PA/KPA : K/L/D/I :
STKER : PDAM T irta Tandik Kabupaten Musi Banyuasin PPK : Azmi Julian, ST
T.A : 2012
PERKIRAAN MASA
No VOLUME PERKIRAAN SUMBER WAKTU MULAI PELAKSANAAN KETERANGAN
(Rp) DANA PELAKSANAAN (BULAN)
1 PENGADAAN BAHAN KIMIA UNTUK UNIT PENGOLAHAN PDAM KAB. MUBA
- PDAM SEKAYU, KAYUARA, LUMPATAN, MUARA TELADAN DAN BAILANGU PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012 - PDAM SUKARAMI, BABAT TOMAN, MANGUNJAYA, DAN ULAK PACEH JAYA PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012 - PDAM NGULAK, AIR BALUI, KEBAN I, PENGAGE DAN KEBAN II PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012 - PDAM TANAH ABANG, KELUANG, SUPAT, DAN SUNGAI LILIN PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012 - PDAM BAYUNG LENCIR, PENINGGALAN DAN LALAN PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012 - PDAM EPIL, LAIS, TELUK KIJING, PETALING DAN TANJUNG AGUNG BARAT PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012
- PDAM SUNGAI KERUH, JIRAK, DAN SINAR JAYA PBJ 1 Paket Sekayu 400,000,000 APBD April 2012 April-Agustus 2012
- PDAM PLAKAT TINGGI, AIR PUTIH ULU, SIALANG AGUNG, DAN BUKIT INDAH PBJ 1 Paket Sekayu 343,900,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,150,000 APBD April 2012 April-Agustus 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 300,000 APBD April 2012 April-Agustus 2012
- Belanja Pengandaan PBJ 1 Paket 375,000 APBD April 2012 April-Agustus 2012
1
PBJ 1 Paket Plakat Tinggi 3,298,985,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,790,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 375,000 APBD April 2012 April-Desember 2012
2
PBJ 1 Paket Plakat Tinggi 1,248,045,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,280,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
3
PBJ 1 Paket Plakat Tinggi 1,601,045,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,280,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
4
PBJ 1 Paket Sungai Lilin 5,715,290,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,830,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 300,000 APBD April 2012 April-Desember 2012
PENGUMUMAN
RENCANA UMUM PENGADAAN BARANG / JASA PEMERINTAH
NAMA PAKET PEKERJAAN
PEMBANGUNAN IPA KAPASITAS 5 L/DTK. BERIKUT JARINGAN PIPA DI DESA AIR PUTIH ILIR KEC. PLAKAT TINGGI
PEK. PEMASANGAN JARINGAN PIPA TRANSMISI DISTRIBUSI DI DESA CINTA KARYA KEC. PLAKAT TINGGI
PEK. PENAMBAHAN JARINGAN PIPA TRANSMISI DISTRIBUSI KE DESA TANJUNG KAPUTREN KEC. PLAKAT TINGGI
CARA PENGADAA
N
PEK. PENAMBAHAN IPA BARU KAPASITAS 30 L/DTK. BERIKUT JARINGAN PIPA TRANSMISI PADA PDAM CABANG SUNGAI LILIN
RENCANA PENGANGGARAN LOKASI
PEKERJAAN
PERKIRAAN MASA
No VOLUME PERKIRAAN SUMBER WAKTU MULAI PELAKSANAAN KETERANGAN
(Rp) DANA PELAKSANAAN (BULAN)
NAMA PAKET PEKERJAAN
CARA PENGADAA
N
RENCANA PENGANGGARAN LOKASI
PEKERJAAN
5
PBJ 1 Paket Sungai Lilin 2,951,335,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,790,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 375,000 APBD April 2012 April-Desember 2012
6
PBJ 1 Paket Babat Supat 5,889,404,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,871,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 300,000 APBD April 2012 April-Desember 2012
7
PBJ 1 Paket Bayung Lencir 4,241,015,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,410,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
8
PBJ 1 Paket Bayung Lencir 4,091,015,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,410,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
9
PBJ 1 Paket Keluang 7,797,290,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,830,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 300,000 APBD April 2012 April-Desember 2012
10
PBJ 1 Paket Keluang 1,313,045,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,280,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
11
PBJ 1 Paket Keluang 1,531,045,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,280,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
12
PBJ 1 Paket Batanghari Leko 3,635,985,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,790,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 375,000 APBD April 2012 April-Desember 2012
PEK. PEMBANGUNAN BOSTER PUMP STATION BERIKUT JARINGAN PIPA DI DESA SUKAMAJU DAN DESA LET ANG KECAMATAN BABAT SUPAT
PEK. PEMBANGUNAN BOSTER PUMP STATION BERIKUT JARINGAN PIPA DI DESA SUKAJAYA DAN WONOREJO KECAMATAN BAYUNG LENCIR
PEK. PEMBANGUNAN BOSTER PUMP STATION BERIKUT JARINGAN PIPA DI DESA SIMPANG BAYAT DAN LUBUK HARJO KEC. BAYUNG LENCIR
PEK. PEMBANGUNAN IPA KAPASITAS 40 L/DTK. BERIKUT JARINGAN PIPA TRANSMISI DISTRIBUSI DI DESA SRIDAMAI KE BOSTER PUMP KARYA MAJU KECAMATAN KELUANG
PEK. PEMASANGAN JARINGAN PIPA DISTRIBUSI DI DESA TEGAL MULYO KECAMATAN KELUANG
PEK. PEMBANGUNAN BOSTER PUMP STATION SUNGAI LILIN JAYA BERIKUT PEMASANGAN PIPA DI DESA MEKAR JADI DAN SUMBER REJEKI.
