• Tidak ada hasil yang ditemukan

Format Penilaian Refrigeration LKS 2017

N/A
N/A
Protected

Academic year: 2017

Membagikan "Format Penilaian Refrigeration LKS 2017"

Copied!
9
0
0

Teks penuh

(1)

Skill name

Refrigeration and Air Conditioning

Criteria

Mark

Mark

A

Component Fabrication

12.00

12.000

B

Component & System Installation

20.00

20.000

C

Electrical Installation

12.00

12.000

D

Commissioning & Adjustment

24.00

24.000

E

Mechanical Fault Finding & Repair

10.00

10.000

F

Refrigerant Recovery & Emission control

13.00

13.000

G

Work practices and Safety

9.00

9.000

Total

100.00

100.000

Sub

Criteria

ID

WSSS

Section

Sub - Criteria

Name or Description

Aspect

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

0

Add - (Extra Aspect Information)

A1 Module A: Copper Fabrication 1 O Fabricated headers has inlet and outlets pipes arrangesd as per specifications at 90 degress to headers 1st side 0 - 1 degree

0.40

1 - 3 degree 0.20

>3 degree 0.00

2nd side 0 - 1 degree 0.40

1 - 3 degree 0.20

>3 degree 0.00

2 O Fabricated headders are squared and lies flat on the tables A1 0 - 1 mm 0.80

1 - 3 mm 0.40

>3 mm r 0.00

3 O Fabricated headders arranges as per specifications at 90 degrees to 1/2" soft drawn copper tubes 0 - 1 degree 0.80

1 - 3 degree 0.40

>3 degree 0.00

4 O Overall width D1 is as per specifications 1st Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

2nd Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

5 O Overall width D2 is as per specifications 1st Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

2nd Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

6 O Overall width D3 is as per specifications 1st Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

2nd Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

(2)

7 O Overall width D4 is as per specifications 1st Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

2nd Side 0 - 1 mm refer drawing 0.40

1 - 3 mm refer drawing 0.20

>3 mm refer drawing 0.00

8 O Overall width D5 is as per specifications 1st Side 0 - 1 mm refer drawing 0.20

1 - 3 mm refer drawing 0.10

>3 mm refer drawing 0.00

2nd Side 0 - 1 mm refer drawing 0.20

1 - 3 mm refer drawing 0.10

>3 mm refer drawing 0.00

3rd Side 0 - 1 mm refer drawing 0.20

1 - 3 mm refer drawing 0.10

>3 mm refer drawing 0.00

4st Side 0 - 1 mm refer drawing 0.20

1 - 3 mm refer drawing 0.10

>3 mm refer drawing 0.00

9 O Fabricated copper tube is leak tight on first attemp Pressure tested to 10 bars +/- 1.50

10 O Brazed joint B1 is made to acceptable standard Yes/No 2% solder used 0.40

11 O Brazed joint B2 is made to acceptable standard Yes/No 2% solder used 0.40

12 O Brazed joint B3 is made to acceptable standard Yes/No 2% solder used 0.40

13 O Brazed joint B4 is made to acceptable standard Yes/No 2% solder used 0.40

14 O Brazed joint B5 is made to acceptable standard Yes/No 2% solder used 0.40

15 O Nitrogen was used while brazing a pipework 0.50

16 O The competitor prevented moisture contamination inside the pipe during the assembly process. Yes LIVE MARKING 0.50

17 O The bare coil is fabricated according to the drawing and specification. Yes 0.70

18 O No extra material used due to mistake during the process Yes LIVE MARKING 0.40

(3)

Sub

Criteria

ID

WSSSS

section

Sub - Criteria

Name or Description

Aspect no

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

B1 Module B - Major Components 19 O Electrical switchboard installed in specified location and securely fixed to wall 0.4

20 O Condensing unit installed in specified location and securely fixed to cradle 0.4

21 O Tube in tube heat exchanger installed in specified location and securely fixed to wall 0.4

22 O Glycol tank is installed as speciffied 0.4

23 O Fabricated copper coil installed in ice ring as specified 0.2

24 O All pipework is installed within boundaries of supplied cradle 0.4

B2 Module B - Refrigerant Controls 25 O TXV installed in correct location in system, with correct flow and as per manufacturer instruction. 0.50

