• Tidak ada hasil yang ditemukan

RENCANA/ RELISASI PENGADAAN TA 2009 * Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B & C

N/A
N/A
Protected

Academic year: 2021

Membagikan "RENCANA/ RELISASI PENGADAAN TA 2009 * Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B & C"

Copied!
15
0
0

Teks penuh

(1)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pekerjaan Umum Pengairan Kab. Sidoarjo Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Pengadaan Alat Pengolah Data 33,000,000 3,882 PL 12-Mar-09 30-Mar-09 30-Mar-09 6-Apr-09 30 hari

Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) - -TOTAL KEGIATAN I (Loan + Pend) - -TOTAL KEGIATAN II (GOI-PF/APBD) 33,000,000 0 Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

Public Disclosure Authorized

(2)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pekerjaan Umum Binamarga & Pengairan Kab. Jombang Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

662,500,000

77,941

Pelaksanaan Rehabilitasi di D.I :

1 CW 1 Mojowarno 160,000,000 18,824 SW Post 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 90 hari

2 CW 2 Mundusewu 142,500,000 16,765 SW Post 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 90 hari

3 CW 3 Bareng Sekunder Mojosari 160,000,000 18,824 SW Post 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 90 hari

4 CW 4 Tawangsari 200,000,000 23,529 SW Post 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 90 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD) 1 Pengadaan Peralatan Kantor :

GD 1 Almari Arsip 10,500,000 PL 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 45 hari

GD 2 Kursi Meja 3,500,000 PL 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 45 hari

2 CW 1 Rehabilitasi DI. Karangan IV 199,615,000 LU 4-Mar-09 10-Mar-09 13-Mar-09 9-Apr-09 90 hari

Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 662,500,000 77,941.18 TOTAL KEGIATAN I (Loan + Pend) 662,500,000 77,941.18 TOTAL KEGIATAN II (GOI-PF/APBD) 213,615,000 0 Sub Prject A1 (Category 7)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

(3)

RENCANA/ RELISASI PENGADAAN TA 2009 *

Unit Kerja Dinas PU Pengairan Keb. Mojokerto Status

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$) Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego Penandata-nganan Kontrak Jangka Waktu Kontrak 1 2 3 4 5 6 7 8 9 10 11 12

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

440,500,000

51,824 Rehabilitasi Saluran Sekunder :

1 CW 1 - Urung-Urung Hulu 75,000,000 8,824 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari 2 CW 2 - Urung-Urung Tengah 60,000,000 7,059 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari

3 CW 3 - Bacem Hilir 78,000,000 9,176 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari

4 CW 4 - Bacem Tengah 78,000,000 9,176 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari

5 CW 5 - Janjing Tengah 98,000,000 11,529 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari

6 CW 6 Perbaikan Sayap Primer Janjing Tengah 51,500,000 6,059 SW Post Maret 09 Maret 09 Maret 09 Apr 09 45 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Biaya Operasional Penunjang WISMP 104,500,000 12,294

2 Pengadaan Computer & UPS 14,500,000 1,706 PL Mei 09 Mei 09 Mei 09 Mei 09 7 hari

3 Pengadaan GPS 6,000,000 706 PL Mei 09 Mei 09 Mei 09 Mei 09 7 hari

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 440,500,000 51,823.53

TOTAL KEGIATAN I (Loan + Pend) 440,500,000 51,823.53

TOTAL KEGIATAN II (GOI-PF/APBD) 125,000,000 0 Sub Prject A1 (Category 7)

Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B & C

(4)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pengairan Kab. Kediri Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Perjalanan Dinas 55,000,000 swakelola

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) -

-TOTAL KEGIATAN I (Loan + Pend) -

-TOTAL KEGIATAN II (GOI-PF/APBD) 55,000,000 0

Water Resources and Irrigation Sector Management Project (WISMP) APL I

(5)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pekerjaan Umum Pengairan Kab. Probolinggo Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

362,045,000 42,594

Pelaksanaan Rehabilitasi & Peingkatan Partisipatif (Bahan Baku Bangunan di DI.) :

1 CW 1 Mentor 248 Ha 105,384,000 12,398 NS Post 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

2 CW 2 Sidowayah Sewuluh 90,511,000 10,648 NS Post 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

3 CW 3 Sidowayah Ambulu 78,188,000 9,199 NS Post 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

4 CW 4 Tunggak 207 Ha 87,962,000 10,348 NS Post 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Pengadaan GPS 10,000,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

