CR 1034 26 03 2020 – MLM - 2020 2021 SDBIP
FOREWORD BY HIS WORSHIP THE MAYOR
Matatiele Local Municipality’s 2020/2021 Service Delivery and Budget Implementation Plan (SDBIP) marks the contract between the Matatiele Local municipality and the community of Matatiele. This contract (SDBIP) helps facilitate the process for holding management accountable for its performance. The SDBIP is a management, implementation and monitoring tool that will assist the mayor, councilors, municipal manager, senior managers and community.
The SDBIP will enable the Mayor and Executive Committee to monitor and evaluate the performance of the Municipal Manager, enable the Municipal Manager to monitor the performance of senior managers, and for the community to monitor the performance of the municipality. This enables the mayor and the municipal manager to be pro-active and take remedial steps in the event of poor performance in order to improve performance. This SDBIP aims to ensure that all managers are problem-solvers, who routinely look out for unanticipated risks and problems and resolve them as soon as possible.
The SDBIP should therefore determine (and be consistent with) the performance agreements between the mayor and the municipal manager; and the municipal manager and managers reporting directly to the Municipal Manager and Middle Managers at the start of every financial year and approved by the mayor. A properly formulated SDBIP will ensure that appropriate information is circulated internally and externally for purposes of monitoring the execution of the budget, performance of both the senior and middle management and achievement of the strategic objectives set by council; including the outputs and deadlines for which they will be held responsible. In-year monitoring designed to identify major problems from an early stage and ensuring that the Mayor and Municipal Manager are taking corrective steps when any unanticipated problems arise.
The SDBIP serves a critical role to focus both the administration and council on outputs by providing clarity of service delivery expectations, expenditure and revenue requirements, service delivery targets and performance indicators. It is the output and goals made public in the SDBIP that will be used to measure performance on a quarterly basis during the financial year. Note that such in-year monitoring meant to be a light form of monitoring. The council should reserve its oversight role over performance at the end of the financial year, when the mayor tables the annual report of the municipality.
Municipal managers are encouraged to develop the SDBIP concept further so that it is meaningful and useful to managers. Many municipal managers will have some form of management plan and the challenge is to develop such management plans as a SDBIP.
Whilst the budget is approved yearly, service delivery and budget targets (revenue and expenditure per vote), it is imperative that in-year mechanisms are able to measure performance and progress on a continuous basis. Hence, the end-of-year targets are based on quarterly and monthly targets, and the municipal manager must ensure that the budget is built around quarterly and monthly information. Being a start-of-year planning and target tool, the SDBIP gives meaning to both in-year reporting in terms of section 71 (monthly reporting), section 72 (mid-year report) and Section 121 (end-of-year annual reports).
Therefore, the Mayor Approves the Draft SDBIP for 2020/2021 in terms of Section 53 (1) (c) (ii) of Local Government:
Municipal Finance Management Act 56 of 2003
CLLR. M.M. MBEDLA HIS WORSHIP THE MAYOR
26 March 2020
1.1 Vision & Mission
5 year VISION: Where Nature, Agriculture and Tourism are Investments of Choice. (5 year vision)
LONG TERM VISION: Sustainable Livelihoods by 2030 and beyond
MISSION STATEMENT: (1) To improve infrastructure and enhance investment potential, (2) To create an awareness on nature conservation, (3) To promote and improve agriculture, (4) To promote and grow local tourism (5) To promote sustainable Small, Medium, and micro Enterprises, (6) To advance proper spatial planning (7) To stimulate sustainable rural communities.
1.2 Legislative Mandates
The Municipal Finance Management Act (MFMA) of 2003 requires that municipalities prepare a Service Delivery and Budget Implementation Plan (SDBIP) as a strategic financial management tool to ensure that budgetary decisions that are adopted by municipalities for the financial year are aligned with their Integrated Development Plan.
Section 69(3) (a) of the Municipal Finance Management Act, Act 56 of 2003 (MFMA) states that the Accounting Officer to submit a draft Service Delivery and Budget Implementation Plan (SDBIP) to the Mayor:
Section 1 of the MFMA defines the SDBIP as:
a detailed plan approved by the mayor of a municipality in terms of section 53(1)(c)(ii) for implementing the municipality's delivery of services and the execution of its annual budget to include:
(a) Projections for each month of
(i) Revenue to be collected by source; and (ii) Operational and capital expenditure by vote
(b) Service Delivery targets and performance indicators for each quarter; and
(c) Any other matters that may be prescribed, and includes any revisions of such plan by the mayor in terms of section 54 (1)(c).
This Plan is therefore largely a one year detailed implementation plan that gives effect to the IDP and Budget of the Municipality. It is a contract between the administration, Council and community expressing the goals and objectives set by Council as quantifiable outcomes that can be implemented by the administration over the next twelve months.
This provides the basis of measuring the performance in service delivery against end year targets and implementing budget.
