Project Management

(2)

The Elements of Project Management

CPM/PERT Networks

Probabilistic Activity Times

Microsoft Project

Project Crashing and Time-Cost Trade-Off

Formulating the CPM/PERT Network as a Linear

Programming Model

(3)

■ Network representation is useful for project analysis.

■ Networks show how project activities are organized and are used to determine time duration of projects.

■ Network techniques used are:

▪ CPM (Critical Path Method)

▪ PERT (Project Evaluation and Review Technique) ■ Developed independently during late 1950’s.

(4)

Elements of Project Management

■ Management is generally perceived as concerned with planning, organizing, and control of an ongoing process or activity.

■ Project Management is concerned with control of an activity for a relatively short period of time after which management effort ends. ■ Primary elements of Project Management to be discussed:

 Project Planning

 Project Team

(5)

8-5

Elements of Project Management

Project Planning

Risk and Problem Analysis

(6)

■ Project team typically consists of a group of individuals from various areas in an organization and often includes outside consultants.

■ Members of engineering staff often assigned to project work. ■ Project team may include workers.

■ Most important member of project team is the project manager.

■ Project manager is often under great pressure because of uncertainty inherent in project activities and possibility of failure. Potential

rewards, however, can be substantial.

■ Project manager must be able to coordinate various skills of team members into a single focused effort.

(7)

Figure 8.1 The project management process

(8)

Elements of Project Management

Scope Statement

■ Document providing common understanding of project.

■ Justification describing the factors giving rise to need for project.

Expected results and what constitutes success.

■ List of necessary documents and planning reports.

Statement of work (SOW) - a planning document for

individuals, team members, groups, departments, subcontractors and suppliers, describing what are required for successful

(9)

Elements of Project Management

Work Breakdown Structure (WBS) (1 of 2)

WBS breaks down project into major components (modules).

Modules are further broken down into activities and, finally, into individual tasks.

■ Identifies activities, tasks, resource requirements and relationships

between modules and activities.

■ Helps avoid duplication of effort.

■ Basis for project development, management , schedule, resources and

modifications.

■ Approaches for WBS development:

(10)

Figure 8.2 WBS for Computer Order-processing System Project

(11)

Elements of Project Management

Responsibility Assignment Matrix (1 of 2)

■ Project manager assigns work elements to organizational units, departments, groups, individuals or subcontractors.

■ Uses an organizational breakdown structure (OBS).

■ OBS is a table or a chart showing which organizational units are responsible for work items.

■ OBS leads to the responsibility assignment matrix (RAM)

■ RAM shows who is responsible for doing the necessary work in the project

(12)

Elements of Project Management

(13)

Elements of Project Management

Project Scheduling

■ Project Schedule evolves from planning documents, with focus on timely completion.

■ Critical element in project management – source of most conflicts and problems.

■ Schedule development steps:

1. Define activities, 2. Sequence activities, 3. Estimate activity times, 4. Construct schedule.

Gantt chart and CPM/PERT techniques can be useful.

(14)

Elements of Project Management

Gantt Chart (1 of 2)

■ Popular, traditional technique, also known as a bar chart -developed by Henry Gantt (1914).

■ Direct precursor of CPM/PERT for monitoring work progress.

■ A visual display of project schedule showing activity start and finish times and where extra time is available.

■ Suitable for projects with few activities and precedence relationships.

(15)

Elements of Project Management

Gantt Chart (2 of 2)

(16)

Elements of Project Management

Project Control

■ Process of ensuring progress toward successful completion.

■ Monitoring project to minimize deviations from project plan and schedule.

■ Corrective actions necessary if deviations occur.

■ Key elements of project control

 Time management

 Cost management

 Performance management

(17)

■ A branch reflects an activity of a project.

■ A node represents the beginning and end of activities, referred to as

events.

■ Branches in the network indicate precedence relationships. ■ When an activity is completed at a node, it has been realized.

The Project Network

CPM/PERT

(18)

■ Network aids in planning and scheduling.