2 Pengadaan Lemari Arsip 3,000,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

3 Pengadaan Laptop & Printer 18,000,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

4 Pengadaan Kamera Digital 10,000,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

5 Bahan Rehabilitasi Sumber Sempol 31,010,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

6 Bahan Rehabilitasi Pintu Sal. Kekunder Taposan 11,250,000 PL 19-Feb-09 5-Mar-09 11-Mar-09 31-Mar-09 60 hari

Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 362,045,000 42,593.53 TOTAL KEGIATAN I (Loan + Pend) 362,045,000 42,593.53 TOTAL KEGIATAN II (GOI-PF/APBD) 83,260,000 0

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

(6)

RENCANA/ RELISASI PENGADAAN TA 2009 *

Unit Kerja Dinas Pengairan Kab. Pasuruan Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego nganan Kontrak Penandata- Jangka Waktu Kontrak Permasalahan/ Keterangan:

1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

430,800,000 50,682 Pelaksanaan Rehabilitasi di DI. : 1 CW 1 Tanggul 427 Ha 96,857,000 11,395 SWA 2 CW 2 Krikil 369 Ha 69,243,400 8,146 SWA 3 CW 3 Sindupati 240 Ha 64,409,300 7,578 SWA Upah Rehabilitasi di DI. : 4 CW 1 Tanggul 427 Ha 79,742,900 9,382 SWA 5 CW 2 Krikil 369 Ha 81,536,600 9,593 SWA 6 CW 3 Sindupati 240 Ha 39,010,800 4,590 SWA

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1

Pelaksanaan Desain Partisipatif DI. Sumberingin, DI. Moyo, DI. Sukun, DI. Sebandung, DI. Sibon

91,785,200

2 Belanja Modal Peralatan kantor :

- Almari Arsip 4,750,000 PL Jul-09 Aug-09 Aug-09 Sep-09 30 hari - Filling Cabinet

4 Laci (3 buah) 4,500,000 PL Jul-09 Aug-09 Aug-09 Sep-09 30 hari

- Laptop 15,000,000 PL Jul-09 Aug-09 Aug-09 Sep-09 30 hari

- Portable

Printer 4,000,000 PL Jul-09 Aug-09 Aug-09 Sep-09 30 hari

- Printer Dot

matrix A3 10,000,000 PL Jul-09 Aug-09 Aug-09 Sep-09 30 hari

Sub Total Keg Cat 3 (Loan -

-Sub Total Keg Selain Cat 430,800,000 50,682.35

TOTAL KEGIATAN I (Loa 430,800,000 50,682.35

TOTAL KEGIATAN II (GOI- 130,035,200 0

Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B & C

(7)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pekerjaan Umum Kab. Jember Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

437,000,000 51,412

Saluran Sekunder :

1 CW 1 Suno 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

2 CW 2 Makam 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

3 CW 3 Kebon Gunung 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

4 CW 4 Candri 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

5 CW 5 Tamansari 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

6 CW 6 Tempurejo 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

7 CW 7 Karang Bayat 56,500,000 6,647 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

8 CW 8 Sumber Koong 2 41,500,000 4,882 NS Post 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Suno L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

2 Makam L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

3 Kebon Gunung L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

4 Candri L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

5 Tamansari L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

6 Tempurejo L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

7 Karang Bayat L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

8 Sumber Koong 2 L 6-Apr-09 13-Apr-09 16-Apr-09 20-Apr-09 20 hari

9 Implementasi Redefinisi KPI-PPSIP 7,500,000

Pelaksanaan Desain Partisipatif 60,000,000

Operasional Workshop 27,500,000

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 437,000,000 51,411.76

TOTAL KEGIATAN I (Loan + Pend) 437,000,000 51,411.76

TOTAL KEGIATAN II (GOI-PF/APBD) 95,000,000 0

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

(8)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pengairan Kab. Banyuwangi Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

850,000,000

100,000

Pelaksanaan Rehabilitasi Dengan Metode Partisipatif di DI. :

1 CW 1 Poncowati (513 Ha) 50,000,000 5,882 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

2 CW 2 Kelir (191 Ha) 100,000,000 11,765 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

3 CW 3 Cerme (220 Ha) 50,000,000 5,882 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

4 CW 4 Telepak (230 Ha) 100,000,000 11,765 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

5 CW 5 Tembelang (332 Ha) 75,000,000 8,824 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

6 CW 6 Larangan (234 Ha) 50,000,000 5,882 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

7 CW 7 Sragi (280 Ha) 50,000,000 5,882 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

8 CW 8 Panggangharjo (309 Ha) 75,000,000 8,824 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

9 CW 9 Suko (112 Ha) 50,000,000 5,882 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

10 CW 10 Sempu (300 Ha) 75,000,000 8,824 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

11 CW 11 Paras Tembok (167 Ha) 75,000,000 8,824 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

12 CW 12 Baru Manis (434 Ha) 100,000,000 11,765 SW Post Mar 09 Mar 09 Mar 09 Apr 09 90 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 DI. Tugu (286 Ha) 50,000,000 5,882 PML Apr 09 Apr 09 Apr 09 Apr 09 90 hari

