PEKERJAAN MEKANIKAL DAN ELEKTRIKAL

PROYEK RUMAH SAKIT - SARI ASIH CIPUTAT, TANGERANG

NO. URAIAN BIAYA

(Rp)

A. PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan 227,600,000

2 Perizinan PLN (1000 KVA) 150,000,000

3 Perizinan PT Telkom Indonesia 9,600,000 4 Perizinan PAL (Pembuangan air limbah) 12,000,000

B. PEKERJAAN MEKANIKAL

1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000 2 Pekerjaan Sistem Transportasi (Lift) 1,373,000,000

3 Pekerjaan Sistem Plumbing 1,997,681,188

4 Seawage Treatment Plant (STP) 456,997,000

5 Pekerjaan Sistem Fire Fighting 2,845,815,864

6 Pekerjaan Sistem Gas Medic 1,553,439,767

C. PEKERJAAN ELEKTRIKAL

1 Pekerjaan Sistem Listrik 4,512,322,298

2 Pekerjaan Sistem Genset 1,914,503,750

3 Pekerjaan Sistem Penangkal Petir 41,400,000 4 Pekerjaan Sistem Telepon dan Data 294,710,000

5 Pekerjaan Sistem Tata Suara 141,120,000

6 Pekerjaan Fire Alarm 372,454,520

7 Pekerjaan Sistem MATV 112,926,000

8 Pekerjaan Sistem CCTV 288,495,320

9 Pekerjaan Sistem Nurse Call 1,651,986,275

Total A + B + C 20,249,933,982

Keuntungan Pemborong 10% 2,024,993,398

Sub total A + B + C + Keuntungan Pemborong 22,274,927,380

PPN 10 % 2,227,492,738

TOTAL 24,502,420,119

(2)

NO. URAIAN BIAYA (Rp)

A. PEKERJAAN PERSIAPAN

1 Pekerjaan Persiapan 227,600,000

2 Perizinan PLN (1000 KVA) 150,000,000

3 Perizinan PT Telkom Indonesia 9,600,000 4 Perizinan PAL (Pembuangan air limbah) 12,000,000

B. PEKERJAAN MEKANIKAL

1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000

2 Pekerjaan Sistem Transportasi (Lift) ( By Owner )

3 Pekerjaan Sistem Plumbing 1,997,681,188

4 Seawage Treatment Plant (STP) ( By Owner )

5 Pekerjaan Sistem Fire Fighting 2,845,815,864

6 Pekerjaan Sistem Gas Medic ( By Owner )

C. PEKERJAAN ELEKTRIKAL

1 Pekerjaan Sistem Listrik 4,512,322,298

8 Pekerjaan Sistem Genset ( By Owner )

2 Pekerjaan Sistem Penangkal Petir 41,400,000 3 Pekerjaan Sistem Telepon dan Data 294,710,000

4 Pekerjaan Sistem Tata Suara 141,120,000

5 Pekerjaan Fire Alarm 372,454,520

6 Pekerjaan Sistem MATV 112,926,000

7 Pekerjaan Sistem CCTV 288,495,320

9 Pekerjaan Sistem Nurse Call 1,651,986,275

Total A + B + C 14,951,993,465

Keuntungan Pemborong 10% 1,495,199,347

Sub total A + B + C + Keuntungan Pemborong 16,447,192,812

PPN 10 % 1,644,719,281

TOTAL 18,091,912,093

(3)

PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN

PEKERJAAN PERSIAPAN

No Uraian Qty Sat H.Sat (Rp)

Pekerjaan Persiapan

1 Biaya -biaya pengadaan staf dan peralatan kantor yang akan 1 lot 40,000,000 mengelola pelaksanaan pekerjaan dan mengurus segala hal

yang berhubungan dengan administrasi proyek (mobilisasi)

2 Biaya - Biaya pemindahan peralatan kantor dan staff yang 1 lot 25,000,000 telah dipergunakan untuk pelaksanaan proyek (demobilisasi)

3 Pemborong harus mengadakan peralatan kerja yang cukup, 1 lot 100,000,000 jumlah kualitas dan kapasitasnya untuk melaksanakan

peker-jaan yang dimaksudkan dalam dokumen tender ini.

Termasuk dalam biaya ini adalah pembuatan dan pembong -karan serta perampihan kembali tempat penyimpanan barang.

4 Pembuatan dan penggandaan dokumen kontrak lengkap gam- 1 lot 2,000,000 bar-gambar kontrak sebanyak lima (5) set, dimana 4(empat)

set diberikan kepada pemberi tugas.

5 Pembuatan gambar- gambar pelaksanaan /shop drawing, gam- 1 lot 5,000,000 bar-gambar yang telah dilaksanakan /as built drawing yang

ha-rus diberikan kepada pemberi tugas dalam bentuk kalkir 1(satu) set dan 2(dua) set blue print.

6 Pengadaan contoh - contoh bahan yang dikehendaki oleh pem- 1 lot incl beri tugas atau wakilnya sesuai dengan spesifikasi tehnis yang

dipersyaratkan dalam dokumen tender harus segera diadakan tanpa keterlambatan

7 Pemborong harus mengangkat keluar lokasi proyek semua 1 lot 15,000,000 sampah-sampah hasil pekerjaan secara teratur sehingga

kea-daan lapangan selalu bersih. Termasuk didalamnya pengakea-daan tempat sampah sementara dan peralatan kebesihannya.

8 Pemborong harus penyiapkan kantor proyek untuk wakil pem- 1 lot 12,000,000 beri tugas termasuk didalamnya kantor pemborong lengkap

dengan lampu penerangan dan instalasinya.

9 Pengadaan peralatan pencegahan terhadap bahan kebakaran 1 lot 600,000 berupa APAR dan menyediakan tenaga-tenaga yang terlatih.

10 Pemborong bertanggung jawab terhadap penjagaan / perlindu- 1 lot 4,000,000 ngan peralatan kerja dan material kerja terhadap kehilangan

atau kerusakan yang sedang dipergunakan dalam proyek.

11 Pengadaan Sepatu Safety, Handy talky (HT), Helm proyek, 1 lot 9,000,000 jas hujan, payung untuk pemberi tugas dan pengawas lapangan

12 Semua pekerja pemborong harus mendaftarkan seluruh pega- 1 lot 15,000,000 wainya yang terlibat dalam proyek ini kepada asuransi JAM-

SOSTEK Sub Total

(4)
(5)

Total (Rp) 40,000,000 25,000,000 100,000,000 2,000,000 5,000,000 15,000,000 12,000,000 600,000 4,000,000 9,000,000 15,000,000 227,600,000

(6)
(7)

PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN PEKERJAAN SISTEM TATA UDARA

No Uraian QTY SAT HARGA SATUAN Rp.

A PEKERJAAN PLUMBING

I Peralatan Utama

1 Transfer Pump 2 Unit 16,100,000 Kapasitas : 475 l/m

Head : 40 mtr Speed : 2900 rpm

Daya : 7,5 kw/ 3Ø/ 380 V/50 hz/3 ph Jenis : Pakaged (1set 2 pompa) Berikut kabel electroda GWT dan Roof Tank

2 Booster Pump 1 Unit 48,000,000 Kapasitas : 150 l/m

Head : 20 mH20 Speed : 2900 rpm

Daya : 3 kw/ 3Ø/ 380 V/50 hz/3 ph Jenis : Pakaged (1set 2 pompa) Spesifikasi Pompa :

1 Paket Booster Pump terdiri dari : - 2 unit Pompa + Motor

- 1 unit Panel Control Automatic/ Alternate - 1 unit Diagprahma Pressure Tank - 1 lot Accessories

3 Pompa Deep Well 1 Unit 262,500,000 Kapasitas : 150 Lpm

Head : 20 mH20 Speed : 2900 rpm

Daya : 3 kw/ 3Ø/ 380 V/50 hz/3 ph 4 Sand Filter

Type : Automatic Backwash 1 Unit 42,625,000 Kap : 150 l/min

5 Carbon Filter

Type : Automatic Backwash 1 Unit 48,625,000 Kap : 150 l/min

6 Tanki Air Atas (Roof tank) , Lokasi Atap 1 set 83,125,000 Kapasitas : 20 m3

Bahan : FRP

Lengkap dengan dudukan pondasi, dan pipa over, flow dan sistem drain. Termasuk tangga pengontrol

7 Sump Pump 1 (Basement) 18 unit 15,312,000 Kapasitas : 150 Lpm

Head : 20 m H2O Speed : 1450 rpm

Daya : 1,5 kW, 3Ø, 380 V, 50 Hz

Jenis : Submersible Pump, lengkap dengan panel kontrol dan pengkabelannya dan Accessories

