3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS

BIL KETERANGAN KERJA UNIT

* PURATA KADAR HARGA  KERJA 

2008 2009

(RM) (RM) (RM)

A Insitu Concrete

1 Concrete Grade 10 as blinding M3 200.00 200.00 200.00

2 Concrete Grade 15 as blinding M3 187.00 200.00 194.00

3 Concrete Grade 20 as blinding M3 226.67 ‐ 227.00

B Reinforced Concrete

1 Reinforced concrete Grade 20 in bases,  footing, pile caps or ground slabs

M3 200.00 200.00 200.00

2 Reinforced concrete Grade 25 in  structure

M3 220.00 220.00 220.00

PURATA KADAR HARGA KERJA  BAGI TAHUN

3 Reinforced concrete Grade 30 in pile  caps

M3 250.00 250.00 250.00

4 Reinforced concrete Grade 30 in  structure

M3 280.00 280.00 280.00

5 Reinforced concrete Grade 35 in  structure

M3 297.00 300.00 299.00

6 Reinforced concrete Grade 40 in  structure

M3 300.00 ‐ 300.00

C Bar Reinforcement

1 Mild steel bar reinforcement; 6mm  diameter

KG 2.80 2.80 3.00

2 Mild steel bar reinforcement; 10mm  diameter

KG 2.99 2.98 3.00

* Purata Keseluruhan (rounded up) yang ditetapkan 13

(2)

3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS

BIL KETERANGAN KERJA UNIT

* PURATA KADAR HARGA  KERJA 

2008 2009

(RM) (RM) (RM)

PURATA KADAR HARGA KERJA  BAGI TAHUN

3 Mild steel bar reinforcement; 16mm  diameter

KG 3.25 3.33 3.00

4 High tensile bar reinforcement; 10mm  diameter

KG 3.33 3.30 3.00

5 High tensile bar reinforcement; 12mm  diameter

KG 3.93 3.83 4.00

6 High tensile bar reinforcement; 16mm  diameter

KG 3.94 3.15 4.00

7 High tensile bar reinforcement; 20mm  diameter

KG 3.83 3.30 4.00

D Fabric Reinforcement

1 Steel fabric reinforcement BMC A10 M2 32.22 25.00 29.00

2 Steel fabric reinforcement BMC A6 M2 13.30 13.30 13.00

3 Steel fabric reinforcement BRC A7 M2 20.00 20.00 20.00

4 Steel fabric reinforcement BRC A8 M2 19.40 19.40 20.00

E Formwork

1 Sawn formwork to sides and soffit of  beam

M2 33.50 40.00 37.00

2 Sawn formwork to sides of wall M2 32.00 32.67 32.00

3 Sawn formwork to wall, slabs or beams M2 35.22 32.50 34.00

4 Fair finish formwork to sides and soffit of  beam

M2 26.50 26.50 27.00

5 Fair finish formwork to sides of wall M2 42.80 39.50 41.00

* Purata Keseluruhan (rounded up) yang ditetapkan 14

(3)

3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS

BIL KETERANGAN KERJA UNIT

* PURATA KADAR HARGA  KERJA 

2008 2009

(RM) (RM) (RM)

PURATA KADAR HARGA KERJA  BAGI TAHUN

F Precast Concrete

1 Precast concrete beam complete with  reinforcement, formwork, joints and  finishes

M 65.00 ‐ 65.00

* Purata Keseluruhan (rounded up) yang ditetapkan 15