2 DI. Astiyar (334 Ha) 50,000,000 5,882 PML Apr 09 Apr 09 Apr 09 Apr 09 90 hari

3 DI. Gumuk (182 Ha) 50,000,000 5,882 PML Apr 09 Apr 09 Apr 09 Apr 09 90 hari

4 DI. Pakem (269 Ha) 80,000,000 9,412 PML Apr 09 Apr 09 Apr 09 Apr 09 90 hari

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 850,000,000 100,000.00

TOTAL KEGIATAN I (Loan + Pend) 850,000,000 100,000.00

TOTAL KEGIATAN II (GOI-PF/APBD) 230,000,000 0

Sub Prject A1 (Category 7)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

(9)

Page 1 of 2

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pengairan Kab. Bondowoso Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

545,090,000 64,128 Desain Partisipatif di DI.:

1 CW 1 Gambangan (130 Ha) 10,540,000 1,240 Swa

2 CW 2 Selokambang (342 Ha) 11,220,000 1,320 Swa

3 CW 3 Selolembu (292 Ha) 10,620,000 1,249 Swa

4 CW 4 Pringduri (237 Ha) 10,540,000 1,240 Swa

5 CW 5 Garu (212 Ha) 9,860,000 1,160 Swa

6 CW 6 Cangkring (141 Ha) 9,230,000 1,086 Swa

7 CW 7 Peh (152 Ha) 10,540,000 1,240 Swa

8 CW 8 Makam (193 Ha) 10,540,000 1,240 Swa

Belanja Bahan Baku :

9 CW 1 Tlogo 52,032,000 6,121 NS Post Mar-09 Mar-09 Mar-09 Mar-09 30 hari

10 CW 2 Pakisan 31,624,000 3,720 NS Post Mar-09 Mar-09 Mar-09 Mar-09 30 hari

11 CW 3 Selolembu 28,459,000 3,348 NS Post Jul-09 Jul-09 Jul-09 Jul-09 30 hari

12 CW 4 Clangap 56,064,000 6,596 NS Post Mar-09 Mar-09 Mar-09 Mar-09 30 hari

13 CW 5 Gubri 22,896,000 2,694 NS Post Mar-09 Mar-09 Mar-09 Mar-09 30 hari

14 CW 6 Pager Gunung 55,657,000 6,548 NS Post Jul-09 Jul-09 Jul-09 Jul-09 30 hari

15 CW 7 Gambangan 36,614,000 4,308 NS Post Jul-09 Jul-09 Jul-09 Jul-09 30 hari

16 CW 8 Selokambang 42,334,000 4,980 NS Post Jul-09 Jul-09 Jul-09 Jul-09 30 hari

Sub Prject A2 (Category 8)

Water Resources and Irrigation Sector Management Project (WISMP) APL I Komponen B & C

(10)

Page 2 of 2

Unit Kerja Dinas Pengairan Kab. Bondowoso Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13 Upah : 17 CW 9 Tlogo 21,167,000 2,490 Swa 18 CW 10 Pakisan 13,175,000 1,550 Swa 19 CW 11 Selolembu 11,541,000 1,358 Swa 20 CW 12 Clangap 23,935,000 2,816 Swa 21 CW 13 Gubri 9,103,000 1,071 Swa

22 CW 14 Pager Gunung 24,343,000 2,864 Swa

23 CW 15 Gambangan 15,386,000 1,810 Swa

24 CW 16 Selokambang 17,670,000 2,079 Swa

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Pelaksanaan Desain Pertisipatif 45,710,000 PL

2 Pelaksanaan Rehabilitasi Metode Partisipatif 157,900,000 L

3 Penguatan Pengelola Proyek Kab. KPIU Irigasi dinas Pengairan 10,400,000 Swa

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 545,090,000 64,128.24

TOTAL KEGIATAN I (Loan + Pend) 545,090,000 64,128.24

(11)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Bina Marga & Pengairan Kab. Situbondo Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya eqv(US$) PengadaanMetode Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego nganan Kontrak Penandata- Jangka Waktu Kontrak

Keterangan: Permasalahan/

1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

15,000,000

1,765

3 Peralatan Kantor :

GD 1 Pengadaan GPS 15,000,000 1,765 NS Post April-09 April-09 May-09 May-09 30 Hari

