1
Brief analysis of variable renewable energy contribution during loadshedding (Q1-2019)
CSIR Energy Centre
CSIR Energy Centre Pretoria. 15 April 2019
v1.1
JARRAD WRIGHT
JOANNE CALITZ
2
Key takeaways
A constrained power system meant South Africa had to loadshed again in Q1-2019
• The RSA power system again became constrained in Q1-2019 with Eskom needing to loadshed (Stage 4 at times)
• Causes of loadshedding have been cited as high unplanned plant failures on the thermal coal fleet, the loss of Cahora Bassa import from Mozambique followed by intensive use of diesel (at OCGTs) and water (at pumped storage schemes) which eventually depleted
1• This has been the most intensive loadshedding experienced in RSA with 595 GWh of load shed just in March 2019 of the total 769 GWh in Q1-2019 (there was 1325 GWh of loadshedding throughout 2015)
The utility-scale VRE fleet notably contributed to limit the extent of loadshedding in Q1-2019
• The utility-scale VRE fleet
2contributed 2 975 GWh (5.3%) to the RSA power system in Q1-2019 with monthly contributions ranging from 4.9-6.0%, weekly contributions from 4.1-7.0% and daily contributions from 2.9-7.7%
• During loadshedding periods, the utility-scale VRE fleet contributed 357 GWh of the total 2975 GWh from VRE during Q1-2019 i.e. loadshedding could have increased from 769 GWh to 1126 GWh (a 46% increase)
• Instantaneous contributions from the VRE fleet during loadshedding periods was up to 2.3 GW i.e. without the VRE fleet, loadshedding stage 5 & 6 could have been envoked
1Department of Public Enterprises, UPDATE : ESKOM ELECTRICITY SUPPLY, 03 April 2019;
21.5 GW solar PV, 2.0 GW wind and 0.5 GW CSP (CSP is marginally dispatchable considering coupling with thermal storage) RSA = Republic of South Africa; VRE = variable renewable energy
3
100 600
200 300 400
250
0 450
50 550
150 350 500
Apr- 18 21
6
6
Jul- 18 9 3
GWh of load shedding
306
164
122
5 42
Jan- 15
Feb- 19 200
Nov- 15 71
Feb- 15
36 36
Mar- 15
60
Nov- 18 122
156
77
Aug- 15 56 May-
15
Jul- 15
40 260
Jun- 15
84 19
Oct- 15
Dec- 15
Jan- 18
Aug- 18
384
Feb- 18
Mar- 18
May- 18
Sep- 18
15 Oct-
18 24
Jun- 18
106 32 Dec-
18 Jan-
19 36
54 190
Sep- 15
Mar- 19 63
283
Apr- 15
233 178
49 3
43 138
174 595
184
27 12
63
Stage 4 Stage 3 Stage 2 Stage 1
First 3 months of 2019 – most intensive loadshedding in March with 595 GWh of 769 GWh in 2019... 1325 GWh throughout 2015
Year 2015 2016 2017 2018 2019
Energy
(GWh)1325 - - 192 769 Duration
(hours)858 - - 127 272
Notes: Load shedding assumed to have taken place for the full hours in which it was implemented. Practically, load shedding (and the Stage) may occassionally change/end during a particular hour; Total GWh calculated assuming Stage 1 = 1 000 MW, Stage 2 = 2 000 MW, Stage 3 = 3 000 MW, Stage 4 = 4 000 MW Sources: Eskom Twitter account; Eskom se Push (mobile app); CSIR analysis
4
Loadshedding in 2015 predominantly during high demand periods (day and evening peaks)… most recently in 2019 this has been day/night
Hour of the day -->
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Total
Jan 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Feb 0 0 0 0 0 0 0 0 8 10 10 10 10 14 14 14 14 14 14 14 14 14 0 0 174
Mar 13 13 13 13 13 13 13 13 19 30 31 32 33 33 33 34 34 34 34 34 34 34 29 13 595
No load shedding No load shedding 2015
2016 2017
2019 2018
Notes: Load shedding assumed to have taken place for the full hours in which it was implemented. Practically, load shedding (and the Stage) may occassionally change/end during a particular hour; Total GWh calculated assuming Stage 1 = 1 000 MW, Stage 2 = 2 000 MW, Stage 3 = 3 000 MW, Stage 4 = 4 000 MW Sources: Eskom Twitter account; Eskom se Push (mobile app); CSIR analysis
No
Loadshedding
Intensive loadshedding Loadshedding intensity (per year)
5
100 450 100
BW 2 BW 4
BW 1 BW 3
100
BW 3.5 BW 4
Expedited
150 50 200 200 450
649 559
676 650
686
BW 2 BW 3 BW 3.5
BW 1 BW 4 BW 4
Expedited 787
1 362
650
415 591
398
BW 3.5 BW 3
BW 1 BW 2 BW 4 BW 4
Expedited 627
417 435
813
591
Supply Sources
Notes: RSA = Republic of South Africa. Wind excludes Eskom’s Sere wind farm (100 MW). BW = Bid Window. PPA = Power Purchase Agreement. BW 4 includes BW 4 additional.
