13. ANALISA BIAYA KONSTRUKSI PEKERJAAN PENUTUP LANTAI

13.1 1 m² Pasang lantai ubin pc abu - abu ukuran 40 x 40 cm

13.1.1 Bahan

6.630 Bh Ubin abu - abu @ Rp- = Rp-

9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 Jumlah (1) = Rp12,736.95

13.1.2 Tenaga

0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp25,406.95 13.1 1 m² Pasang lantai ubin pc abu - abu ukuran 30 x 30 cm

13.1.1 Bahan

1.000 m2 Ubin abu - abu @ Rp42,900.00 = Rp42,900.00 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00

0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 Jumlah (1) = Rp55,833.75

13.1.2 Tenaga

0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,182.50

Jumlah (1) + (2) = Rp69,016.25 13.1 1 m² Pasang lantai ubin pc abu - abu ukuran 20 x 20 cm

13.1.1 Bahan

1.060 m2 Ubin abu - abu @ Rp24,640.00 = Rp26,118.40 10.400 Kg Semen portland @ Rp984.00 = Rp10,233.60

0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 Jumlah (1) = Rp39,445.75

13.1.2 Tenaga

0.270 Org Pekerja @ Rp30,000.00 = Rp8,100.00 0.130 Org Tukang batu @ Rp35,000.00 = Rp4,550.00 0.130 Org Kepala tukang @ Rp37,500.00 = Rp4,875.00 0.014 Org Mandor @ Rp40,000.00 = Rp560.00 Jumlah (2) = Rp18,085.00

Jumlah (1) + (2) = Rp57,530.75 13.1 1 m² Pasang lantai ubin pc abu - abu ukuran 20 x 20 cm

13.1.1 Bahan

1.000 m2 Ubin abu - abu 20 x 20 cm @ Rp24,640.00 = Rp24,640.00 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00 0.0215 M³ Pasir pasang @ Rp68,750.00 = Rp1,478.13 Jumlah (1) = Rp35,958.13

BIDANG BANGUNAN

0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.0125 Org Kepala tukang @ Rp37,500.00 = Rp468.75 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,163.75

Jumlah (1) + (2) = Rp49,121.88 13.2 1 m² Pasang lantai ubin warna ukuran 40 x 40 cm

13.2.1 Bahan 6.630 bh Ubin warna @ = Rp- 9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.300 Kg Semen warna @ Rp2,875.00 = Rp3,737.50 Jumlah (1) = Rp16,474.45 13.2.2 Tenaga 0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp29,144.45 13.2 1 m² Pasang lantai ubin warna ukuran 30 x 30 cm

13.2.1 Bahan 11.870 bh Ubin warna 30 x 30 cm @ = Rp- 10.00 Kg Semen portland @ Rp984.00 = Rp9,840.00 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp17,246.25 13.2.2 Tenaga 0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,182.50

BIDANG BANGUNAN

13.3 1 m² Pasang lantai ubin warna ukuran 20 x 20 cm

13.3.1 Bahan 26.500 bh Ubin warna 20 x 20 cm @ Rp- = Rp- 10.400 Kg Semen portland @ Rp984.00 = Rp10,233.60 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.620 Kg Semen warna @ Rp2,875.00 = Rp4,657.50 Jumlah (1) = Rp17,984.85 13.3.1 Tenaga 0.270 Org Pekerja @ Rp30,000.00 = Rp8,100.00 0.130 Org Tukang batu @ Rp35,000.00 = Rp4,550.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.014 Org Mandor @ Rp40,000.00 = Rp540.00 Jumlah (2) = Rp13,677.50

Jumlah (1) + (2) = Rp31,662.35 13.4 1 m² Pasang lantai ubin teraso ukuran 40 x 40 cm

13.4.1 Bahan 6.630 bh Ubin teraso @ Rp- = Rp- 9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.300 Kg Semen warna @ Rp2,875.00 = Rp3,737.50 Jumlah (1) = Rp16,474.45 13.4.2 Tenaga 0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp29,144.45 13.4 1 m² Pasang lantai ubin teraso ukuran 30 x 30 cm

