TIME SCHEDULE FOR SHUT DOWN PLANT (CLEANING E-305 A)

N/A
N/A
Yasenk Saputra

Academic year: 2023

Membagikan "TIME SCHEDULE FOR SHUT DOWN PLANT (CLEANING E-305 A)"

Copied!
3
0
0

Teks penuh

(1)

TIME SCHEDULE FOR SHUT DOWN PLANT ( CLEANING E-305 A )

No. DESCRIPTION TIME 26 27 28 29 30 31 1

1 UNINSTALL INSULATION COLD 2 OPEN LINE PIPE IN & OUT E-305 A

3 INSTALL SELANG IN & OUT FOR CIRCULATION 4 INSTALL CIRCULATION PUMP & WATER TANK 5 MAKE UP CLEAN WATER TO CIRCULATION TANK 6 RUNNING PUMP FOR CLEANING PIPE AND E-305A 7 CHECK LEAK

8 CHANGE CLEAN WATER CIRCULATION FOR E-305A 9 START CIRCULATION WITH CHEMICAL CLEANING 10 CHANGE CLEAN WATER CIRCULATION FOR E-305A 11 START CIRCULATION WITH CLEAN WATER

12 CHANGE METHANOL

13 START CIRCULATION WITH METHANOL 8 HOURS 14 UNINSTALL PIPE AND PUMP

15 INSTAL TUBING(LINE) INSTRUMENT AIR AND N2 2 HOURS 16 FLUSHING USE AIR COMPRESSOR 4 HOURS

17 FLUSHING USE N2 2 HOURS

18 INSTALL LINE PIPE IN & OUT

19 LEAK TEST & TIGHTENING ( USE NATURAL GAS ) 20 INSTALL INSULATION COLD

21 DRY OUT WITH GAS 24 HOURS

22 RUNNING PLANT

(2)

START END CLEANING E 305 DENGAN AIR

SIRKULASI CLEANING DENGAN CHEMICAL SIRKULASI E 305 DENGAN AIR BERSIH SIRKULASI E 305 DENGAN METHANOL FLUSHING DENGAN AIR COMPRESSOR FLUSHING DENGAN N2

DRY OUT

(3)

NOTE APPROVE