Milestone Review
Improvement Phase Complete
Matt Evans | www.exinfm.
com
2
Three Immediate Improvements
1. Require a reconciliation / comparison to the
General Ledger
2. Require training:
1. Invoices – Entering Expense Entries into the Project
Management System
2. Time Sheets – Entering Time Sheets into the
Project Management System
Matt Evans | www.exinfm.
com
3
Two Long Term Solutions
1. Automated comparison of invoices by invoice
number between GL and PMS
2. Automated Email notification to employees
who fail to submit time sheets
Matt Evans | www.exinfm.
com
4
Implementation Timeline
Ref
Solution
Implement
Complete
VS.1 Reconcile Vendor Invoices to General
Ledger System Request 2 to 4 months to complete VS.3 &
TS.2 Training – Invoice Entry ProceduresTraining – Submitting Time Sheets 3/1/084/1/08 5/1/085/1/08
TS.1 Project Managers approve time sheets 5/1/08 6/1/08
VL.1 Automated Reconciliation Routine
between PMS and General Ledger System Request 10 to 14 months to complete TL.1 Automated Email Notifications when
Matt Evans | www.exinfm.
com
5
Two Phases to Immediate
Solutions
Lead
By
Example
All Remaining Projects:
15 Projects / 28% of Total Costs
Four Major Projects:
D001196QC02
D002743LB02
D008763VM01
D009441GS02
72% of Total Costs
Phase 1: March 2008 through May 2008 Phase 2: June 2008 through September 2008
Leverage on what we’ve already done with the four big projects and get them
compliant early. This will set a strong example for getting the remaining
Matt Evans | www.exinfm.
com
6
Monitor and Control
Final project phase will:
• Establish a Control Plan to monitor defect
rates per continuous sampling
• Set initial performance goals and revisit
performance goals once initial goals have
been met
Matt Evans | www.exinfm.
com
7
Project Status
• Project is essentially complete –
approximately 30 work products delivered
(Thought Process Map, Sample Plan,
Attribute MSA, Scatter Plots, Z Test, etc.)
• Major task ahead is to implement
solutions over the next six months
• Impact should be felt within three months
– higher quality of cost data
Matt Evans | www.exinfm.
com
8
Project Performance
The project is ahead of the current schedule. We originally expected to be completed the end of February 2008. Probably can move this up to early February 2008 with a final close out report in late February 2008.
Reason: Fairly straight forward now that we know what the solutions are.
The project should come in under-budget since once we got past the Analysis Phase, the final project steps were fairly straight forward.
Total costs incurred to date (as of December 6, 2007) . . . $ 282,000 (54% spent) Project Budget . . . $ 522,000
Remaining Budget . . . $ 240,000
Schedule Performance
Matt Evans | www.exinfm.
com
9