BAHAGIAN 5.0 : KOS SEWA LOJI DAN PERALATAN

UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT

(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

1 Backhoe sejam 55.00 55.00 62.17 53.00 - 75.00 65.00 55.00 - 80.00 60.72 53.00 - 80.00

2 Dragline

RB 19 sejam 80.00 80.00 56.63 43.75 - 80.00 78.33 50.00 - 100.00 71.65 43.75 - 100.00

RB 22 sejam 90.00 90.00 75.42 55.00 - 112.50 100.00 80.00 - 120.00 88.47 55.00 - 120.00

RB 30 sejam 100.00 100.00 97.50 70.00 - 122.50 128.33 115.00 - 150.00 108.61 70.00 - 150.00

3 Excavator

Up to 0.5 m3 sejam 85.00 85.00 70.13 63.00 - 80.00 83.00 60.00 - 100.00 79.38 60.00 -100.00

KESELURUHAN

Item Keterangan Kerja

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR

Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak

Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan, Selangor dan Johor

Kawasan Timur - Pahang, Terengganu dan Kelantan

Up to 0.5 m3 sejam 85.00 85.00 70.13 63.00 - 80.00 83.00 60.00 - 100.00 79.38 60.00 -100.00

0.5 m3to 1.0 m3 sejam 125.00 125.00 85.21 75.00 - 100.00 103.33 80.00 -140.00 104.51 75.00 - 140.00

Over 1.0 m3 sejam 175.00 175.00 105.33 82.00 - 150.00 133.33 80.00 - 180.00 137.89 80.00 - 180.00

4 Excavator houdralic operated

Up to 0.5 m3 sejam 85.00 85.00 89.08 70.00 - 122.50 91.67 80.00 - 100.00 88.58 70.00 -122.50

0.5 m3to 1.0 m3 sejam 125.00 125.00 102.92 88.00 - 125.00 110.00 90.00 - 140.00 112.64 88.00 -140.00

Over 1.0 m3 sejam 175.00 175.00 128.50 100.00 - 150.00 146.67 120.00 - 180.00 150.06 100.00 - 180.00

5 Face Showel

Model 920 sejam 85.00 85.00 75.00 60.00 - 100.00 100.00 100.00 86.67 60.00 - 100.00

Model 950 sejam 125.00 125.00 84.38 67.00 - 106.25 120.00 100.00 - 140.00 109.79 67.00 -140.00

Model 966 sejam 175.00 175.00 94.58 75.00 - 112.50 140.00 100.00 - 180.00 136.53 75.00 - 180.00

6 Back Pusher sejam 60.00 60.00 52.67 33.00 - 75.00 81.67 70.00 - 95.00 64.78 33.00 - 95.00

7 Vibrating Roller 15 tonne sejam 105.00 105.00 68.42 55.00 - 100.00 88.33 65.00 - 100.00 87.25 55.00 - 105.00

8 Compressor sejam 35.00 35.00 46.25 25.00 - 80.00 42.50 30.00 - 55.00 41.25 25.00 - 80.00

9 Bulldozer

Model D4 sejam 90.00 90.00 96.75 58.00 - 140.00 86.67 80.00 - 100.00 91.14 58.00 - 140.00

Model D6 sejam 110.00 110.00 109.58 70.00 - 150.00 94.00 80.00 - 120.00 104.53 70.00 - 150.00

Model D8 sejam 140.00 140.00 144.50 120.00 - 190.00 105.00 80.00 - 150.00 129.83 80.00-190.00

Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak

Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan, Selangor dan Johor

Kawasan Timur - Pahang, Terengganu dan Kelantan

76

(2)

BAHAGIAN 5.0 : KOS SEWA LOJI DAN PERALATAN

UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT

(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

KESELURUHAN

Item Keterangan Kerja

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR

Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak

Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan, Selangor dan Johor

Kawasan Timur - Pahang, Terengganu dan Kelantan

10 Tractor sejam - - 60.00 37.00 - 100.00 60.00 60.00 60.00 37.00 - 100.00

11 Mobile Crane

3 tonne sejam 70.00 70.00 65.83 40.00 - 100.00 80.67 70.00 - 100.00 72.17 40.00 - 100.00

16 tonne sejam 80.00 80.00 83.30 56.00 - 122.50 80.00 80.00 81.10 56.00 - 122.50

25 tonne sejam 90.00 90.00 116.67 75.00 - 150.00 85.00 80.00 - 90.00 97.22 75.00 - 150.00

35tonne sejam 120.00 120.00 158.33 85.00 - 250.00 140.00 130.00 - 150.00 139.44 85.00 - 250.00

40 tonne sejam 150.00 150.00 210.00 115.00 -315.00 170.00 160.00 - 180.00 176.67 115.00 -315.00

12 Motor Grader sejam 180.00 180.00 118.54 80.00 -165.00 116.67 80.00 - 190.00 138.40 80.00 - 190.00

13 Dumper

Up to 0.5 m3 sejam 75.00 75.00 66.00 37.50 - 100.00 80.00 80.00 73.67 37.50 - 100.00