Matatiele is one of four local municipalities within the Alfred Nzo District, and is located on the northern part of the Eastern Cape. Matatiele has three towns, namely:
Matatiele, Cedarville and Maluti. Matatiele consists of the following 26 wards:
Population of Matatiele per Ward and the Number of Households:
Wards Population size per ward Number of households in a ward
1 6434 1330
2 13574 3069
3 7811 1880
4 8324 2006
5 8474 2037
6 7399 1968
7 7611 1684
8 9747 1207
9 6605 1659
10 8864 2155
11 11421 2815
12 6626 1643
13 8241 1672
14 6586 1678
15 6715 1855
16 6405 1652
17 8509 2200
18 7253 1921
19 4124 1378
20 11816 3548
21 7142 1625
22 6288 1752
23 6344 1553
24 5570 1 378
25 7067 1 659
26 8894 2 202
203844 49526
3. MONTHLY PROJECTIONS OF REVENUE TO BE COLLECTED BY SOURCE
EC441 Matatiele - Supporting Table SA25 Budgeted monthly revenue and
expenditure
Description R
e f
Budget Year 2020/21 Medium Term Revenue
and Expenditure Framework
R thousand July Aug
ust Sept. Octo
ber Nov emb er
Dece mbe r
Janu
ary Febr
uary Marc
h April May June
Budg et Year 2020/
21 Budg
et Year
+1 2021/
22 Budg
et Year
+2 2022/
23 Revenue By
Source
Property
rates
4 016
4 016
4 016
4 016
4 016
4 016
4 016
4 016
4 016
4 016
4 016
4 016
48 190
50 600
53 129 Service
charges - electricity
revenue
4 441
4 441
4 441
4 441
4 441
4 441
4 441
4 441
4 441
4 441
4 441
4 441
53 291
59 871
63 055 Service
charges - water
revenue
–
–
–
–
–
–
–
–
–
–
–
–
–
–
– Service
charges - sanitation
revenue
–
–
–
–
–
–
–
–
–
–
–
–
–
–
– Service
charges -
refuse revenue
1 294
1 294
1 294
1 294
1 294
1 294
1 294
1 294
1 294
1 294
1 294
1 294
15 526
16 302
17 117 Rental of
facilities and
equipment
42
42
42
42
42
42
42
42
42
42
42
42
500
525
551 Interest
earned - external
investments
1 221
1 221
1 221
1 221
1 221
1 221
1 221
1 221
1 221
1 221
1 221
1 221
14 650
15 383
16 152 Interest
earned - outstanding
debtors
983
983
983
983
983
983
983
983
983
983
983
983
11 799
12 389
13 008 Dividends
received
–
–
–
–
–
–
–
–
–
–
–
–
–
–
– Fines,
penalties and
forfeits
174
174
174
174
174
174
174
174
174
174
174
174
2 094
2 198
2 308 Licences and
permits
377
377
377
377
377
377
377
377
377
377
377
377
4 525
4 751
4 988 Agency
services
–
–
–
–
–
–
–
–
–
–
–
–
–
–
– Transfers
and subsidies-
Operational
21 351
21 351
21 351
21 351
21 351
21 351
21 351
21 351
21 351
21 351
21 351
21 351
256 212
267 930
281 432
Transfers and subsidies-
Capital
8 461
8 461
8 461
8 461
8 461
8 461
8 461
8 461
8 461
8 461
8 461
163 146
256 212
267 930
281 432 Other
revenue
134
134
134
134
134
134
134
134
134
134
134
134
1 608
1 688
1 773
Gains
–
–
–
–
–
–
–
–
–
–
–
–
–
–
–
Total Revenue 42 493
42 493
42 493
42 493
42 493
42 493
42 493
42 493
42 493
42 493
42 493
197 178
664 606
699 567
734 947
4. QUARTERLY PROJECTIONS OF SERVICE DELIVERY TARGETS AND PERFORMANCE INDICATORS FOR EACH VOTE
CONSTRUCTION LEGEND
GRAVEL ROADS SURFACED
ROADS
BUILDING
CONSTRUCTION
SPORTSFIEL
D BRIDGES
Stage 1 (10%) Stage 1 (10%) Stage 1 (10%) Stage 1 (10%)
Stage 1 Stage 1 (10%)
· Contractor establishment
· Contractor establishment
· Contractor establishment.
· Contracto r Establishment
· Cont ractor Establish ment
The contractor will have to
comply with all
requirements in line with the Contract document (acceptance letter, insurance, surety, programme of works, letter of good standing, occupational health and safety file).
The contractor will have to comply
with all
requirements in line with the Contract
document
(acceptance letter, insurance, surety, programme of works, letter of good standing, occupational health and safety file).
The contractor will have to comply with all requirements in line with the construction laws and MLM policies before the date of establishment.