■ Time duration of activities shown on branches.

■ Activities can occur at the same time (concurrently).

■ A dummy activity shows a precedence relationship but reflects no passage of time.

■ Two or more activities cannot share the same start and end nodes.

The Project Network

Concurrent Activities

(19)

The Project Network

House Building Project Data

(20)

The Project Network

AOA Network for House Building Project

Figure 8.6

(21)

The Project Network

AON Network for House Building Project

Activity-on-Node (AON) Network

A node represents an activity, with its label and time shown on the node  The branches show the precedence relationships

 Convention used in Microsoft Project software

(22)

The Project Network

Paths Through a Network

Table 8.1

Paths Through the House-Building Network

Path

Events

A

1

2

4

7

B

1

2

5

6

7

C

1

3

4

7

(23)

The critical path is the longest path through the network; the

minimum time the network can be completed. From Figure 8.8:

(24)

The Project Network

Activity Start Times

(25)

The Project Network

Activity-on-Node Configuration

(26)

■ ES is the earliest time an activity can start: ES = Maximum (EF) ■ EF is the earliest start time plus the activity time: EF = ES + t

The Project Network

Activity Scheduling : Earliest Times

(27)

■ LS is the latest time an activity can start without delaying critical path time: LS = LF - t

■ LF is the latest finish time. LF = Minimum (LS)

The Project Network

Activity Scheduling : Latest Times

(28)

Slack is the amount of time an activity can be delayed without delaying the project: S = LS – ES = LF - EF

Slack Time exists for those activities not on the critical path for which the earliest and latest start times are not equal.

Shared Slack is slack available for a sequence of activities.

(29)

The Project Network

Activity Slack Time (2 of 2)

(30)

Activity time estimates usually cannot be made with

certainty.

PERT used for probabilistic

activity times.

(31)

Probabilistic Activity Times

Example (1 of 3)

(32)

Probabilistic Activity Times

Example (2 of 3)

(33)

Probabilistic Activity Times

Example (3 of 3)

(34)

Expected project time is the sum of the expected times of the critical path activities.

Project variance is the sum of the critical path activities’ variances

■ The expected project time is assumed to be normally distributed

(based on central limit theorem).

■ In example, expected project time (tp) and variance (vp) interpreted as the mean () and variance (2) of a normal distribution:

= 25 weeks

2 = 62/9

= 6.9 (weeks)2

Probabilistic Activity Times

(35)

Using the normal distribution, probabilities are determined

by computing the number of standard deviations (Z) a

value is from the mean.

The Z value is used to find corresponding probability in

Table A.1, Appendix A.

(36)

Probability Analysis of a Project Network (2 of 2)

(37)

What is the probability that the new order processing system will be Appendix A. Probability of completing project in 30 weeks or less: (.5000 + .4713) = .9713.

(38)

Probability Analysis of a Project Network

Example 1 (2 of 2)

(39)

■ A customer will trade elsewhere if the new ordering system is not working within 22 weeks. What is the probability that she will be retained?

Z = (22 - 25)/2.63 = -1.14

■ Z value of 1.14 (ignore negative) corresponds to probability of .3729 in Table A.1, appendix A.

■ Probability that customer will be retained is .1271

(40)

Probability Analysis of a Project Network

Example 2 (2 of 2)

(41)

CPM/PERT Analysis with

(42)

CPM/PERT Analysis with

(43)

Microsoft Project handles only AON networks.

Analysis with Microsoft Project (1 of 13)

(44)

Analysis with Microsoft Project (2 of 13)

(45)

Analysis with Microsoft Project (3 of 13)

(46)
(47)

Figure 8.7

(48)

Analysis with Microsoft Project (6 of 13)

(49)

Exhibit 8.9

(50)

Analysis with Microsoft Project (8 of 13)

(51)

Exhibit 8.11

(52)
(53)
(54)

Exhibit 8.14

(55)
(56)

■ Project duration can be reduced by assigning more resources to project activities.

