SULIT EPM321 - 1 -

…2/- SULIT First Semester Examination

2021/2022 Academic Session February/March 2022

EPM321 – Manufacturing System

Duration : 3 hours

Please check that this examination paper consists of SEVEN [7] printed pages before you begin the examination.

INSTRUCTIONS : Answer ALL FOUR [4] questions.

In the event of any discrepancies, the English version shall be used.

(2)

SULIT EPM321 - 2 -

…3/- SULIT 1. Figure 1 depicts the factory plan of Atom Sdn Bhd producing two types of

products, ABS and ARS. Raw materials arrived from supplier delivery have to go through the sequence of washing, machining, deburring and assembly before shipping. Please answer the following questions.

[a] Identify and locate TWO(2) types of production layout present in the factory.

(2 marks) [b] Identify TWO (2) advantages for each production layout stated in 1[a].

(2 marks) [c] Give TWO (2) reasons why the two layouts coexist in the production area

and explain ONE (1) resulted management complication.

(3 marks) [d] A worker is responsible for tending machines in the machining process.

The service time per machine is 200 sec and the time to walk between machines is 15 sec. The machine automatic cycle time is 25 minute. The worker's hourly wage rate is RM10 and the hourly operating cost rate for each machine is RM30. Calculate the number of machines that should be tended by the worker to result in the minimum cost per unit of product.

(3)

SULIT EPM321 - 3 -

…4/- SULIT Figure 1

(3 marks) 2. A product can be manufactured by going through six processes as depicted in Figure 2. The standard batch size is 100 units. Based on the information given in the figure, answer the following questions:

[a] Determine the average production time and the production rate of Process 3.

(1 marks) [b] Identify the bottleneck of the production system.

(1 marks) [c] Determine FIVE (5) considerations need to make for Process 3 to run

unattended and in mixed model mode.

(3 marks/markah)

(4)

SULIT EPM321 - 4 -

…5/- SULIT [d] The production is running five days per week, two shifts per day and 8 hours per shift. The production has the availability of 90%, utilization of 80% and defect rate of 0.12%.

(i) Calculate the weekly capacity.

(ii) Estimate the level of work-in-process (WIP).

(iii) A customer places an order of 1,000 units on Monday. Determine how soon the order can be fulfilled.

Process 1

Tc = 11 sec Tsu = 10 min

Tc = 8 sec Tsu = 15 min

Tc = 11 sec Tsu = 5 min

Tc = 16 sec Tsu = 1 min Process 2

Process 3

Process 4

Process 5

Process 6

Tc = 10 sec Tsu = 18 min

Tc = 13 sec Tsu = 5 min

Figure 2

(5 marks) 3.

4.

- oooOooo -

Referensi

Dokumen terkait

For questions marked “ ”, full marks will be given for a correct answer placed in the appropriate box in the answer booklet?. Marks may be given for

For questions marked “ ”, full marks will be given for a correct answer placed in the appropriate box in the answer booklet.. If an incorrect answer is given, marks may be given

The scores of each problem are allocated in the following ways: 2 marks will be given for a correct answer, 1 mark will be deducted from a wrong answer and 0 mark will be given for

SEPTEMBER 2014 CONFIDENTIAL FIB36403 PRODUCTION & OPERATION MANAGEMENT 2 SECTION B Total: 60 marks INSTRUCTION: Answer only THREE questions.. Please use the answer booklet

c Answer the following questions: i Determine the binary numbers for the following hexadecimal numbers:  10A416  CF8EI6 6 marks ii Design the logic circuit that has three inputs

Part-B Section I 15 Marks Attempt any One of the following questions in the space provided below.. The answer must not exceed 500

Page I of2 ENTRANCE EXAMINATION - 2OL6 Maximum Marks: 75 GENERAT INSTRUCTIONS: A Please read the instractions for each section carefully, Duration:2 hours B Pleasereturnthe '

The cable system shown in Figure 4 carries a uniformly distributed load of 15 kN/m between the supports and two point loads of 10 kN and 20 kN at 10 m away from both supports A and B,