Sources: Eskom; DoE IPP Office
Procured and operational capacity under RSA’s RE IPP Procurement Programme (REIPPPP) with only 100 MW of CSP added in Q1-2019
2078 MW 1479 MW
Capacity operational
(1 January 2019)
400 MW 2078 MW 1479 MW 500 MW
435
415 398
BW 4 BW 3
BW 2
BW 1 BW 3.5 BW 4
Expedited 627
417
813
591
649 559 787
676 650
686
BW 4 Expedited BW 2
BW 1 BW 3 BW 3.5
650 1 362
BW 4
200 100 450
100
BW 2 50
BW 4
BW 1 BW 3 BW 3.5 BW 4
Expedited
150 200 200 450
Capacity operational
(31 March 2019)
Solar PV procured, PPAs not signed yet Solar PV procured, PPAs signed
Solar PV operational
Wind procured, PPAs not signed yet
Wind operational Wind procured, PPAs signed
CSP procured, PPAs not signed yet CSP procured, PPAs signed CSP operational
6
257 560
1 075
300 400 500
210
960
965
1 460
2 078 2 078 2 078
1 479
1 479 1 479 1 479
467
2018 3 857
2013 2015
3 139
2014 2016
200
2020 2 040
2017
3 957 4 057
2019 (Q1) 1 520
+1 053
+520
+1 094
+718 +100 +100
Wind Solar PV CSP Supply Sources
Notes: RSA = Republic of South Africa. Solar PV capacity = capacity at point of common coupling. Wind includes Eskom’s Sere wind farm (100 MW).
Sources: Eskom; DoE IPP Office
From 1 November 2013 to 31 March 2019, 2 078 MW of wind, 1 479 MW of large-scale solar PV and 500 MW of CSP became operational in RSA
Capacity operational
[MW]
7
Notes: Wind includes Eskom’s Sere wind farm (100 MW). CSP energy measured from date when more than two CSP plant were commissioned.
Wind and solar PV energy excludes curtailment and is thus lower than actual wind and solar PV generation Sources: Eskom; DoE IPP Office
In Q1-2019 - 3.0 TWh of wind, solar PV and CSP energy was produced in RSA with estimates of over 12 TWh for 2019 expected
Supply Sources Annual energy produced
[TWh] 12.4
4.7
5.0
0.05
2013
6.5
1.1
2014
1.1
2.2
2.5 1.6
2015
2.6
3.7 0.01
9.0
2.2
0.5
2016
3.3
0.7
2017
3.3
6.9
1.0
9.4
2018
0.9 0.4
2019 2020
0.1
10.8
Wind
Estimate for rest of 2019
Solar PV
CSP
8
176 121 137
649
485 503
337
273 294
0 100 200 300 400 500 600 700 800 900 1 000 1 100 1 200 1 300 1 400
Monthly electricity production in GWh
1 161
880 933
5.0%
6.0%
4.9%
Monthly electricity production of SA’s wind, solar PV and CSP fleet ranging from 4.9-6.0% (similar to previous year)
Solar PV Wind CSP
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Supply Sources
Note: Wind generation includes Eskom’s 100 MW Sere wind farm. CSP energy only measured from date when more than two CSP plant were commissioned.
