Gambar Kerja
Perencanaan Rumah Tinggal Pribadi
By:
400
375 125 250 100
Car Port - 0.20
DENAH LANTAI 1 (EXIXTING) SKALA 1:50
A B C D E
1
2
375 125 250 100
400
78
Office+ 3.90
DENAH LANTAI 2 SKALA 1:50
Garden + 3.90 1
2
DETAIL STRUKTUR GRID 2 SKALA1:75 380
210 90 250
375 125 250 100
Bangunan Existing Ring Balok
Slab Ring Balok
340 40 235 58 250 100
DETAIL STRUKTUR GRID B SKALA1:75
Slab Slab Balok Latey Ring Balok Ring Balok
340 40 185
10 60 250
383 383 200
TAMPAK DEPAN SKALA1:75 20
25
85 250 515 340
40 65 140
95
TAMPAK BELAKANG SKALA1:75
TAMPAK SAMPING KIRI SKALA1:75 Bangunan Existing
560 120 250
400 78
TAMPAK SAMPING KANAN SKALA1:75
400 78
60
340 40 70 170
375 125 250 100
400
78
RENCANA BALOK & KOLOM SKALA1:50
Balok 0.2.02
Balok 0.2.02
Kolom 0.2.02 Kolom 0.2.02
400
78
Office+ 3.90
RENCANA KUSEN PINTU & JENDELA SKALA1:50
Garden + 3.90 J1
R1 J1 P1
KETERANGAN P1
J1 R1
Pintu Type 1 Jendela Type 1 Roster 0.2.0.2
JUMLAH 1 2 48
80 55 55 55
190
53 53
140
DETAIL KUSEN PINTU & JENDELA
SKALA1:25
20
20
20
20
DETAIL PENULANGAN STRUKTUR SKALA1:10
70
10
SLAB
KOLOM (K1) BALOK (B1) RING BALOK (R1)
20
15
BALOK LATEY (B2)
20
15
Keterangan:
DETAIL KUDA-KUDA BAJA RINGAN C.75.75 & TASO R 45.45 SKALA1:50
750
40 20
451
92
250
SKALA1:50
PREFEKTIF TAMPAK SAMPING
SKALA1:50
Pekerjaan 1 M3 Pek.Campuran 1 : 2 : 3
Pjg Lebar Atas
Lebar
Bawah Tinggi Koef Sat Upah/Alat/bahan Vol.Pek(
f x h) Sat
b c d e f g h i j k l m n
1 Balok (B1) 25 0.2 0.2 1 M3 7.296 Zak Semen 27.25 Zak 27 Zak
2 Balok Latey (B2) 10.5 0.2 0.15 0.315 M3 0.507 M3 Pasir 1.89 M3 2 M3
3 Kolom (K1) 18 0.2 0.2 0.72 M3 0.760 M3 Krikil/Suplit 2.84 M3 3 M3
4 Ring Balok (R1) 25 0.2 0.15 0.75 M4
5 Ring Balok (R2) 20 0.2 0.15 0.6 M5
6 Concrate Slab 5 0.7 0.1 0.35 M6
Pekerjaan Dinding Tembok Campuran 1:4
Pjg Lebar Atas
Lebar
Bawah Unit Koef Sat Upah/Alat/bahan Vol.Pek(
f x h) Sat
b c d e f g h i j k l m n
a Pasangan Bata Ringan 21.4 2.6 55.64 M2 0.138 Zak Semen 8.06 Zak 8 Zak
Kusen Pintu 0.8 2.1 2 3.36 M2 0.019 M3 Pasir 1.12 M3 1 M3
Kusen Jendela (J1) 0.6 1.6 4 3.84 M2 8.333 M2 Bata Ringan 486.08 M2 486 bh
Kusen Jendela (J2) 0.6 2 3 3.6 M2
Roster 0.2 0.2 94 3.76 M2
c Kuda-Kuda 7.5 2.3 17.25 M2
Pekerjaan Pembesian
Pjg Lebar Atas
Lebar
Bawah Unit Koef Sat Upah/Alat/bahan Vol.Pek(
f / h) Sat
b c d e f g h i j k l m n
Balok (B1) 25 4 100 m 11.60 Btg Besi 10 35.69 Btg 36 Btg
Balok Latey (B2) 10.5 4 42 m 11.60 Btg Besi 8 29.98 Btg 30 Btg
Kolom (K1) 18 4 72 m 0.150 Kg Kawat Beton 58.86 Kg 59 Kg