(8)

8 Material bantu 1 lot 3,500,000 9 Testing commissioning 1 lot 7,500,000

Sub. Total I

II Site Plan dan R. Pompa

- Ø 100 mm ( Header ) 1 lot 3,500,000

- Ø 65 mm 131 mtr 164,260

- Ø 32 mm 70 mtr 76,879

- Ø 25 mm 196 mtr 61,155

- Ø 20 mm 210 mtr 42,881

Water meter dia 65mm 1 bh 1,970,250

Bak kontrol 40 x 40 x 40 cm 8 bh 1,750,000 Gate valve , tekanan kerja 10 bar

- Ø 150 mm 5 bh 3,787,500

- Ø 80 mm 2 bh 1,413,750

- Ø 20 mm 8 bh 156,603

Check Valve, tekanan kerja 10 kg

- Ø 65 mm 2 bh 1,970,250

Strainer, tekanan kerja 10 bar :

- Ø 80 mm 2 bh 1,833,750 Flexibel joint - Ø 80 mm 2 bh 993,750 - Ø 65 mm 2 bh 861,250 Foot Valve - Ø 80 mm 2 bh 1,613,750 Pressure Gauge 2 bh 185,000 Floating Valve - Ø 50 mm 1 bh 2,500,000 Kran Taman 9 bh 130,000

Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air kotor

dia. 150 mm 48 m 131,719 dia. 100 mm 102 m 51,333 Sub Total II

III INSTALASI AIR HUJAN Pipa PVC AW Class 10 K Site Plan

Ø 200 150 m 289,200

(9)

Rp. Instalasi pipa tegak

Ø 50 28 m 33,384 Ø 80 56 m 55,650 Ø 150 168 m 197,710 Lantai-dasar Ø 150 73 m 197,710 Lantai-dua Ø 150 95 m 197,710 Ø 80 70 m 55,650 Roof drain Ø 80 10 bh 162,750 Lantai-tiga Ø 150 76 m 93,780 Lantai-empat Ø 150 76 m 93,780 Lantai-lima Ø 100 76 m 93,780 Lantai-atap Ø 100 76 m 93,780 Roof drain Ø 100 20 bh 187,250

Lantai-atap (ruang mesin)

Ø 80 41 m 51,333 Ø 100 20 m 93,780 Roof drain Ø 80 5 bh 162,750 Ø 100 4 bh 187,250 Fitting-fitting 1 lot 12,500,000 Material bantu 1 lot 5,000,000 Testing commissioning 1 lot 4,500,000 Sub. Total III

IV LANTAI BASEMENT

Instalasi Air Bersih

(Pipa Galvanized Iron Medium Class)

dia. 80 mm 30 mtr 210,825 dia. 50 mm 30 mtr 119,550 dia. 40 mm 55 mtr 87,345 dia. 32 mm 85 mtr 76,879 dia. 25 mm 75 mtr 61,155 dia. 20 mm 120 mtr 42,881 dia. 15 mm 300 mtr 33,608

(10)

Gate Valve dia. 50 mm 1 bh 396,700 dia. 40 mm 2 bh 256,250 dia. 32 mm 2 bh 209,450 dia. 25 mm 8 bh 157,600 Fitting 1 lot 2,750,000

Material bantu 1 lot 1,375,000 Pengetesan 1 lot 2,500,000

INSTALASI AIR KOTOR, BEKAS DAN VENT Instalasi Air Bekas

(Pipa PVC Class AW, class 10 K) air kotor

dia. 150 mm 8 m 197,710 dia. 100 mm 88 m 93,780

dia. 80 mm 100 m 55,650

dia. 65 mm 72 m 44,295 dia. 50 mm 30 m 33,384 Gate valve dia 80 mm 18 bh 1,335,750 Check valve dia 80 mm 18 bh 1,593,750 Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air bekas

dia. 150 mm 48 m 197,710 dia. 100 mm 30 m 93,780 Instalasi Air Vent

dia. 50 mm 71 m 32,100 dia. 40 mm 17 m 24,825 dia. 32 mm 45 m 22,688 Floor Drain (FD)

dia. 50 mm 9 bh 147,650 Clean Out lantai (Co)

dia. 100 mm 2 bh 164,286 dia. 50 mm 4 bh 136,905

Fitting 1 lot 2,750,000

Material bantu 1 lot 1,350,000 Pengetesan 1 lot 2,500,000

V LANTAI SATU Instalasi Air Bersih

(Pipa Galvanized Iron Medium Class)

(11)

Rp. dia. 40 mm 46 m 87,345 dia. 32 mm 85 m 76,879 dia. 25 mm 66 m 61,155 dia. 20 mm 133 m 42,881 dia. 15 mm 285 m 33,608 Gate Valve dia. 50 mm 1 bh 396,700 dia. 32 mm 2 bh 209,450 dia. 25 mm 2 bh 157,600 dia. 20 mm 3 bh 120,000 Fitting 1 lot 1,250,000

Material bantu 1 lot 750,000 INSTALASI AIR KOTOR, BEKAS DAN VENT

Instalasi Air Bekas

(Pipa PVC Class AW, class 10 K) air kotor

dia. 100 mm 25 m 93,780 dia. 80 mm 75 m 55,650 dia. 65 mm 90 m 44,295 dia. 50 mm 115 m 44,295 Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air bekas

dia. 150 mm 22 m

dia. 100 mm 85 m 93,780 dia. 80 mm 12 m 55,650 Pipa Vent PVC Class D Class 5 K

dia. 50 mm 92 m 32,100 dia. 40 mm 54 m 24,825

dia. 32 mm 120 m 22,688

Floor Drain (FD)

dia. 50 mm 15 bh 147,650 Clean out lantai (Co)

dia. 80 mm 5 bh 164,286 dia. 65 mm 3 bh 136,905

Fitting 1 lot 2,250,000

Material bantu 1 lot 1,450,000 Pengetesan 1 lot 2,500,000

VI LANTAI DUA Instalasi Air Bersih

(Pipa Galvanized Iron Medium Class)

dia. 50 mm 3 mtr 119,550 dia. 40 mm 65 mtr 87,345 dia. 32 mm 36 mtr 76,879

(12)

dia. 20 mm 68 mtr 42,881 dia. 15 mm 265 mtr 33,608 Gate Valve dia. 50 mm 1 bh 396,700 dia. 32 mm 2 bh 256,250 dia. 25 mm 2 bh 209,450 Fitting 1 lot 1,000,000

Material bantu 1 lot 650,000 Instalasi Air Bekas

(Pipa PVC Class AW, class 10 K) air kotor

dia. 100 mm 150 mtr 93,780 dia. 80 mm 20 m 55,650 dia. 65 mm 25 m 44,295 dia. 50 mm 25 m 32,100 Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air bekas

dia. 100 mm 14 mtr 93,780 dia. 150 mm 14 mtr 197,750 Pipa Vent PVC Class D Class 5 K

dia. 50 mm 51 mtr 32,100 dia. 40 mm 50 mtr 24,825 dia. 32 mm 80 mtr 22,688 Floor Drain (FD) dia. 50 mm 5 bh 147,650 dia. 65 mm 2 bh 175,000 Clean out lantai (Co)

dia. 50 mm 3 bh 32,100 dia. 65 mm 5 bh 136,905 dia. 150 mm 7 bh 197,750

Fitting 1 lot 2,738,095

Material bantu 1 lot 2,190,476 .

Pengetesan 1 lot 2,190,476

VII LANTAI TIGA Instalasi Air Bersih

(Pipa Galvanized Iron Medium Class)

dia. 65 mm 20 mtr 164,260 dia. 40 mm 65 mtr 87,345 dia. 32 mm 64 mtr 76,879 dia. 25 mm 60 mtr 61,155 dia. 20 mm 60 mtr 42,881 dia. 15 mm 205 mtr 33,608

(13)

Rp. Gate Valve dia. 65 mm 1 bh 164,260 dia. 40 mm 2 bh 465,476 dia. 32 mm 2 bh 186,174 dia. 25 mm 5 bh 156,603 dia. 15 mm 3 bh 33,608 Fitting 1 lot 2,738,095

Material bantu 1 lot 2,190,476 Instalasi Air Bekas

(Pipa PVC Class AW, class 10 K) air kotor

dia. 80 mm 230 m 55,650

dia. 65 mm 230 m 44,295

Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air bekas

dia. 100 mm 329 m 93,780 dia. 150 mm 91 m 55,650 Pipa Vent PVC Class D Class 5 K

dia. 50 mm 45 m 32,100 dia. 40 mm 60 m 24,825 dia. 32 mm 132 m 22,688 Floor Drain (FD) dia. 50 mm 32 bh 147,650 dia. 65 mm 6 bh 175,000 Clean out lantai (Co)

dia. 100 mm 4 bh 164,286 dia. 65 mm 22 bh 136,905

Fitting 1 lot 3,500,000

Material bantu 1 lot 2,000,000 .

