PULAU SUfiATESA
TECHNICALASSISTANCE
FOR SUPPORT OF
THE PROJECT MANAGEMENT
UNIT
coRE
TEAM CONSULTANTS
(CTC)
QUARTERLY
REPORT
For
the
Second
12nd;
Quarter of
the
Year
2017
MINISTRY
OF PUBLIC WORI(S
&
HOUSING
DIRECTORATE GENERAL OF HIGHWAYS
DIRECTORATE
OF
ROAD NETWORK DEVELOPMENT
@re
Team
Gonsultant
for
West€rn Indonesia t{ational Roads Improvement ptej€€t (WINRIP)
IBRD
Loan
o,8043-tD
Perentftna
OjajaI
t
t
I
I
I
I
I
I
t
I
I
I
I
I
I
I
I
I
'
OurRef.No.
:03
10/LFWO/Q-2.2017
Jakarta,
July24,2O17
Directorate
General of Highways,
MpWH
Jl.
Patimura
20
Kebayoran Baru
Jakarta
Selatan
lndonesia
Attention :
Andria
Muharami Fitra,
ST.
M.Eng
Ofiicer
In
Charge pMU WlNRlp
Subject
:1.
Direktur
Jenderal
Bina Marga
2.
Inspektorat
Jenderal,
Kementrian
PU-PEM
3.
Direktur Transportasi
-
Bappenas
!
Direktur Pengelolaan
Kas Negara
(PKN), Kementrian
Keuangan
q
pireKur
Pengembangan Jaringan
Jalan,
Dit.Jen Bina Marga
6.
Direktur
Jalan
Bebas Hambatan, Perkotaan
dan Fasilitasi Jalan Daerah, Dii.Jen Bita\4arga
7.
Direktur
Pembangunan
Jalan,
Dit.Jen
Bina
I
arga
B. Direktur
Preservasi Jalan, Dit.Jen
Bina
Marga
9.
Biro Perencanaan
&
KLN,
Kementrian PU-PERA
10.
Kepala Balai Besar Pelaksanaan
Jalan Nasional ll
Medan
11.
Kepala
Balai
Pelaksanaan
Jalan Nasional
lll
padang
12.
Kepala Balai Besar Pelaksanaan
Jalan
Nasional
V palembang
13.
Kasubdit
Keterpadtran
Perencanaan
&
Sistem
J€ringan,
DPJJ
-
DJBM
14. Kasubdit
Manajemen Konstruksi, DPJJ
-
DJBM
'15.
Kepala satker
Pembinaan
Administrasi
dan
Pelaksanaan pengendalian pHLN
16.
The
World
Bank Office, Jakarta
17.
PT.
Perentjana
Djaja
18.
Yongma
Engineering
Co, Ltd
19.
PT.
Epadascon
Perrnata
Engineering
Consr:lltant20.
File
PT. PEREr'ITJAflA DJAIA ln subconiultancy
with fr
Yongma Engineering Co. ttd andilFr.
Epadascon permaF. Engineering consultant CTC Office; ll, Ciniru Vll No. 25, Kebayoran Baru, Jakana Selatan, 12180Phone /Far: (021) 7229823
In
compliance with ltem
No.3 (List of Documents
To
Be Delivered) of
our Consultancy
Contract, we
submil
herewith the Quarlerly Progress Report covering the Second (2nd) Quarter
of
the Vear
2fi 7 (April,
May,June
2017).
This report
is
reproduced
and
submitled
intwenty
(20) copies for distribution to all concerned authorities.
Should
you have any comment or
additional
information
that
need to
be
incorporated in the
Repori,
please
feel free
to
get
intouch
with
us.t
-l
G
=
=
o
-F
u
o
J
F
(J
ul
'f
o
E
r
I
I
I
I
t
t
I
I
I
I
I
I
I
T
z?
3 $
/ a/
a<'
&,7,tr
_11
I
7. al
/ ?a
/'.
z-z
tt
tl
:'
+. ,i i.!
f3
-<
f.,t
:t
F:
a, ?.
6
{
!.a..
:
'l
,
l
I
3
t
r
t
I
T
t.
b
s
;
I
+
E
3
I
:t
z
{
a
!
n-{
7
z
z
x
F;.:
\p
!|4
5
I
I
t
I
I
I
I
I
I
t
I
I
l
i
I
I
I
I
I
I
2017
Quarterly Progress Report
2noQuafter
:ApriFMay-June
I
I
I
I
t
I
T
t
I
I
t
I
I
I
I
I
I
I
t
APPENDICES
Appendix
S-1Appendix
S-2Appendix
S-3Appendix
S-4Appendix
1-Appendix
2Appendix
3
Appendix
4
Appendix
5Appendix
6
Appendix
7Appendix 8
Appendix
9Appendix
10Appendix
11Appendix
12Appendix
L3Appendix
14Appendix
15Appendix
16Appendix
L7Summary of Studies and Reports
(Environmental Activity)
Summary
of Studies
and
Reports
(SocialActivity)
Com
munity Development Activity
Reports
Community
Representative Observers
(CRO)Reports
Disbursement and
Expenditu resStatus
Report
At
The
Endof
TheQuarter
(December 2016)
Detailed
Summary of
the
Project
CostMonitoring
Procurement Management of
CivilWorks
Procurement
Planfor
Consulting
ServicesList
of
Names
of Community
Representative Observers
(CRO)Anti Corruption Action
Plan (ACAP)Activity
Progress
of Community
Representative Observers
(CRO)List
of
Appointed Third
Party
Monitors
(TPM)
Progress
of Third
Party
Monitoring
(TPM)
Activities
Complaints
Handling
Mechanism
System
(CHS)Work Activities
On
Pub licationr/Disclosu reEnvironmental
Safegua rdsEnvironmental Management
Plan (EMP)Compliance
Status
of Monitoring of Environmental Mitigation
Overall
Land
Acquisition
Status
asof
Endof
December 2016
Status
of
Road SafetyAudits
Summary of
Workshops and Trainings In 2013 up
to
December 2015
2016
Quarterly
ProgressRepoft
2noQuarter
:April-May-June
I
I
I
I
I
I
I
li
I
I
I
t
Annex
P-l
Annex
P-2An
nex
P-3Annex
P-4Annex
P-5Annex
P-6Annex
P-7An
nex
P-8Annex
P-11Annex
P-12Annex
P-13Annex
P-14Annex
P-15Annex
P-16Annex
P-17Annex
P-LgAnnex
P-20Annex
P-21ANNEXES
Package
No. 1
(Biha-
Krui)
Package
No.
2 (Pd. Sawah-
Sp.Empat)
Package
No.
3(Manggopoh
-
Pd, Sawah)Package
No. 4
(lpuh
-
Bantal)
Package
No.
5 (Sp, Rampa-
Poriaha)
Package
No.
6 (Ps.Pedati
-
Kerkap)
Package
No.