1 Pelaksanaan Desain Partisipatif di DI. : 194,000,000 22,824

CW 1 Curah Suri 24,000,000 2,824 FA

CW 2 Campalok 28,000,000 3,294 FA

CW 3 Macan 16,000,000 1,882 FA

CW 4 Setimbo 20,000,000 2,353 FA

CW 5 Cangkring 16,000,000 1,882 FA

2 Rehabilitasi & Peningkatan dengan Metode partisipatif di DI.:

CW 6 Curah Suri 30,000,000 3,529 CDD Post Review Mei 2009 60 hari

CW 7 Campalok 30,000,000 3,529 CDD Post Review Mei 2009 60 hari

CW 8 Setimbo 30,000,000 3,529 CDD Post Review Mei 2009 60 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Peralatan Kantor :

2 Pengadaan Laptop 15,000,000 PL April-09 April-09 May-09 May-09 30 Hari

3 Pengadaan Kamera Digital 5,000,000 PL April-09 April-09 May-09 May-09 30 Hari

4 Pengadaan Printer 3,000,000 PL April-09 April-09 May-09 May-09 30 Hari

5 Pengadaan Handycam 10,000,000 PL April-09 April-09 May-09 May-09 30 Hari

6 Pengadaan Sepeda Motor 35,000,000 PL April-09 April-09 May-09 May-09 30 Hari

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 209,000,000 24,588.24

TOTAL KEGIATAN I (Loan + Pend) 209,000,000 24,588.24

TOTAL KEGIATAN II (GOI-PF/APBD) 68,000,000 0

Sub Prject A2 (Category 8)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

(12)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas PU. Bina Marga & Pengairan Kab. Bangkalan Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

10,000,000

1,176

1 GD 1 Pengadaan Modal Peralatan & Mesin 10,000,000 1,176 NS Post Mar-09 Mar-09 Mar-09 Apr-09 10 hari

388,500,000

45,706

2 CW 1 Rehab Saluran Sek. DI. Kesatryean 131 Ha 196,500,000 23,118 SW Post Apr-09 May-09 May-09 May-09 90 hari

3 CW 2 Rehab Saluran Sek. DI. Budduk 128 Ha 192,000,000 22,588 SW Post Apr-09 May-09 May-09 May-09 90 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Rehabilitasi/Pemeliharaan Petani Pemakai Air 200,000,000

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 398,500,000 46,882.35

TOTAL KEGIATAN I (Loan + Pend) 398,500,000 46,882.35

TOTAL KEGIATAN II (GOI-PF/APBD) 200,000,000 0

Sub Prject A1 (Category 7)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

(13)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pekerjaan Umum Kab. Pamekasan Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

70,000,000

8,235

1 Rehabilitasi di DI. :

CW 1 Samiran 35,000,000 4,118 SW Post 01-Jun-09 03-Jun-09 12-Jun-09 15-Jun-09 90 hari

CW 2 Sbr. Raja 35,000,000 4,118 SW Post 01-Jun-09 03-Jun-09 12-Jun-09 15-Jun-09 90 hari

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 GD 1 Pengadaan Peralatan Komputer : PL 30-Mar-09 10-Mar-09 12-Mar-09 13-Mar-09 15 hari

- Laptop 12,000,000

- Printer 3 in 1 2,000,000

- Flash Modem 2,500,000

2 GD 2 Pengadaan GPS 10,000,000 PL 06-Apr-09 09-Apr-09 13-Apr-09 16-Apr-09 15 hari

3 Penyusunan RTTG 5,540,000

4 Penyusunan AKNOP Irigasi 5,430,000

5 Penyusunan Rencana Kebutuhan Air 7,230,000

6 Penyusunan Rencana O&P 8,090,000

7 Penilaian Peringkat IP3A 5,440,000

8 Pelaksanaan Desain Partisipatif 42,000,000

9 Evaluasi Pelaksanaan PAI Oleh Bupati 4,780,000

10 Analisa Ketersediaan Air & kebutuhan Air Primer & Sek 3,630,000

11 Perlindungan Kualitas Air Irigasi 10,400,000

Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 70,000,000 8,235.29 TOTAL KEGIATAN I (Loan + Pend) 70,000,000 8,235.29

TOTAL KEGIATAN II (GOI-PF/APBD) 119,040,000 0

Sub Prject A1 (Category 7)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

(14)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas Pengairan Kab. Sampang Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