Pengetesan 1 lot 2,500,000

VIII LANTAI EMPAT Instalasi Air Bersih

(Pipa Galvanized Iron Medium Class)

dia. 65 mm 20 mtr 164,260 dia. 50 mm 6 mtr 119,550 dia. 40 mm 65 mtr 87,345 dia. 25 mm 60 mtr 61,155 dia. 20 mm 60 mtr 42,881 dia. 15 mm 205 mtr 33,608 Gate Valve dia. 65 mm 1 bh 485,587 dia. 40 mm 2 bh 465,476 dia. 25 mm 16 bh 156,603 dia. 15 mm 3 bh

(14)

Fitting 1 lot 2,738,095 Material bantu 1 lot 2,190,476 Instalasi Air Bekas

(Pipa PVC Class AW, class 10 K) air kotor

dia. 80 mm 230 m 55,650

dia. 65 mm 230 m 44,295

Instalasi Air Kotor

(Pipa PVC Class AW, class 10 K) air bekas

dia. 100 mm 329 m 93,780 dia. 150 mm 75 m 55,650 Pipa Vent PVC Class D Class 5 K

dia. 50 mm 45 m 32,100 dia. 40 mm 60 m 24,825 dia. 32 mm 132 m 22,688 Floor Drain (FD) dia. 50 mm 32 bh 147,650 dia. 65 mm 6 bh 175,000 Clean out lantai (Co)

dia. 100 mm 29 bh 164,286 dia. 65 mm 31 bh 136,905

Fitting 1 lot 3,500,000

Material bantu 1 lot 2,000,000 .

Pengetesan 1 lot 2,500,000

IX LANTAI LIMA

(Pipa Galvanized Iron Medium Class)

dia. 32 mm 60 mtr 76,879 dia. 25 mm 75 mtr 61,155 dia. 20 mm 220 mtr 42,881 dia. 15 mm 245 mtr 33,608 Gate Valve dia. 32 mm 16 bh 186,174 Fitting 1 lot 2,400,000

Material bantu 1 lot 1,250,000 INSTALASI AIR KOTOR, BEKAS DAN VENT

(Pipa PVC Class AW, class 10 K) air kotor

dia. 150 mm 6 m 197,710 dia. 100 mm 48 m 93,780 dia. 80 mm 6 m 55,650 dia. 65 mm 6 m 44,295

(15)

Rp.

dia. 50 mm 6 m 33,384 (Pipa PVC Class AW, class 10 K) air bekas

dia. 150 mm 34 m 197,710 dia. 100 mm 25 m 93,780 dia. 80 mm 6 m 55,650 dia. 65 mm 25 m 44,295 dia. 50 mm 20 m 33,384 Pipa Vent PVC Class D Class 5 K

dia. 50 mm 6 m 32,100 dia. 40 mm 22 m 24,825 dia. 32 mm 21 m 22,688 dia. 50 mm 6 bh 147,650 Clean out lantai (Co)

dia. 100 mm 2 bh 164,286 dia. 50 mm 2 bh 136,905

Fitting 1 lot 2,000,000

Material bantu 1 lot 1,500,000 Pengetesan 1 lot 2,500,000

X Lantai - Atap

(Pipa Galvanized Iron Medium Class)

dia. 100 mm 12 mtr 279,145 dia. 80 mm 189 mtr 210,825 dia. 65 mm 16 mtr 164,260 dia. 50 mm 8 mtr 119,550 dia. 40 mm 3 mtr 87,345 Gate Valve dia. 32 mm 1 bh 186,174 dia. 25 mm 28 bh 156,603 Fitting 1 lot 1,750,000

Material bantu 1 lot 1,500,000 INSTALASI AIR KOTOR, BEKAS DAN VENT

Lantai- Atap dia. 150 mm 6 m 197,710 dia. 100 mm 48 m 93,780 dia. 80 mm 6 m 55,650 dia. 65 mm 6 m 44,295 dia. 50 mm 6 m 33,384 (Pipa PVC Class AW, class 10 K) Air bekas

dia. 150 mm 34 m 197,710 dia. 100 mm 6 m 93,780 dia. 80 mm 6 m 55,650 dia. 65 mm 6 m 44,295 dia. 50 mm 20 m 33,384

(16)

dia. 65 mm 6 m 44,295 dia. 50 mm 6 m 32,100 dia. 40 mm 6 m 24,825 dia. 32 mm 21 m 22,688 Floor Drain (FD) dia. 50 mm 6 bh 147,650 Clean out lantai (Co)

dia. 100 mm 2 bh 164,286 dia. 50 mm 2 bh 136,905

Fitting 1 lot 1,350,000

Material bantu 1 lot 750,000 Pengetesan 1 lot 2,500,000

Instalasi Air Bersih

dia 80 mm ( supplay ke Roof Tank ) 70 mtr 210,825 dia 80 mm ( Gravitasi ke lt. B dan lt. 1 ) 70 mtr 210,825 Instalasi Air Kotor & Air Bekas

dia 150 mm 50 mtr 197,710 dia 100 mm 50 mtr 93,780 Instalasi Ventilasi

dia 80 mm 50 mtr 71,888 Testing commissioning 1 lot 7,500,000

VI. Instalasi Air Panas Sistem Water Heater PERALATAN UTAMA

Pengadaan dan pemasangan matrial utama water heater system Gas lengkap dengan matrial Pendukung dan Accesoriesnya sehingga dapat berpungsi dengan baik

Air Panas Sistem Electrical

GWH (Gas Water Heater) di lantai Basement 2 unit 11,000,000 Model : 25V30-7P

ENERGY : LPG/Nat Gas Heat Input : 30.000 BTUH Capacity : 30 USG/114 Liter Dray Weight : 44 Kg

Instalasi pipa air panas dari Water heater solar panel ke Outlet. Menggunakan pipa PPR Type PN - 20 Lantai Basement

(17)

Rp.

Ball Valve dia 15 mm 6 bh 175,000 Instalasi Air Panas Sistem Water Heater

PERALATAN UTAMA

Pengadaan dan pemasangan matrial utama water heater system Electrical lengkap dengan matrial Pendukung dan Accesoriesnya sehingga dapat berpungsi dengan baik

Air Panas Sistem Electrical

EWH (Electric Water Heater) di lantai 2 2 unit 1,600,000 Kapasitas 50 Liter

Daya1500 Watt

Instalasi pipa air panas dari Water heater solar panel ke Outlet. Menggunakan pipa PPR Type PN - 20 Lantai Dua

dia 15 mm 50 mtr 24,900 Ball Valve dia 15 mm 3 bh 175,000 PERALATAN UTAMA

Pengadaan dan pemasangan matrial utama water heater system solar panel lengkap dengan matrial Pendukung dan Accesoriesnya sehingga dapat berpungsi dengan baik

Air Panas Sistem Solar Panel

SWH (Solar Water Heater) di lantai atap 13 unit 21,000,000 Kapasitas 300 Liter

Type 300 LXC Daya 1500 Watt

Instalasi pipa air panas dari Water heater solar panel ke Outlet. Menggunakan pipa PPR Type PN - 20 Lantai 1

dia 20 mm 17 mtr 38,900 dia 15 mm 33 mtr 24,900 Ball Valve dia 15 mm 1 bh 175,000 Lantai 2

dia 20 mm 22 mtr 38,900 dia 15 mm 65 mtr 24,900 Ball Valve dia 15 mm 2 bh 175,000 Lantai 3

dia 20 mm 22 mtr 38,900 dia 15 mm 90 mtr 24,900 Ball Valve dia 15 mm 3 bh 175,000 Lantai 4

dia 20 mm 8 mtr 38,900 dia 15 mm 40 mtr 24,900 Ball Valve dia 15 mm 2 bh 175,000 Lantai 5

(18)

dia 15 mm 320 mtr 24,900 Ball Valve dia 15 mm 8 bh 175,000 Lantai Atap

dia 25 mm 120 mtr 62,600 Ball Valve dia 25 mm 1 bh 225,000 Ball Valve dia 15 mm 13 bh 175,000 Material bantu 1 lot 3,000,000 Testing commissioning 1 lot 7,500,000