The contractor will have to comply with all requirements in line with the Contract
document (acceptance letter, insurance, surety,
programme of works, letter of good standing, occupational health and safety file).
The contractor will have to comply with all requiremen ts in line with the Contract document (acceptanc e letter, insurance, surety, programm e of works, letter of good standing, occupation al health and safety file).
. .
The MLM will hand over the site to the appointed bidder after the contractor has been appointed.
The MLM will hand over the site to the appointed bidder after the contractor has been Appointed.
The MLM handover the site to the appointed bidder after the contractor has been presented to the community affected.
The MLM will hand over the site to the appointed bidder
after the
contractor has been Appointed.
The MLM will hand over the site to the appointed bidder after the
contractor has been Appointed Stage 2 (20%) Stage 2 (20%) Stage 2 (40%) Stage 2 (50%) Stage 2
(40%) Clear and grub · Mass
Earthworks · Site layout: · Earthwor ks
· Base foundation slab
· Roadbed preparation
The contractor will clear the existing layer of material and spoil at an agreed spoil site.
The contractor will be issued with construction
drawings to establish a layout and indicate the pegs on each construction item.
The contractor will clear the existing layer of material and spoil at an agreed spoil site.
The contractor will construct base foundation slab according to the design drawings and bending schedules issued by the
Engineer
The contractor will clear the existing topsoil layer of material and spoil at an agreed spoil site.
The contractor will excavate to the agreed levels as per the Engineer’s designs and spoil or stock pile as per the
Instructions from Engineer.
· Earthworks:
The contractor will excavate to the agreed levels as per the Engineer’s designs and spoil or stock pile as per the Instructions from Engineer.
The contractor will excavate to the agreed levels and spoil or stock pile as per the Instructions from Engineer
The contractor will hire tools or plant to move soil in line with the engineer’s instruction and contract the commercial material (Sabonga) to be compacted and tested for approval.
Stage 3 (40%) Stage 3 (40%) Stage 3 (50%) Stage 3 (65%) Stage 3 (60%)
Installation of pipe culverts
· Installation of pipe culverts
· Foundation
for excavations: · Fencing
· Colu mns / pre- cast culverts
Excavation of trenches to the required width and depth.
Excavation of trenches to the required width and depth.
After the compaction soil has been approved, the contractor is to dig trenches in line with the foundation plan provided by the engineer. The engineer will do site visit to inspect the foundations and the levels including compaction within the foundation bases.
Installation of fence according to the design drawings.
· Top slabs
Prepare bedding from in-situ material or imported material and compact.
Prepare bedding from in-situ material or imported material and compact.
· Concrete casting:
The contractor will construct top slab according to the design drawings and bending schedules issued by the
Engineer
Lay the pipes and backfill in layers with selected backfill or imported material.
Lay the pipes and backfill in layers with selected backfill or imported material.
After the test results
approved by
engineer, the contractor will install the reinforcement in line with the engineer’s drawings and cast concrete that has MPa indicated by engineer.
Foundation walls will be done by contractor when engineer has approved the foundations.
The concrete slabs will be casted only when the engineer has approved foundation walls and the compaction of soil material test results approved by engineer. The contractor to issue pests control certificate on contacted soil
Stage 4 (60%) Stage 4 (60%) Stage 4 (60%) Stage 4 (85%) Stage 4 (80%)
· Tipping of gravel · Building of walls
· Wing walls
· Processing of gravel · Pavement Layers
The building walls to be done in line with the engineers drawings and specification
including material finishing. The engineer will do ongoing inspections during construction
and issue
instructions.
· Building and concrete works
The contractor will construct the wing walls according to the design drawings and bending schedules issued by the
Engineer
The Contractor will import gravel material from borrow pit for layer works and compact each layer as per the design specification.
The Contractor will import gravel material from borrow pit or commercial source for layer works and compact each layer (ie G5,G2)as per the design specification.
· Roof installation
Construction of ablution
facilities and change rooms.
· Prote ction Works
· Sealants
The engineer will issue instruction for roof to be installed after the approval of walls.
The installation of gabion structure to protect the unstable banks as per the design
Stabilization of sub base layer with
cement or
lime/polymer.
The engineer will issue roof design for the contractor to buy the material and including engineer designed roof structure and before delivery the manufacture is to visit the site for re- measuring and to get the correct measurements.
· Road signs
The contractor will install the traffic control signs as indicated on the road layout drawings.
Stage 5 (80%) Stage 5 (80%) Stage 5 (80%)
· Kerbing · Windows
· Protection Works
Once the Sub base layer has been completed,
Concrete Kerbing will be installed with concrete channels or as per the design.
Window schedules will be issued to the contractor. That information has specifications.
· Installation of road
signs · Plastering
· Asphalt
The specifications will be issued to the contractor and has to
follow the
specification and the finishing methods.
The contractor will construct the headwalls/inlets and outlet structures or catch pits.
· Landscaping
The contractor will install the lay the hot mix Asphalt.