7(lndrapura
-
Tapan)
Package
No. 8 (Bts. Kota Pariaman -
Manggopoh)
Package
No. 11 (Bantal
-
Mukomuko)
Package
No. 12 (Kambang
- Indrapura)
Package
No.
13
(Sp. Rukis-
Tj. Kemuning)
Package
No.
14(Painan - Kambang)
Package
No. 15
(Sibolga-
Bts. Tapsel)Package
No. 16
(Seblat-
lpuh)
Package
No, 17
(Sp.Gunung
Kemala-
PugungTampak)
Package
No.
19 (Lais-
Bintunan)
Package
No. 20 (Lubuk
Alung
-Sicincin)
Package
No. 21
(LubukAlung
-Kuraitaji)
I
,]
I
I
I
I
I
2nd
I
I
I
I
T
I
I
I
t
I
T
I
T
I
t
T
I
I
I
2017
Quarterly
Progress
Report 2ndQuafter
:April-May-June
Executive
Summary
7.!
CurrentlmplementationSituation
1.1.1
Civil
Works
lmplementation of the
WINRIP
Project
is scheduled
to be implemented into
three
(3)
Annual
Work
Programs (AWP's). The implementation starts
with
the
preparation
of
tender documents (detailed
design
drawings including
associated
bidding documents),
tendering stage
(procurement
of works) and
the
actual civil works
construction
implementation.
The
original implementation
schedules
of
the
three
(3)Annual
Work
Programs
(AWPs)are
scheduled
inthree
(3) phases,
namely;
AWp-1
to start
in
mid-2011
andto
becompleted on
the
last quarter
of 20t4,
AWP-2 is
expected
to begin in mid 2012 with
target date of completion
by
mid-2016
and AWP-3
isexpected
to
start during the early
part of
2013 and
to
becompleted during the middle part of Z0t7.
However,
due to
some unavoidable
circumstances
the
original
implementation
schedules
did
not materialized.
Based
on the
present
status
of
the
program implementation
progress,
a
revised
implementation
schedule,
the
Project
lmplementation Timeline
(asshown
on
Page2)
isto be
implemented in order
to
accommodate
the originally
delayed schedule
into the
remaining
time
frame
of the
wlNRlp
program
until the
expiry date
of the
loan
agreement
by
the
end
of December
2017. Shown
on
Page3
isthe current construction
status
of
the implementation relative
to
the Project lmplementation Timeline. Table
1 [image:7.597.59.552.462.786.2]shows
the present
status.
Table 1- lm
Status
asof
Endof
the
2noQuarter
on June
3Q
2017
Faci(No. Package Name
eontract Sign
under Construct
ijnder Defeci Liabiiiiy
Perlod
1 Krui- Biha
{
Completed2 Padang Sawah - Sp.Empat Completed
Manggopoh - PadanB Sawah Completed
4 lpuh - Bantal Completed
5 Sp, Rampa - Poriaha
6 Ps. Pedati . Kerkap Completed
7 Indrapura - Tapan 8 Bts,Pariaman - Manggopoh
T! Bantal - Mukomuko
t2 KambanB - Indrapura 13 Sp. Rukis - Tj. Kemuning
74 Painan - Kambang .i
15 Sibolga - Bts.Tap Sel 16 Seblat - lpuh
"j
Sp,Gn.Kemala - Pg.Tampak ./
19 Lais - Bintunan .J Completed
20 Lubuk Alung - Sicincin
2L Lubuk AlunS - Kuraijati .J \i
TOTAL: 18 12 6
Pa€kage No.9 (Rantau lijans - Kota Agung), Package No.18 (Mukomuko - Bts, Sumbar) are cancelled from the program and No,10 l5p. Emoat- SD. Alr Ealaml is
Western Indonesia National Roads Irnprovement project
to be cancelled,
\l o!
Nl |nl bl
ol EI
I
:
i
f,3i
rIi
{{E:T
!-3 e
P isid
"iE nno-o'.-llo
;
o o F -5fr!,
ds
-$qjr i
;FA
o
o
o
t!
o
c
o
o. EP l,
o
o
tl
€*o
SBfBH
;.,
P'!
(Uf
>-E
o_
(u P
(o f
ct
N
t
o
OJ
(n
\
d! o)
s
a)
t
f N NI
T
t
t
t
I
I
I
I
I
I
t
I
I
t
I
.!t ! r:F
a
e\
l
I
E
d
F
z
E
z
5
z
t
bE
to6
!:FF;
l<{ F i r
n,:!tc'
odd{;
!i ci o'
.-i
:;;,
i];
;r
8i:
a; !
,t.;:
36;
6o;
sBidf;
]E
v
d
d
Etl)
o-E
E
lo
d
rg
c
.F
|o
z
.lE
o
c
o
C
o
E,
z
3
o
(u
E
c
o
|E
o
Eg
CL
(g
IJ c,
=
-!
'tr:
o)
P
N
E
c.)
d
aJ) OJL
6)
0)
r
5N
o
N
I
l
I
I
t
I
t
I
I
I
I
t
I
I
t
I
I
t
I
2017
Quafterly
Progress Report
2ndQuarter
:April-May-June
t
I
I
I
T
I
I
I,
I
t
I
1.1.2
Consultancy
Services
cTc
lul2012
5
Nov 2012 L2 Nov 2012DSC Jul2012 11Jun 2013 19Jun 201"3
Capacity Building for Disaster Risks Reduction
Cancelled
Development of Slope Stabilization, Design and Management
June 20L7
Capacity Building
for
Environmental Management Cancelled
Capacity Building
for
Road Safety Cancelled
The technical
assistance
for
consultancy
of
"capacity
Building For Disaster
RiskReduction"
has been deleted,
but
replaced
by
,'Technical
Assistance
for
Development
of
SlopeStabilization,
Deslgnand
Management,,.
To accommodate the new consultancy
assistance,
allocated funds from category
3which
is
originally intended
for
"capacity Building
for Disaster
RiskReduction,,
hasbeen realigned
to
category
2
to
fund
the
implementation
of the
new technical
assista nce.
I
t
l'
t
I
I
I
t
2017 Quarterly
progress Report
2no
Quarter
: April-May-June
L.2
Current
Status
of
Loan
At
the
end
of this
quarter on June g0,
zor7
some 47.64%
or
usD r.r.9.09
million of
the
available
loan had been disbursed,
which
is 5.64%o overthe revised
forecasted expenditures
of 42.00%
(USD105.00
million)
at the end of the quarter.
Total
disbursements
during
this
Quarter
amounted
to
USD 13.51
mition
covering
the
payments
for
"Statement
of
work
Accomplished,
(Mc) to
civil works contractors of the
on-golng construction packages and advance payments
to
Contractors
of
newlv
started
contract
packages.