■ However, doing this increases project cost.

■ Decision is based on analysis of trade-off between time and cost.

Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time.

Project Crashing and

(57)

Project Crashing and Time-Cost Trade-Off

Example Problem (1 of 5)

(58)

Project Crashing and Time-Cost Trade-Off

Example Problem (2 of 5)

Figure 8.20

Crash cost & crash time have a linear relationship:

(59)
(60)

Figure 8.21 Network with Normal Activity Times and Weekly Crashing Costs

(61)

Figure 8.22

Revised Network with Activity 1 Crashed

Project Crashing and Time-Cost Trade-Off

Example Problem (5 of 5)

(62)
(63)

Project Crashing and Time-Cost Trade-Off

General Relationship of Time and Cost (1 of 2)

Project crashing costs and indirect costs have an

inverse

relationship.

Crashing costs are highest when the project is shortened.

Indirect costs increase as the project duration increases.

(64)

Project Crashing and Time-Cost Trade-Off

General Relationship of Time and Cost (2 of 2)

(65)

General linear programming model with AOA convention:

The objective is to minimize the project duration (critical path time).

The CPM/PERT Network

Formulating as a Linear Programming Model

(66)

The CPM/PERT Network

Example Problem Formulation and Data (1 of 2)

(67)

Minimize Z = x

1

+ x

2

+ x

3

+ x

4

+ x

5

+ x

6

+ x

7

The CPM/PERT Network

(68)

The CPM/PERT Network

Example Problem Solution with Excel (1 of 4)

(69)

Exhibit 8.18

The CPM/PERT Network

(70)

The CPM/PERT Network

(71)

Exhibit 8.20

The CPM/PERT Network

(72)

Minimize Z = $400y12 + 500y23 + 3000y24 + 200y45 + 7000y46

Project Crashing with Linear Programming

Example Problem

Model Formulation

(73)
(74)
(75)
(76)

Given this network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.

Example Problem

(77)

Example Problem

(78)

6

Example Problem Solution (1 of 4)

(79)

Example Problem Solution (2 of 4)

(80)

Example Problem Solution (3 of 4)

Step 3: Identify the critical path and compute expected completion time and variance.

 Critical path (activities with no slack): 1  3  5  7

 Expected project completion time: tp = 9+5+6+4 = 24 days

(81)

Example Problem Solution (4 of 4)

Step 4: Determine the Probability That the Project Will be Completed in 28 days or less (µ = 24,  = 5)

Z = (x - )/ = (28 -24)/5 = 1.79

Gambar

Figure 8.1     The project management process
Figure 8.2   WBS for Computer Order-processing System Project
Figure 8.3    A responsibility assignment matrix Copyright © 2010 Pearson Education, Inc
Figure 8.4   A Gantt chart
+7

Referensi

Dokumen terkait

As an application we determine the exact and approximate probability that the first card has the uniquely highest rank among the top l cards of a standard card deck..

The grant recipient must disclose to MOSTI in writing, of the existence of the Project Intellectual Property not later than 60 days from the Project Completion

Determine earliest start, earliest finish, latest start, latest finish, and slack times for each activity, along with the total project..

Location : Bulacan State University, City of Malolos, Bulacan ABC : Php 1,999,163.44 Completion Date : Forty Five 45 Calendar Days The prospective bidder must have completed a Single

National 2013 Completed Research Project SI.NO Name of the project Investigators Year of Completion 1 “HISTOPATHOLOGY IN NORMALLY APPEARING FALLOPIAN TUBES REMOVED DURING

PERT Method PERT Method • Do CPM using its Mean D for th e duration of each activity • CPM yields the Mean project du ration • The variance of project duratio n T VarT = sum of

d Fixed and Flexible Budget pñWa Ed§ bmoMXma ~OQ> 12 From the following information find out material cost variance, price variance, usage variance, mix variance and yield variance:

Accuracy %: number of correct answers out of those completed The completion and accuracy percentages allow one to track 2 things: • How quickly they are answering in the given time