The drawing will be issued for the contractor to follow and comply.
The installation of gabion structure to protect the unstable banks as per the design.
· Protection Works
The contractor will construct the headwalls/inlets and outlet structures or catch pits.
The contractor will install the traffic control signs as indicated on the road layout drawings
The installation of gabion structure to protect the
unstable banks as per the design.
Stage 6 (95%) Stage 6 (90%) Stage 6 (90%) Stage 6 (95%) Stage 6 (95%)
· Attending to snaglist · Road signs · Finishes
· Pract ical Completio n
certificate The specifications
will be issued to the contractor and has to
follow the
specification and the finishing methods (painting, floor covering, ceiling, lights, plumbing and furnisher)
· Practical completion certificate
A list of outstanding items that a contractor must attend before each completion stage is reached.
The contractor will install the traffic control signs as indicated on the road layout drawings.
When the road is ready for
operations, the Contractor will indicate to the Engineer and a Snag list will be compiled by the Engineer/PSC.
When the road is ready for operations, the
Contractor will
indicate to the
Engineer and a Snag list will be compiled by the Engineer/P SC.
· Landscaping
The specifications will be issued to the contractor and has to
follow the
specification and methods (paving, tree planting and fencing).
· Practical Completion certificate
· Road markings
When the road is ready for operations, the Contractor will indicate to the Engineer and a Snag list will be
compiled by the
Engineer/PSC.
Marking of the road (solid and broken lines)
Upon completion of the snag list, the contractor will hand over the site to the Community
Stage7 (95%)
· Snag list:
A list of outstanding items that a contractor must attend before each completion stage is reached.
· Practical Completion certificate
When the road is
ready for
operations, the Contractor will indicate to the Engineer and a Snag list will be compiled by the Engineer/PSC.
Upon completion of the snag list, the contractor will hand over the site to the Community
Stage 7(100 %) Stage7 (95%) Stage 7 (95%) Stage 7 (100%) Stage 7 (100%)
· Final Completion
certificate · Snag list:
· Practical Completion
certificate
· Final Completion certificate
· Final Completion certificate
The certificate will be issued after the defect liability period has lapsed. The Engineer will visit the site and if there are no defects, the final completion certificate will be issued.
A list of outstanding items that a contractor must attend before each completion stage is reached.
When the building is operational to be used by the community, the contractor will hand it over to the client and the engineer will issue the snag list on items that the contractor will have to attend. The retention period starts from the date of engineer issuing practical completion certificate and is a six (6) months period.
The certificate will be issued after the defect liability period has lapsed. The Engineer will visit the site and if there are no defects, the final completion certificate will be issued.
The certificate will be issued after the defect liability period has lapsed. The Engineer will visit the site and if there are no defects, the final completion certificate will be issued.
· Practical Completion certificate
When the road is
ready for
operations, the Contractor will indicate to the Engineer and a Snag list will be compiled by the Engineer/PSC.
Upon completion of the snag list, the contractor will hand over the site to the Community
Stage 8 (100%) Stage 8 (100%)
· Final Completion
Certificate
· Final Completion certificate
The certificate will be issued when the engineer has visited the building and is happy with the construction overall response and quality.
The certificate will be issued after the defect liability period has lapsed.
The Engineer will visit the site and if there are no defects, the final completion
certificate will be issued.
Number IDP Ref. No. National KPA Departmental Programme Ward
Project Description
Means of Verific
ation
BAS ELI NE
KPI
Unit of Measu
re
Actucal Budget 2020/2021 FYProject Total Cost Opex, Segmetn Description Capex Segment Description. Revenue Segment Description Funding Source
ANN UAL TAR GET
Quarter 1 (July -
Sept.)
Quarter 2 (Oct. -
Dec.)
Quarter 3 (Jan. -
Mar.)
Quarter 4 (April -
June)
1 P1G1O1.01 Basic Service Delivery and Infrastructure Revenue and Expenditure Management All wards
Indigent support
Q1 – Q4: 12 monthl y Indigen t reconci led status reports submitt ed to MTM.
2018/
2019 1196 6 benef iciari es recei ving suppo rt
Num ber of regist ered indig ent benef iciari es recei ving free basic servi ces by set date
Numbe r Date
R9 396 216,00 R9 396 216,00 Free Basic Electricity, Solid Waste indigent N/A N/A Operational
Provi de servic es to 15760 regist ered indige nt benefi ciaries as follow s:
Electr icity, Refus e and rates, Altern ative energ y by 30 June 2021
Provide services 3940 to indigent beneficiari es an on monthly basis as follows:
Electricity Refuse and Rates:
Alternative energy by and submit three (3) monthly reports to MTM by 30
September 2020.
Provide services 3940 to indigent beneficiari es an on monthly basis as follows:
Electricity Refuse and Rates:
Alternative energy by and submit three (3) monthly reports to MTM by 31
December 2020.