Details
of the
Disbursements
ancl
Expenditures Status are presented
in Appendix
1.A
more
detailed
and
updated status
of
the
roan
are fuily
described
and
presented
ineighteenth (l8th) Quarterly Financial Report covering
the 2nd
euarter
(April-May-J
une)
of
the
Year2017 which
isunder preparation
and
wiil
besubmitted separatery.
Current
Problems and
Action
Required
t
l,
t
I
I
I
I
I
I
I
I
I
I
1.3
Program
AWP.1
4 FJos. Completed and provisionaily l-rarrded over. iJnder ciefecis
liability period for seven hundred and thirty (730) days.
Contractol, DSC aitd
PPK
Ca pacity
Buildrngfor
I cancelled
LJrsasrer Htsl(s Keduction I
Technical Assistance
for
Still in selection process. Development of SlopeStabilization, Design and I
Managernent
I Ca pacity Buildingfor
i
Environmental
]
CancelledManagement
lContractor, DSC and PPK
Contractor, DSC and PPK
POlg4 Sub-Directorate
of
Geotechnical and Slope l\ilanagement, Directorateof
Road Construction, DGH,MPWH
Capacity Building
for
IRoad
Safety
I
Cancelledt
l,
t
I
I
I
2017
Quarterly Progress
Repot
2ndQuarter
:April-May-lune
General
2.t
Reporting Requirements
Quarterlv
Prosress Reports:
This is thirteenth
(13th)
euarterly
progress Report
asrequired and stipulated
in
CTC'sconsultancy
contract
and
the
Loan Agreement, Prior
to
the production of this report, Monthly
Progress Reports have been prepared
and
have
dealt with
all
aspects
of
the
works. This
report
attempts to bring
the
situation
upto
date
by
covering overall progress up
to the
end
of
second
(2no)euarter
of
the
year
201-7.Financial
Monitoring
Reports: These have been prepared
for each quarter since the
beginning
of
2013
with
the first
Report,
issued
in May 2013,
covering
the
period
January
-
March
2013. Since that
date
quarterly
reports have
been prepared
and
su b mitted
regularly.
Report Period Covered Date lssued
Financial Monitoring Report No.
I
January 2013-
March 2013 May 15, 2013Financial Monitoring Report No. 2 April 2013 -June 2013 AuBust 15,2013 Financlal Monitoring Repon No, 3 July 2013
-
September 2013 November 15. 2013 Financial Monitoring Report No. 4 October 2013-
December 2013 February 15, 2014 Financial Monitoring Report No. 5 January 2014-
March 2014 May 15, 20L4Financial lv"ionitoring Repoit No. 5 April 2014
-
June 2014 August 15,2014 Financial Monitoring Report No. 7 July 2014-
September 2014 November 15. 2014 Financial Monitoring Report No.I
October 2014-
December 2014 April 7, 2015Financial Monitoring Report No. 9 Januarv 2015
-
March 2015 August 31, 2015Financial Monitoring Report No. 10 April 2015 -June 2015 October 2,2015 Financial Monitoring Report No. 11 July 2015
-
September 2015 December 16, 2015 Financial Monitoring Report No. 12 October 2015-
December 2015 February 10, 2016 Financial Monitoring Report No. 13 Januarv 2016-
March 2016 June 8, 2016Financial MonitorinB Report No. 14 April 2016
-
June 2016 August 25,2016 Financial Monitoring Repori No, 15 July 2016-
September 2016 December 2, 2016 Financial Monitoring Report No. 16 October 2016-
December 2016 March 20, 2017Financial Monitorin8 Report No. 17 January 2017
-
March 2017 June L4, 2017Financial Monitoring Report No. 18 April 2013
-
June 2013 Under Preparationcrc Monthlv
Proeress Reports: These
report have
been prepared covering each full
month
since January 2013, subsequent
reports have been submitted
on
a
regular
monthly
basis.Environmental studies and
Activitv Reports: These
report
have been
continuously
updated and submitted
to
PMU
for
subrnission
to
World
Bank
for
Bank's issuance
of
Noobjection Letter
(NoL).
Appendix
s-1 shows the summary
of
submitted
of
Reports
covering
each
contract
packagesince
inception
of
the project.
social lmpact
studies and
Activitv
Reports: These
report
which mainly dealt
with
the
implementation
of "Land Acquisition Resettlement
Action plan"
(LARAP)
have
oeen
continuously submitted
to
PMU
for
submission to world
Bank
for Bank's issuance
of
No Objection Letter
(NOL).
Appendix
S-2 indicates
the
updated summarv
of
all
submitted
Reports.
I
I
These
Reports
have
Appendix
S-3
shows
been
prepared
the summary
of
and
continuously
submitted
to
the
Client.
submitted
Reports
from the
very
first
(1't)
I
I
T
I
I
I
2017 Quafterly
ProgressReport
2ndQuarter
:April-May-June
Reports: These Reports
were
consolidated and reviewed by
CTC
as prepared
and
submitted
by
the
appointed
CRO's
and
TPMs
of
the
respective
contract
package.
Their reports
were based
on
their
actual
observations and monitoring
during
pre-bid
meetings, site visit and bid openings of every contract
package
under procurement.
Appendix
S-4shows
the updated summary of
all
reports which were forwarded
to PMU.
2.2
Loan
Status
The agreed
allocation of
loan
funds
from the original loan agreement together with the
%disbursed
bythe World
Bank
to the end
of
the quarter date
(June30,2Ot7') is presented
in
Table
2
Table
22.3
Financial
Management
S-Curve
for
Financial
Progress
*F*F
J,"d"
""F*P
'*"9
-"$
*d*F
'J
".C
""F*d
*+"
,"tr
*t'*s
*S ,J
""t
*f
,.S
A
report
at theend
ofthe
quarter
(June30, 2017)
ispresented
in Appendix 2t
l.
I
I
I
t
I
I'
t
I
I
I
t
C€tegory Description Ioan Restructurlng Amount USS
Total Dlsbursernent forthe 2d Quarter ol
2017
Previous Dlsbursement
TotalDisbursed by WB to End June30,
2017In Uss
% Dlsbursed
1 Part
l
Betterment and :apacity Expanslon of NatlonaRoads.
220,400,000.00 x3,509,633.35 98,794,523.72 I72.304.756,4'' 50 95
Pan 2 [[PrEIrEnrduqI Julrlru] r
17,000,000.00 0 6,790,105.83 6,79 0, 105.83 39.94
3 Part 3
Road Sector Institutional
0 0 0 0 0
4 Part 4
Contingency for Disaster Risk
0 0 0 0 0
llnallocated 12,600,000.00 0 0 0 0
OrlglnilLoEn
Amo!nt 250,000,000.00 13,509,633.35 105,584,628.95 119.094.262,30 47,64
[image:13.597.0.571.209.777.2]I
I
I
t
T
I
I
I
I
2017 Quarterly
ProgressRepoft
2noQuafter
: April-May-June
2.4
Project Cost
Monitoring
A detailed
summary
of
the
project cost monitoring
in
tabular
format
is presented
asAppendix 3 at the
end of
this report.
