• Tidak ada hasil yang ditemukan

Challenging the Status Quo

N/A
N/A
Protected

Academic year: 2023

Membagikan "Challenging the Status Quo"

Copied!
33
0
0

Teks penuh

(1)

Challenging the Status Quo - An Innovative Approach to the Structural Renewal of a Large Box

Culvert

A collaborative paper by:

• Tara Manning (Brisbane City Council)

• Steven Latimer (Interflow)

(2)

Case Study – Brisbane Corso Park Fairfield

• Project initiation

• Consideration of Options

• Reference Design Specification

• Tendering

• Design

• Construction

Case

Study

(3)

Brisbane

Corso,

Fairfield

(4)

Structure

Original Structure

Extension

Current

Structure

Elevation

(5)

Condition

Prior to

Relining

(6)

Traditional Renewal

Open

Trenching

(7)

Possible Trenchless Alternatives to Dig and Replace

Shotcreting over Steel Reinforcement

Shotcreting with Fibre Reinforced

Concrete

Sliplining with Reinforced Concrete

Sections

Sliplining with Glass Reinforced Plastic

(8)

Design Basis for Structural Relining of Culvert

Culvert Section to

Relined be

Under Road

Way

(9)

Key Design Considerations

Cross Sectional Area Loss

Decay of Existing Structure

Early Structural

Loading

(10)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Environmental Restrictions / Limitations Brisbane Corso Park

• Operational work for temporary waterway barrier works

• Destruction of Marine Plants

• Acid Sulfate Soils (AHD between 1 to 4m)

• Erosion & Sediment Control

• Water quality (discharge limits)

• NALL permit for tree removal

Outlet

(11)

Care of workers

& structure

Traffic Restrictions Congestion Reduction

Unit

Finding

(12)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Geotechnical Data – Fill Over Culvert

(13)

Tendering

RFP

Proposals

Site Meeting

Request for Proposal from Open Market

Looking for Proposals from the Market, Innovation in Design Solutions for a D&C

Independent Structural Liner

Mandatory Tender Site Meeting

(14)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Temporary Propping & Lead times

• Lead time of Channeline from Dubai was 10 weeks

• Residual life of culvert –6 months

Temporary Propping Plan

Weekly

Monitoring

(15)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Tender Award - Interflow

D&C Contract awarded to Interflow who provided:

• Innovative design using Channeline meeting all the mandatory design criteria

• Construction methodology that limited the risk of environmental harm

• Short construction duration minimising impact to traffic

(16)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Glass Reinforced Plastic (GRP)

Structural Lining Systems

(17)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Channeline Properties

• High Mechanical Properties for Design purposes

• Long Term Flexural Modulus 4,000Mpa

• Hydraulic Performance “n” 0.009, “K” 0.03

• Design life of 100 years

(18)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Design Standards

• AS5100 Bridge Design Code

• AS1170 Structural Design Actions

• AS3571 Plastic Piping System GRP

• Water Research Centre – Sewer Rehabilitation Manual

• TMR’s Bridge Design Criteria & Other

Structures

(19)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Design Submission

• Design developed from first principles by SASTTI JV, Sewer Assessment & Trenchless Technology Specialist Consulting Engineers

• Finite element model created

Figure of the FEA Model Combined Stress due to Soil, Hydrostatic and Vehicular Loads

(20)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Construction Design Drawings

• 11 Channeline Sections –10 x 1200mm + 1 x 900mm

• Gap between outside of liner & inside of liner filled with grout

• Timber packers used to hold segments

• Sacrificial rails at base on culvert for installation

(21)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Confirmation of Site Measurements

Prior to Channeline

Material Order

Styrofoam Cut to Shape of Channeline

Used to Confirm ‘Fit’

on Site​

(22)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Installation of Temporary Propping

• Multi prop MP250’ –min. capacity 65kN

• Timber beams along top of culvert (1200mm lengths)

• Diagonal bracing at each end

• Scaffold tubes at top and bottom of props

(23)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Delivery of Channeline

(24)

Construction

(25)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Rails and Winch Set-up

(26)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Unloading Channeline at Site

Tyres Used to Protect Channeline Orientate to Installation Position Lowering to Apron

(27)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Installation into Host Culvert

Lower to Apron Maneuver to Outlet of Culvert Winching into Culvert

(28)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Continuous Inst alla tion

• Timber packers

• Joints sealed between Channeline segments

• Flush finish between segments

(29)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading Temporary

Propping Plan

Weekly Monitoring

Sealing Ends Prior to Grouting

• Build End Seal with Quadex Hyperform

• Install Grout Feed Tubes

• Install Air Bleed Tubes

(30)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Weekly Monitoring

Grouting Operations

• Grout supplied by Boral

• Grouting operation completed in 3 stages

Grout Profile

(31)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Weekly Monitoring

Practical Completion

• Grout tubes were cut and sealed

• Ends Rendered to match existing profile

(32)

Cross Sectional Area Loss

Care of workers

& structure

Early Structural Loading

Weekly Monitoring

Summary

• First time installed in Queensland

• Cost effective alternative to open trench excavation methods

• Less disruptive to residents, traffic and environment

• Confined space suitable

• Overall reduced construction duration

• Construction Duration of 4 weeks (6 days spread over 4 weeks)

Day 1 - Install rails and Winch, remove Propping, install first section of Channeline and packing, reinstate propping

Day 2 –Remove propping, install 8 sections of Channeline and packing, reinstate propping

Day 3 - Remove propping, install last Channeline section, seal ends and install grout and air bleed tubes

3 Days for grout installation and final rendering of culvert ends and demobilisation

(33)

Questions?

Gambar

Figure of the FEA Model Combined Stress due to Soil,  Hydrostatic and Vehicular Loads

Referensi

Dokumen terkait

Bagaimana hubungan kandungan geokimia sedimen dengan biodiversitas mikroorganisme, dominansi dan kerapatan vegetasi ekosistem mangrove dan biodiversitas makrozoobentos

ناور هزﺎﺳ ﻦﻳا ﺖﻴﻤﻫا ﻪﺑ ﻪﺟﻮﺗ ﺎﺑ رد نآ ﻲﺳرﺮﺑ مﺪﻋ و ﻲﺘﺧﺎﻨﺷ يژﻮـﻟﻮﻨﻜﺗ و ﻢـﻠﻋ رد ار ﻲﺳﺎﺳا ﺶﻘﻧ ﻪﻛ نﺎﮕﺒﺨﻧ ﺪﻨﻧﺎﻣ ﻲﻤﻬﻣ ﻪﻌﻣﺎﺟ ﻲﻣ ﺎﻔﻳا رﻮﺸﻛ ﻚﻳ بﺎﺗ توﺎﻔﺗ ﻪﻌﻟﺎﻄﻣ فﺪﻫ ﺎﺑ ﺶﻫوﮋﭘ ﻦﻳا ،ﺪﻨﻨﻛ نﺎﮕﺒﺨﻧ