Provide services 3940 to indigent beneficiari es an on monthly basis as follows:
Electricity Refuse and Rates:
Alternative energy by and submit three (3) monthly reports to MTM by 31 March 2021.
Provide services 3940 to indigent beneficiari es an on monthly basis as follows:
Electricity Refuse and Rates:
Alternative energy by and submit three (3) monthly reports to MTM by 30 June 2021.
Quarterly Cash Flow
R9 396 216,0 0
R2 349 054,00
R2 349 054,00
R2 349 054,00
R2 349 054,00
2 P1G102.02 Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 4
Constructio n of 9km Nkasela access road
Bill of Quantit ies, Progres s Report s to MTM, Interna l Audit Report, Compl etion Certific ate
643.7 km of existi ng roads
Perce ntage of work on acces s roads comp leted by set date
Date, KM, Stage/
Percen tage
R8 000 000,00 R8 000 000,00 N/A N/A N/A MIG
80%
constr uction of Nkase la access road compl eted by 30 June 2021
Stage 1 (10%) Contractor establishm ent. By 30 September 2020.
Stage 2 (20%) Clear and grub Roadbed preparation
by 30
September 2020.
Stage 3 (40%) Installation of pipes by 31
December 2020
Stage 4 (60%) Tipping of gravel.
Processing of gravel
by 31
March 2021.
Stage 5 (80%) Protection Works, Installation of road signs by 30 June 2021.
Basic Service Delivery and InfrastructureProjects, Operations and Maintenance Management 22
Constructio n of 5,6km Mkhemane access road
R6 000 000,00 R6 000 000,00
95%
constr uction of Mkhe mane access road compl eted by 30 June 2021
Stage 4 (60%).
Tipping of gravel.
Processing of gravel
by 31
March 2021
Stage 5 (80%).
Protection Works, Installation of road signs by 30 June 2021.
N/A
Stage 7(95%) {Practical Completio n
Certificate } by 31 March 2020
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 3
Constructio n of Masakala accesss road
R1 500 000,00 R1 500 000,00
80%
Const ructio n of Masa kala access road compl ete by 30 June 2021
Stage 1 (10%).
Contractor establishm ent. By 30 September 2020.
Stage 2 (20%).
Clear and grub Roadbed preparation
by 30
September 2020.
Stage 3 (40%) Installation of pipes by 31
December 2020.
Stage 4 (60%).
Tipping of gravel.
Processing of gravel
by 31
March 2021
Stage 5 (80%).
Protection Works, Installation of road signs by 30 June 2021.
Basic Service Delivery and InfrastructureProjects, Operations and Maintenance Management 14
Constructio n of 6km Moiketsi access road
R2 500 000,00 R2 500 000,00
100%
constr uction of Moike tsi access road compl eted by 30 June 2021
Stage 6 (95%) {attending to snag list)
by 30
September 2020
N/A N/A
Stage 7(100%) {Final Completiti on Certificate } by 30 June 2021
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 10
Constructio n of magonqolw eni accesss road
R2 500 000,00 R2 500 000,00
80%
Const ructio n of Mago nqolw eni Road compl ete by 30 June 2021
Stage 1 (10%).
Contractor establishm ent. By 30 September 2020.
Stage 2 (20%).
Clear and grub Roadbed preparation
by 30
September 2020.
Stage 3 (40%) Installation of pipes by 31
December 2020.
Stage 4 (60%).
Tipping of gravel.
Processing of gravel
by 31
March 2021
Stage 5 (80%).
Protection Works, Installation of road signs by 30 June 2021.
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 21
Constructio n of Msukeni access road
R2 000 000,00 R2 000 000,00
80%
Const ructio n of Msuk eni access road compl ete by 30 June 2021
Stage 1 (10%).
Contractor establishm ent. By 30 September 2020.
Stage 2 (20%).
Clear and grub Roadbed preparation
by 30
September 2020.
Stage 3 (40%) Installation of pipes by 31
December 2020.
Stage 4 (60%).
Tipping of gravel.
Processing of gravel
by 31
March 2021
Stage 5 (80%).
Protection Works, Installation of road signs by 30 June 2021.
Basic Service Delivery and InfrastructureProjects, Operations and Maintenance Management 13
Constructio n of 4.6 km Mohapi access
R2 500 000,00 R2 500 000,00 40%
Const ructio n of Moha pi access road compl ete by 30 June 2021
N/A N/A
Stage 1 (10%) Contracto r
establishm ent by 31 March 2021
Stage 3 (40%) Base foundation slab by 30 June 2021.
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 9
Constructio n of Mahangu access road
and bridge R2 500 000,00 R2 500 000,00
40%
Const ructio n of Maha ngu access road and bridge compl ete by 30 June 2021
N/A N/A
Stage 1 (10%) Contracto r
establishm ent by 31 March 2021
Stage 3 (40%) Base foundation slab by 30 June 2021.
