• Tidak ada hasil yang ditemukan

Material Requirements Planning (MRP)

N/A
N/A
Protected

Academic year: 2018

Membagikan "Material Requirements Planning (MRP)"

Copied!
59
0
0

Teks penuh

(1)

Budi Harsanto

Dept. of Management & Business, Faculty of Economics, Universitas Padjadjaran budi.harsanto@fe.unpad.ac.id

Material

(2)

Review Last Topic

INVENTORY MANAGEMENT

Probabilistic Models and Safety StockSingle Period Model

(3)

Today Outline

MRP

Dependent Demand

Dependent Inventory Model

Requirements

MRP Structure

MRP Management

Lot Sizing Technique

(4)

Operations

Management

Operations

Management

Chapter 14 –

Material Requirements

Planning (MRP) and

ERP

PowerPoint presentation to accompany

Heizer/Render

(5)

Benefts of MRP

1. Better response to customer

orders

2. Faster response to market

changes

3. Improved utilization of facilities

and labor

(6)

Dependent Demand

The demand for one item is

related to the demand for

another item

Given a quantity for the end

item, the demand for all parts

and components can be

calculated

In general, used whenever a

schedule can be established for

an item

(7)

Dependent Demand

1. Master production schedule

2. Specifcations or bill of material 3. Inventory availability

4. Purchase orders outstanding 5. Lead times

Efective use of dependent

(8)

Master Production Schedule

(MPS)

Specifes what is to be made and whenMust be in accordance with the

aggregate production plan

Inputs from fnancial plans, customer

demand, engineering, supplier performance

 As the process moves from planning to execution, each step must be tested for feasibility

The MPS is the result of the production

(9)

Master Production Schedule

(MPS)

MPS is established in terms of specifc

products

Schedule must be followed for a

reasonable length of time

 The MPS is quite often fxed or frozen in the near term part of the plan

 The MPS is a rolling schedule

(10)
(11)
(12)

Aggregate

Production Plan

Months January February

Aggregate Production Plan 1,500 1,200

(Shows the total

quantity of amplifers)

Weeks 1 2 3 4 5 6 7 8

Master Production Schedule (Shows the specifc type and quantity of amplifer to be produced

240-watt amplifer 100 100 100 100

150-watt amplifer 500 500 450 450

75-watt amplifer 300 100

(13)

Master Production Schedule

(MPS)

A customer order in a job shop

(make-to-order) company

 Modules in a repetitive (assemble-to-order or forecast) company

An end item in a continuous

(stock-to-forecast) company

(14)

Focus for Diferent

Process Strategies

Stock to Forecast

(Product Focus)

Schedule fnished product

Assemble to Order or Forecast

(Repetitive)

Schedule modules

Make to Order

(Process Focus)

Schedule orders

Examples: Print shop Motorcycles Steel, Beer, Bread Machine shop Autos, TVs Lightbulbs Fine-dining restaurant Fast-food restaurant Paper

(15)

MPS Examples

Gross Requirements for Crabmeat Quiche

Gross Requirements for Spinach Quiche

Day 6 7 8 9 10 11 12 13 14 and so on

Amount 50 100 47 60 110 75

Day 7 8 9 10 11 12 13 14 15 16 and so on

Amount 100 200 150 60 75 100

Table 14.1

(16)

Bills of Material

List of components, ingredients,

and materials needed to make

product

Provides product structure

Items above given level are called

parents

(17)

BOM Example

B(2) Std. 12” Speaker kit C(3) Std. 12” Speaker kit w/ amp-booster

1

E(2)

E(2) F(2)

Packing box and installation kit of wire,

bolts, and screws

Std. 12” Speaker booster assembly 2 D(2) 12” Speaker D(2) 12” Speaker G(1) Amp-booster 3

Product structure for “Awesome” (A) A

(18)

BOM Example

B(2) Std. 12” Speaker kit C(3) Std. 12” Speaker kit w/ amp-booster

1

E(2)

E(2) F(2)

Packing box and installation kit of wire,

bolts, and screws

Std. 12” Speaker booster assembly 2 D(2) 12” Speaker D(2) 12” Speaker G(1) Amp-booster 3