24,500,000

2,882

1 GD 1 Pengadaan Komputer Dekstop & Printer 9,500,000 1,118 NS Post Apr-09 Apr-09 May-09 May-09 15 hari

2 GD 2 Pengadaan Scanner 5,000,000 588 NS Post Apr-09 Apr-09 May-09 May-09 15 hari

3 GD 3 Pengadaan Handycam 10,000,000 1,176 NS Post Apr-09 Apr-09 May-09 May-09 15 hari

36,861,200 4,337

4 CW 1 Perbaikan Ringan Jaringan Irigasi DI. 36,861,200 4,337 CDD Post Sep-09 Sep-09 Oct-09 Oct-09 30 hari SPKS

II KEGIATAN YANG DIBIAYAI GOI (PARALEL FINANCING/APBD)

1 Pelaksanaan Desain Partisipatif 22,710,000 swa

Sub Total Keg Cat 3 (Loan + Pend) -

-Sub Total Keg Selain Cat 3 (Loan) 61,361,200 14,437.93

TOTAL KEGIATAN I (Loan + Pend) 61,361,200 14,437.93

TOTAL KEGIATAN II (GOI-PF/APBD) 22,710,000 0

Sub Prject A2 (Category 8)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Komponen B & C

(15)

RENCANA/ RELISASI PENGADAAN TA 2009

*

Unit Kerja Dinas PU Pengairan Kab. Sumenep Status : Januari 2009

No Kode Nama Paket Estimasi Biaya (Rp) Estimasi Biaya

eqv(US$)

Metode

Pengadaan Post/ Prior Review Pengumuman Pengadaan Pemasukan Penawaran Eval/ Nego

Penandata-nganan Kontrak Jangka Waktu Kontrak Keterangan: Permasalahan/ 1 2 3 4 5 6 7 8 9 10 11 12 13

I KEGIATAN YANG DIBIAYAI LOAN & GOI/ PENDAMPING

217,100,000 25,541

Pelaksanaan/Pembuatan Desain Partisipatif di DI. :

1 CS 1 Jepun (SS. Jepun Tengah) 30,300,000 3,565 FA Swakelola Dinas

2 CS 2 Jepun (SS. Puncang) 10,800,000 1,271 FA Swakelola Dinas

3 CS 3 Karpenang 15,800,000 1,859 FA Swakelola Dinas

4 CS 4 Braji 21,300,000 2,506 FA Swakelola Dinas

5 CS 5 Banjar 18,700,000 2,200 FA Swakelola Dinas

6 CS 6 Banjeru 19,400,000 2,282 FA Swakelola Dinas

Pelaksanaan Rehabilitasi & Peningkatan Partisipatif :

7 CW 1 Jepun (SS. Jepun Tengah) 60,800,000 7,153 CDD Post Review Jul-09 SPKS

8 CW 2 Jepun (SS. Puncang) 40,000,000 4,706 CDD Post Review Jul-09 SPKS

Sub Total Keg Cat 3 (Loan + Pend) - -Sub Total Keg Selain Cat 3 (Loan) 217,100,000 25,541.18 TOTAL KEGIATAN I (Loan + Pend) 217,100,000 25,541.18 TOTAL KEGIATAN II (GOI-PF/APBD) - 0 Sub Prject A2 (Category 8)

Water Resources and Irrigation Sector Management Project (WISMP) APL I

Referensi

Dokumen terkait

Rajah di sebelah kanan ialah grid petak yang terdiri daripada 6×6 petak segi empat sama , dalam grid petak terdapat 49 titik persilangan, terdapat sejumlah ________ segi

Saya tidak mengerjakan revisi dari dosen pembimbing ketika tidak mendapat masukan yang sesuai

= ' ( ' ) ' = λ ………..(2.15) Lebih jelasnya, kondisi yang diperlukan untuk menghasilkan suatu kondisi pengoperasian yang minimum untuk sistem daya termal adalah bahwa

Tujuan penelitian ini dilakukan untuk mengetahui (1) Perkembangan wisatawan ke kebun binatang Taman Rimba Provinsi Jambi, (2) Menganalisis faktor - faktor pengaruh

Hasil analisis uji t menunjukkan dari sepuluh variabel yang digunakan terdapat delapan variabel yang memberikan pengaruh yang signifikan terhadap keputusan pembelian

Jaksa Agung Suprapto 63 Malang Bank BTPN Cabang Malang. Jl Terusan Danau Sentani No 100 Malang

Beberapa alternatif solusi jika model menyalahi asumsi heteroskedastisitas adalah dengan mentransformasikan ke dalam bentuk logaritma, yang hanya dapat dilakukan jika

Kabupaten Sleman Yogyakarta, untuk mengetahui pengaruh gaya hidup (aktivitas, minat, opini, nilai budaya, kepribadian) secara parsial terhadap pembelian gadget dengan sistem