13.4.1 Bahan 11.870 bh Ubin teraso 30 x 30 cm @ = Rp- 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp17,246.25 13.4.2 Tenaga 0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,182.50

Jumlah (1) + (2) = Rp30,428.75 13.5 1 m² Pasang lantai ubin granito ukuran 40 x 40 cm

13.5.1 Bahan

6.630 bh Ubin granito @ = Rp-

9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.300 Kg Semen warna @ Rp2,875.00 = Rp3,737.50

BIDANG BANGUNAN

13.5.2 Tenaga

0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp29,144.45 13.5 1 m² Pasang lantai ubin granito ukuran 30 x 30 cm

13.5.1 Bahan 11.870 bh Ubin granito 30 x 30 cm @ = Rp- 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp17,246.25 13.5.2 Tenaga 0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp468.75 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,163.75

Jumlah (1) + (2) = Rp30,410.00 13.6 1 m² Pasang lantai ubin teralux ukuran 40 x 40 cm

13.6.1 Bahan

6.630 bh Ubin teralux kerang @ = Rp-

9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.300 Kg Semen warna @ Rp2,875.00 = Rp3,737.50 Jumlah (1) = Rp16,474.45 13.6.2 Tenaga 0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,707.50

BIDANG BANGUNAN

13.6 1 m² Pasang lantai ubin teralux ukuran 30 x 30 cm

13.6.1 Bahan

11.870 bh Ubin teralux kerang @ = Rp- 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp17,246.25 13.6.2 Tenaga 0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,182.50

Jumlah (1) + (2) = Rp30,428.75 13.6 1 m² Pasang lantai ubin teralux marmer ukuran 60 x 60 cm

13.6.1 Bahan

3.100 bh Ubin teralux marmer @ = Rp-

9.600 Kg Semen portland @ Rp984.00 = Rp9,446.40 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp16,852.65 13.6.2 Tenaga 0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp29,522.65 13.6 1 m² Pasang lantai ubin teralux marmer ukuran 40 x 40 cm

13.6.1 Bahan

6.630 bh Ubin teralux marmer @ = Rp-

9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.300 Kg Semen warna @ Rp2,875.00 = Rp3,737.50 Jumlah (1) = Rp16,474.45 13.6.2 Tenaga 0.250 Org Pekerja @ Rp30,000.00 = Rp7,500.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp12,670.00

Jumlah (1) + (2) = Rp29,144.45 13.6 1 m² Pasang lantai ubin teralux marmer ukuran 30 x 30 cm

13.6.1 Bahan

11.870 bh Ubin teralux marmer @ = Rp- 10.000 Kg Semen portland @ Rp984.00 = Rp9,840.00

0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50

BIDANG BANGUNAN

13.6.2 Tenaga

0.260 Org Pekerja @ Rp30,000.00 = Rp7,800.00 0.125 Org Tukang batu @ Rp35,000.00 = Rp4,375.00 0.013 Org Kepala tukang @ Rp37,500.00 = Rp487.50 0.013 Org Mandor @ Rp40,000.00 = Rp520.00 Jumlah (2) = Rp13,182.50

Jumlah (1) + (2) = Rp30,428.75 13.7 1 m' Pasang plint ubin pc abu - abu ukuran 15 x 20 cm

13.7.1 Bahan 5.300 bh Plint ubin 15 x 20 cm @ = Rp- 1.650 Kg Semen portland @ Rp984.00 = Rp1,623.60 0.004 M³ Pasir pasang @ Rp68,750.00 = Rp275.00 Jumlah (1) = Rp1,898.60 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,286.10 13.7 1 m' Pasang plint ubin pc abu - abu ukuran 10 x 30 cm

13.7.1 Bahan 3.530 bh Plint ubin 10 x 30 cm @ = Rp- 1.240 Kg Semen portland @ Rp984.00 = Rp1,220.16 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 Jumlah (1) = Rp1,426.41 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp7,813.91 13.7 1 m' Pasang plint ubin pc abu - abu ukuran 10 x 40 cm

