Flowchart Description Action By Reference
A
1
- Provisional Sum is
included in the Contract Sum
Refer Flowchart 20.1
CAO/
Ir/Sr
2
-
3 Yes
-
5 4
Prepare cost estimates of works under Provisional Sum.
Is the estimates of works 30% more than the Provisional Sum.
Is the estimates of works 30% - 50%
Obtain approval from Division Director A
1.
2.
3.
4. CAO / Division
Director
Use
‘Borang E’
Yes
No
Is the estimates of works 50% - 100%
5. -
6
7
Obtain approval from Deputy DG
6. CAO / Deputy
DG
Use
‘Borang E’
Yes
No
Obtain approval from
7. DG CAO / DG Use
‘Borang E’
8 No
Does the work require the involvement of the Main Contractor
8 -
9 No
Quotation exercise
9. SOR
10 Yes
Is it specialist works?
10. -
11 Yes
Tender or quotation Exercise by Contractor
11. SOR
12
Issue SO instruction to main contractor, and prepare valuation of works
12. SOR/ SO/
CAO
13 Obtain approval (on costs)
from Committee
13. CAO/
Committee
Use
‘Borang F’
Appointment of sub- contractor or supplier 14.
Flowchart 20.2 – Administration of Provisional Sums
20-2 Revision 1 : April 2010
No
14
15 Adjustment to Contract
Sum
15. SOR/ SO/
CAO
Use PHK
April 2010
20-11 Revision 0 : March 2009
Step Procedures / Tasks Action By
/ Reference A Provisional Sums
Please refer to Flowchart 20.2 – Administration of Provisional Sums.
The Project Team must give due consideration to the overall works programme, and ensure the timely appointment of sub- contractor or supplier so as to avoid any delay to the works.
1 Preparation of Cost Estimates
Prepare cost estimates for the works to be carried out under each Provisional Sum.
At this stage, the scope of works shall have been sufficiently clearly identified or defined to enable the works to be priced.
The cost estimate for the works shall be prepared by an officer who has the relevant experience or expertise.
Action by: CAO
2 Approval Before Proceeding with Procurement
Approval of the Authorised Person is required if the estimated cost of works for each Provisional Sum exceeds that
Provisional Sum by more than 30%.
Use the current‘Borang E’ – Permohonan Permohonan Untuk Melaksanakan Item Di Bawah Wang Peruntukan Sementara Yang Dijangka Melebihi *30%/50% Dari Peruntukan Asal..
Action by: CAO JPS SP Bil 1/2007
3, 4 & 5 Authorised Person
x If the estimated cost of works exceeds the Provisional Sum by more than 30% up to the limit of 50%, the Authorised Person shall be the Division Director.
x If the estimated cost of works exceeds the Provisional Sum by more than 50%, the Authorised Person shall be the Director General or Deputy Director General.
April 2010
SPJPS Bil. 1/2010
20-12 Revision 0 : March 2009
Step Procedures / Tasks Action By
/ Reference 6 & 7 Procurement of Works Not Requiring Involvement of the Main
Contractor
If the works do not require the involvement of the Contractor (eg aerial photography or works carried out off-site), then proceed to invite tender/quotation directly from qualified sub- contractors or suppliers.
Comply with the DID guidelines on calling of tender/quotation.
Direct payment may be to such sub-contractor or supplier may be effected through Indent or Local Purchase Order (Inden / Pesanan Tempatan).
Action by: SOR/CAO
For information.
8 & 9 Works To Be Carried Out By Specialists – Calling of Tender/Quotation By Contractor
For specialist works exceeding RM500,000, open/selective tender shall be called by the Contractor.
For works value not exceeding RM500,000, work may be procured by the Contractor through quotation exercise.
The Contractor may tender/quote for the specialist works, if has the necessary qualifications. In such cases, the
Contractor shall not be entitled to profit and attendance on his tender/quotation.
For information
Contractor shall prepare and call tender/quotation
x The SOR/PT shall prepare specifications, Needs Statement, or design (‘design documents’), and provide the same to the Contractor.
x Design and Build. For DB contracts, the Contractor shall prepare the specifications, Needs Statement or design (‘design documents’) for the tender/quotation documents.
x The Contractor shall prepare the tender/quotation document based on the design documents, and provide the list of suitably qualified sub-contractors or suppliers (‘tenderers’) for the SOR’s approval.
x The SOR/PT must check the tender/quotation documents are in order and free from errors. The SOR shall provide a list of suitably qualified tenderers.
x To total number of tenders shall not be less than 5, selected from both the lists provided by Contractor and the SOR.