(19)

Rp. 32,200,000 48,000,000 262,500,000 42,625,000 48,625,000 83,125,000 275,616,000

(20)

3,500,000 7,500,000 803,691,000 3,500,000 21,518,060 5,381,513 11,986,380 9,005,063 1,970,250 14,000,000 18,937,500 2,827,500 1,252,821 3,940,500 3,667,500 1,987,500 1,722,500 370,000 2,500,000 1,170,000 6,322,514 5,236,000 117,295,600 43,380,000 13,246,570

(21)

Rp. 934,752 3,116,400 33,215,280 14,432,830 18,782,450 3,895,500 1,627,500 7,127,280 7,127,280 7,127,280 7,127,280 3,745,000 2,104,667 1,875,600 813,750 749,000 12,500,000 5,000,000 4,500,000 192,428,419 6,324,750 3,586,500 4,803,975 6,534,694 4,586,625 5,145,750 10,082,250

(22)

396,700 512,500 418,900 1,260,800 2,750,000 1,375,000 2,500,000 47,778,444 1,581,680 8,252,640 5,565,000 3,189,240 1,001,520 24,043,500 28,687,500 9,490,080 2,813,400 2,279,100 422,025 1,020,938 1,328,850 328,571 547,619 2,750,000 1,350,000 2,500,000 97,151,663 717,300

(23)

Rp. 4,017,870 6,534,694 4,036,230 5,703,206 9,574,777 396,700 418,900 315,200 360,000 1,250,000 750,000 2,344,500 4,173,750 3,986,550 5,093,925 - 7,971,300 667,800 2,953,200 1,340,550 2,722,500 2,214,750 821,429 410,714 2,250,000 1,450,000 2,500,000 74,975,845 358,650 5,677,425 2,767,635

(24)

2,915,925 8,905,988 396,700 512,500 418,900 1,000,000 650,000 14,067,000 1,113,000 1,107,375 802,500 1,312,920 2,768,500 1,637,100 1,241,250 1,815,000 738,250 350,000 96,300 684,524 1,384,250 2,738,095 2,190,476 2,190,476 62,592,714 3,285,200 5,677,425 4,920,240 3,669,300 2,572,875 6,889,538

(25)

Rp. 930,952 372,348 783,013 100,823 2,738,095 2,190,476 12,799,500 10,187,850 30,853,620 5,064,150 1,444,500 1,489,500 2,994,750 4,724,800 1,050,000 657,143 3,011,905 3,500,000 2,000,000 2,500,000 116,408,003 3,285,200 717,300 5,677,425 3,669,300 2,572,875 6,889,538 485,587 930,952 2,505,642

(26)

2,738,095 2,190,476 12,799,500 10,187,850 30,853,620 4,173,750 1,444,500 1,489,500 2,994,750 4,724,800 1,050,000 4,764,294 4,244,048 3,500,000 2,000,000 2,500,000 118,389,002 4,612,725 4,586,625 9,433,875 8,233,838 2,978,785 2,400,000 1,250,000 1,186,260 4,501,440 333,900 265,770

(27)

Rp. 200,304 6,722,140 2,344,500 333,900 1,107,375 667,680 192,600 546,150 476,438 885,900 328,571 273,810 2,000,000 1,500,000 2,500,000 59,862,585 3,349,740 39,845,925 2,628,160 956,400 262,035 186,174 4,384,873 1,750,000 1,500,000 1,186,260 4,501,440 333,900 265,770 200,304 6,722,140 562,680 333,900 265,770 667,680

(28)

265,770 192,600 148,950 476,438 885,900 328,571 273,810 1,350,000 750,000 2,500,000 77,075,190 14,757,750 14,757,750 9,885,500 4,689,000 3,594,375 7,500,000 55,184,375 22,000,000 1,245,000

(29)

Rp. 1,050,000 3,200,000 1,245,000 525,000 273,000,000 661,300 821,700 175,000 855,800 1,618,500 350,000 855,800 2,241,000 525,000 311,200 996,000 350,000

(30)

7,968,000 1,400,000 7,512,000 225,000 2,275,000 3,000,000 7,500,000 317,931,700 1,997,681,188

(31)

PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN PEKERJAAN SISTEM TATA UDARA

No Uraian Qty Sat H.Sat(Rp)

A. TATA UDARA LANTAI BASEMENT

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - B.1,B.2,B.3, B.9 4 Unit 6,150,000

Lokasi :Rekam Medis, R.Dewasa, Lift Lobby Kapasitas :12200 BTUH

Air flow :350 CFM

Daya :1120 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - B.4,B.7 B.8, B.11, B.12, B.14 6 Unit 4,950,000 Lokasi :Ruangan I, Work Shop, R.Kebidanan,

R. Anak, Bank Kapasitas :8900 BTUH Air flow :311 CFM

Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - B.6, B.15, B.16, B.17 4 Unit 9,200,000 Lokasi :R.Dewasa,Gudang Apotik, Bank

Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ IU/OU - B.13 1 Unit 4,500,000 Lokasi :KA Kapasitas :4500 BTUH Air flow :240 CFM Daya :350 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

EF - B.1 1 Unit 2,200,000

Lokasi :R.pompa

Air flow :1000 CFM

Daya :150 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ

(32)

EF - B.2 1 Unit 5,000,000 Lokasi :Parkir Basement

Air flow :3000 CFM

Daya :350 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ EF - B.3 1 Unit 2,200,000 Lokasi Toilet Air flow :1000 CFM Daya :150 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - B.4 1 Unit 5,000,000

Lokasi :Parkir Basement Air flow :3000 CFM

Daya :350 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ

EF - B.5 1 Unit 5,000,000

Lokasi :Parkir Basement Air flow :3000 CFM

Daya :350 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ EF - B.6 1 Unit 5,000,000 Lokasi :Loundry Air flow :3000 CFM Daya :350 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - B.7 1 Unit 700,000 Lokasi :Dapur Air flow :200 CFM Daya :150 WATT Type :Axial Power Suplai :1P/220V/50HZ EF - B.8 1 Unit 5,000,000

Lokasi :Parkir Basement Air flow :3000 CFM

Daya :350 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ

EF - B.9 1 Unit 1,100,000

Lokasi :Gudang Apotik Air flow :100 CFM

Daya :30 WATT

Type :Ceilling Power Suplai :1P/220V/50HZ

(33)

(Rp) EF - B.10 1 Unit 1,100,000 Lokasi :R Jenazah Air flow :100 CFM Daya :30 WATT Type :Ceilling Power Suplai :1P/220V/50HZ EF - B.11 1 Unit 2,200,000 Lokasi Koridor Air flow :1000 CFM Daya :150 WATT Type :Axial Power Suplai :3P/380V/50HZ IF - B.1 1 Unit 5,000,000 Lokasi :Loundry Air flow :3000 CFM Daya :350 WATT Type :Axial Power Suplai :3P/380V/50HZ IF - B.2 1 Unit 5,000,000 Lokasi Kitchen Air flow :3000 CFM Daya :350 WATT Type :Axial Power Suplai :3P/380V/50HZ IF - B.3 1 Unit 2,200,000 Lokasi Koridor Air flow :1000 CFM Daya :150 WATT Type :Axial Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Grill Fan R Pompa ( EF=B.1) ukuran

500 x 500 1 Buah 450,000

Grill Fan Parkir Basement ( EF=B.2) ukuran

600 x 600 1 Buah 600,000

Ducting Exhaust Toilet ukuran

100 x 100 30 Meter 120,000 150 x 100 8 Meter 130,000 200 x 200 7 Meter 160,000 300 x 250 10 Meter 190,000 350 x 250 10 Meter 200,000 400 x 300 20 Meter 220,000 400 x 400 5 Meter 240,000

(34)