0.5 m3to 3.5 m3 sejam 80.00 80.00 91.25 70.00 - 120.00 105.00 90.00 - 120.00 92.08 70.00 - 120.00

14 Steel Roller

8 tonne sejam 100.00 100.00 88.50 70.00 - 112.50 80.00 60.00 - 100.00 89.50 60.00 - 112.50

12 tonne sejam 120.00 120.00 100.50 80.00 - 122.50 96.67 80.00 - 110.00 105.72 80.00 - 122.50

15 Low Loader sejam 380.00 380.00 223.75 150.00 - 375.00 223.33 120.00 - 400.00 275.69 120.00 - 400.00

16 Lorry

6 tonne sejam 60.00 60.00 67.68 60.00 - 85.00 56.67 50.00 - 60.00 61.45 50.00 - 85.00

8 tonne sejam 70.00 70.00 77.68 68.75 - 100.00 76.67 60.00 - 100.00 74.78 60.00 - 100.00

10 tonne sejam 80.00 80.00 93.39 68.75 - 125.00 110.00 80.00 - 150.00 94.46 68.75 - 150.00

17 Tipper without road tax

6 tonne sejam 40.00 40.00 53.75 30.00 - 72.50 51.67 40.00 - 60.00 48.47 30.00 - 72.50

10 tonne sejam 50.00 50.00 62.50 40.00 - 85.00 60.00 50.00 - 70.00 57.50 40.00 - 85.00

18 Tipper with road tax

6 tonne sejam 50.00 50.00 70.00 60.00 - 80.00 62.50 60.00 - 65.00 60.83 50.00 - 80.00

10 tonne sejam 70.00 70.00 84.00 70.00 - 100.00 85.00 70.00 - 100.00 79.67 70.00 - 100.00

77

(3)

BAHAGIAN 5.0 : KOS SEWA LOJI DAN PERALATAN

UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT

(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

KESELURUHAN

Item Keterangan Kerja

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR

Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak

Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan, Selangor dan Johor

Kawasan Timur - Pahang, Terengganu dan Kelantan

19 Concrete Mixer

Concrete Mixer 7/5 sejam 40.00 40.00 30.92 10.00 - 62.50 40.00 30.00 - 50.00 36.97 10.00 - 62.50

Concrete Mixer 10/7 sejam 60.00 60.00 36.75 15.00 - 80.00 70.00 40.00 - 100.00 55.58 15.00 - 100.00

Concrete Mixer 14/10 sejam 90.00 90.00 44.08 17.00 - 100.00 86.67 60.00 - 100.00 73.58 17.00 - 100.00

Concrete Mixer 21/14 sejam 120.00 120.00 62.75 19.00 - 120.00 100.00 80.00 - 120.00 94.25 19.00 - 120.00

20 Water Pump

3'' Diameter sejam 35.00 35.00 29.25 15.00 - 47.50 56.67 30.00 - 100.00 40.31 15.00 - 100.00

6'' Diameter sejam 40.00 40.00 42.08 25.00 - 60.00 66.67 40.00 - 100.00 49.58 25.00 - 100.00

6'' Diameter sejam 40.00 40.00 42.08 25.00 - 60.00 66.67 40.00 - 100.00 49.58 25.00 - 100.00

8" Diameter sejam 45.00 45.00 63.25 40.00 - 100.00 83.33 50.00 - 120.00 63.86 40.00 -120.00

21 Welding and cutting set complete 0.00

Oxy - acetylene sejam 40.00 40.00 59.60 25.00 - 110.00 35.00 35.00 44.87 25.00 - 110

Electric sejam 50.00 50.00 77.00 38.00 - 120.00 45.00 45.00 57.33 38.00 - 120.00

22 Drilling machine complete with all necessary equipment

sejam

200.00 200.00 143.13 100.00 - 200.00 310.00 250.00 - 380.00 217.71 100.00 -380.00

78

Referensi

Dokumen terkait

[r]

[r]

2015 PADA BAGIAN KESRA SFTOA KABUPATEN|MUSI

Berdasarkan penjelasan di atas dapat disimpulkan bahwa yang dimaksud dengan judul di atas adalah praktik penambahan uang sewa kamar kos bagi pemilik kendaraan agar

Problematika yang timbul antara lain kenaikan harga sepihak yang dilakukan oleh pemilik rumah kos serta problematika lain, seperti kepastian hukum terhadap penghuni kamar

Event-event atau Pesta tidak terlepas dari kehidupan masyarakat yang tidak akan pernah lekang oleh waktu karena dari lahir hingga meninggalnya manusia selalu diadakan

Hubungan dimana perubahan yang terjadi pada suatu elemen mandiri (independent) akan mempengaruhi elemen yang bergantung padanya elemen yang

BAHAGIAN 3.14 : MISCELLANEOUS WORKS PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT RM RM RM RM RM RM RM RM KAWASAN TENGAH KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN BIL