Action by:
SOR/PT
April 2010
20-13 Revision 0 : March 2009
8 & 9 (Cont’d)
Works To Be Carried Out By Specialists – Calling of Tender/Quotation By Contractor (Cont’d)
Contractor shall prepare and call tender/quotation (Cont’d) x The Contractor shall prepare sufficient number of tender
documents.
x For quotations, the tenderers must submit 2 set of documents.
Action by:
SOR/PT
Closing of Tender/Quotation
x The SOR shall prepare and issue the invitation for tenders/quotations.
x The tenders/quotations shall be closed on the fixed date and time.
x The quotations/tenders shall be opened in the presence of a committee, comprising representatives of the SOR and Contractor.
Evaluation of Tender/Quotation
x For tenders, the evaluation shall be carried out by the SOR, and the SOR shall recommend the lowest and technically complying tender.
x Design and Build. For DB contracts, the evaluation shall be carried out by the Contractor, and the Contractor shall recommend the lowest and technically complying
quotation.
x For quotations, the evaluation shall be carried out by the Contractor, and the Contractor shall recommend the lowest and technically complying quotation.
(a) The SOR shall verify the recommendation, and may further negotiate for a fair sub-contract sum or contract rates.
(b) The sub-contract sum or contract rates shall be inclusive of the Contractor’s Profit and Attendance.
20-14 Revision 0 : March 2009
Step Procedures / Tasks Action By
/ Reference 8 & 9
(Cont’d)
Works To Be Carried Out By Specialists – Calling of Tender/Quotation By Contractor (Cont’d)
Profit and Attendance (P&A)
The Profit and Attendance (P&A) shall be inclusive of Contractor’s management costs, profit and attendance.
x For Quotation, the Contractor’s P&A shall be as stated in the Contract or, if not stated then, it shall not exceed 7.5%.
x For Tender, the Contractor’s P&A shall be as stated in the Contract or, if not stated then, it shall not exceed the following rates:
Value of Works Maximum Rate for P&A
RM500,000 or less 7.5%
> RM500,000 – RM 1 million 5%
> RM 1 million - RM 5 million 4%
> RM 5 million – RM 10 million 3%
> RM 10 million <3%
x If the Contractor’s tender/quotation is accepted, the Contractor shall not be entitled to profit and attendance on his tender/quotation.
10 Works To Be Carried Out By Main Contractor
For normal category of works (‘kategori biasa’), or works which the Contractor possesses the necessary skills, the SO may issue the necessary SO Instruction for the Contractor to carry out the works.
The valuation of works shall be in accordance with the valuation rules of the Contract, i.e. based on contract rates or, in the absence of contract rates, based on fair valuation.
Action by: SOR / SO
20-15 Revision 0 : March 2009
11 Approval of Value of Works
The tender/quotation evaluation and recommended sub- contract / supply contract value shall be approved by a Variation Order Committee (‘Authorised Person’).
The sub-contract / supply contract value shall be inclusive of the Contractor’s Profit and Attendance.
Submit the application for the approval of sub-contract value / supply contract value to the Authorised Person for approval.
Use the current‘Borang F’ – Permohonan Untuk Kelulusan Harga Bagi Item Wang Peruntukan Sementara.
See Chapter 5 – Authority for Authorised Person, and limit of authority
Action by: SOR
12 Appointment of Sub-Contractor or Supplier SO’s Instruction
Issue the necessary instruction to the Contractor to effect the appointment of the sub-contractor or supplier, as approved by the VO Committee.
Direct Payment and Deed of Assignment
The DID may make direct payment to such sub-contractor or supplier through the execution by the Contractor of the ‘Deed of Assignment’ (Surat Ikatan Penyerahan Hak Faedah), in favour of the appointed sub-contractor or supplier.
For avoidance of disputes, a copy of the Deed of Assignment shall be appended to the SO’s Instruction for the appointment of sub-contractor or supplier.
The Deed of Assignment may be used if there is no overlapping of sums which is assigned under the main contract.
Form JKR 203N
For works let under Form JKR 203N, direct payment to the sub-contractor shall be effected through the procedures for Nominated Sub-Contractor or Nominated Supplier (see Section 20.3.2, above).
Action by: SOR/SO