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 24
Constructio n of Purutle to Moyeni access road
and bridge R2 500 000,00 R2 500 000,00
40%
Const ructio n of Purutl e to Moye ni access road and bridge compl ete by 30 June 2021
N/A N/A
Stage 1 (10%) Contracto r
establishm ent by 31 March 2021
Stage 3 (40%) Base foundation slab by 30 June 2021.
Quarterly Cash Flow
R30 000 000,0 0
R0,00 R0,00 R15 000
000,00
R15 000 000,00
3 P1G1O2.03 Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 26
Constructio n of 5 km Cedarville Internal Streets- Phase 3
Bill of Quantit ies, Progres s Report s to MTM, Interna l Audit Report, Compl etion Certific ate
53.08 km of surfa ced rods
Perce ntage of work on Inter nal Stree ts comp leted by set date
Date, Km, Stage /Perce ntage
R7 229 200,00 R7 229 200,00 N/A N/A MIG
95%
constr uction of Cedar ville Intern al Street s- Phase 3 of surfac ed road compl
Stage 3 (40%) installation of pipes by 30
September 2021
Stage4 (60%) pavement layers and sealants by 30 March 2021
Stage 5 (80%) Kerbing, protection works and asphalt by 31 March 2021
Stage 6 (95%) {attending to snag list)
by 31
March 2021
eted by 30 June 2021
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 1
Constructio n of 5 km Maluti Internal Streets- Phase 4
R15 000 000,00 R15 000 000,00
95%
compl etion of Malut i Intern al Street s- Phase 4 of surfac ed roads by 30 June 2021
Stage 5 (80%) Kerbing, protection works and asphalt by 31 March 2021
Stage 6 (95%) {attending to snag list) by 31 March 2021
N/A N/A
Basic Service Delivery and InfrastructureProjects, Operations and Maintenance Management 20
Constructio n of 5km Harry Gwala internal streets
R2 000 000,00 R2 000 000,00
100%
compl etion of Harry Gwala intern al Street s- by 30 June 2021
N/A N/A N/A
Stage 7(100%) {Contracto r
establishm ent } by 30 June 2021
Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 19
Constructio n of 5km Matatiele internal streets- Phase 2
R4 000 000,00 R4 000 000,00
100%
compl etion of Matati ele Intern al Street s- Phase 2 streets by 30 June 2021
N/A N/A N/A
Stage 7(100%) {Final Completiti on Certificate } by 30 June 2021
Basic Service Delivery and InfrastructureProjects, Operations and Maintenance Management 7
Constructio n of 5km Matatiele internal streets- Phase 3
R1 000 000,00 R1 000 000,00
60%
compl etion of Matati ele intern al
N/A N/A N/A
Stage 4 (60%) {Pavement layers, sealants completed
by 31
Street s- Phase 3stree ts by 30 June 2021
March 2021
Quarterly Cash Flow
R29 229 200,0 0
R7 307 300,00
R7 307 300,00
R7 307 300,00
R7 307 300,00
4 P1G1O2.05 Basic Service Delivery and Infrastructure Electricity Unit
Q1:
Contra ct Award letter.
Q2:
Kickof f Meetin g Minute s, Progres s reports (minut es of Progres s meetin gs) and photos.
. Q3:
Progres s
3704 Hous ehold s electr ified in 201`9 /20
Num ber of hous ehold s conn ected to by set date
Numbe r, Date
R71 852 100,00 R71 852 100,00
N / A
Rural Electr
ificati on
N / A
I N E P
Conne ct house holds in Ward 5,7,9, 13, 18, 20, 22 and 26 by 30 June 2021
Contract award letter issued by 30
September 2020.
Site Establishm ent, Excavation , Planting of poles by 31
December 2020.
Continue Planting of poles &
Stringing of
conductor by 31 March 2021.
Connection of 4121 households by 30 June 2021.
Report s (minut es of progres s Meetin gs).
