 9 14 0

Task % Complete EV AC PV CV = EV-AC SV = EV-PV $

A 100 40 35 40 5 0

B 100 32 24 24 8 8

Cummulative Totals 72 59 64 13 8 0

Task % Complete EV AC PV CV = EV-AC SV = EV-PV $

A 100 40 35 40 5 0

B 100 32 24 32 8 0

C 75 36 24 24 12 12

D 0 0 0 6 0 -6

E 50 14 10 8 4 6

Cummulative Totals 122 93 110 29 12 0

Task % Complete EV AC PV CV = EV-AC SV = EV-PV $

A 100 40 35 40 5 0

B 100 32 24 32 8 0

C 100 48 32 48 16 0

D 33 5,94 20 10 -14,06 -4,06

E 100 28 20 28 8 0

Cummulative Totals 153,94 131 158 22,94 -4,06 0

Manajemen Proyek : Project Control

Status Report: Ending Period 2

Status Report: Ending Period 4

Status Report: Ending Period 6

Status Report: Ending Period 8

(3)

Performance Indexes Summary

EV AC PV CV = EV-AC SV = EV-PV CPI = EV : PV SPI = EV : AC

46 37 32 9 14 1,4375 1,24324324

72 59 64 13 8 1,125 1,22033898

122 93 110 29 12 1,109090909 1,31182796

153,94 131 158 22,94 -4,06 0,974303797 1,1751145

175

VAC

f

= BAC - EAC

f 30,7

EAC

f

= ((BAC - EV) / (EV/AC)) + AC

8

Task 2 4 6

Referensi

Dokumen terkait

Analysis of Cost and Time Performance in the Implementation of Construction Projects Using the Earned Value Method (Case Study of Mall and Hotel X Construction Projects

56 of 2003 Municipal Budget Circular for the 2015/16 MTREF 01 July 2015 Page 1 of 2 Municipal Budget Circular for the 2015/16 MTREF This circular provides further guidance to

Serkolinas Aman Nusantara Indonesia, budget planning is very important, based on the information above, budget planning can be used as a tool in motivating organizational members to

Headline Budget 2023: Infrastructure projects get a boost with RM16.5bil allocation for transport sector Language ENGLISH Media Title The Star Section/Page No Nation Date 7 October

The ratio of realization to the budget proves that the budget has been absorbed in the various programs that have been Abstract This study aims to prove empirically the effect of

The document outlines the various types of construction projects and

This document provides guidance on conducting developmental research projects in the field of instructional design and

This document provides a comprehensive overview of the concepts related to income statement preparation, including income measurement and computation, condensed and detailed income statements, and various accounting changes and