2.5
World
Bank
lmplementation
Review
Mission
and
Site
Visit
During
this
2ndquarter,
there
was
a
World Bank
supervision
for
implementation review
took
place
on
Jul L7,
2017with the
kickoffandwrap up
meeting
respectively.
The
Technical and
Financial
Audit Consultant
(TFAC)rnission
took place
on
25,
April 20J.7
until 24, March 201.7
with site
visit inspection
on Packages No.74,2O and
20respectively.
Introducing
TFACwas
held on January
2ot7
for
packages
No.g,
12, L4,
16,
zo and
2J. inPadang by
World
Bank.An "Agreed Key
Action
Plans"
for
progress compliance monitoring
of
the
status
of
the
works on
monthly interval
is shown in Table3.
Table 3
"fureed
Key
Action and plans',
Status
as
of
end
of
2nd
Quarter
{June
20Ul
I
I
I
t
l'
T
I
I
I
I
No. Action By Whom
Upciaie Staius tulv t7, 2Ol7
New Deadline
!.
Send to the World Bank (WB) the contract modification request for package 03 {for additional stone masonry)
-
World Bank will only approve it if TFAC findings for packages 2 and 3 are followed up/contractor complies with his defect liability.PMU and CTC.
After the follow-up by the contractor of the TFAC findings of packages
lanoS
Send to the WB the request for contract
modification and time extension for package 05- PMU and CTC.
July 18, 2017 3. Send IPPKH license to work in the 1.59 km where
the road crosses the protected forest for package 5. PMU and CTC.
Septem ber 11,2017
Inform the WB about the possibility use ABpN money to construct the additional drainage under package 06 to avoid that water enters into a housing area.
PMU, CTC and DSC.
This is included in 2018 ABPN budget.
5. Send to the WB a reevaluation of the proposed solution, including a unit rate analysis for the concrete pavement construction for package 15.
WB End of July 2017
Send to the WB report with the results of the investigation conducted by the Inspectorate General regarding the problem of the undue invoice under package 14 and the follow up by Bina Marga.
PPK, PMU and cTc
End of July 2017
Inform the WB about what they plan to do with package 12 (PT LMA and PT. CTA), which is currently for consideration with the Director (third show cause meeting failed ).
PMU and cTc. Next review meeting
L
Send WB the DSC report with analysis that shows that the solution is adequate given the deterioration of the pavement (cracking one year after overlay for biking event- possible problems underneath) in
package 20.
DSC, PMU and cTc.
End of )uly 2077
9. Inform the WB about the progress in package 21 (3'd
Show Cause Meeting succeeded) PMU and CTC.
Next review meeting 10. Inform WB about the need for a contract
[image:14.598.23.585.313.802.2]I
I
2017 Quarterly
Progress
Report
2nd
Quarter
: ApriFMay-June
I
I
I
t
T
I
l(
t
T
I
I
I
I
I
I
I
I
I
No, Action By Whom Update Status
luly
L7,2017New Deadline
additional sections.
11
|
Package 8 may need a variation orderfor a seiondI
lanefor part of the section (contract ends inI
December 2017).PMU and CTC. No dea dline yet provided
different
ng by the Next review meeting
13. Start contract for the slope stabilization, design, and
management assignment (11 months). July 7, 2OI7
14 Send to the WB the 2nd DSC contract modification
for price escalation. PMU and CTC. No date provided
t5
Send to the WB the information on how the inundated spots on the road of package 7 will be fixed.PMU and CTC. End of July 2017
l_6
Re-send to the WB the revised environmental management and monitoring plan (RKppL)
for
package 16, including additional info on partofthe
section as well as the environmental docurnentation used to obtain the quarry licenses.
PMU and CTC. As soon as possible
L7
Send to the WB the environmental management and monitoring plan of RKppls and UKL-UpL implementation quarterly and every semesTer respectiveiy for all packages.
PMU and CTC.
Quarterly and each semester
10
Report to the WB on the implementation of the action plan on how to avoid spills in base camps and improve base camp management in all packages with problems (including photos of progress in the field)
PMU and CTC. lmplementalion ongoing
End of July 2017 or
if
posslble earlier19. Carry out the last HIV/AIDS workshop for package
r|]. PMU/Crcl DSC.
.
Packages 16: May20L7 20 Provide WB with a list of the packa8e with base
camp management issues (oil spills, inadequate drainage).
PMU/CTC
Done email to WB on 2 May 201,7
21. Training on base camp management for contactors,
DSC, PPK. WB
Done on 11, 18 & 22 May
20t7
22. Send letters to the contractors informinB them that they are violating the rules by not adhering to cenain base camp management practices.
DGH/PMU/CTC
Done (the list of letters emailed to WB on 6 June 2OL7l
t3
Inform the WB on the role BLH and the
environmental department of Bina Marga can play to improve base camp management performance since this is against the local laws.
Subdit LKJ/PMU/CTC
Mid-August 2017
24 Update the Winrip website with all environmental documents including RKPPLs, RKPPL and other monitoring reports, etc.
PMU and cTc. End o{ July 2017
25 submit to the WB LARAPS monitoring reports for
packages 07, 08, 12, 73, 1,4, ].5, L7,20, and 21. PMU and CTC. Reporting ongoing
End of August 2017
26 For package 05, send to the WB the LAMp
implemenlation repon for the remedial action. PMU and cTc.
Delayed
september 2017
I
t
t
I
I
I
I
l,
t
I
I
I
I
I
t
I
I
I
I
2017 Quarterly
ProgressRepoft
2ndQuarter
:
Aprir-May-JuneNo. Action By Whom Update Status
tuly
t7,2OI7
New Deadline
27.
I
For package 05, send to the WB the addt'tionalI
LARAPfoT additional affected assets. PMU and CTC.Delayed Mid of August 2017
z8'
|
,rbr,,.o
,h"
*B
the 2016 tinancial audit report. PMU and CTC. End of Dec 201729.
I
Submit to the WB the quarterly tFR for the periodI
April to June 2017. PMU. August 15, 201730 Send to the WB the TFAC response for the first visit
of packages 20, 2L, !4.
PMU/Dsc/ cTc.
.
Package L4: UnderprocesS
.
Package 20: lnformal(June 5, 2017) PackaBe 21: Informal
(June 15, 2017)
Package L4: Mid of August 2017
Package 20: End of
July zOU
5-t.
Send to the WB the follow up to TFAC findings
for
packages 3 (never received a feedback - concrete
drainage broken, asphalt start waving, ...) and 2
(asphalt already broken).
.
Mid-August 2017.Send to rhe WB the TFAC response:
1. For the first visit of packages 05, 08, 13, 15 and 17
2. For the second visit of package 06packages 0S, 06,
08, 13, 15, and 17.