13.7.1 Bahan 2.650 bh Plint ubin 10 x 40 cm @ = Rp- 1.240 Kg Semen portland @ Rp984.00 = Rp1,220.16 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 Jumlah (1) = Rp1,426.41 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp7,813.91 13.7 1 m' Pasang plint ubin pc warna ukuran 10 x 20 cm

BIDANG BANGUNAN 1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin pc warna ukuran 10 x 30 cm

13.7.1 Bahan

3.530 bh Plint ubin PC warna @ Rp- = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin pc warna ukuran 10 x 40 cm

13.7.1 Bahan

2.650 bh Plint ubin PC warna @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teraso ukuran 10 x 30 cm

13.7.1 Bahan

3.530 bh Plint ubin teraso @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00

BIDANG BANGUNAN

0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teraso ukuran 10 x 40 cm

13.7.1 Bahan

2.650 bh Plint ubin teraso @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin granit ukuran 10 x 40 cm

13.7.1 Bahan

2.650 bh Plint ubin granit @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin granit ukuran 10 x 30 cm

13.7.1 Bahan

3.530 bh Plint ubin granit @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teralux kerang ukuran 10 x 40 cm

BIDANG BANGUNAN 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teralux kerang ukuran 10 x 30 cm

13.7.1 Bahan

3.530 bh Plint ubin teralux kerang @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teralux marmer ukuran 10 x 60 cm

13.7.1 Bahan

1.700 bh Plint ubin teralux marmer @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teralux marmer ukuran 10 x 40 cm

13.7.1 Bahan

2.650 bh Plint ubin teralux marmer @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50

BIDANG BANGUNAN

Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m' Pasang plint ubin teralux marmer ukuran 10 x 30 cm

13.7.1 Bahan

3.530 bh Plint ubin teralux marmer @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.100 Kg Semen warna @ Rp2,875.00 = Rp287.50 Jumlah (1) = Rp1,615.51 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp8,003.01 13.7 1 m2 Pasang lantai teraso cor ditempat, tebal 3 cm

13.7.1 Bahan

0.036 m3 Bahan teraso cor @ Rp- = Rp- Jumlah (1) = Rp-

13.7.2 Tenaga

0.360 Org Pekerja @ Rp30,000.00 = Rp10,800.00 0.180 Org Tukang batu @ Rp35,000.00 = Rp6,300.00 0.018 Org Kepala tukang @ Rp37,500.00 = Rp675.00 0.018 Org Mandor @ Rp40,000.00 = Rp720.00 Jumlah (2) = Rp18,495.00

Jumlah (1) + (2) = Rp18,495.00 13.7 1 m2 Pasang lantai teralux cor ditempat, tebal 3 cm

13.7.1 Bahan

0.0036 m3 Bahan teralux cor @ Rp- = Rp- Jumlah (1) = Rp-

13.7.2 Tenaga

0.900 Org Pekerja @ Rp30,000.00 = Rp27,000.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.0045 Org Mandor @ Rp40,000.00 = Rp180.00 Jumlah (2) = Rp30,667.50

Jumlah (1) + (2) = Rp30,667.50 13.12 1 m² Pasang ubin tahan asam

13.12.1 Bahan 1.050 m2 Semen portland @ Rp984.00 = Rp1,033.20 14.140 Kg Pasir pasang @ Rp68,750.00 = Rp972,125.00 0.040 m3 Semen warna @ Rp2,875.00 = Rp115.00 Jumlah (1) = Rp973,273.20 13.12.2 Tenaga 0.270 Org Pekerja @ Rp30,000.00 = Rp8,100.00 0.150 Org Tukang batu @ Rp35,000.00 = Rp5,250.00

BIDANG BANGUNAN

Jumlah (2) = Rp14,452.50

Jumlah (1) + (2) = Rp987,725.70 13.12 1 m² Pasang lantai keramik artistik ukuran 10 x 20 cm