PEK. PEMASANGAN JARINGAN PIPA DISTRIBUSI DI DESA TENGGARO KECAMATAN KELUANG
PEK. PEMBANGUNAN IPA KAPASITAS 5 L/DTK. BERIKUT JARINGAN PIPA DI DESA SUNGAI NAPAL KECAMATAN BATANGHARI LEKO
PERKIRAAN MASA
No VOLUME PERKIRAAN SUMBER WAKTU MULAI PELAKSANAAN KETERANGAN
(Rp) DANA PELAKSANAAN (BULAN)
NAMA PAKET PEKERJAAN
CARA PENGADAA
N
RENCANA PENGANGGARAN LOKASI
PEKERJAAN
13
PBJ 1 Paket Sanga Desa 2,701,885,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,790,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 240,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 375,000 APBD April 2012 April-Desember 2012
14
PBJ 1 Paket Sanga Desa 1,363,045,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,280,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
15 PEK. REHAB SIPAS DESA KRAMAT JAYA KECAMATAN SUNGAI KERUH PBJ 1 Paket Sungai Keruh 285,478,500 APBD April 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,004,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 112,500 APBD April 2012 April-Desember 2012
16 PEK. REHAB SIPAS DESA JIRAK KECAMATAN SUNGAI KERUH PBJ 1 Paket Sungai Keruh 285,478,500 APBD April 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,004,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 112,500 APBD April 2012 April-Desember 2012
17
PBJ 1 Paket Sekayu 5,486,195,000 APBD Mei 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 2,410,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 225,000 APBD April 2012 April-Desember 2012
18 PENGADAAN PRINTER KHUSUS PENCETAK REKENING AIR PBJ 1 Paket Sekayu 173,012,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 538,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 90,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 75,000 APBD April 2012 April-Desember 2012
19 PENGADAAN MATERIAL SAMBUNGAN PELANGGAN PBJ 1 Paket Sekayu 772,830,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,235,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
20 PENGADAAN 2 UNIT KENDARAAN MOBIL T ANGKI AIR PBJ 1 Paket Sekayu 700,115,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,235,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 180,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
21 PENGADAAN 1 UNIT KENDARAAN MOBIL OPERASIONAL PBJ 1 Paket Sekayu 213,372,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,083,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 120,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 90,000 APBD April 2012 April-Desember 2012
PEK. PEMBANGUNAN IPA BARU KAPASITAS 50 L/DTK. UNTUK PENINGKATAN KAPASITAS PDAM PUSAT SEKAYU
PEK. PEMINDAHAN IPA PDAM LUMPATAN KE PDAM AIR BALUI KAPASITAS 5 LITER/DETIK BERIKUT BANGUNAN INTAKE, PEMBUATAN GROUND KAP. 50 M3 DAN MEKANIKAL ELEKT RIKAL KECAMATAN SANGA DESA
PEK. PEMBANGUNAN BOSTER PUMP STATION DESA KEMANG DAN PENAMBAHAN PIPA KE DESA TERUSAN KEC. SANGA DESA
PERKIRAAN MASA
No VOLUME PERKIRAAN SUMBER WAKTU MULAI PELAKSANAAN KETERANGAN
(Rp) DANA PELAKSANAAN (BULAN)
NAMA PAKET PEKERJAAN
CARA PENGADAA
N
RENCANA PENGANGGARAN LOKASI
PEKERJAAN
22 PENGADAAN KENDARAAN SEPEDA MOTOR OPERASIONAL PBJ 1 Paket Sekayu 213,372,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,083,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 120,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 90,000 APBD April 2012 April-Desember 2012
23 PENGADAAN POMPA INTAKE AIR BAKU TYPE SUBMERSIBLE PBJ 1 Paket Sekayu 772,830,000 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,235,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
24 PENGADAAN POMPA DISTRIBUSI TYPE CENTRIFUGAL PBJ 1 Paket Sekayu 578,212,500 APBD April 2012 April-Agustus 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,235,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 150,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 112,500 APBD April 2012 April-Desember 2012
25 PEK. PEMBUATAN GUDANG PENYIMPANAN BAHAN MATERIAL PDAM KAYUARA PBJ 1 Paket Sekayu 238,372,000 APBD April 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 1,083,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 120,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 90,000 APBD April 2012 April-Desember 2012
26 PEMASANGAN JARINGAN LISTRIK DAN TRAFO PLN UNTUK PDAM SINAR JAYA PBJ 1 Paket Sekayu 366,217,000 APBD April 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 538,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 90,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 75,000 APBD April 2012 April-Desember 2012
27 PEMASANGAN JARINGAN LISTRIK DAN TRAFO PLN BOSTER KARYA MAJU PBJ 1 Paket Sekayu 412,638,500 APBD April 2012 April-Desember 2012
- Belanja Alat Tulis Kantor PBJ 1 Paket 679,000 APBD April 2012 April-Desember 2012
- Belanja Prangko, Metrai dan benda pos PBJ 1 Paket 120,000 APBD April 2012 April-Desember 2012
- Belanja Pengandaan PBJ 1 Paket 112,500 APBD April 2012 April-Desember 2012
Sekayu, 26 Mart 2012 PDAM TIRTA RANDIK KAB. MUBA
DIREKTUR
FIRDAUS L. DINE, ST NIP. 19610520 199603 1 001