Wind and solar PV energy excludes curtailment and is thus lower than actual wind and solar PV generation.
Sources: Eskom; CSIR Energy Centre analysis
Capacity operational (1 Jan-31 Mar)
2078 MW 1479 MW
500 MW
% of total system load
9
Monthly electricity production from wind, solar PV, CSP, residual load and loadshedding impact in Q1-2019
0 18
2 10 20
4 6 8 12 14 16 22
19.3 Monthly electricity
production in TWh
18.2 16.8 18.2 17.9
19.8
Loadshedding Solar PV
Residual Load CSP Wind
Notes: Pumping load excluded. Wind generation includes Eskom’s 100 MW Sere wind farm.
Sources: Eskom; CSIR Energy Centre analysis
Supply Sources
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Capacity operational (1 Jan-31 Mar)
2078 MW 1479 MW
500 MW
10
0 50 100 150 200 250 300 350 400 450
13 22 37 40 43
Electricity production in GWh/week
1 4 7 10 16 19 25 28 31 34 46 49 52
5.9%
5.7%
6.9%
6.1%
4.5%
5.6%
4.5%
5.2%4.9%
5.8%
4.8%
4.1%
Weekly contribution from utility-scale RE in first 3 months of 2019 ranges from 4.1-6.9% of total system demand
Note: Design as per Fraunhofer ISE.
Sources: Eskom; CSIR Energy Centre analysis
% of total system load
CSP Solar PV Wind Supply Sources 2078 MW 1479 MW Capacity operational
500 MW
11
Weekly electricity production wind, solar PV, CSP, residual load and loadshedding in Q1-2019
0 500 1 000 1 500 2 000 2 500 3 000 3 500 4 000 4 500 5 000
1 40
Electricity production in GWh/week
4 7 10 13 16 19 22 25 28 31 34 37 43 46 49 52
Supply Sources
Note: Week 1 only 6 of 7 days; Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
Loadshedding
Wind CSP Solar PV Residual Load 2078 MW 1479 MW Capacity operational
500 MW
12
For Jan-Mar 2019, electricity production from wind, solar PV and CSP was above 25 GWh/d 90% of the time with maximum of 48 GWh/d
0 5 10 15 20 25 30 35 40 45 50
Electricity production in GWh/day
Supply Sources
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Note: Design as per Fraunhofer ISE.Wind includes Eskom‘s Sere wind plant.
Sources: Eskom; CSIR Energy Centre analysis
Wind Solar PV CSP 2078 MW 1479 MW Capacity operational (end of month)
400 MW
13
Daily electricity production of between 543-666 GWh in Jan 2019 with VRE contributing 5-8%
0 100 200 300 400 500 600 700 800
21 GWh/day
7
3 4 15 17
1 2 5 6 8 9 10 11 12 13 14 16 18 19 20 22 23 24 25 26 27 28 29 30 31
CSP Solar PV Wind Residual Load
Loadshedding Supply
Sources 2078 MW 1479 MW Capacity operational (end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere.