13.12.1 Bahan

53.000 bh Ubin keramik artistik 10 x 20 cm @ = Rp- 8.190 Kg Semen portland @ Rp984.00 = Rp8,058.96 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 2.750 Kg Semen warna @ Rp2,875.00 = Rp7,906.25 Jumlah (1) = Rp19,058.96 13.12.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp52,421.46 13.12 1 m² Pasang lantai keramik artistik ukuran 10 x 10 cm atau ( 5 x 20 ) cm

13.12.1 Bahan

106.000 bh Ubin keramik artistik @ = Rp- 8.190 Kg Semen portland @ Rp984.00 = Rp8,058.96 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 3.200 Kg Semen warna @ Rp2,875.00 = Rp9,200.00 Jumlah (1) = Rp20,352.71 13.12.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp53,715.21 13.12 1 m² Pasang lantai keramik ukuran ( 33 x 33 ) cm

13.12.1 Bahan 10.000 bh Ubin keramik @ = Rp- 8.190 Kg Semen portland @ Rp984.00 = Rp8,058.96 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.620 Kg Semen warna @ Rp2,875.00 = Rp4,657.50 Jumlah (1) = Rp15,810.21 13.12.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp49,172.71 13.12 1 m² Pasang lantai keramik ukuran ( 30 x 30 ) cm

13.12.1 Bahan

11.870 bh Ubin keramik @ = Rp-

BIDANG BANGUNAN

1.500 Kg Semen warna @ Rp2,875.00 = Rp4,312.50 Jumlah (1) = Rp17,246.25

13.12.2 Tenaga

0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp50,608.75 13.14 1 m² Pasang lantai keramik 20 x 20 cm

13.14.1 Bahan 26.500 bh Ubin keramik 20 x 20 cm @ = Rp- 10.400 Kg Semen portland @ Rp984.00 = Rp10,233.60 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 1.620 Kg Semen warna @ Rp2,875.00 = Rp4,657.50 Jumlah (1) = Rp17,984.85 13.14.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp51,347.35 13.14 1 m² Pasang lantai keramik ukuran (10 x 33) cm, variasi / border

13.14.1 Bahan 33.000 bh Ubin keramik @ = Rp- 9.800 Kg Semen portland @ Rp984.00 = Rp9,643.20 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 4.370 Kg Semen warna @ Rp2,875.00 = Rp12,563.75 Jumlah (1) = Rp25,300.70 13.14.2 Tenaga 0.930 Org Pekerja @ Rp30,000.00 = Rp27,900.00 0.525 Org Tukang batu @ Rp35,000.00 = Rp18,375.00 0.053 Org Kepala tukang @ Rp37,500.00 = Rp1,987.50 0.047 Org Mandor @ Rp40,000.00 = Rp1,880.00 Jumlah (2) = Rp50,142.50

Jumlah (1) + (2) = Rp75,443.20 13.14 1 m² Pasang lantai mosaik ukuran (30 x 30) cm, campuran spesi 1 PC : 3 PP

13.14.1 Bahan 11.870 bh Mosaik @ Rp- = Rp- 14.150 Kg Semen portland @ Rp984.00 = Rp13,923.60 0.039 M³ Pasir pasang @ Rp68,750.00 = Rp2,681.25 2.000 Kg Semen warna @ Rp2,875.00 = Rp5,750.00 Jumlah (1) = Rp22,354.85 13.14.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50

BIDANG BANGUNAN

Jumlah (1) + (2) = Rp55,717.35 13.7 1 m' Pasang plint keramik ukuran 10 x 20 cm

13.7.1 Bahan

5.300 bh Plint keramik artistik @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.025 Kg Semen warna @ Rp2,875.00 = Rp71.88 Jumlah (1) = Rp1,399.89 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp7,787.39 13.7 1 m' Pasang plint keramik ukuran 10 x 10 cm

13.7.1 Bahan

10.600 bh Plint keramik artistik @ = Rp-

1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.003 M³ Pasir pasang @ Rp68,750.00 = Rp206.25 0.050 Kg Semen warna @ Rp2,875.00 = Rp143.75 Jumlah (1) = Rp1,471.76 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50