Ring Balok (R1) 25 4 100 m
Ring Balok (R2) 20 4 80 m
Concrate Slab 5 4 20 m Besi 10 0.616 414 255.02
Balok (B1) 0.6 166.67 100 m Besi 8 0.395 348 137.36 +
Besi 10
Besi 8 b
No Elemen
DIMENSI
VOL Sat
Analisa SNI
Real Vol
RAB Sat
Sat
Volume = a - b + c 58.33
No Elemen
No Elemen
DIMENSI
VOL Sat
Analisa SNI
Real Vol RAB DIMENSI
VOL Sat
Analisa SNI
Real Vol
RAB Sat
Balok Latey (B2) 0.5 52.50 26.25 m 392.39 Kg
Kolom (K1) 0.6 90.00 54 m
Ring Balok (R1) 0.5 125.00 62.5 m
Ring Balok (R2) 0.5 100.00 50 m
Concrate Slab 2.2 25.00 55 m
Pekerjaan Plesteran Campuran 1:4
Pjg Lebar Atas
Lebar
Bawah Unit Koef Sat Upah/Alat/bahan Vol.Pek(
f x h) Sat
b c d e f g h i j k l m n
a Plesteran 21.4 2.6 55.64 M2 0.115 Zak Semen 13.81 Zak 14 Zak
Kusen Pintu 0.8 2.1 2 3.36 M2 0.016 M3 Pasir 1.92 M3 2 M3
Kusen Jendela (J1) 0.6 1.6 4 3.84 M2
Kusen Jendela (J2) 0.6 2 3 3.6 M2
Roster 0.2 0.2 54 2.16 M2
c Kuda-Kuda 7.5 2.3 17.25 M2
Pekerjaan Granite
Pjg Lebar Atas
Lebar
Bawah Tinggi Koef Sat Upah/Alat/bahan Vol.Pek(
f x h) Sat
b c d e f g h i j k l m n
1 Granite 0.6.0.6 4 7.5 30 M2 2.778 Bh Granite 83.33 Bh 83 Bh
2 Adukan/Perekat 4 7.5 30 M2 0.230 M3 Semen 6.91 Zak 7 Zak
0.032 M2 Pasir Halus 0.96 M3 1 M3
Pemasangan 1 m2 Pasang Kuda-Kuda Baja Ringan + Reng untuk Atap Genteng Biasa/Metal
Pjg Lebar Atas
Lebar
Bawah Unit Koef Sat Upah/Alat/bahan Vol.Pek(
f x h) Sat
b c d e f g h i j k l m n
1 Baja ringan canai dingin C75 18 4 72 M' 3.72 M' Baja ringan canai dingin C75 267.84 M' 268 M'
2 Baut (Srew driver) 20 bh 28.00 bh Baut (Srew driver) 560.00 bh 560 bh
3 Dynabol dia 12 x 120 mm 8 4 32 bh 2.00 bh Dynabol dia 12 x 120 mm 64.00 bh 64 bh
4 Gording Taso 4.5 7.5 10 75 M' 1.10 M' Gording Taso 4.5 82.50 M' 83 M'
5 Talang / Jurai Canai Dingin 7.5 2 15 M' 1.10 M' Talang / Jurai Canai Dingin 16.50 M' 17 M'
6 Atap Spandek 0.8.12 18 7.5 135 M2 9.20 Lmbr Atap Spandek 0.8.12 14.67 Lmbr 15 Lmbr
Analisa SNI
Real Vol
RAB Sat
No Elemen
DIMENSI
VOL Sat
Real Vol
RAB Sat
No Elemen
DIMENSI
VOL Sat
Analisa SNI
Analisa SNI Real Vol
RAB Sat
b Volume = a - b + c
119.86
No Elemen
DIMENSI
VOL Sat
Besi 8
No Material Volume Sat
1 Semen 56 Zak
2 Pasir 5 M3
3 Krikil/Suplit 3 M3
4 Bata Ringan 486 Bh
5 Besi 10 36 Btg
6 Besi 8 30 Btg
7 Kawat Beton 59 Kg
8 Roster 54 Bh
9 Pasir Halus 1 M3
10 Granite 0.6.0.6 83 Bh
11 Baja ringan canai dingin C75 268 M'
12 Baut (Srew driver) 560 bh
13 Dynabol dia 12 x 120 mm 64 bh
14 Gording Taso 4.5 83 M'
15 Talang / Jurai Canai Dingin 17 M'
16 Atap Spandek 0.8.12 15 M2
17 18