Sources: Eskom; CSIR Energy Centre analysis
400 MW
14
Daily electricity production of between 593-672 GWh/d in Feb 2019, VRE supplied 3-6% of system demand and up to 7% of load was shed
0 100 200 300 400 500 600 700 800
2 30
GWh/day
24 28
15 13
1 3 4 5 6 7 8 9 10 11 12 14 16 17 18 19 20 21 22 23 25 26 27 29 31
Residual Load
Loadshedding Solar PV CSP Wind Supply Sources Capacity operational (end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW
500 MW
15
Daily electricity production of 538-658 GWh/d in Mar 2019, VRE contributed 3-7% everyday and up to 14% of load was shed
0 100 200 300 400 500 600 700 800
28 31
27 GWh/day
2
1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 29 30
Solar PV CSP Wind
Loadshedding
Residual Load Supply Sources Capacity operational (end of month)
Note: Design as per Fraunhofer ISE. Daily production excludes pumping load. Wind includes Sere.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW
500 MW
16 0.0 2.0
0.5 1.0 1.5 2.5 3.0 3.5 4.0
GW
CSP Solar PV Wind
Hourly VRE production in Jan 2019 shows periodic solar PV and CSP;
wind varies but contributes notably during evening peaks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Supply Sources
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
400 MW
17 2.0 4.0
0.0 1.0 2.5
0.5 1.5 3.0 3.5
GW
Wind Solar PV CSP
Hourly VRE electricity production in Feb 2019 shows how loadshedding could have increased to Stage 5-6 without VRE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Supply Sources
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
500 MW
3 2 1
4
Loadshedding stage
18 0.0 2.0 1.5 1.0 0.5 2.5 3.0 3.5 4.0
GW
Solar PV Wind CSP
Hourly VRE electricity production in Mar 2019 shows again how loadshedding could have increased to Stage 5-6 without VRE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Supply Sources
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
500 MW
4 3 2 1
Loadshedding stage
19 0 5 15 20
10 25 30 35 40
GW
Supply Sources
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Hourly electricity production in Jan 2019 highlighting role of VRE fleet
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
400 MW
Residual Load
Loadshedding
CSP Solar PV Wind
20 0 5 30
15 10 20 25 35 40
GW
Loadshedding
Residual Load Solar PV Wind CSP
Hourly electricity production in Feb 2019 with 5 days of loadshedding
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Supply Sources
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
500 MW 5 days of
loadshedding
21 15
0 5 10 20 40
25 30 35
GW
Loadshedding Wind
CSP Solar PV
Residual Load
Hourly electricity production in Mar 2019 with 10 days of loadshedding
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Supply Sources
Note: Design as per Fraunhofer ISE. Pumping load excluded.
Sources: Eskom; CSIR Energy Centre analysis
2078 MW 1479 MW Capacity operational (end of month)
500 MW 10 days of
loadshedding
22
0 20 30
2 14 16
4 6 28
8 12 26 22 24 32 34
18 36
10
Power in GW
Loadshedding Wind
PV CSP
Residual (Eskom)
Sources: Eskom; CSIR Energy Centre analysis
Significant contribution from VRE during loadshedding in Feb 2019 – 103 GWh and a maximum inst. contribution of 2.0 GW
2078 MW 1479 MW Capacity operational (end of month)
500 MW
System demand
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Week of 11-17 February 2019
Supply Sources
23
10 14 18 22 26 34
0 28
20 32 30 36
16
2 4 6 8 12 24
Power in GW
Loadshedding PV
Residual (Eskom) Wind
CSP
Supply Sources
Sources: Eskom; CSIR Energy Centre analysis
Similarly, VRE provided valuable capacity during loadshedding in March 2019 – 254 GWh and a maximum inst. contribution of 2.3 GW
System demand
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
Week of 18-24 March 2019
2078 MW 1479 MW Capacity operational (end of month)
500 MW
24
LDC = Load Duration Curve; 1When demand is >90% of peak demand;
VRE = variable renewable energy (solar PV, wind and CSP) Sources: Eskom; CSIR Energy Centre analysis
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200
10
0 2 18 16 22 20 34
14 12 26
8 38
6 30
4 32
24 28 36 40
Hours of the year (sorted) Power in GW
-1.1 GW
System demand (before loadshedding)
Residual demand
(after VRE & loadshedding) System demand
(after loadshedding)
VRE reduced peak by 1.1 GW & high demand hours notably;
loadshedding could have increased by as much as 46% without VRE
LDC (1 Jan – 31 Mar 2019)
With VRE fleet, peak demand was reduced by 1.1 GW.
1
But more importantly, high demand hours1 were reduced from 730 hrs to 144 hrs.
2
2
1
2
357 GWh of 2975 GWh from VRE was during loadshedding between Jan-Mar 2019.
Without VRE, loadshedding would have been more severe, it could have increased by 46% from 769 GWh to 1126 GWh.
25