Grill Fan Toilet (EF-B.3) ukuran 500 x 500 1 Buah 450,000 Ducting Intake Fan Kitchen ukuran 600 x 300 34 Meter 280,000 Grill Kitchen (IF=B.2) Hood ukuran 600 x 300 1 Buah 600,000 Suplay Air Grill Kitchen ukuran 500 x 250 4 Buah 400,000 Ducting Exhaust Fan Kitchen ukuran 600 x 300 58 Meter 280,000 Stove Hood Ukuran 5000 x 1500 2 Set 6,500,000 Grill Kitchen (EF=B.4) Hood ukuran 600 x 600 1 Buah 600,000 Grill Fan Parkir Basement ( EF=B.5) Hood ukuran 600 x 600 1 Buah 600,000 Ducting Intake Fan Loundry ukuran 34 Meter 280,000 Grill Loundry (IF=B.1) ukuran 600 x 300 1 Buah 600,000 Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 Ducting Exhaust Fan Loundry ukuran 600 x 300 58 Meter 280,000 Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 Grill Fan Loundry (EF=B.6) Hood ukuran 600 x 600 1 Buah 600,000 Ducting Exhaust Dapur ukuran 200 x 200 7 Meter 160,000 Exhaust Air Grill Dapur ukuran 300 x 300 2 Buah 105,000 Grill Fan Dapur (EF-B.7) Hood ukuran 500 x 500 1 Buah 450,000 Grill Fan Parkir Basement ( EF=B.8) Hood ukuran 600 x 600 1 Buah 600,000 Ducting Exhaust Gudang Apotik ukuran 200 x 200 9 Meter 160,000 Grill Fan Gudang Apotik (EF-B.9) ukuran 250 x 250 1 Buah 105,000 Ducting Exhaust R jenazah ukuran 200 x 200 9 Meter 160,000 Grill Fan R jenazah (EF-B.10) ukuran 250 x 250 1 Buah 105,000 Ducting Intake dan Exhaust Fan Koridor ukuran

250 x 250 16 Meter 180,000 300 x 250 16 Meter 190,000 300 x 300 16 Meter 200,000 350 x 300 16 Meter 220,000 350 x 350 16 Meter 220,000 400 x 400 42 Meter 240,000

Grill Fan Koridor (IF-B.3) ukuran

500 x 500 1 Buah 600,000

(35)

(Rp)

400 x 400 6 Buah 400,000

Grill Fan Koridor (EF-B.3) ukuran

500 x 500 1 Buah 600,000

Exhaust Air Grill Koridor ukuran

400 x 400 6 Buah 400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berfungsi dengan baik

Diameter 3/4" 39 Meter 37,000

Diameter 1" 96 Meter 40,000

Riser Diameter 2" 16 Meter 75,000

Sub Total A

B TATA UDARA LANTAI 1 ( SATU )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 1.1,1.5,1.10, 1.11,1.12,1.13,1.14,1.16,1.21, 1.22, 20 Unit 4,750,000 1.23,1.24,1.25, 1.27,1.28,1.29,1.30,1.35,1.36,1.39

Lokasi :Play room, Nursery, USG, Dokter, Kapasitas :6750 BTUH

Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.2,1.3,1.4 1.6, 1.7,1.8, 1.17,1.18,1.3.7, 1.4.4,1.4.5,1.4.6 12 Unit 4,500,000 Lokasi :Alat, KA, Panoramic, Dokter, KA Lab,

:Sperma Kapasitas :4500 BTUH Air flow :240 CFM

Daya :350 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.9,1.15,1.26,1.38, 1.62, 1.63, 1.64 7 Unit 4,950,000 Lokasi :R.Tunggu Exutive, Locket, Rawat jalan,

:Pendaptaran, Bank Kapasitas :8900 BTUH Air flow :311 CFM

Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.19,1.20,1.40,1.41,1.42,1.43, 1.60, 1.61 8 Unit 9,200,000 Lokasi :Racik, KA, IGD,

Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

(36)

IU/OU - 1.31,1.32,1.33,1.34,1.47,1.51, 1.65 7 Unit 6,150,000 Lokasi :Rontgen, CT Scan, Lab, Minimarket

Kapasitas :12200 BTUH Air flow :350 CFM

Daya :1120 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.52 1 Unit 42,000,000

Lokasi :Ruang tunggu Poliklinik Kapasitas :90 000 BTUH

Air flow : CFM

Daya :9650 WATT

Type :Split Duct Power Suplai :3P/380V/50HZ

IU/OU - 1.53 1 Unit 9,200,000

Lokasi :Ruang tunggu Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.54 1 Unit 9,200,000

Lokasi :Ruang tunggu Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.55 1 Unit 4,750,000

Lokasi :Poli Umum Kapasitas :6750 BTUH Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 1.56 1 Unit 39,000,000

Lokasi :Ruang tunggu, Koridor Kapasitas :774 00 BTUH

Air flow : CFM

Daya :6500 WATT

Type :Split Duct Power Suplai :3P/380V/50HZ

IU/OU - 1.57 1 Unit 46,500,000

Lokasi :Koridor, Food Court Kapasitas :115 000 BTUH Air flow : CFM

Daya :9 800 WATT

(37)

(Rp) Power Suplai :3P/380V/50HZ

IU/OU - 1.58 1 Unit 48,000,000

Lokasi :Lift Lobby Kapasitas :126 000 BTUH Air flow : CFM

Daya :10 000 WATT

Type :Split Duct Power Suplai :3P/380V/50HZ

IU/OU - 1.59 1 Unit 46,500,000

Lokasi :Ruang tunggu Kapasitas :116 000 BTUH Air flow : CFM

Daya :9 800 WATT

Type :Split Duct Power Suplai :3P/380V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

EF - 1.1 1 Unit 1,100,000

Lokasi :Toilet Poli Air flow :100 CFM

Daya :30 WATT

Type :Ceilling Power Suplai :1P/220V/50HZ

EF - 1.2 1 Unit 1,400,000

Lokasi :Toilet Publik Air flow :700 CFM Daya :100 WATT Type :Axial Power Suplai :1P/220V/50HZ EF - 1.3 1 Unit 1,100,000 Lokasi :R Gelap Air flow :100 CFM Daya :30 WATT Type :Ceilling Power Suplai :1P/220V/50HZ EF - 1.4 dan EF 1.5 2 Unit 1,100,000

Lokasi :R Racik Apotik Air flow :100 CFM

Daya :30 WATT

Type :Ceilling Power Suplai :1P/220V/50HZ

EF - 1.6 dan 1.7 1 Unit 1,100,000

Lokasi :Wastafel Lab Air flow :100 CFM

Daya :30 WATT

(38)

EF - 1.8 1 Unit 1,300,000 Lokasi :Micro Biologi

Air flow :200 CFM

Daya :30 WATT

Type :Ceilling Power Suplai :1P/220V/50HZ

3 Pengadaan dan Pemasangan Ducting AC Split Duct fan leng kap berikut isolasi, hanger, suport, vibration mounting, plexible joint,plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Flexible Duct c/w Isolasi dia 200 mm 35 Meter 95,000

200 x 200 bjls 50 80 Meter 148,000 250 x 200 bjls 50 30 Meter 185,000 250 x 250 bjls 50 40 Meter 231,000 300 x 250 bjls 50 16 Meter 277,000 300 x 300 bjls 50 22 Meter 333,000 350 x 300 bjls 50 7 Meter 388,000 SAD 250 x 250 34 Buah 147,500 RAG 250 x 250 15 Buah 105,000 FAG 250 x 250 5 Buah 165,000

Plenum Box 5 Set 200,000

4 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Ducting Exhaust Toilet Poli (EF-1.1) ukuran

100 x 100 12 Meter 110,000

Ducting Exhaust Toilet Publik (EF-1.2) ukuran

100 x 100 51 Meter 110,000

150 x 100 15 Meter 130,000

200 x 200 2 Meter 160,000

300 x 300 3 Meter 200,000

Ducting Exhaust R Gelap (EF-1.3) ukuran

100 x 100 3 Meter 110,000

Ducting Exhaust R Racik (EF-1.4dan EF-1.5) ukuran

200 x 200 26 Meter 160,000

Ducting Exhaust Wastafel Lab (EF-1.6) ukuran

PVC Type D 100 22 Meter 25,000

Ducting Exhaust R Lab (EF-1.7) ukuran

PVC Type D 100 20 Meter 25,000

Ducting Exhaust Micro Biologi (EF-1.7) ukuran

PVC Type D 150 15 Meter 30,000

(39)

(Rp)

250 x 250 11 Buah 105,000

Grill fan Toilet Poli (EF-1.1) ukuran

250 x 250 1 Buah 105,000

Grill fan Toilet Publik (EF-1.2) ukuran

300 x 300 1 Buah 180,000

Grill fan R Gelap (EF-1.3) ukuran

250 x 250 1 Buah 105,000

Grill fan R Racik (EF-1.4 dan EF- 1.5) ukuran

300 x 300 1 Buah 180,000

Grill fan Wastafel Lab (EF-1.6) ukuran

250 x 250 1 Buah 105,000

Grill fan R Lab (EF-1.7) ukuran

250 x 250 1 Buah 105,000

Grill fan Micro Biologi (EF-1.8) ukuran

300 x 300 1 Buah 180,000

5 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berpungsi dengan baik

Diameter 3/4" 320 Meter 37,000

Diameter 1" 112 Meter 40,000

Diameter 2" 90 Meter 75,000

Sub Total B

C TATA UDARA LANTAI 2 ( DUA )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 2.1, 2.3, 2.6 3 Unit 9,200,000