PMU/DSC/ cTc,
Package 05: Done (April 4, 2c171 Package 06: Done
(March 21, 2017) Pack-age 08: Done
(March 31, 2017)
Package 13: Done {March 21, 2017} Package 15: Done
(March 31, 201.7) Package 17: Done
(March 21, 2017)
33
Send to the WB the TFAC response:
1.
For the first visit of package 122.
For the second visit of packages OS, OB, 75, 07, 13 and 17PMU/Dsc/ cTc.
r
Package 05, August 9,2017
.
Package 08, August 10, 2017o
Package 15, August 9, 2017r
Package 07, August 11. 2D17.
Package 13, August 18, 2017.
Package 17, August 14, 2017.
Package 12, August 11, 20175.+. Next supervision mission document progress in
terms of cancelled combonent C, WB
.
August 201735 Submit regularly to the WB the quarterly progress
reports. PMU,
This adivity must be
carried out every
ca lendar quarter.
36.
U pdate the newsletter quarterly, including the list of contracts, implementation progress, project related workshops, and number, typology and status of complaints.
PMU.
This activity must be
carried out every
calenda r quarter.
37 Send the quarterly newsletter to the civil society
fonrm in each project province in hard copy or PMU.
This activity must be
carried out every
2017
Quarterly
progress Report
2nd
Quafter
: April-May-June
2.6
Project Steering
Committee Meeting
No
Steering
Committee meeting during this quarter,
t
t
t
I
I
I
I
Ir
t
T
I
I
I
l(
I
I
I
I
I
2017 Quafterly
ProgressReport
2ndQuafter
:April-May-June
I
I
I
I
I
t
I
I
I
t
I
I
I
I
I
t
I
I
I
(_,
Project
Management and lmplementation
3.1
Procurement
Status
(A) Civil
Works
Civil
Works
are now
being implemented
in
Annual
Work
Programs
(AWP)
which
have
been
numbered
AWP-I,
AWP-2, and AWP-3.
All Contract Agreements
for
the
four
(4) AWP-1 contract
packages
were signed by
the
end
of
2013
with
actual work commencement
on
january
2014.
Under
the other
two (2) implementation programs,
AWP-2
and
AWP-3,
fourteen
(14)
packages
were already procured.
Table
4 Shows
the actual pre-construction
and
procurement status
under
the
implementation
schedules AWP-2 and AWP-3
Table
4
Procured. Under construction since
the
issuanceof
Notice To Proceed (NTP) on June L8, 2015Procured. Under construction since
the
issuanceof
Notice To Proceed (NTP) on March 11, 2015Indrapura
-
TapanProcured, Under construction since
the
issuanceof
Notice To Proceed (NTP) on December 10, 2015Bts. Pariaman
-
ManggopohProcured.
Under
constructlon
slnce
the
issuance
of
Notice To
Proceed (NTP)on
March23,20L6
Sp. Empat
-
Sp.Air
BalamCancelled .
The
road isstill in relatively
in goodcondition
and
wldening
is
not
needed lmmediately.Bantal
-Mukomuko
Procured. Under constructionof Notice
To
Proceed
(NTP) sinceon
February
the
issuance23,2015
Kambang
-
IndrapuraProcured. Under construction since
the
issuance of Notice To Proceed (NTP) on May 23, 2016. [image:18.597.16.545.100.768.2]2017 Quafterly
ProgressRepoft
2noQuater
:April-May-June
I
I
I
I
I
13 Sp, Rukis
-
Tj. KemuningProcured. Under construction since
the
issuance of Notice To Proceed on July 22,
2015
AWP.3
t4
Painan-
Kambang Procured. Under constructionof
Notice To Proceed on August since 3, 2016the
issuancet5
Sibolga-
Bts. TapselProcured. Under constructlon since
the
issuanceof
Notlce To Proceed (NTP) on Novesrber 20,2015
16 Seblat - lpuh
Procured. Under construction since
the
issuanceof
Notice To Proceed on November 8, 2016.t7
Sp.Gn.Kemala-
Pg. TampakProcured. Under construction since
the
issuanceof
Notice To Proceed (NTP)on September 4,2015.
19 Lais
-
Bintunan Procured. Constructioncompleted.
UnderDefect
Notification
periodfor
730 days.20 Lubuk Alung
-
Sicincin Procured. Under construction sincethe
issuanceof
Notice To Proceed on September 1, 2016.zt
Lubuk Alung - KuraitajiProcured, Under construction since
the
issuanceof
Notice To Proceed on September 1, 2016.Note : No.g and No.18 are cancelled from the m.
Presented in
Appendix 4
isthe current status of procurement management.
(B)
Services
The Core
Team
(CTC),Design
&
Supervision
Consultant
(DSC),and
the others
Capacity
Building Consultancy status are discussed in Section 3.4.
lmplementation
Status
-
Civil
Works
As
of
end
of this reporting quarter (June 2017),
six
(6)
of
contract
packages
were
already
completed and
currently under defects
liability
period
for
seven hundred and
thirty
(730)
days
effective
on
the
day
the
TOCswere
issued.
Twelfth
(12)
packages
are
on-going construction. Details
of
each
contract
package are
shown
inTable
5.I
I
Ir
t
I
I
I
t
It
3.2
I
I
I
I
I
t)
0)ll
(EF
0) ro:
-J-Itt'r
c!
ts
o-o
&.I
=
p.,l EI
T
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
t
! F-.'^ d:>x
tr F\Sr.
;ri D3R
o
i';
5ER
3h
ER
H:
B.
$5
o
t'i \
t
t
oo-c
o
c
q) o-E (!E
o
(Dz
(!o
E E E F. o F,o o 6 A
o
oa\
c
t\
o
o
o@
f.. N l'-N
F oiF. o
6
F]
N
t
o.9
o
dF.
a o
:
d oI
3
o
c
o
l'-o o o o
oi a 6
(\1-)
g:
EN
L::-.-9
$5
Nd o c Eo
6 o F.o o o 6 o o o
;
o 6 o ao
l'. @ l'-o_ F-N
g*
I o .:z
FE3
dc
(.o_
iN o
dx
R.c ln_ ,^
R9
N-p3R
d.^
:5
z
dtoz
J E$rn
BF
2 o o :-tsHz
:5
tg
8N
z,>o9-g
3R
c'l=g
o3R
9g
.}9
5
2O.r' 2 e=E
;g
BE
9E
:
E f,!u -ai E 5a tq?3E
!fig
3E
z
g=E
ez\
E @ g;g
3E
3E
e o 4 Ez
:F
'.=
", L^P6*-(,
E ci .:€:
>d
1!
;
cc .9F I g E
YE
:s
ii2 co2 I !49i:s
tr.!:. c
E
.s
I
-bo I
_a T boE -9 I
:
I <6-3c
39
ot
e IJ f.-'a(!UE
Jo oErs
_a '6 e2+
9E
l-=F
fi6 n6 oEtr>
F6o
to
tE
;g
5>
ijiqzE
-BFE
.