Jumlah (1) + (2) = Rp7,859.26 13.7 1 m' Pasang plint keramik ukuran 5 x 20 cm

13.7.1 Bahan

5.300 bh Plint keramik artistik @ = Rp-

0.570 Kg Semen portland @ Rp984.00 = Rp560.88 0.0015 M³ Pasir pasang @ Rp68,750.00 = Rp103.13 0.013 Kg Semen warna @ Rp2,875.00 = Rp37.38 Jumlah (1) = Rp701.38 13.7.2 Tenaga 0.090 Org Pekerja @ Rp30,000.00 = Rp2,700.00 0.090 Org Tukang batu @ Rp35,000.00 = Rp3,150.00 0.009 Org Kepala tukang @ Rp37,500.00 = Rp337.50 0.005 Org Mandor @ Rp40,000.00 = Rp200.00 Jumlah (2) = Rp6,387.50 Jumlah (1) + (2) = Rp7,088.88 13.7 13.7.1 Bahan 5.300 bh Internal cove @ = Rp- 1.140 Kg Semen portland @ Rp984.00 = Rp1,121.76 0.0030 M³ Pasir pasang @ Rp68,750.00 = Rp206.25

BIDANG BANGUNAN

Jumlah (1) = Rp1,615.51

13.7.2 Tenaga

0.750 Org Pekerja @ Rp30,000.00 = Rp22,500.00 0.450 Org Tukang batu @ Rp35,000.00 = Rp15,750.00 0.045 Org Kepala tukang @ Rp37,500.00 = Rp1,687.50 0.038 Org Mandor @ Rp40,000.00 = Rp1,520.00 Jumlah (2) = Rp41,457.50

Jumlah (1) + (2) = Rp43,073.01 13.19 1 m² Pasang lantai marmer ukuran ( 100 x 100 ) cm

13.19.1 Bahan 1.060 bh Marmer @ Rp- = Rp- 8.190 Kg Semen portland @ Rp984.00 = Rp8,058.96 0.045 M³ Pasir pasang @ Rp68,750.00 = Rp3,093.75 0.650 Kg Semen warna @ Rp2,875.00 = Rp1,868.75 Jumlah (1) = Rp13,021.46 13.19.2 Tenaga 0.620 Org Pekerja @ Rp30,000.00 = Rp18,600.00 0.350 Org Tukang batu @ Rp35,000.00 = Rp12,250.00 0.035 Org Kepala tukang @ Rp37,500.00 = Rp1,312.50 0.030 Org Mandor @ Rp40,000.00 = Rp1,200.00 Jumlah (2) = Rp33,362.50

Jumlah (1) + (2) = Rp46,383.96 13.22 1 m² Pasang lantai karpet

13.22.1 Bahan 1.050 m2 Carpet @ Rp- = Rp- 0.350 Kg Lem vinyl @ Rp- = Rp- Jumlah (1) = Rp- 13.22.2 Tenaga 0.170 Org Pekerja @ Rp30,000.00 = Rp5,100.00 0.170 Org Tukang batu @ Rp35,000.00 = Rp5,950.00 0.017 Org Kepala tukang @ Rp37,500.00 = Rp637.50 0.0085 Org Mandor @ Rp40,000.00 = Rp340.00 Jumlah (2) = Rp12,027.50

Jumlah (1) + (2) = Rp12,027.50 13.22

13.22.1 Bahan

1.050 m2 Underlayer / rubber corrugated @ Rp- = Rp-

0.350 Kg Lem @ Rp- = Rp-

Jumlah (1) = Rp-

13.22.2 Tenaga

0.120 Org Pekerja @ Rp30,000.00 = Rp3,600.00 0.120 Org Tukang batu @ Rp35,000.00 = Rp4,200.00 0.012 Org Kepala tukang @ Rp37,500.00 = Rp450.00 0.006 Org Mandor @ Rp40,000.00 = Rp240.00 Jumlah (2) = Rp8,490.00

Jumlah (1) + (2) = Rp8,490.00 13.22 1 m² Pasang lantai parquet