PLAGIARISM
PUBLICATION
World energy outlook
Predictions from the '450' scenario for a reduction in greenhouse gases in 2035 require a growth in renewable energy sources from 13% to 27%. The share of energy sources translates from the scenario forecast to the technology mix for each scenario, as shown in Figure 1-2.
International demand for renewable energy
South African demand for renewable energy
- Capacity and sizing alternatives
- Location options
- South Africa’s investment in renewable energy
- Renewable power plant network assessment challenges
The DOE's acceleration of REI4P is commitment to start up renewable power plants (RPPs) to support the state-owned utility. The accelerated connection plan and technical impact of RE capacity on the Eskom power system led to the definition of the following research questions 1.5.
Research hypothesis
Long-term equipment size and power vary for single-entity connections compared to multiple connections.
Research questions
Objectives and approach
Significance of research
Structure of dissertation
Chapter in perspective
Optimal placement techniques
This chapter aims to search scholarly works in the area of ideal placement of DG.
What critical electrical factors determine the optimal placement of DG to reduce power
In [17], a network unbundling algorithm was presented that enables radial protection in the presence of DG. While DG placement improves the network voltage profile, optimal placement and sizing play an important role in reducing system losses [29].
What is the importance of reactive power control for the integration DG ?
The layout and dimensioning of the DG unit was designed by mixed integer nonlinear programming, the aim of which was to improve the stability limit. This index method was implemented using a 69-node IEEE radial distribution network to determine the optimal layout and size of DG units.
How does DG penetration and concentration affect power system losses?
A method to detect and determine DG units to improve the voltage stability in the presence of probabilistic load and renewable DG generation was presented in [50]. The characterization of these sources and sinks by network impedance supports the research questions leading to the hypothesis.
Characteristics of time variant loads
- Load types
- Time variant loads
Utility planners must account for likely permutations of generation and load patterns when sizing and locating DG. High generation – low load; Low generation – high load and low generation – low load scenarios represent the critical study points for generation and load profiles.
Characteristics of time variant sources of renewable generation
- Global wind patterns
- Weibull distribution
- Wind power equation
- Wind power curve
Electrical characteristics of renewable wind generation
- Real power
- Reactive power
Solar PV - partially predictable source of renewable energy
- Global solar irradiance
- Solar power curve
In reality, the power output is affected by cloud disturbances, as shown in Figure 3-3 below. Depending on the time of day and cloud cover, the PV output varies as shown in Figure 3-3.
Electrical characteristics of renewable solar PV generation
- Real power
- Reactive power
Concentrated solar plants
Bagasse
Hydro / pumped storage
- Electrical characteristics of renewable non-solar PV and non-wind generation
- Real power
- Reactive power
RPCC is limited by the excitation current in the capacitive scale; from the stator currents to the inductive step. Unlike the PV inverter, the synchronous generator is a relatively clean source of electricity as very few harmonics are injected into the grid.
Dispatchable Vs non-dispatchable generation
Characteristics of power losses
- Energy losses
- Power losses
Characteristics of distribution network topology
- Typology of distribution networks
- Radial networks
- Tie line radial networks
- Meshed networks
- Voltage profile of distribution networks
- Thermal capability of distribution networks
- Fault level characteristic of radial networks
For increased network reliability, radial network designs include switchable normally open link lines to support interconnection. They are placed at the beginning of the network, connected to the bypass circuit breaker for maintenance purposes. Another option is in the middle of a traditional trunked network; or at the end of the feeder.
The voltage profiles of radial and tie-line radial feeders are tapered from source to end of the line. Regulatory codes may limit the use of DG to resolve existing voltage problems as it may be too expensive for this purpose alone [87]. Strategic and optimal placement and sizing of DG on radial and tie-line radial networks can increase thermal transfer on the network.
Impact of distributed generation on distribution network topology
Department of energy’s renewable energy requirement
Eskom transmission connection strategy
Where concentrated RE sources are to be evacuated through EHV networks, the following connection strategy is considered. Passive voltage control through reactive power is limited by the impedance of the sub-transmission lines between the satellite, solar collector and MTS. Integration, shown in Figure 3-10, favors loss reduction as DG is consumed at the load center.
Connections for network expansion, while managing voltage control; reactive power control and loss minimization, should be robust.
