URAI AN ANALI SA ALAT
SATUAN KET.
E. LAIN LAIN KODE KET.
KODE KET. SATUAN KOEF. U R A I A N SATUAN No. KOEF. U R A I A N No.
29. Cutting machine
A. URAIAN PERALATAN
1. Jenis Peralatan Cutting machine
2. Tenaga Pw 3,00 HP
3. Kapasitas Cp 32,00 Ton
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 14.500.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 1.450.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 1.946,51 Rupiah W
b. Asuransi, dll = 0,002 x B F 14,50 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 1.961,01 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 4.641,84 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 1.800,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 634 Rupiah
W
3. Perawatan dan = (12,5 % - 17,5 % ) x B K 906,25 Rupiah perbaikan W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 37.982,47 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 39.943,47 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15,00 % / Tahun 2. Operator alat berat U1 21.428,57 Rp./ Jam 3. Pembantu operator alat berat U2 8.571,43 Rp./ Jam
4. Bensin (industri) Mb 11.783,00 liter
5. Solar (industri) Ms 12.894,00 liter
6. Minyak pelumas Mp 24.000,00 liter
7. PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
30. Dump truck 40 ton
A. URAIAN PERALATAN
1. Jenis Peralatan Dump truck 40 ton
2. Tenaga Pw 260,00 HP
3. Kapasitas Cp 40,00 Ton
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 680.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 68.000.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 91.284,56 Rupiah W
b. Asuransi, dll = 0,002 x B F 680,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 91.964,56 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 402.292,80 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 156.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 29.750 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 42.500,00 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 660.542,80 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 752.507,36 Rupiah
E. LAIN - LAIN SATUAN KOEF. KOEF. KET. KET. KODE KODE SATUAN No. U R A I A N U R A I A N No.
31. Dump truck 20 ton
A. URAIAN PERALATAN
1. Jenis Peralatan Dump truck 20 ton
2. Tenaga Pw 220,00 HP
3. Kapasitas Cp 20,00 Ton
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 494.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 49.400.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 66.315,55 Rupiah W
b. Asuransi, dll = 0,002 x B F 494,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 66.809,55 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 340.401,60 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 132.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 21.613 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 30.875,00 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 554.889,10 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 621.698,65 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15,00 % / Tahun 2. Operator alat berat U1 21.428,57 Rp./ Jam 3. Pembantu operator alat berat U2 8.571,43 Rp./ Jam
4. Bensin (industri) Mb 11.783,00 liter
5. Solar (industri) Ms 12.894,00 liter
6. Minyak pelumas Mp 24.000,00 liter
7. PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
32. Dump truck 7,5 ton
A. URAIAN PERALATAN
1. Jenis Peralatan Dump truck 7,5 ton
2. Tenaga Pw 110,00 HP
3. Kapasitas Cp 7,50 Ton
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 191.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 19.100.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 25.640,22 Rupiah W
b. Asuransi, dll = 0,002 x B F 191,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 25.831,22 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 170.200,80 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 66.000,00 Rupiah
Biaya bengkel (6.25% dan 8.75% ) x B J 8.356 W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 11.937,50 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 286.494,55 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 312.325,77 Rupiah
E. LAIN - LAIN KODE KOEF. KOEF. SATUAN KET. KET. KODE SATUAN No. No. U R A I A N U R A I A N
33. Excavator 80-140 HP
A. URAIAN PERALATAN
1. Jenis Peralatan Excavator 80-140 HP
2. Tenaga Pw 200,00 HP
3. Kapasitas Cp 0,80 M3
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 850.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 85.000.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 114.105,70 Rupiah W
b. Asuransi, dll = 0,002 x B F 850,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 114.955,70 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 309.456,00 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 120.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 37.188 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 53.125,00 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 549.768,50 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 664.724,20 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15,00 % / Tahun 2. Operator alat berat U1 21.428,57 Rp./ Jam 3. Pembantu operator alat berat U2 8.571,43 Rp./ Jam
4. Bensin (industri) Mb 11.783,00 liter
5. Solar (industri) Ms 12.894,00 liter
6. Minyak pelumas Mp 24.000,00 liter
7. PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
34. Flat bed truck 3-4 m³
A. URAIAN PERALATAN
1. Jenis Peralatan Flat bed truck 3-4 m³
2. Tenaga Pw 190,00 HP
3. Kapasitas Cp 10,00 M3
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 330.800.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 33.080.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 44.407,25 Rupiah W
b. Asuransi, dll = 0,002 x B F 330,80 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 44.738,05 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 293.983,20 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 114.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 14.473 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 20.675,00 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 473.130,70 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 517.868,75 Rupiah
E. LAIN - LAIN U R A I A N U R A I A N No. KODE KODE KOEF. KOEF. KET. KET. SATUAN SATUAN No.
35. Fulvi mixer
A. URAIAN PERALATAN
1. Jenis Peralatan Fulvi mixer
2. Tenaga Pw 345,00 HP
3. Kapasitas Cp 2.005,00 -
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 900.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 90.000.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 120.817,80 Rupiah W
b. Asuransi, dll = 0,002 x B F 900,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 121.717,80 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 533.811,60 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 207.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 39.375 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 56.250,00 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 866.436,60 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 988.154,40 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15,00 % / Tahun 2. Operator alat berat U1 21.428,57 Rp./ Jam 3. Pembantu operator alat berat U2 8.571,43 Rp./ Jam
4. Bensin (industri) Mb 11.783,00 liter
5. Solar (industri) Ms 12.894,00 liter
6. Minyak pelumas Mp 24.000,00 liter
7. PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
36. Generator set 135 KVA
A. URAIAN PERALATAN
1. Jenis Peralatan Generator set 135 KVA
2. Tenaga Pw 180,00 HP
3. Kapasitas Cp 135,00 KVA
4. Alat Baru a. Umur Ekonomis A 5,00 Tahun b. Jam Kerja Dalam 1 Tahun W 2.000,00 Jam c. Harga Alat B 207.000.000,00 Rupiah B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 20.700.000 Rupiah 2. Faktor Angsuran Modal = i x (1 + i)^ A D 0,29832 -
(1 + i)^ A - 1 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B - C ) x D E 27.788,09 Rupiah W
b. Asuransi, dll = 0,002 x B F 207,00 Rupiah W
Biaya Pasti per Jam = ( E + F ) G 27.995,09 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (12% -15% ) x Pw x Ms H 278.510,40 Rupiah 2. Pelumas = (2.5% -3% ) x Pw x Mp I 108.000,00 Rupiah Biaya bengkel (6.25% dan 8.75% ) x B J 9.056 Rupiah
W
3. Perawatan dan (12,5 % - 17,5 % ) x B K 12.937,50 Rupiah perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 21.428,57 Rupiah 5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.571,43 Rupiah
Biaya Operasi per Jam = (H+ I + K+ L+ M) P 438.504,15 Rupiah
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 466.499,24 Rupiah
E. LAIN - LAIN