= F=
o F.
EYr>.
f,>
F fq EO j-; F< -3ittr
o^s
fi!!;e
cq8:i
Ec xq-q, E Fd >Y
ea
UE
v!hs
.= F-2
F -ti = FHE
t*
o83
.\
F. F.
a.l €
IR
! = 3I
2017 Quafterly
Progress
Repot
2noQuarter
:ApriFMay-June
I
I
I
I
I
I
Activities done during
this
month on
the
on-going
construction
packages
were repair
and
restoration
of
deteriorated existing
pavements,
roadway
excavation,
embankment
formation, spreading of granular pavement
for
roadway widening, asphalt
paving,
structural
works,
construction
of
stone masonry side ditches, stockpiling
of
raw material, production
of crush
aggregates,
other minor
works, bridge
construction, finalization
of
,,FieldEngineering" surveys
and mobilization
of
resources of
the
newly started contract package,
The
four (4)
contract
packages
under
implementation program
AWp-1
were
already
completed
and now
under defects
liability
period
for
two
(2) years
since
the
issuance
of
TOCs.
Under
the
implementation program AWP-2 and AWP-3,
there are
currently
twelve
(12)contract
packages
that
are on-going construction implementation.
Physical
progress
of
six
(6)of the
packages
are
lagging
far behind
schedule
with
negative slippages
trom -34,62%to
-72.21%
while
progress
for the
other
four
(4)
packages
are
still
slightly
on or
behind
schedule,
two
(2) packages are on ahead schedule.
[image:21.598.14.563.28.806.2]Progress
status
of
the on-going
civil
works contracts
asof
this reporting period
are
shown
in
Table 4.2.
Following are
brief status of
the on-going construction contract
packages: PackageNo.
1 : Biha
-
Krul
The
contract
package
is completedon
January 20,20L5 and provisionally
handed over
to the
Employeer
and
currently under
"Defects
Notification period"
until
after
two
(2)
years
reckoned
from the
issuanceofthe
TOC.A more detailed previous status during the whole duration
of
the contract implementation
ofthis Package
ispresented in
ANNEX P-l Executive
Summary Report.
Package
No.
2
: Padang
Sawah-
Sp.Empat (lncluding
Air
Gadang Bridge)
The contract
package
is completed
on April
14,2oLE
and provisionally handed over
to
the
Employeer
and
currently under "Defects Notification
period"
until
after
two
(2)
years
reckoned
from the
issuance of
the
TOC.ANNEX P-2
Executive
summary Report present
a
more detailed status during
the
whole
duration
of the contract implementationof
the Contract
Package.Package
No,
3 :
Manggopoh
-
Padang Sawah
The
contract
package is
completed
on March 77,20L6 and provisionally
handed
over
to
the
Employeer
on
March
t7,20].6
and
currently under "Defects Notification Period"
until
after
two
(2)years reckoned
from
the
issuance of
the
TOC.A more detailed status of
the
project progress during
the
whole duration of
the
contract
implementation
are
shown in
ANNEX
P-3"Executive Summary Report',.
Package
No.4
rlpuh
-
Bantal
The contract
package
is completed
on
May
3r,20!6
and provisionally handed over
to
the
Employeer
on
May
31", 2OLGand
currently under "Defects Notification period,,
until
after
two
(2)years reckoned
from the
issuance of
the
TOC.I
(.-I
I
I
I
I
It
I
I
I
I
I
l
ANNEX
p-4"Executlve Summary Report"
shows
the
details
and status of
the project,
I
(!
g
lt
lcF
c
3
?
(!E
1
dt E -! Nt
o
al E. E Et-.>
Ll .E f!,
t c,c
(o -iv .ly '',JU^
(o;.\
Err
=r=
5<
u'.
x
(oo
-N5.4
u'
o
- o-(o-41qj r'
E
c.i;>.
Es
I e) .E ti c, 'So ;! xo oc r-.o
'cr N POO llN,Y
..I o E U o o o
'5
o)-Y. 7i:l ;'o col! qJ E Itt o _o o
';
oreX
6;
;-E (EC F !N qco..:g .\r
Fr!
-o
- o-o) 'r= o';.)
oJ= .? 6'D .E G|tu lEC OJ E (o 7)'= o,
L=
-Y
;iv
o F ! C)'; a,
o= 6_E ;-o aors d, F x g
't
q.)o=
-Y 5_E oc tor5 (o 9?OE.o
c=
o..
o
- o-itj E q, o q) aO o tr 'F i: -o o ro o) ao ]J >'F (!y -od (EF r!> -v N= F. l:.o
J4.>
.9=E
-o2
:(u
tJc
.cl
o
.Ee
CF
0)
E
o
u
o
Ut\
(J F
Ol
(J F Ucrl
d
u
N E'l (J t\ Ch oo (J F F (, EI u'l cls
ln l-' :R{
.!
6 COs
o
ro N<t ,rt 'o
s
oq Ols
ln\
ros
ao q F :R rqri
tYl }R m E(l I\ oi lns
t\ q rn o b! o CI CIls
N ar?€
Nx
(o N N t\ F K t\ qt |n No
U: Fs
F{ or+
N rn o! <lx
a
€
".\Nx
rn
s
GI'4
(o
x
Nto@
rt
s
lr'l\
sr Fs
o!
s
Olct ltl
s
cDq
iYls
tn F cri*
o,i ;R It F Fx
t\ t\ uls
tngP
trtr\
U0CFIguJo
d.sli
e==$Ei
Fg
*
>RtnI
Ot (h
*
bs(ou1ct ql
s
(o ctt ci Fs
t\ Fx
F aot\
s
o
ao N dls
ro$
>R E(l Fo
}R tYt oi F ;€ CO cs F{ Fx
ot ul lrl IE o G2
= roiE
ql oDx 0t) ! l! I :f;-E;
>3
c a" |! E o-o) (u ,. N IE l: I c loY5i
iirEco>
CD o cT
o! c G, E '-l E q) F I .9 3 E cr E I (! '6 o-qJ a-I (! I -.oqJ o! I _a E e= (! c' '-:a I OD I uo J o o (J _g (! boF
-.,2VF
qE
s
GI b! o! J 9-SZF>E
ga
j b! o '|n f?v
>tr
+g
Fi:o-
o-F C^ roO
Eff
=E
f,:
bD .T .= !r F o c,z
F (E -tE:
(tl Fb
E
_oi
-j=
i
Gi
t!i
(E U F A'=
loC /'\
j-F:q
o Q.) e OJ;
.
b_tr
=
(-,) F I l!tr92
toJ tr.o -rf,o-
o-o E =
=
.! F j b.0P -v.