Typical Distribution connection options
Utility technical challenges
- Critical electrical factors that determine optimal location to reduce power loss
- Practical power flow simulation methodology applied for placement of DG for loss
- The importance of reactive power support for integration of distributed generation 31
They show high reactive power losses when operating at high thermal demands, due to I2X losses. A lower Thevenin equivalent source impedance provides higher error levels and allows connections with higher DG capacity. Error rates can be too high and reduce the size of the connection. Due to the above problems, the integration and strengthening of the network will increase the costs.
This research aims to develop a practical approach for optimal placement and sizing of DG with the aim of reducing power losses. Sizing of DG at potential reverse flow locations should ideally be moved at higher load factors [100]. Incorporating dispatchable DG technologies can reduce reverse current flows, especially on older protection technology networks.
Chapter in perspective
Modeling these parameters to analyze optimal placement of DG are important factors in the assessment process.
Objective of method
Problem statement
Technical constraints
Scope of method
Assumptions
Exclusions
Optimal placement methodology
- Overview
- Pre-DG evaluation
- Defining power system busbars
- Ranking power system busbars
- Profiling power system busbars for DG sizing
- Activating DG for placement
- Evaluate DG sizing for voltage variation
- Optimal selection process
Pre-DG evaluates and analyzes a convergent DIgSILENT Power Factory © (DPF) version 15.1.4 utility network file. The pre-DG survey took place before August 2015 and the post-DG survey took place in September and October 2015. Optimal selection of candidate rails based on a comparative overview of optimal placement as described in section 4.7.8.
The method of defining identifies load and non-load (network) busbars suitable for DG connection. Profiling load and network rails to DG profiles classifies the expected impact of load and loss reduction. Voltage variation tests performed on load and network busbars confirm the grid code requirement for generation loss.
Analysis of results
Chapter in perspective
The utility test network shows the interconnection of a typical network supplying industrial, commercial and rural load.
Transmission grid
Sub-Transmission
- Grid I and Grid II
- Line Parameters
The electrical network was simulated with the conductor impedances and conductor lengths shown in Table 8-1 and Table 8-2 in 8.3.1.
System overview prior to distributed generation
- Load types and profiles
- Sub – transmission grid loading
- System fault level
- High-voltage fault level
- Medium voltage fault level
- System voltage level
- High-voltage busbar system per unit values
- Medium voltage busbar system per unit values
- Active power load flow
- Reactive power load flow
- Sub-transmission phase angles – power factor
- Sub-transmission grid loss
The absence of reactive power from a solar PV plant implies other means of reactive compensation. Utilities can capitalize on inherent reactive power during these cycles so as not to negatively impact peak output capacity. This is an important finding that seeks to optimize the reactive power flow through solar DG without additional reactive power compensation.
Reactive power losses recorded the difference in flow between "from" and "to" busbars, shown in Table 8-10 and Table 8-11. Examination of the pre-DG phase angle of the 11kV ground bus, obtained from Table 8-3 row 17, shows the power factor of 0.965. Active power is reduced from the DG's supply; reactive power remains unchanged, resulting in a negative impact on the upstream power factor.
Distributed generation profile characteristic
Subtracting the DG profile from the load profiles gives the resultant "duck" shaped profile shown in Figure 5-3. The negative real power represents the excess DG that will flow upstream, from the connection point, to feed the adjacent load centers. The reverse power flow will cause losses if the mismatch between the load profile and the DG profile is large.
Voltage variation results
- Voltage variation results – Earth 11kV busbar
- Sub-transmission load flow – post DG 11kV Earth bus
- Sub-transmission grid loss – post DG 11kV earth
The pre- and post-DG comparison at the 66 kV Earth bus shows the deepening of the midday profile as the DG injection increases. Earth 11kV BB: Output Current, Active Power in MW Earth 11kV BB: Output Power, Reactive Power in Mvar. Earth 66kV BB: Output Current, Active Power in MW Earth 66kV BB: Output Power, Reactive Power in Mvar.
The 11 kV ground collector hosted a relatively small DG solar plant due to its relatively low fault rate. The introduction of 8 MWs of DG reduced network losses by 9.5% for real power and 13% for reactive power. The analysis showed different levels of network losses depending on the load profile; type of load; error rate.