Q4:
Progres s Report s (minut es of progres s Meetin gs), Compl etion Certific ate and photos
Basic Service Delivery and InfrastructureElectricity Unit
7
Hillside –Manzi
322 HH
Num ber of hous ehold s conn ected by set date
Numbe r, Date
R5 796 000,00 R5 796 000,00 N/A Rural Electrification N/A INEP
Basic Service Delivery and InfrastructureElectricity Unit
7
Sifolweni 155
HH
R282 100,00 R282 100,00
Basic Service Delivery and InfrastructureElectricity Unit
7
Ngcwengana
147 HH
R2 646 000,00 R2 646 000,00
Basic Service Delivery and InfrastructureElectricity Unit
9
Mbombo 390 HH
R7 128 000,00 R7 128 000,00
Basic Service Delivery and InfrastructureElectricity Unit
18
Mnyamaneni (Kesa, Sdakeni) :400 HH
R7 200 000,00 R7 200 000,00
Basic Service Delivery and InfrastructureElectricity Unit
5
Vikinduku – Lubaleko (500) HH
R9 000 000,00 R9 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
9
Matiase B (Mhlangeni, Vimba,Mav undleni,Mn gayi)
500HH R9 000 000,00 R9 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
22
Small Location- Mpofini :500 HH
R9 000 000,00 R9 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
22
Epiphany (800)
R10 000 000,00 R10 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
26
Shenxa (428)
R6 000 000,00 R6 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
13
Mohapi #2 (290)
R4 000 000,00 R4 000 000,00
Basic Service Delivery and InfrastructureElectricity Unit
19 AN D 20
1500 m MV Paper Cable)R300 000,00 R300 000,00
Basic Service Delivery and InfrastructureElectricity Unit
19 AN D 20
Substation – Switch gearsR1 500 000,00 R1 500 000,00
Quarterly Cash Flow
R71 852 100,0 0
R17 963 025,00
R17 963 025,00
R17 963 025,00
R17 963 025,00
5 P1G1O2.06 Basic Service Delivery and Infrastructure Electricity Unit
Contra ct Award letters, Deliver y notes, Invoice s and photos
Existi ng Trans forme rs, Subst ation Switc h Gears and Ring Main Units are overl oaded and aging
Num ber of Subst ation switc h gears , trans form ers and ring main unit repla ced by set date
Numbe r, Date
R2 750 000,00 R2 750 000,00 N/A Substation N/A CRR
Repla cemen t of {1} 3 Transf ormer s, {2}
substa tion switch gears, {3}
50 x electri cal poles, {4}
1500 m MV Paper Cable and {5}
Christ mas lights by 30 June 2021
Basic Service Delivery and InfrastructureElectricity Unit 19, 20
Replacemen t of 3 transformer s
R800 000,00 R800 000,00 N/A Substation N/A CRR
Contract award letter issued by 30
September 2020.
N/A
Delivery of 3
transforme rs by 31 March 2021
N/A
Basic Service Delivery and InfrastructureElectricity Unit 19, 20
50 x
Electrical Poles
R150 000,00 R150 000,00
Contract award letter issued by 30
September 2020.
Replaceme nt of 100 Low Voltage Staywires - North End
Replaceme nt of 50 Low Voltage Staywires - North End
N/A
Basic Service Delivery and InfrastructureElectricity Unit 19, 20
1500m MV
Paper Cable
R300 000,00 R300 000,00
Contract award letter issued by 30
September 2020.
N/A
Delivery of 1500m MV Paper Cable by 31 March 2021
N/A
Basic Service Delivery and InfrastructureElectricity Unit 19, 20
Replacing Substation Switch Gears
R1 500 000,00 R1 500 000,00
Contract award letter issued by 30
September 2020.
N/A
Replaceme nt of 3 substation gears by 31 March 2021
N/A
Basic Service Delivery and InfrastructureElectricity Unit 1 9
Christmas
Lights
R250 000,00 R250 000,00
Procureme nt process completed
by 30
September 2020
Christmas lights replaced AND Installed by 31 December 2020
N/A N/A
Quarterly Cash Flow
R2 750 000,0 0
R687 500,00
R687 500,00
R687 500,00
R687 500,00
6 P1G1O2.07 Basic Service Delivery and Infrastructure Electricity Unit 19, 20
Replacemen t of 40 Street Lights & 3 High Mast Lights
Q1:
N/A.
Q2:
N/A.
Q3:
Award letter issued and Contra ct signed.
Q4:
Deliver y note
&
photos.
Existi ng street lights
&
High Mast Light s in Matat iele CBD
Num ber of Stree t lights
&
High Mast Light s instal led by set date
Numbe r, Date
R2 500 000,00 R2 500 000,00 N/A High mast lights AND Street Lights CBD N/A CRR
Repla cemen t of 40 Street Lights
& 3 High Mast Lights
N/A N/A
Appointme nt of the service provider by 31 March 2021
Install 3 high mast lights and replace 30 street lights in ward 20 by 30 June 2021.
Quarterly Cash Flow
R2 500 000,0
0
N/A N/A N/A R2 500
000,00
7 P1G1O3.01 Basic Service Delivery and Infrastructure Projects, Operations and Maintenance Management 19
Constructio n of 6400m2 Extension of Matatiele Sport Center
Q1:
Progres s meetin g minute s and attenda nce register . Q2:
Progres s meetin g minute s and attenda nce register . Q3:
Progres s meetin g minute s and attenda nce register . Q4:
Practic al comple tion certific ates
6 existi ng sports fields
Perce ntage of sport s cente r const ructe d and comp leted by set date
Percen tage, Date
R4 000 000,00 R4 000 000,00 N/A Sport center N/A MIG
95%
constr uction of Matati ele Sport center compl eted by 30 June 2020
Stage 4 (85%) Building concrete works by 30
December 2019
N/A N/A
Stage 6 (95%) Matatiele aPractical Completio n
certificate issued by 31 March 2021
Quarterly Cash Flow
R4 700 000,0 0
R1 175 000,00
R1 175 000,00
R1 175 000,00
R1 175 000,00
8 P1G1O4.01 Basic Service Delivery and Infrastructure Building Control/Human Settlement Admin
Completion of council chambers and Offices
Q1:
Progres s meetin g minute s and attenda nce register . Q2:
Progres s meetin g minute s and attenda nce register . Q3:
Progres s meetin g minute s and attenda nce register . Q4:
Practic al comple
Main Contr actor appoi nted and proje ct under const ructio n.