26 O Sigh glass & filter dryer installed in correct location in system with correct flow direction Yes 0.50

27 O Dual pressure control pipes installed as per specification Yes 0.50

28 O Pressure control is leveled and securely mounted to wall Yes 0.30

B3 Module B - Low Presure Vapor Lines 29 O All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight. Yes 0.30

30 O All bends of appropriate radius with no kinks Yes 0.10

31 O Suction line is securely fastened using appropriate method Yes 0.30

32 O Installed pipe work does not rub on any components when operating (fan blades, penetration, etc) Yes 0.20

33 O Nitrogen was used while brazing a pipework LIVE MARKING 0.20

34 O Brazed joint 1 is made to acceptable standard 0.40

35 O Suction, low pressure liquid and low pressure lines are set out so that these pipes don't cross each other. 0.20

36 O All Suction line is neatly insulated the entire length of the installation Yes 0.20

37 0 Single gauge installed as specified and standard 0.20

B4 Module B - High Pressure Liquid Line 38 O All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight. Yes 0.30

39 O All bends of appropriate radius with no kinks 0.10

40 O Liquid line is securely fastened using appropriate method 0.30

41 O Installed pipe work does not rub on any components when operating (fan blades, penetration, etc) Yes 0.20

42 O Nitrogen was used while brazing a pipework LIVE MARKING 0.20

43 O Brazed joint 2 is made to acceptable standard 0.40

44 0 Single gauge installed as specified and standard 0.20

B6 Module B - High Pressure Discharge Line 45 O All pipe installed in vertical and horizontal planes and the pipe work is vertically and horizontally straight. Yes 0.30

46 O All bends of appropriate radius with no kinks 0.10

47 O High Pressure line is securely fastened using appropriate method 0.30

48 O Installed pipe work does not rub on any components when operating (fan blades, penetration, etc) Yes 0.20

49 O Nitrogen was used while brazing a pipework LIVE MARKING 0.20

50 O Brazed joint 3 is made to acceptable standard 0.40

(4)

B6 Module B - Tube in Tube Heat Exchanger 52 O Heat Exchanger is piped as per diagram 0.50

53 O Brazed joint 4 on refrigerant side of heat exchanger is acceptable 0.40

54 O Glycol pipework installed as per diagram 0.40

55 O All glycol pipework lines are insulated 0.20

56 O Glycol pipework has no kinks on copper and plastic tubing 0.10

57 O All pipe work does not rub on any components when operating (fan blades, penetration, etc) 0.10

58 O All pipe installed in vertical and horizontal planes. 0.20

59 O Glycol line is securely fastened using appropriate method 0.10

60 O Brazed joint 5 on glycol side heat exchanger is acceptable 0.40

B7 Module B - Pressure Test 61 O Starting presure of all attempts meet required standards 0.50

62 O The appropriate valves were opened to ensure pressure testing of entire system 0.40

63 O Gauge were correctly fitted to the system 0.20

64 O Nitrogen was safely added to the system to the desired test pressure 0.40

65 O System was leak tested while under pressure 0.20

66 O No leaks were detected on FIRST pressure attempt 2.00

67 O System held pressure for complete standing time after any leaks repaired 0.50

68 O Nitrogen was released from system at completion of pressure test. 0.20

69 O The service manifold gauge lines were removed with minimal refrigerant loss Yes 0.30

B8 Module B - Evacuation 70 O Vacuum level (value) of all atempts meet required standards 0.50

71 O The appropriate valve were opened to ensure evacuation of the entire system Yes/No 0.20

72 O Vacuum gauge installed so it can be isolated from vacuum pump and still measure system Yes/No 0.20

73 O The vacuum held when isolated from the vacuum pump for 10 minutes after FIRST attempt 2.00

74 O The vacuum held when isolated from the vacuum pump for 10 minutes after FINAL attempt Yes/No 0.50

20.00

Sub

Criteria

ID

WSSS

section

Sub - Criteria

Name or Description

Aspect

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

C1 Module B - Connect the Electrical Circuit 75 O All wiring installed as per supplied drawing Yes/No 0.50