Lokasi :OK1, OK2, OK3 (Plasma Cluster) Kapasitas :18100 BTUH

Air flow :572 CFM

Daya :1650 WATT

Type :PLASMA CLUSTER

Power Suplai :1P/220V/50HZ

IU/OU - 2.7, 2.10, 2.18, 2.19, 2.24, 2.25, 2.32, 2.33, 2.34 10 Unit 9,200,000 2.36

Lokasi :Resulasi,RR, Keuangan, PT, Hemodialisa, NS, Meeteng Room 2

Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 2.8,2.9,2.17,2.31,2.32 4 Unit 6,150,000 Lokasi :Dirut, Fisio terafi, Meeting

:room 1, SPI Kapasitas :12200 BTUH Air flow :350 CFM

Daya :1120 WATT

(40)

IU/OU - 2.11,2.12,2.16, 2.21,2.22,2.23,2.28,2.29,2.36 9 Unit 4,750,000 Lokasi :RR, NS, Meeting, EDP, SDM, Scre

:tary, Dokter, KA, RO Kapasitas :6750 BTUH

Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 2.13,2.14,2,15, 2.20, 2.26,2.30 6 Unit 4,950,000 Lokasi :ODC, Dokter,R.Tunggu OK, Keuangan

Kapasitas :8900 BTUH Air flow :311 CFM

Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

EF - 2.1 1 Unit 2,200,000

Lokasi :OK1, OK2, OK3 Air flow :1000 CFM Daya :150 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - 2.2 1 Unit 1,300,000 Lokasi Toilet Air flow :250 CFM Daya :100 WATT Type :Axial Power Suplai :1P/220V/50HZ EF - 2.3 1 Unit 1,100,000 Lokasi :Toilet Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ EF - 2.4 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - 2.5 1 Unit 1,100,000 Lokasi :Hemodialisa Air flow :100 CFM Daya :30 WATT

(41)

(Rp) Type :Axial Power Suplai :1P/220V/50HZ EF - 2.6 1 Unit 1,100,000 Lokasi :Hempdialisa Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ EF - 2.7 1 Unit 1,100,000 Lokasi :Alat Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ IF - 2.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Exhaust Air Grill OK1, OK2, OK3 ukuran

400 x 400 3 Buah 400,000

Grill fan (EF-2.1) OK1, OK2, OK3) ukuran

400 x 400 1 Buah 400,000

Filter 3 Set 2,000,000

Ducting Exhaust Fan Toilet ukuran

100 x 100 36 Meter 110,000

150 x 150 15 Meter 130,000

200 x 200 12 Meter 160,000

Ducting Exhaust Fan OK ukuran

300 x 200 20 Meter 130,000

300 x300 10 Meter 160,000

Exhaust Air Grill Toilet Publik ukuran

250 x 250 6 Buah 105,000

Grill fan (EF-2.2) Toilet Publik ukuran

300 x 300 1 Buah 105,000

Grill fan (EF-2.3) Toilet Hemodilisa ukuran

250 x 250 1 Buah 105,000

Ducting Exhaust (EF-2.5 dan EF-2.6) Hemodialisa ukuran

100 x 100 8 Meter 110,000

Grill fan (EF-2.5 dan EF-2.6) Hemodialisa ukuran

(42)

250 x 250 20 Meter 180,000 300 x 250 20 Meter 190,000 300 x 300 20 Meter 200,000 350 x 300 20 Meter 210,000 350 x 350 20 Meter 220,000 400 x 350 20 Meter 230,000 400 x 400 40 Meter 240,000

Grill Fan Koridor (IF=2.1) ukuran

500 x 500 1 Buah 600,000

Suplay Air Grill Koridor ukuran

400 x 400 7 Buah 400,000

Grill Fan Koridor (EF=2.4) ukuran

500 x 500 1 Buah 600,000

Return Air Grill Koridor ukuran

400 x 400 6 Buah 400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berpungsi dengan baik

Diameter 3/4" 328 Meter 37,000

Diameter 2" 80 Meter 75,000

Sub Total C

D TATA UDARA LANTAI 3 ( TIGA )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 3.1,3.5,3.13,3.17,3.20,3.21,3.22,3.24,3.26, 3.29,3.30 11 Unit 4,750,000 Lokasi :Dokter, Isolasi, Karu, menyusui, mandi

:bayi, kala Kapasitas :6750 BTUH Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 3.2, 3.6, 3.15, 3.16, 3.18,3.25,3.28, 3.31, 3.33 9 Unit 4,950,000 Lokasi :ICU VIP, R tunggu VK, NICU, Kala,

:Lounge, Preinatologi, Nurse (OK, VK pakai AC Plasma Cluster) Kapasitas :8900 BTUH

Air flow :311 CFM

Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 3.6, 3.7,3.8,3.9,3.10,3.11,3.12, 3.19, 13 Unit 4,150,000 3.27,3.34,3.35,3.36,3.37,3.38

Lokasi :Kelas I, II, III, VTP, NICU, Primatologi :Kala, Bayi VIP,

(43)

(Rp) Kapasitas :12200 BTUH

Air flow :350 CFM

Daya :1120 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 3.14,3.23, 3.32, 3.33, 3.34, 3.39 6 Unit 9,200,000 Lokasi :High Care, VK, Bayi, TCU

Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ 2

berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik. EF -.3.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - 3.2 s/d EF-3.21 20 Unit 1,100,000 Lokasi :Toilet Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ IF - 3.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ CF - 3.1 1 Unit 700,000 Lokasi :Mushola Air flow :200 CFM Daya :100 WATT Type :Ceilling Power Suplai :1P/220V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Ducting Exhaust Toilet ukuran

100 x 100 82 Meter 110,000

Ducting Intake dan Exhaust Fan Koridor ukuran

(44)

300 x 300 32 Meter 200,000

350 x 300 32 Meter 220,000

400 x 400 20 Meter 240,000

Grill Fan Koridor (IF=3.1) ukuran

500 x 500 1 Buah 600,000

Suplay Air Grill Koridor ukuran

400 x 400 8 Buah 400,000

Grill Fan Koridor (EF=3.1) ukuran

500 x 500 1 Buah 600,000

Return Air Grill Koridor ukuran

400 x 400 9 Buah 400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berfungsi dengan baik

Diameter 3/4" 280 Meter 37,000

Diameter 1" 10 Meter 40,000

Diameter 2" 80 Meter 75,000

Sub Total D

E TATA UDARA LANTAI 4 ( EMPAT )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 4.1,4.2,4.8,4.9,4.25, 5 Unit 9,200,000 Lokasi :Kelas III, Rtunggu,

Kapasitas :18100 BTUH Air flow :572 CFM

Daya :1650 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 4.3,4.4,4.5,4.6,4.7,4.10,4.11,4.12,4.13,4.14,4.15, 23 Unit 6,150,000 4.16,4.17,4.18,4.19,4.23,4.24,4.27,4.28,4.29,4.30

4.31,4.34

Lokasi :Kelas II, Nurse Kapasitas :12200 BTUH Air flow :350 CFM

Daya :1120 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 4.20,4.21,4.32,4.33,4.36 5 Unit 4,750,000 Lokasi :Observasi, Karu, Kelas II, obat, Kon

sultasi Kapasitas :6750 BTUH Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

(45)

(Rp) IU/OU - 4.22 1 Unit 4,950,000 Lokasi :Nurse Kapasitas :8900 BTUH Air flow :311 CFM Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik. EF -.4.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ EF - 4.2 s/d EF-4.30 29 Unit 1,100,000 Lokasi :Toilet Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ IF - 4.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Ducting Exhaust Toilet ukuran

100 x 100 75 Meter 110,000

Ducting Exhaust Toilet (Riser) ukuran

300 x 300 108 Meter 200,000

Ducting Intake dan Exhaust Fan Koridor ukuran

250 x 250 16 Meter 180,000 300 x 250 16 Meter 190,000 300 x 300 16 Meter 200,000 350 x 300 16 Meter 220,000 350 x 350 16 Meter 220,000 400 x 350 16 Meter 230,000 400 x 400 16 Meter 240,000 450 x 400 16 Meter 250,000

Grill Fan Koridor (IF=4.1) ukuran

(46)