Product structure for “Awesome” (A) A

Level 0

Part B: 2 x number of As = (2)(50) = 100

Part C: 3 x number of As = (3)(50) = 150

Part D: 2 x number of Bs

+ 2 x number of Fs = (2)(100) + (2)(300) = 800

Part E: 2 x number of Bs

+ 2 x number of Cs = (2)(100) + (2)(150) = 500

Part F: 2 x number of Cs = (2)(150) = 300

(19)

Bills of Material

Modular Bills

 Modules are not fnal products but components that can be

assembled into multiple end items

(20)

Bills of Material

Planning Bills (Pseudo Bills)

 Created to assign an artifcial parent to the BOM

Used to group subassemblies to

reduce the number of items planned and scheduled

Used to create standard “kits” for

(21)

Bills of Material

Phantom Bills

 Describe subassemblies that exist only temporarily

Are part of another assembly and

never go into inventory

Low-Level Coding

 Item is coded at the lowest level at which it occurs

(22)

Accurate Records

Accurate inventory records are

absolutely required for MRP (or

any dependent demand system)

to operate correctly

Generally MRP systems require

99% accuracy

Outstanding purchase orders

(23)

Lead Times

The time required to purchase,

produce, or assemble an item

 For production – the sum of the order, wait, move, setup, store, and run times

(24)

Time-Phased Product

Structure

| | | | | | | |

1 2 3 4 5 6 7 8

Time in weeks

F 2 weeks 3 weeks 1 week A 2 weeks 1 week D E 2 weeks D G 1 week 1 week 2 weeks to produce B C E

Start production of D Must have D and E completed here so production can

begin on B

(25)

MRP Structure

Figure 14.5 Output Reports MRP by period report MRP by date report Planned order report Purchase advice Exception reports Order early or

late or not needed Order quantity too small or too

large

Data Files

Purchasing data BOM

Lead times

(Item master fle)

(26)

Determining Gross

Requirements

Starts with a production schedule for

the end item – 50 units of Item A in week 8

Using the lead time for the item,

determine the week in which the order should be released – a 1 week lead

time means the order for 50 units should be released in week 7

(27)

Determining Gross

Requirements

 From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A

The lead time for the Item B is 2 weeks

– release an order for 100 units of Item B in week 5

 The timing and quantity for component requirements are determined by the

(28)

Determining Gross

Requirements

The process continues through the

entire BOM one level at a time – often called “explosion”

By processing the BOM by level, items

with multiple parents are only

processed once, saving time and resources and reducing confusion

Low-level coding ensures that each

(29)

Gross Requirements Plan

Table 14.3 Week

1 2 3 4 5 6 7 8 Lead Time

A. Required date 50

Order release date 50 1 week

B. Required date 100

Order release date 100 2 weeks

C. Required date 150

Order release date 150 1 week

E. Required date 200 300

Order release date 200 300 2 weeks

F. Required date 300

Order release date 300 3 weeks

G. Required date 600 200

Order release date 600 200 1 week G. Required date 300

(30)
(31)
(32)

Determining Net

Requirements

 Starts with a production schedule for the end item – 50 units of Item A in week 8

 Because there are 10 Item As on hand, only 40 are actually required – (net

requirement) = (gross requirement - on- hand inventory)

(33)

Determining Net

Requirements

 Following the lead time ofset

procedure, the planned order release for Item A is now 40 units in week 7

 The gross requirement for Item B is now 80 units in week 7

There are 15 units of Item B on hand,

so the net requirement is 65 units in week 7

A planned order receipt of 65 units in

(34)

Determining Net

Requirements

 A planned order receipt of 65 units in week 7 generates a planned order

release of 65 units in week 5

 The on-hand inventory record for Item B is updated to refect the use of the 15 items in inventory and shows no on-hand inventory in week 8

 This is referred to as the Gross-to-Net calculation and is the third basic

(35)

Net Requirements Plan

The logic of net requirements

Available inventory

Net requirements On

hand + Scheduled receipts

– =

Total requirements Gross

(36)