76 O Supply voltage is wired correctly on supplied plug Yes/No 0.50

77 O 220V supply wired to correct terminals in switchboard, and correctly terminated Yes/No 0.50

78 O Condensing unit wired to correct terminal in switchboard, and correctly terminated Yes/No 0.50

79 O Pressure control wired to correct terminal in switchboard, and correctly terminated Yes/No 0.50

80 O Glycol pump wired to correct terminal in switchboard, and correctly terminated Yes/No 0.50

81 O All cables saddled (fixed) and secured separate to piping Yes/No 0.80

82 O Installed cables not to be crush by piping or other components Yes/No 0.50

83 O Installed cables and wires installed as per test project for adequate protection Yes/No 0.50

(5)

C2 Module B - Connect the Electronic Controls 85 O Temperature probe is wired to the correct terminals in switchboard, and terminated correctly 0.50

86 O Temperature probe is installed in conduit/cable trunking correctly Yes/No 0.30

87 O Conduit/cable trunking is verticaly and horizontaly leveled and securely fastened Yes/No 0.30

88 O Before turning the power on: the Earth circuit was correctly tested for continuity Yes/No 0.50

89 O Before turning the power on: the Neutral circuit was correctly tested for continuity Yes/No 0.50

C3 Module B - Electrical Testing 90 O Installation tested for earth continuity to power supply 0.50

91 O Installation tested for earth continuity to condensing unit proir to energising Yes/No 0.50

92 O Installation tested for earth leakage proir energising Yes/No 0.50

93 O Installation tested for short between active and neutral prior energising Yes/No 0.50

94 O No wiring fault found on circuit testing Yes/No 0.50

95 O Circuit energised safely the first time without blowing fuses/circuit breaker/etc Yes/No 1.00

96 O circuit operated safely and correctly the first time without wiring modifications Yes/No 0.50

97 O Circuit operated safely and correctly after any necessary modifications Yes/No 0.50

12.00

Sub

Criteria

ID

WSSS

section

Sub - Criteria

Name or Description

Aspect

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

D1 Module B - Charge with Refrigerant Primary Circuit 98 O The correct valves were opened prior to operation 0.40

99 O Liquid refrigeration was added to the liquid line only (not suction) no leakage 1.00

100 O The correct refrigerant charge weighed into the system and recorded, using an acceptable method 1.00

101 O Amount of refrigerant added is within acceptable guidelines Yes 0.80

102 O Electronic leak check was made during charging of refrigerant Yes 1.00

103 O The gauge were removed from the system with no avoidable loss of refrigerant 0.80

D2 Module B - Charge with Refrigerant Secondary Circuit 104 O Water added to the system was measured to ensure 60% water by volume and a 40% glycol by volume 1.00

105 O Glycol pump circulated prior to any refrigeration being energised 0.50

D3 Module B - Commissioning report 106 O Commissioning report - Ambient temperature is recorded correctly 0.40

107 O Commissioning report - Refrigerant type is recorded correctly Yes 0.40

108 O Commissioning report - Mass of refrigerant is recorded correctly Yes 0.40

109 O Commissioning report - Suction pressure is recorded correctly Yes 0.40

110 O Commissioning report - Discharge pressure is recorded correctly Yes 0.40

111 O Commissioning report - Condenser subcooling measured and recorded correctly Yes 0.40

112 O Commissioning report - Total system superheat measured and recorded correctly Yes 0.40

113 O Commissioning report - LP control cut in set and cut out are set and recorded correctly Yes 0.60

114 O Commissioning report - HP cut out is set and recorded correctly Yes 0.60

115 O Commissioning report - Capacity regulator is set and recorded correctly Yes 0.50

116 O Commissioning report - Glycol supply and return temperature to and from ice rink recorded correctly 0.40

(6)