400 x 400 9 Buah 400,000 Grill Fan Koridor (EF=4.1) ukuran

500 x 500 1 Buah 600,000

Return Air Grill Koridor ukuran

400 x 400 8 Buah 400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berpungsi dengan baik

Diameter 3/4" 260 Meter 37,000

Diameter 1" 4 Meter 40,000

Diameter 2" 80 Meter 75,000

Sub Total E

F TATA UDARA LANTAI 5 ( LIMA )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 5.1,5.2,5.3,5.4,5.5,5.6,5.7,5.8,5.9,5.10,5.11,5.12, 33 Unit 6,150,000 5.13,5.14,5.15,5.16,5.17,5.18,5.19,5.20,5.21,5.22,

5.23,5.24,5.25,5.26,5.27,5.28,5.29,5.30,5.31, 5.32,5.36

Lokasi :VIP, R TUNGGU,Kelas I, Obat, NS Kapasitas :12200 BTUH

Air flow :350 CFM

Daya :1120 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

IU/OU - 5.33,5.34,5.37 3 Unit 4,750,000

Lokasi :Konsultasi, Karu, :sultasi

Kapasitas :6750 BTUH Air flow :296 CFM

Daya :552 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik. EF -.5.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ

(47)

(Rp) EF - 5.2 s/d EF-5.33 32 Unit 1,100,000 Lokasi :Toilet Air flow :100 CFM Daya :30 WATT Type :Axial Power Suplai :1P/220V/50HZ IF - 5.1 1 Unit 2,200,000 Lokasi :Koridor Air flow :1000 CFM Daya :250 WATT Type :Axial Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berpungsi dengan baik.

Ducting Exhaust Toilet ukuran

100 x 100 92 Meter 110,000

Ducting Exhaust Toilet (Riser) ukuran

300 x 300 120 Meter 200,000

Ducting Intake Fan Koridor ukuran

250 x 250 16 Meter 180,000 300 x 250 16 Meter 190,000 300 x 300 16 Meter 200,000 350 x 300 16 Meter 220,000 350 x 350 16 Meter 220,000 400 x 350 16 Meter 230,000 400 x 400 16 Meter 240,000 450 x 400 16 Meter 250,000

Grill Fan Koridor (IF=5.1) ukuran

500 x 500 1 Buah 600,000

Suplay Air Grill Koridor ukuran

400 x 400 9 Buah 400,000

Grill Fan Koridor (EF=5.1) ukuran

500 x 500 1 Buah 600,000

Return Air Grill Koridor ukuran

400 x 400 8 Buah 400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berpungsi dengan baik

Diameter 3/4" 250 Meter 37,000

Diameter 1" 8 Meter 40,000

Diameter 2" 80 Meter 75,000

Sub Total F

G TATA UDARA LANTAI A ( ATAP )

1 Pengadaan dan Pemasangan peralatan utama AC & FAN Lengkap dengan Instalasi pengkabelan, berikut

-Pipa Refrigran, Isolasi, Thermostat, hanger, suport, vibration mounting, flexible joint,plenum box dan

(48)

IU/OU - A.01,A.02,A.03 3 Unit 4,950,000 Lokasi :R mesin Lift

Kapasitas :8900 BTUH Air flow :311 CFM

Daya :815 WATT

Type :Split Wall Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan Presh Air fan lengkap berikut hanger, suport, vibration mounting, plexible joint, plenum box dan accesoriesnya sehingga dapat berfungsi dengan baik.(Interpace to Fire Alarm)

PAF - A..1 1 Unit 14,000,000

Lokasi :Lantai Tangga kebakaran Air flow :11000 CFM

Daya :3000 WATT

Type :Axial

Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting/Hood PAF lengkap berikut hanger, suport, vibration mounting, flexible joint, plenum box dan accesoriesnya sehingga dapat berfungsi dengan baik.

Ducting Presh air fan ukuran

800 x 800 4 Meter 440,000

Presh air fan grill

800 x 800 2 Buah 480,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan accesoriesnya sehingga dapat berpungsi dengan baik

Diameter 3/4" 12 Meter 37,000

5 Grill tangga kebakaran 600 x 300 6 Buah 400,000

Sub Total G

H TATA UDARA R. GENSET DAN TRAFO

1 Pengadaan dan Pemasangan peralatan utama FAN Lengkap dengan Instalasi pengkabelan, berikut -accesoriesnya.sehingga dapat berpungsi dengan baik

EF - G.1/ EF - G.2 2 Unit 3,800,000

Lokasi :R. Genset Air flow :2000 CFM

Daya :250 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ

EF - T1 1 Unit 4,800,000

(49)

(Rp) Air flow :7000 CFM

Daya :700 WATT

Type :Wall Industrial Power Suplai :3P/380V/50HZ Sub Total H

(50)

Total (Rp) 66,500,000 29,700,000 36,800,000 4,500,000 2,200,000

(51)

(Rp) 5,000,000 2,200,000 5,000,000 5,000,000 5,000,000 700,000 5,000,000 1,100,000

(52)

1,100,000 2,200,000 5,000,000 5,000,000 2,200,000 450,000 600,000 3,600,000 1,040,000 1,120,000 1,900,000 2,000,000 4,400,000 1,200,000

(53)

(Rp) 840,000 450,000 9,520,000 600,000 1,600,000 16,240,000 13,000,000 600,000 600,000 9,520,000 600,000 1,200,000 16,240,000 1,200,000 600,000 1,120,000 210,000 450,000 600,000 1,440,000 105,000 1,440,000 105,000 2,880,000 3,040,000 3,200,000 3,520,000 3,520,000 10,080,000 600,000

(54)

600,000 2,400,000 1,443,000 3,840,000 1,200,000 317,513,000 95,000,000 54,000,000 34,650,000 73,600,000

(55)

(Rp) 43,050,000 42,000,000 9,200,000 9,200,000 4,750,000 39,000,000 46,500,000

(56)

48,000,000 46,500,000 1,100,000 1,400,000 1,100,000 2,200,000 1,100,000

(57)

(Rp) 1,300,000 3,325,000 11,840,000 5,550,000 9,240,000 4,432,000 7,326,000 2,716,000 5,015,000 1,575,000 825,000 1,000,000 1,320,000 5,610,000 1,950,000 320,000 600,000 330,000 4,160,000 550,000 500,000 450,000

(58)

105,000 180,000 105,000 180,000 105,000 105,000 180,000 11,840,000 4,480,000 6,750,000 647,469,000 27,600,000 92,000,000 24,600,000

(59)

(Rp) 42,750,000 29,700,000 2,200,000 1,300,000 1,100,000 2,200,000 1,100,000

(60)

1,100,000 1,100,000 2,200,000 1,200,000 400,000 6,000,000 3,960,000 1,950,000 1,920,000 2,600,000 1,600,000 630,000 105,000 105,000 880,000 210,000

(61)

(Rp) 3,600,000 3,800,000 4,000,000 4,200,000 4,400,000 4,600,000 9,600,000 600,000 2,800,000 600,000 2,400,000 12,136,000 6,000,000 309,246,000 52,250,000 44,550,000 53,950,000

(62)

55,200,000 2,200,000 22,000,000 2,200,000 700,000 9,020,000 5,760,000

(63)

(Rp) 6,080,000 6,400,000 7,040,000 4,800,000 600,000 3,200,000 600,000 3,600,000 10,360,000 400,000 6,000,000 296,910,000 46,000,000 141,450,000 23,750,000

(64)

4,950,000 2,200,000 31,900,000 2,200,000 8,250,000 21,600,000 2,880,000 3,040,000 3,200,000 3,520,000 3,520,000 3,680,000 3,840,000 4,000,000 600,000

(65)

(Rp) 3,600,000 600,000 3,200,000 9,620,000 160,000 6,000,000 333,760,000 202,950,000 14,250,000 2,200,000

(66)

2,200,000 10,120,000 24,000,000 2,880,000 3,040,000 3,200,000 3,520,000 3,520,000 3,680,000 3,840,000 4,000,000 600,000 3,600,000 600,000 3,200,000 9,250,000 320,000 6,000,000 342,170,000

(67)

(Rp) 14,850,000 14,000,000 1,760,000 960,000 444,000 2,400,000 34,414,000 7,600,000 4,800,000

(68)

12,400,000 2,293,882,000

(69)

PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN PEKERJAAN SISTEM PEMADAM KEBAKARAN

No Uraian QTY SAT HARGA SATUAN Rp.

