3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS
BIL KETERANGAN KERJA UNIT
* PURATA KADAR HARGA KERJA
2008 2009
(RM) (RM) (RM)
A Insitu Concrete
1 Concrete Grade 10 as blinding M3 200.00 200.00 200.00
2 Concrete Grade 15 as blinding M3 187.00 200.00 194.00
3 Concrete Grade 20 as blinding M3 226.67 ‐ 227.00
B Reinforced Concrete
1 Reinforced concrete Grade 20 in bases, footing, pile caps or ground slabs
M3 200.00 200.00 200.00
2 Reinforced concrete Grade 25 in structure
M3 220.00 220.00 220.00
PURATA KADAR HARGA KERJA BAGI TAHUN
3 Reinforced concrete Grade 30 in pile caps
M3 250.00 250.00 250.00
4 Reinforced concrete Grade 30 in structure
M3 280.00 280.00 280.00
5 Reinforced concrete Grade 35 in structure
M3 297.00 300.00 299.00
6 Reinforced concrete Grade 40 in structure
M3 300.00 ‐ 300.00
C Bar Reinforcement
1 Mild steel bar reinforcement; 6mm diameter
KG 2.80 2.80 3.00
2 Mild steel bar reinforcement; 10mm diameter
KG 2.99 2.98 3.00
* Purata Keseluruhan (rounded up) yang ditetapkan 13
3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS
BIL KETERANGAN KERJA UNIT
* PURATA KADAR HARGA KERJA
2008 2009
(RM) (RM) (RM)
PURATA KADAR HARGA KERJA BAGI TAHUN
3 Mild steel bar reinforcement; 16mm diameter
KG 3.25 3.33 3.00
4 High tensile bar reinforcement; 10mm diameter
KG 3.33 3.30 3.00
5 High tensile bar reinforcement; 12mm diameter
KG 3.93 3.83 4.00
6 High tensile bar reinforcement; 16mm diameter
KG 3.94 3.15 4.00
7 High tensile bar reinforcement; 20mm diameter
KG 3.83 3.30 4.00
D Fabric Reinforcement
1 Steel fabric reinforcement BMC A10 M2 32.22 25.00 29.00
2 Steel fabric reinforcement BMC A6 M2 13.30 13.30 13.00
3 Steel fabric reinforcement BRC A7 M2 20.00 20.00 20.00
4 Steel fabric reinforcement BRC A8 M2 19.40 19.40 20.00
E Formwork
1 Sawn formwork to sides and soffit of beam
M2 33.50 40.00 37.00
2 Sawn formwork to sides of wall M2 32.00 32.67 32.00
3 Sawn formwork to wall, slabs or beams M2 35.22 32.50 34.00
4 Fair finish formwork to sides and soffit of beam
M2 26.50 26.50 27.00
5 Fair finish formwork to sides of wall M2 42.80 39.50 41.00
* Purata Keseluruhan (rounded up) yang ditetapkan 14
3.0 KOS ITEM‐ITEM KERJA 3.4 CONCRETE WORKS
BIL KETERANGAN KERJA UNIT
* PURATA KADAR HARGA KERJA
2008 2009
(RM) (RM) (RM)
PURATA KADAR HARGA KERJA BAGI TAHUN
F Precast Concrete
1 Precast concrete beam complete with reinforcement, formwork, joints and finishes
M 65.00 ‐ 65.00
* Purata Keseluruhan (rounded up) yang ditetapkan 15