D4 Module B - Commissioning; Complete Installation 119 O Project completed requiring no additional materilas 0.30

120 O Covers installed securely on all equipment Yes 0.30

121 O Correct refrigerant type was recorded Yes 0.30

122 O No burn marks and no damage on any equipment from installation 0.70

123 O System left operation at completion of module 0.50

124 O After minimum 12hrs run time there is NO water present above the fabricated copper tubing submerged in the ice ring 1.00

125 O The control was correctly programmed as per test project specifications 0.50

D5 Module C - Commissioning Report 126 O Commissioning Report - Ambient temperature measured and recorded correctly. 0.30

127 O Commissioning Report - return air temperature dry bulb/wet bulb measured, recorded and plotted correctly Yes/No 1.00

128 O Commissioning Report - supply air temperature dry bulb/wet bulb measured, recorded and plotted correctly Yes/No 1.00

129 O Commissioning Report - Indoor fan speed and mode of operation selected and recorded correctly Yes/No 0.30

130 O Commissioning report - Refrigerant type is recorded correctly Yes/No 0.40

131 O Commissioning report - Suction pressure is recorded correctly Yes/No 0.50

132 O Commissioning report - Total system superheat measured and recorded correctly Yes/No 0.50

133 O Commissioning report - Condensing unit operating current measured and recorded correctly Yes/No 0.50

134 O Commissioning report - Indoor fan operating current measured and recorded correctly Yes/No 0.50

135 O Supply and return air conditions were joined to indicate cooling process Yes/No 0.50

O

D6 Module C - Commissioning - Complete Installation 136 O Project completed requiring no additional materilas Yes/No 0.50

137 O Covers installed securely on all equipment Yes/No 0.50

138 O No burn marks and no damage on any equipment from installation Yes/No 0.70

139 O Installation not damaged in any ways Yes/No 0.50

140 O System left in correct operation Yes/No 0.50

24.00

Sub

Criteria

ID

WSSS

section

Sub - Criteria

Name or Description

Aspect

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

E1 ModuleC - Mechanical Fault Finding 141 O The unit was tested for short circuit, insulation resistance and earth continuity prior to energising 1.00

142 O The fault was correctly identified, repaired, recorded and reclaim started in under 30 minutes 3.00

143 O The fault was correctly identified, repaired, recorded and reclaim started in under 60 minutes 2.50

144 O The fault was correctly identified, repaired, recorded and reclaim started in under 90 minutes 2.00

145 O The fault was correctly identified, repaired, recorded and reclaim started in under 120 minutes 1.50

(7)

Sub

Criteria

ID

WSSS

section

Sub - Criteria

Name or Description

Asepct

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

F1 Module C - Reclaim Refrigerant 146 O Power supply to air conditioner was isolated before refrigerant recovery started 0.60

147 O Service manifold gauge lines were fitted to the system in the correct way with minimal loss of refrigerant 0.50

148 O Moisture contamination was prevented without loss of refrigerant 0.50

149 O The correct refrigerant cylinder was selected for the recovery of refrigerant 0.40

150 O Refrigerant cylinder weighed and recorded before recovery started 1.00

151 O Refrigerant recovery lines set up was correct first time 1.00

152 O The full refrigerant charge was removed from the system using recovery machine 1.00

153 O Electronic leak check was made during recovery of refrigerant 1.00

154 O Syetem pressure were at atmospheric pressure or below after recovery was completed 1.00

155 O All service caps repalced on the recovery unit and recovery cylinder 0.50

156 O The quantity of refrigernat recovered from the system was recorded 0.50

F2 Module C - Evacuation 157 O First vacuum attemp meets required standards 1.00

158 O The vacuum held when isolated from vacuum pump for 10 minutes after any attempt 1.50

F3 Module C - Charge with Refrigerant 159 O The correct refrigerant charge weighed into the system and recorded, using an accetable method 1.00