Pekerjaan Pemadam Kebakaran 1 Pekerjaan Equipment Utama

1.1 Pompa Elektrik Hydrant (Ruang pompa lt, B ) 1 unit 104,000,000 - Kapasitas : 500 GPM

- Head : 100 meter - Put : 2900 Rpm - Type : splite case - Operation : start automatik, stop manual

1.2 Pompa Diesel Hydrant (Ruang pompa lt, B ) 1 unit 200,000,000 - Kapasitas : 500 GPM

- Head : 100 meter - Put : 2900 Rpm - Type : splite case - Operation : start automatik,

1.3 Pompa Jokey (Ruang pompa lt, B ) 1 unit 25,794,500 - Kapasitas : 25 GPM

- Head : 100 meter - Put : 2900 Rpm - Type : Vertikal

- Operation : start/stop automatik

1.4 Panel Kontrol Pompa Kebakaran Mengacu ke 3 set INCLUDE Standard NFPA

- Lengkap dengan Pressure tank dan acce sories Dan dapat interface dengan MCFA 1.5 Assesories instalasi pompa

Material Bantu 1 lot 12,500,000 Termasuk pondasi pompa, support,hangger,

Vibration mounting , dan tanki solar harian -kap200 ltr , berikut instalasinya + pengecatan sub total 1

2 Instalasi Pemadam Kebakaran di Ruang Pompa

2.1 Pengadaan dan pemasangan Pipa Black Steel Sch 40 (ASTM A53) berikut Support, penge catan Blind Flange dan Accessories

Header dia. 200 mm termasuk support, 2 set 7,352,500 blind flanges fitting weldolet,air realease dia

(70)

Pipa dia. 150 mm 54 m 781,128 Pipa dia. 100 mm 30 m 470,400 Pipa dia. 50 mm 30 m 185,400 Knalpot pipa dia 80 mm 75 m 375,000 termasuk isolasi panas (asbes type) dan diberi

metal Jakecting 2.2 Assesories - Gate valve Dia. 150 mm 10 bh 10,459,980 Dia. 50 mm 2 bh 824,380 - Check valve Dia. 150 mm 2 bh 6,940,020 Dia. 50 mm 1 bh 631,060 - Fleksible joint Dia. 150 mm 4 bh 1,927,500 Dia. 50 mm 2 bh 533,800 - Strainer Dia. 150 mm 2 bh 6,070,620 dia. 50 mm 1 bh 639,940 - Foot Valve ( lihat diimeter pipa

pompa)

Dia. 150 mm 2 bh 3,421,140 dia. 50 mm 1 bh 2,165,740 - Flow meter dia 150 mm 1 bh 21,156,250

- Pressure Gauge 3 bh 211,250

- Pressure Switch 3 bh 2,131,250

2.3 - Main Control Valve (MCV) dia. 150 mm 1 set 55,875,000 c/w Alarm gong, dan acesoriesnya

Pressure Reducing Valve (PRV) dia 150 mm 1 set 46,815,000 c/w stainer, valve , presurre gauge dan pemi

paan

2.4 Safety Valve dia 150 mm 1 bh 21,156,550 2.5 FE 10 kg (gas) 1 bh 5,282,000 2.6 Fiting- fitting 1 lot 16,562,500 2.7 Material bantu termasuk pengecatan 1 lot 6,625,000 2.8 Pengetesan 1 lot 9,375,000

(71)

Rp. sub total 2

3 Instalasi Pipa Kebakaran (Dari R Pompa dan dalam Shaft) 3.1 Instalasi Pipa Hydrant dan Sprinkler

dalam Shaft s/d Lantai Atap

Pengadaan dan pemasangan Pipa Black Steel Sch 40 (ASTM A53) berikut Support

dia. 150 mm 90 m 799,120 air realease valve dia 40mm dan Accessories 2 bh 1,831,250 3.2 Fitting- fiting 1 lot 16,875,000 3.3 Material bantu 1 lot 6,937,500

Termasuk suport pipa tegak, klem pipa dan pengecatan.

3.4 Pengetesan 1 lot 3,125,000

sub total 3

4 Instalasi Pipa Kebakaran di Site Plan

Sprinkler

4.1 Instalasi pemadam kebakaran

Pengadaan dan pemasangan Pipa Black Steel Sch 40 (ASTM A53) berikut Support

Isolasi pipa dalam tanah (Wrapping) & Primer Coating dan Accessories dan Accessories

dia. 150 mm 437 meter 781,128 dia. 100 mm 40 meter 471,360 Galian Tanah 477 meter 20,000 4.2 Gate valve

dia. 100 mm 5 bh 6,322,160 4.3 Check valve

dia. 150 mm 1 bh 6,940,020 4.5 Siamisse conection 1 bh 3,073,500 4.6 Outdoor hyhdrant Pilar c/w Box 6 bh 3,242,410 Pilar Hidrand 6 bh 3,024,250 4.7 Fitting- fiting 1 lot 18,125,000 4.8 Material Bantu termasuk bak kontrol

pondasi siamesse dan pilar hydrant 1 lot 6,750,000 4.9 Pengetesan 1 lot 6,250,000

sub total 4

(72)

5.1 Instalasi Sprinkler

1 Head sprinkler 291 ttk 60,375 2 Branch Control Valve dia 100 " 1 bh 9,334,000

lengkap dengan pressure gauge

3 Flow Switch dia. 80 mm 1 bh 1,171,250 4 Gate valve

dia. 100 mm 1 bh 6,322,160 dia. 25 mm 3 bh 308,500 5 Sight Glass dia. 25 mm 1 bh 931,250 Pressure Gauge 1 bh 241,250 7 Pengadaan dan pemasangan Pipa Black Steel

6 Sch 40 (ASTM A53) berikut Support dan Accessories dia. 150 mm 69 m 799,128 dia. 100 mm 178 m 470,400 dia. 80 mm 46 m 343,704 dia. 65 mm 20 m 258,240 dia. 50 mm 66 m 186,000 dia. 40 mm 288 m 132,138 dia. 32 mm 242 m 117,030 dia. 25 mm 522 m 88,728 5.2 Instalasi Hydrant

1 Indoor hydrant box lenkap dengan 2 bh 3,770,410 2 Pemadam Api Ringan (PAR)

FE 2 KG (Klas ABC) 2 bh 1,218,750 3 Pengadaan dan pemasangan Pipa Black Steel

Sch 40 (ASTM A53) berikut Support dan Accessories + pengecatan

dia. 150 mm 72 m 799,128 dia. 100 mm 125 m 471,360 dia. 80 mm 33 m 343,704 4 Gate valve dia. 100 mm 1 bh 6,322,160 dia. 65 mm 5 bh 4,399,590 5 Fitting- fiting 1 lot 21,087,500 6 Material Bantu 1 lot 7,237,500

sub total 5

8 Instalasi Pemadam Kebakaran Lantai Satu

8.1 Instalasi Sprinkler

(73)

Rp.

2 Branch Control Valve dia 100mm 1 bh 9,334,000 lengkap dengan pressure gauge

3 Flow Switch dia. 100 mm 1 bh 1,171,250 4 Gate valve

dia. 150 mm 1 bh 10,459,980 dia. 100 mm 1 bh 6,322,160 dia. 25 mm 3 bh 308,500 5 Sight Glass dia. 25 mm 2 bh 931,250 Pressure Gauge 1 bh 241,250 Pengadaan dan pemasangan Pipa Black Steel

Sch 40 (ASTM A53) berikut Support dan Accessories + pengecatan

dia. 100 mm 16 m 470,400 dia. 80 mm 28 m 341,904 dia. 65 mm 46 m 258,240 dia. 50 mm 55 m 186,000 dia. 40 mm 90 m 132,138 dia. 32 mm 120 m 117,030 dia. 25 mm 588 m 88,728 8.2 Instalasi Hydrant

1 Indoor hidran box 2 bh 3,770,410 2 Pemadam Api Ringan (PAR)

FE 2 KG (Klas ABC) 3 bh 1,218,750 3 Pengadaan dan pemasangan Pipa Black Steel

Sch 40 (ASTM A53) berikut Support dan Accessories + pengecatan

dia. 100 mm 16 m 471,360 dia. 80 mm 55 m 343,704 dia. 65 mm 8 m 258,240 4 Gate valve dia. 100 mm 1 bh 6,322,160 dia. 65 mm 2 bh 4,399,590 5 Fitting- fiting 1 lot 23,912,500 6 Material Bantu 1 lot 9,937,500

sub total 8( lantai Satu )

11 Instalasi Pemadam Kebakaran Lantai 2 ( dua )

11.1 Instalasi Sprinkler

1 Head sprinkler 125 ttk 60,375 2 Branch Control Valve dia 100mm 1 bh 9,334,000

lengkap dengan pressure gauge