Summary of post-DG on utility network
- Utility grid – post-DG
Two busbars in this voltage range do not qualify for selection, namely Ruby and LinkedIn. A review of the 22kV results by DG suggests all negative real and reactive losses in the network for selection. Larger dimensioning of DGs showed higher network losses when they were not placed close to the load busbars.
Increased power losses with larger DG sizes are notable for 88 kV rail voltages, shown in Table 5-7. The reduction in actual power losses is attributed to the 88kV Basket bus being closer to the load center. A review of the post-DG table for 132 kV rails does not nominate any rail for selection.
Overview
Summary of findings
Assessing the research questions
- What critical electrical factors determine the optimal placement of DG to reduce
- Network topology
- System impedance and system fault level
- Equipment rating
- Voltage control of active and reactive power flow
- Load types and characteristics
- Solar PV characteristics
- What practical loss optimization power flow method can be applied to place DG on
- What is the importance of reactive power control for the integration DG?
- How does DG penetration and concentration affect power system losses?
Inadequate sizing of transformer and line capacities will overload, resulting in increased real and reactive power losses. As Q decreases, the voltage decreases as the square, referring to causes of voltage drift under low reactive power reserves. Voltage control through transformer tap-changers and reactive power compensation controls constant voltage within prescribed limits.
Reactive power compensation is essential for the integration of DG to address the reduction of reactive power flows. Comparisons were made for each pre- and post-connected DG validating the changes in phase angle; power factor and resulting reactive power current. As the penetration of DG increases to reduce active power, larger reactive power compensation units must be added to the network.
Relevance of research
Penetration and concentration of DG was explained in chapter 2 and demonstrated chapter 5 section and 5.6.7 shows the results for DG integration with 66kV busbars.
Assessing the hypothesis
Future research
Conclusion
Recommendation
Harrison, “Improved Resource Utilization for Voltage Regulation with Distributed Generation,” IEEE Transactions on Power Systems, vol. Atwa, “Optimal placement and sizing method to improve voltage stability margin in a distribution system using distributed generation,” IEEE Transactions on Power Systems, vol. Román, “Assessing Power Distribution Losses for Increasing Penetration of Distributed Generation,” IEEE Transactions on Power Systems, vol.
Reactive Power Compensation," in Electric Power Generation, Transmission, and Distribution, Third Edition, 5 vols., CRC Press, 2012, p. Lee Willis, "Power Delivery Systems," in Power Distribution Planning Reference Book, Second Edition, 0 vols. ., CRC Press, 2004. Khadkikar, “Planning of Active Distribution Networks Considering Multi-General Director Configurations,” IEEE Transactions on Power Systems, vol.
Transmission grid
Sub-transmission grid I
Sub-transmission grid II
- Line parameters
Pre-DG system overview
- Sub – transmission grid loading
- High voltage fault level
- Medium voltage fault level
- High voltage busbar system per unit values
- Medium voltage busbar system per unit values
- High voltage active power load flow
- Medium voltage active power load flow
- High voltage reactive power load flow
- Medium voltage reactive power load flow
- Phase angle results for pre-DG
- Sub-Transmission Grid Loss
Post DG assessment
- Diamond 132kV busbar assessment for DG
- Sub-transmission load flow – post DG 132kV diamond bus
- Voltage variation results – diamond 132kV busbar
- Sub-transmission grid loss – post DG 132kV diamond
- Basket 33kV busbar assessment for DG
- Sub-transmission load flow – post DG 33kV Basket bus
- Voltage variation results – 33kV Basket busbar
- Sub-Transmission Grid Loss – Post DG 33kV Basket
- Phase angle results for post-DG connection to 11kV Earth busbar
The maximum export capacity of 98 MW is injected into the 132 kV diamond busbar and changes the load profile shown in Figure 8-7. The following set of graphs shows the impact of injecting 89 MW of real power into the Diamond 132 kV bus in 10% increments (X-axis). The 132kV diamond voltage variation test by Method 1 reports a pre-DG voltage of 1.035 p.u and a post-DG voltage of 1.031 p.u.
The DG dimensioning for the 132 kV diamond rail shows an increase in grid losses of 98% for real power and 61% for reactive power. Comparison shows the reduction in real power at the peak of solar PV generation. Solar PV injected into the 33kV Basket bus will have the effect of reducing the real power requirement of the 88V Basket busbar.