% of coun cil cham bers and muni cipal offic es comp leted by set date
Percen tage, Date
R13 000 000,00 R13 000 000,00 N/A Council Chambers N/A CRR
100%
Comp letion of Counc il cham bers and munic ipal office s
Stage 4 (60%) Roof installation , dry wall installation , wall and floor tiling and paving
by 30
September 2020
Stage 5 (80%) Painting, glazing and paving by 31
December 2020.
Stage 5 (80%) Painting, glazing and paving continued and completed by 31 March 2021.
Stage 6 (100%) completed by 30 June 2021.
tion certific ate.
Quarterly Cash Flow
R13 000 000
R3 250 000
R3 250 000
R3 250 000
R3 250 000
9 P1G1O5.01 Basic Service Delivery and InfrastructureBuilding Control/Human Settlement 1,19,20,26
Store building renovation
Q1:
Advert, Q2:
Appoin tment letter, Q4:
Progres s report/
comple tion certific ation.
Dilap idate d muni cipal store buildi ng
% of reno vatio ns done by set date
R800 000,00 R800 000,00 N/A N/A Renovation of Municipal Stores Capex
100%
renov ation of munic ipal stores buildi ngs by 30 June 2021
Process for the
appointme nt of the service provider completed
by 30
September 2020.
Stage 1 (10%) Appointme nt of local SMMEs by 31
December 2020.
N/A
Stage 7 (100%) Completio
n of
maintenanc e of the public facility by 30 June 2020.
Quarterly Cash Flow
R800 000,0 0
N/A R400
000,00 N/A R200
000,00
10 P1G1O5.02 Basic Service Delivery and Infrastructure Building Control/Human Settlement 2, 4, 5, 6, 11, 15, 17, 19, 22, 23, 25, 26
Maintenanc e of municipal facilities - Community Halls:
Ward 15 Ward 11 Ward 17 Ward 25 Ward 23 Pre-School:
Ward 04Ward 05 Ward 22 Ward 06 Ward 02 Offices:
Main Office Traffic BTO LED Stores
Q1:
Terms of referen ce and advert.
Q2:
Appoin tment letter.
Q3:
Progres s report and payme nt certific ate Q4:
comple tion and payme nt certific ate
12 muni cipal facilit ies maint ained.
Num ber of facili ties main taine d by set date
Numbe r, Date
R1 300 000,00 R1 300 000,00 Maintenance of Buildings and Facilities, Sewerage Services, Maintenance of Equipment N/A N/A Opex
Maint enanc e of 5 munic ipal public faciliti es by 30 June 2021
Process for the
appointme nt of the service provider completed
by 30
September 2020.
Stage 1 (10%) Appointme nt of local SMMEs for
maintenanc e of Five (5)
municipal public facilities
by 31
December 2020.
Stage 6 (95%) Renovation s of public amenity facilities and Issue Snag list to SMMEs and retention period by 31 March 2021
. Stage 7 (100%) Completio
n of
maintenanc e of the public facility by 30 June 2021.
Quarterly Cash Flow
R1 300 000,0 0
N/A R433
333,33
R433 333,33
R433 333,33
11 P1G1O5.04 Basic Service Delivery and Infrastructure Building Control/Human Settlement 19
Constructio n of municipal pound
Q1 – 4 Site minute s. Q4:
Practic al comple tion and payme nt certific ate PLUS Q1-4 - Quarte rly Progre ss Report to MTM
Poun d site identi fied and servic e provi der appoi nted
% of Poun d Struc ture comp leted by set date
Percen tage, Date
R2 000 000,00 R2 000 000,00 N/A Pound Structure N/A Capex
100%
Comp letion of Pound Struct ure by 30 June 2021
(60%) Stage 4 Roofing, Plumbing works and finishes by 30
September 2020.
(80%) Stage 5 Windows, Plastering, Landscapin g by 31 December 2020.
(90%) Stage 6 Finishes, Landscapi ng by 31 March 2021.
Stage 8 (100%) Final Completio n
Certificate issued by 30 June 2021.
Quarterly Cash Flow
R2 000 000,0 0
R500 000,00
R500 000,00
R500 000,00
R500 000,00