..lo f
o-!
o (! Fa
-oz
F q) f, J Fa! (o t, N F.
a{ c.l
E N
I
2017
Quarterly
Progress Report
2ndQuarter
:April-May-June
I
I
I
Package
No.
5
rSp. Rampa
-
Poriaha
The progress
asof this quarter
isonly
achieved
of
62.37% against
the
scheduled
99.43%.The completion date
is
20,
July
2017, thus the contractor
is
under preparation
of
another
contract amendment for the
increase
of contract value
and
the extension
of
time.
ANNEX
P-5"Executive Summary Report"
shows
the Contractor's
progress Schedule.
Package
No.6:
Kerkap-
Ps.Pedati
The contrast
package
is completed on January
28,20a7
and provisionally handed over
to
the Employer
and currently under "Defects
Notification
Period"
until after
two (2)
years
reckoned from
the
issuance
of TOC.aNNEx
P6
'lExecutive
summary
Repofr!'
shsws
the
complete detail+
of the
contr€ct
package.
Package
No. 7:
Indrapura
-
Tapan
This
quarter
progress
issharply
increased
of 5.4!% comparing the previous month
progress,
L.59%,
Nevertheless
the
main reason
of improved
progress
was
due
to
suspended
working time
for
ci'usher plants
allowed by
the
local people. However
the completion date
of the
lvorks
is3O August 20L7,
hence
the contractor
is
preparing of the contract amendment of contract
value
and
the extension of time including additional lvorks of 4
km
which
issituated
in
the
project
road.
ANNEX
P-7 "Executive
summary Report"
shows
the
complete details
of the
contract
package,
Package
No.8
:Bts. Kota
Pariaman -
Manggopoh
The
progress
as
of
this
reporting quarter is
achieved
of
74.73% against
the
scheduled
73.96% having a
little
ahead
0.77%.Currently unsettled
land
acquisition,
133
paps iscritical
issue
hampering remaining
progress
of
the works
ANNEX
P-8 "Executive Summary
Report"
shows
the
complete details
of the
contract
package.
Package No. 11
:Bantal
-
Mukomuko
The
completion date
ison
26,
May
2017 and
the inspection for the provisional hand-over
isalready
done
and
the
processverbal
has been issued
on
19, May 2017.
For
more
detailed
of
the
contract
Package,
refer
to
ANNEX
p-ll
"Executove summary
Report".
Package No.
12: Kambang- lndrapura
The progress as
of
this
quarter achieved
of
only 7L.93% against
the
scheduled
77.9o%
having
much
lagged
behind,
-65.97%.The
main
reasons
for
delayed progress are likely same
asbefore.
The
Contractor
isdoing
his
I
I
I
Ir
I
I
I
I
T
l(
t
I
I
I
I
I
2017 Quarterly
ProgressRepoft
2noQuarter
;April-May-June
I
I
t
progress.
The
client
isstill looking
for
a resolution
about how
to handle the contractor
in accordance
with
the
contract conditions and what to
be
the most realistic provisions and
measures
to
be
taken.
Details
ofthe Contract
Packageare
shown
in
ANNEXP-12
"Executive Summary
Report',.
Package
No. 13 l Sp.
Rukis-Tj. Kemuning
The progress
asof this quarter,
50.29% ismuch
lagged
behind the scheduled,
97.87%.The
completion
date of this works
is
10,July
2017.
Hence,
the contractor
hasproposed
the
extension
of time
for
unsettled
land
acquisition
of
segment
No.2,
about 18
km
and
segment
No.
3,about
2
km
asof
the end of May
2017.
Details of
the work
progress are
shown
inANNEX
P-l3 "Executive Summary
Reports,
Package
No. 14:
Painan -
Kambang
The
Progress
asof this
month
is
achieved of
32,89"/oagainst
the scheduled
37.80% having
slippage rate
-4.91Yo.The
progress
of Asphalt pavement of this month
is
only
1.42%whleh
is
mueh
less th_anthe
previous
month,
8.89%
because
of a
little
working
areas
for
Asphalt
paving
works.
Nevertheless
this month
progress
of preparatory work like pavement widening &
shoulders,
granular pavement
were
done in very small
areas,
The contractor is repeatly
advised
to
increase
the
work
forces
for
widening teams
to
accommodate
the
progress
of
Asphalt
paving works.
ANNEX
P-14
"Executive Summary Report"
shows
the complete details
of
the project.
Package
No,
15:Sibolga
-
Bts.Tapsel
The
progress
as
of
this
quarter
is
only 43.75%
against
the
scheduled, 84.69%
having
slippage
rate
-40.94%.
The
main
reasons
of
delayed
progress
are unsettled land acquisition, 12.9 km
and
delay of
relocating
the utilities of electrical
poles
(PLN)and
water
pipes (PDAM).
The contractor
had being advised
to
propose
for
design changes
of
typical sections
in
accordance
with site situations utilizing
the existing
ROW
(Ave. 1Lm
width) for the
areaswhich
aresituated
unvery
densely
populated
road.
Detailed
and
work
progresses
ofthe
contract
package are
shown
inANNEX P-15
"Executive
Summary Report".
Package
No.
16 :Seblat
-
lpuh
This quarter progress has been achieved
of
3.43% against
the
scheduled,3.63% and the
accumulated progress as of
this
months
ls L2.t7% against
the scheduled, IO.7% having
a
head progress,
t.33o/o,The
progress
of this
month was
made
with
various
works
like Drainage,
Earthworks,
I
I
I
li
I
I
I
I
I
l(
I
I
t
I
I
2017
Quarterly
Progress Report
2ndQuarter
:April-May-June
I
I
I
I
I
The contractor
has
to
concentrate
for
early
start
of
asphalt paving works
which
is most
major weight of
the works reached
at
53.56%from the total.
ANNEX P-15
"Executive summary
Report"
shows
the
complete
details and work
progressof
the project.
Package No. 17
: Sp.Gunung Kemala
-
Pg.Tampak
The progress
of this
quarter is
achieved
of
A.Bovoagainst
the
scheduled,
4.o2% having
ahead of
0.78%.Ac wearing course
was started
is
this
month and
the
working areas
for
AC-WC is
in
largestretches which could be constructed
for
Zor 3 month.
The contractor should start
for
the minor works and shoulder final layer
assoon
as AC-WCcompletion
ANNEX P-17 "Executive summary
Report" shows
the
complete
details and
work
progress
of
the project.
Package No. 19
: Lais-
Bintunan
The contract
package is completed on June 30, 2016
and provisionally handed over
to
the
employer
and
currentl.T
under "Defects Notification period"
until
after
tr,vo
(2)
.r,earsreckoned from the issuance of the
TOC.complete details
of the
contract
package
are shown
in
ANNEX
p-19 ..Executive summary
Report",
Package No. 20
:Lubuk
Alung
-Siclncin
The progress
asof this quarter
isachieved
of
57,73o/oatainst the scheduled,
71,88% having
slippage
rate,
-'J.4.L5%and
this
month
progress, 3,50%
is
much lagged behind
the
lastmonth
7.45%
especially
asphalt
paving
works.