Gross Requirements

Schedule

Figure 14.6 A

B C

5 6 7 8 9 10 11

40 50 15

Lead time = 4 for A Master schedule for A

S

B C

12 13 8 9 10 11

20 30 40

Lead time = 6 for S Master schedule for S

1 2 3 10 10

Master schedule for B

sold directly

Periods

Therefore, these are the gross requirements for B

Gross requirements: B 10 40+10=50 40 50 20 15+30=45

1 2 3 4 5 6 7 8

(37)

MRP Planning Sheet

(38)

Safety Stock

BOMs, inventory records, purchase

and production quantities may not

be perfect

Consideration of safety stock may

be prudent

Should be minimized and

ultimately eliminated

Typically built into projected

(39)

MRP Management

MRP is a dynamic system

Facilitates replanning when

changes occur

System nervousness can result

from too many changes

Time fences put limits on

replanning

Pegging links each item to its

(40)

Lot-Sizing Techniques

Lot-for-lot techniques order just

what is required for production

based on net requirements

May not always be feasible

If setup costs are high, lot-for-lot can

be expensive

Economic order quantity (EOQ)

 EOQ expects a known constant

(41)

Lot-Sizing Techniques

Part Period Balancing (PPB) looks

at future orders to determine most

economic lot size

The Wagner-Whitin algorithm is a

complex dynamic programming

technique

 Assumes a fnite time horizon

(42)

MRP in Services

Some services or service items

are directly linked to demand for

other services

These can be treated as

dependent demand services or

items

 Restaurants

(43)

Uncooked linguini #30004 Sauce #3000 6 Veal #3000 5

MRP in Services

Chef; Work Center #1 Helper one; Work Center #2 Asst. Chef; Work Center #3 Cooked linguini

#20002 Spinach #20004

Prepared veal and sauce

#20003 (a) PRODUCT STRUCTURE TREE

Veal picante #10001

(44)

MRP in Services

(b) BILL OF MATERIALS

Part

Number Description Quantity MeasureUnit of costUnit 10001 Veal picante 1 Serving —

20002 Cooked linguini 1 Serving

20003 Prepared veal and sauce 1 Serving

20004 Spinach 0.1 Bag 0.94

30004 Uncooked linguini 0.5 Pound

30005 Veal 1 Serving 2.15

(45)

MRP in Services

(c) BILL OF LABOR FOR VEAL PICANTE

Labor Hours Work Center Operation Labor Type Setup Time Run Time

1 Assemble dish Chef .0069 .0041

2 Cook linguini Helper one .0005 .0022

3 Cook veal

(46)

Enterprise Resource Planning

(ERP)

An extension of the MRP system

to tie in customers and suppliers

1. Allows automation and integration of many business processes

2. Shares common data bases and business practices

3. Produces information in real time

Coordinates business from

(47)

Enterprise Resource Planning

(ERP)

ERP modules include

 Basic MRP

Finance

Human resources

Supply chain management (SCM)

Customer relationship

(48)

ERP and MRP

(49)

ERP and MRP

Figure 14.11

Customer Relationship Management

Invoicing

Shipping Distributors,

retailers, and end users Sales Order

(50)

Table 13.6

Bills of Material

Work Orders

Purchasing and Lead Times

Routings and Lead Times Master

Production Schedule

Inventory Management

ERP and MRP

Figure 14.11

(51)

ERP and MRP

Figure 14.11

Supply Chain Management

Vendor Communication

(52)

ERP and MRP

Figure 14.11Table 13.6

Finance/ Accounting

General Ledger Accounts Receivable

Payroll Accounts

(53)

Enterprise Resource Planning

(ERP)

ERP can be highly customized to

meet specifc business

requirements

Enterprise application integration

software (EAI) allows ERP systems

to be integrated with

 Warehouse management

Logistics

Electronic catalogs

(54)

Enterprise Resource Planning

(ERP)

ERP systems have the potential to

Reduce transaction costs

Increase the speed and accuracy of

information

Facilitates a strategic emphasis on

(55)

Advantages of ERP Systems

1. Provides integration of the supply chain, production, and administration

2. Creates commonality of databases 3. Can incorporate improved best

processes

4. Increases communication and

collaboration between business units and sites

(56)

Disadvantages of ERP

Systems

1. Is very expensive to purchase and even more so to customize

2. Implementation may require major changes in the company and its

processes

3. Is so complex that many companies cannot adjust to it

4. Involves an ongoing, possibly never

completed, process for implementation 5. Expertise is limited with ongoing stafng