160 O Amount of refrigerant added is within accetable guidelines 1.00

161 O The gauges were removed from the system with the minimals loss of refrigerant. 0.50

13.00

Sub

Criteria

ID

WSSS

section

Sub - Criteria

Name or Description

Aspect

No

Aspect

Type

O = Obj

S = Sub

Aspect - Description

For Objective Assessment Only

Max

Mark

Requirement

or Nominal

Size

Add - (Extra Aspect Information)

G1 Module A - Work Practices and safety 162 O Protective gloves were worn at all times when exposed to heat sources 0.50

163 O Protective eye wear was worn at all times while brazing 1.00

164 O The competitors always used the correct tools and safe work practices for every actvity 0.50

165 O The competitors brazing torches and regulators are left at atmospheric prssure on completion of modules 1.00

G2 Module B - Work Practices and safety 166 O Protective gloves were worn at all times when exposed to heat sources and cut hazards 0.50

167 O Protective eye wear was worn at all times while brazing, drilling, handling refrigerant, glycol and nitrogen 1.00

168 O The competitors always used the correct tools and safe work practices for every actvity 0.50

169 O The competitors brazing torches and regulators are left at atmospheric prssure on completion of modules 1.00

G3 Module C - Work Practices and safety 170 O Protective gloves were worn at all times when exposed to heat sources and cut hazards 0.50

171 O Protective eye wear was worn at all times while brazing, drilling, handling refrigerant and nitrogen 1.00

172 O The competitors always used the correct tools and safe work practices for every actvity 0.50

(8)

Skill name

Refrigeration and Air Conditioning

Criteria

Marks

Modules

Section

Criterion

Objective

Total

Section

Criterion

A

B

A

Component Fabrication

12

12

A

Component Fabrication

12

B

Component & System Installation

20

20

B

Component & System Installation

20

C

Electrical Installation

12

12

C

Electrical Installation

12

D

Commissioning & Adjustment

24

24

D

Commissioning & Adjustment

15

E

Mechanical Fault Finding & Repair

10

10

E

Mechanical Fault Finding & Repair

F

Electrical Fault Finding & Repair

0

0

F

Electrical Fault Finding & Repair

G

Refrigerant Recovery & Emission

control

13

13

G

Refrigerant Recovery & Emission

control

5

H

Work practices and Safety

9

9

H

Work practices and Safety

3

3

(9)

Modules

Total

C

12

20

0

12

9

24

10

10

0

8

13

3

9

Referensi

Dokumen terkait

BerkatRidho-Nya penulis mampu menyelesaikan skripsi yang berjudul “ Penyesuaian diri pada wanita yang melakukan perkawinan campur ” untuk memenuhi syarat memperoleh

Dalam proses pembelajaran tentang kompetensi dasar: ‘mengidentifikasi kebutuhan tubuh agar tumbuh sehat dan kuat (makanan, air, pakaian, udara, lingkungan sehat)’, guru tampak

Hasil penelitian ini menunjukkan bahwa secara simultan saat ratio (CR), debt to equity ratio (DER), rasio hutang terhadap aset (DAR), perputaran total aset (TATO), dan price

POKJA ULP PEKERJAAN PEMELIHARAAN GEDUNG DAN BANGUNAN STAIN PEKALONGAN TAHUN ANGGARAN 20131. PEMBERITAHUAN Nomor :

Sebagai kelanjutan proses pelelangan ini, kami mengundang saudara untuk menghadiri tahapan verifikasi dan pembuktian kualifikasi paket pekerjaan Peningkatan Jaringan Irigasi D.I

Setiap tumor dengan metastasis pada kelenjar limfe hilus tau mediastinal kontralateral, atau pada kelenjar limfe skalenus atau supraklavikular; atau setiap

Adapun nomina adalah jenis atau kategori kata yang mengandung konsep atau makna kebendaan baik yang bersifat konkret atau abstrak (Wedhawati, dkk., 20006:219).. (8) Yang

Tipikal jawara yang di luar komunitas para kiai di atas, lebih jauh secara historis dikemukakan Kartodirdjo (1984:56-164) bahwa pada saat kesultanan Banten dihapuskan