Moreover,
Drainage
works
are
not
constructed
for
2consecutive months,
unsettled
land acquisition, 117 paps and delaying
of
relocation
of
utilities,
pDAM water
pipes
and electrical poles seem
to
behampering the progress of
works.
ANNEX
P'20
"Executive
summary Report''
shows
the
contractor's
schedule
and
work
progress.
Package
No.21
:Lubuk Alung - KuraitaJi
The progress as
of this
quarter,
9933%
is much
lagged behind
the
scheduled,
ss.gt%
having slippage rate -16.58%.
The progress
of
drainage works are sharply dropped down
to
0.g9%
comparing
to the
lastmonth,5,43%,
Furthermore, the progress
of asphalt pavement works are also so slow.
The Contractor
hasto
maintain
the work continuous financial supports from
their
head office
to
maintain the
progress
in more
than normal.
ANNEX
P-21 "Executive
summary Report"
shows
the
contractor/s schedule
and
work
T
lc
I
I
I
I
T
l'
T
2017 Quarterly
Progress Report
2ndQuarter
: April-May-June
I
I
I
I
I
I
3.3
Variation
Order Details
To
date, amendements and/or variation orders
for
six
(6)
construction contract
packageswere
already
processed
and
approved
by
pejabat
pembuat
Komitmen (ppK), the
authorize
Office
to
approve
financial disbursement.
The
approved variations
orders
were
due
to the following
reasons
:a) change
of
Engineer's Team Leader
from
V.Thiagarajah
to
Johnson
villar
and
from
Johnson Villar
to
Efren
L. Baccani.b)
Change
of
PPK SubProject Manager.
c)
Contract arnount
revision
due
to
Technical
Justification
of
Field
Engineering
results.
Revision
of time for completion (time
ercension).
contract
amount revision due
to contract
price
adjustment (escalation
of unit
rates).
f)
Change
of Contractor's authorize representative.
g)
Deletion
of
unspent provisional sum amountinB
to
Rp.7.1
Billion and balancing
of
quantity overruns/underruns.
h)
Final
Quantity.
i)
Change
BankAccount
In regards
with
additive/ded
uctive
cost
variations, original
cost
of the
six (6)
construction
contract packages
increases
by
Rp. 155,579,234,000 while
the
variation orders
for
the
other contract
packages
are still under evaluation by
DSCand
PPKwhich
isexpected
that
the
results
will
increase
the
respective
original contract amounts.
ln anticipation of future
claims
for varied woiks
bythe Contractors,6yo cost
increasesfor
packages
under AWP-2 and
AWP-3
to
cover any
variation
orders
that
may
arise
during
the implementation
ofthe
Works.
Presented
in Table 7 are details of Variation orders
for the four
(4) sub-projects under
AWP-1
and
nine (9)
contract
packagescovered
byAWp-2 and
AWp-3
I
d)
e)
I
l,
I
T
t
I
l'
t
I
I
I
I
2017 Quarterly
Progress Report
2ndQuarter
: April-May-June
I
I
I
I
I
I
I
I,
Table
7-
Details of Amendments (Variation Orders)
t
I
I
I
I
I
I
I
T
I
I
A
-
Cha nge of Enginee/s Team Leader from V. Thjagarajah to lohnson Villar.B
-
Change of PPK Sub Project M anager,C
-
contract amount revision due to TechnicalJ ustification of Field Engineering results,D
-
Revlslon of time for completion {time extension/contraction).E - Contract amount revision due to contract price adjustments (escalation).
F
-
Change of Contracto/s authorize representative.G -Deletion of unspent provisional sum amounting to Rp, 7.1 Billion and balancingof quantity overruns/underruns. H -Final quantitv (overuns/underruns).
l-
Change Bank Account, Reason For Change iWestern Indonesia National Roads Improvement project )l
[image:27.597.7.576.69.751.2]2017 Quarterly
Progress Report
2noQuarter
: April-May-June
t
I
I
I
I
I
I
l,
t
I
I
I
t
I
I
I
I
I
I
3,4
ConsultancyServices
Technical
Assistance
for
core
Team
consultant
(crc)
to
support the project
Management Unit,
Lead
Consultant:
pT,perentiana Djaja
crc
contract
No.
06-20/crC/TA/LNl8o43/1112
was
signed
on
5
Nov 2012 between
the
Ministry
of
Public
Works
,
Directorate
of
Planning,
DGHand
pT. perentjana
Djaja,Yongma Engineering Co.
Ltd,
PT.Epadascon
Permata
Engineering
Consultant,
JVand
the
work
commenced
on
l-2
November
2012.
Amendment
No.1
to
original contract
was signed
on October
ZS,2OL3.
Amendment
No. 2
wasofficially
approved, on
September
3,2Ot4.
Amendment
No. 3
hasbeen
approved on
November
30,
2015.
Amendment
No.
4to the current
crc
contract
was
signed on March 4,
zot6.
Amendment
No,
5to the current
CTCcontract
was
signed
on
April
],O, ZOL7.Presented
in
Table
8 is
the current status of
CTeeonttaet.
Table 8
Description USD IDR
Originaf
Contract includ
ing t0% VAf
1,404,37O 23,556,940,000Amendment
No.1 including i.0% VATt,447,517.
24,66A,792,sOOVariance Against Original Contract +3,O7% +4,72%
Combine Variance Against Original Contract +4.L2%
Amendment
No. 2 includingI0%VAI
1,509,117 24,7M,s4/.,L9OVariance Against Original Contract +7,4696 +4,87% Combine Variance Against Original Contract +5.81%
Arnendment
No.3 including 70%VAI
1,473,9t7
26,328,054,500Variance Against Original Contract +4.95% +tl,76oA
Combine Variance Against Original Contract +9.29%
Amendment
No. 4 including tO%VAT 1,918,15940,878,!69,529
Variance Against Original Contract +36.58% +73.53% Combine Variance Against Original Contract +60.L2%
Amendment
No. 5 includingI0%VAT
1,59s,403.334t,545'3a6,M6
Varlance Against Original Contract L3.69% 76.36%
Combine Variance Against Original Contract s3.s8%
Note
:combine variance
(USo+ton) is based on 1 usD = Rp. 9,558 exchange rate used duringthe
time
of signingthe
original Contract Agreement. [image:28.598.116.562.395.708.2]2017 Quafterly
Progress Repoft
2noQuarter
: April-May-June
I
I
I
t
I
I
Technical Assistance
for
Design
& Supervision
Consultant
(DSC)Lead
Consultant: Renardet
S.ADsc
contract
No. KU.03,01/ppK-pR/wtNRtp/Bx/o1,lvt/2013 was signed
on
11 Jun
2013
between
the
Ministry