(57)

SAP’s ERP Modules

Figure 14.12

Cash to Cash

Covers all fnancial related activity:

Accounts receivable General ledger Cash management Accounts payable Treasury Asset management

Dock to Dispatch

Covers internal inventory management:

Warehousing Forecasting Physical inventory Distribution planning Replenishment planning Material handling

Promote to Deliver

Covers front-end customer-oriented activities:

Marketing

Quote and order processing Transportation

Documentation and labeling

After sales service Warranty and guarantees

Procure to Pay

Covers sourcing activities: Vendor sourcing Purchase requisitioning Purchase ordering Purchase contracts Inbound logistics Supplier invoicing/ matching Supplier payment/ settlement Supplier performance

Design to Manufacture

Covers internal production activities: Design Shop foor engineering reporting Production

Contract/project

engineering management

Plant Subcontractor maintenance

management

Recruit to Hire

Covers all HR- and payroll-oriented activity:

(58)

Example I

Sebuah perusahaan kayu yang membuat produk X menerima 2 pesanan, yaitu sebesar 100 unit yang harus selesai pada awal minggu ke-4 dan sebesar 150 unit yang harus selesai pada awal minggu ke-8. Produk X terdiri dari 4 unit bagian A dan 2 unit bagian B. Bagian A dibuat sendiri oleh perusahaan yang membutuhkan waktu selama 1 minggu.

Bagian B dipesan dari luar dengan lead time 2

minggu.Untuk merakit produk X dibutuhkan waktu 1 minggu. Persediaan bagian A ada 70 unit.

Tentukan rencana kebutuhan material untuk membuat produk tersebut,

a. Dengan metode lot for lot ordering

b. Dengan metode lot size ordering dengan ELS

produk A 470 unit dan ELS produk B 320 unit.workshe et

(59)

Example II

Demand Supra

7th week: 15 units

X-Trim

8th week: 10 units.

IR , Lot Size & Lead Time

SUPRA: 5, lot4lot (1), 2

X: 5, 25, 1 F: 10, 30, 1 M: 0, 1, 1 W: 2, 12, 3

X-TRIM: 2, 1, 2 K: 3, 1, 1

Gambar

Table 14.3Week
Table 13.6 Bills of  MaterialWork OrdersPurchasingandLead Times Routingsand Lead TimesMaster Production ScheduleInventory ManagementERP and MRP Figure 14.11 MRP

Referensi

Dokumen terkait

a) Kitab Undang-undang Hukum Pidana (KUHP). b) Kitab Undang-undang Hukum Acara Pidana (KUHAP). c) Undang-undang Nomor 14 tahun 1992 tentang Lain Lintas dan Angkutan Jalan. Raya.

14 014/JIB/14 DODY KRISTANTO Lulus JIB PRIBADI Sudah jadi. 15 015/JIB/14 DONNY SEFNEDY TANGKA Lulus

Penilaian pengetahuan dilakukan dalam bentuk penugasan, dimana peserta didik diminta untuk mengumpulkan hasil kerja kelompok tentang Analisis tujuan dan fungsi negara 

Secara definisi, Reksa Dana adalah wadah untuk menghimpun dana masyarakat yang dikelola oleh badan hukum yang bernama Manajer Investasi untuk kemudian diinvestasikan ke portofolio

Berdasarkan hasil penelitian ini telah diperoleh kesimpulan, sebagai berikut: Hasil penelitian tentang perspektif akuntan inter- nal pada lembaga keuangan syariah di

Dengan benda itu, jangankan sampah Nenek Raudah, sampah satu kampung kita ini pun bisa Kamal buang ke bak sampah di ujung kampung,” jelas ibunya sambil memperlihatkan sebuah

Tujuan dari penelitian ini adalah mengetahui nilai – nilai budaya apa yang terdapat pada iklan produk Nabati di Vietnam dan Indonesia.. Kemudian secara khusus, tujuan

Oleh karena itu perusahaan dengan total aset yang besar akan lebih mampu untuk menghasilkan tingkat keuntungan yang tinggi, sehingga laba tersedia bagi pemegang