Electric Power Systems L1 - Olof Samuelsson
1
1. KONSEP DASAR LISTRIK
DAYA LISTRIK, ALIRAN DAYA, SISTEM 3 PHASA, HUBUNGAN Y, Δ.
2. REPRESENTASI SISTEM TENAGA LISTRIK
KOMPONEN-KOMPONEN SISTEM TENAGA LISTRIK, DIAGRAM
SEGARIS, DIAGRAM IMPEDANSI / REAKTANSI, BESARAN PERSATUAN.
3. MODEL RANGKAIAN
MATRIX [ Y Bus ], MATRIX [ Z Bus ]
4. METODA PENYELESAIAN ALIRAN DAYA
METODA GAUSS-SEIDEL, NEWTON-RAPHSON, FAST-DECOUPLED
Electric Power Systems L1 - Olof Samuelsson
2
DALAM ANALISIS SISTEM
TENAGA LISTRIK I, DI ANALISIS
SISTEM TENAGA LISTRIK 3
PHASA YANG
SEIMBANG /
SIMETRI
DAN DALAM
Electric Power Systems L1 - Olof Samuelsson
4
SISTEM YANG MEMBANGKITKAN,
MENGATUR, MENYALURKAN /
MEMBAGI DAN AKHIRNYA YANG
MEMAKAI / MEMANFAATKAN
TENAGA LISTRIK.
Electric Power Systems L1 - Olof Samuelsson 5
From generator to customer
Source: vattenfall.se
Generation
|
Transmission
|
Distribution
|
Consumption
Electric Power Systems L1 - Olof Samuelsson 6
Basic Components of Electric Power:
How electricity gets to you
How electricity gets to you
When electricity leaves a po wer plan t (1), its voltage is increased at a “ste p-up” substation (2). Next, the energ y tr ave ls along a transmi ssion line to the area where the p ower is neede d (3 ). Once th ere, the vo ltag e is decreased, or “ stepped -down,” at a noth er substati on ( 4), and a distribution power line (5) carr ies the electricity until it reaches a home or business (6).
– EEI, Getti ng Ele ctri city Whe re It’s Ne ede d, May 20 00
Electric Power Systems L1 - Olof Samuelsson
7
BAGIAN UTAMA SISTEM
TENAGA LISTRIK
1. PEMBANGKIT
2. SALURAN TRANSMISI
Electric Power Systems L1 - Olof Samuelsson
8
•
PEMBANGKIT
:
GENERATOR-GENERATOR ( + PRIME MOVERNYA )
TEGANGAN YANG DIBANGKITKAN : 13,8 - 24 kV
PERALATAN PENGATUR TEGANGAN DAN FREKWENSI
-TRANSFORMATOR-TRANSFORMATOR TEGANGAN TINGGI
•
SALURAN TRANSMISI / SUB TRANSMISI
:
SALURAN-SALURAN TRANSMISI TEGANGAN TINGGI
TEGANGAN : 34,5 to 765 kV
TRANSFORMATOR-TRANSFORMATOR PENGATUR DAYA AKTIF DAN
REAKTIF
•
DISTRIBUSI / BEBAN
:
FEEDER-FEEDER YANG MENGHUBUNGKAN BERMACAM-MACAM BEBAN
TEGANGAN : 220 VOLT - 34,5 kV
Electric Power Systems L1 - Olof Samuelsson
9
KARAKTERISTIK SISTEM
TENAGA LISTRIK
• SISTEM TENAGA LISTRIK TIDAK DAPAT
MENYIMPAN ENERGI ATAUPUN BUKAN
MERUPAKAN SUMBER ENERGI
• SISTEM TENAGA LISTRIK HANYA
MENGUBAH ENERGI YANG TERSEDIA
DARI SUMBER-SUMBER ALAM MENJADI
ENERGI LISTRIK DAN SISTEM TERSEBUT
MENGATUR PEMAKAIAN ENERGI LISTRIK
SECARA EFISIEN
Electric Power Systems L1 - Olof Samuelsson 10
Electric power production
Wind
Nuclear
Fossil
Hydro
Electric Power Systems L1 - Olof Samuelsson
11
SUMBER-SUMBER ENERGI
ALAM
1. FOSSIL FUEL ( BATUBARA, MINYAK, GAS
ALAM )
2. FISSILE MATERIAL ( URANIUM, THORIUM )
3. ALIRAN AIR
4. ANGIN, TENAGA MATAHARI, TENAGA AIR
LAUT dll
(1), (2), (3) TELAH DIGUNAKAN SECARA
KOMERSIAL
Electric Power Systems L1 - Olof Samuelsson 12
PUSAT PEMBANGKIT TENAGA LISTRIK
SALURAN TRANSMISI
PROSES PRODUKSI TENAGA LISTRIK HINGGA
SAMPAI KE KONSUMEN
GARDU INDUK INDUSTRI BESAR JARINGAN TEGANGAN RENDAH 220 V TRAFO DISTRIBUSI JARINGAN TEGANGAN MENENGAH 20 KV INDUSTRI KECIL MALL / HOTEL INDUSTRI SEDANG RUMAH TANGGA PJUElectric Power Systems L1 - Olof Samuelsson 13
Electric Power Delivery Efficiency
Electric Power Systems L1 - Olof Samuelsson 14 SPP 5-7 : 1800 MW (Coal) SPP 1-4 : 1600 MW (Coal) SURALAYA GTPP : 125 MW Die.PP : 75,8 MW PESANGARAN HEPP : 274,8 MW BRANTAS SCPP : 800 MW PAITON CCPP : 527 MW GTPP : 342 MW GRATI GTPP : 29 MW SOPP (OIL) : 150 MW PERAK CCPP : 1.578 MW GTPP : 100 MW SOPP (G) : 400 MW SOPP (OIL) l : 200 MW GRESIK CCPP : 711 MW CCPP : 328,9 MW SOPP (OIL) : 300 MW TAMBAK LOROK HEPP : 55 MW KEDUNG OMBO GTPP : 80 MW SUNYARAGI HEPP. : 504 MW CIRATA CCPP : 435 MW CCPP : 660 MW MUARA TAWAR CCPP : 1.180 MW GTPP (G) : 195 MW GTPP (OIL) : 72 MW SOPP (OIL) : 100 MW P R I O K CCPP (Gas) : 508 MW SPP (Gas) : 400 MW SPP (OIL) : 300 MW MUARA KARANG Geo.PP : 165 MW SALAK HEPP : 33 MW KRACAK/UBRUG HEPP : 700 MW SAGULING HEPP : 47 MW PLENGAN/LAMAJAN Geo.PP : 195 MW KAMOJANG/DRAJAT HEPP : 214 MW MRICA/GARUNG/KETENGER HEPP : 19 MW W. LINTANG/SEMPOR HEPP : 12 MW WONOGIRI PAITON IPP SCPP : 2400 MW
Electric Power Systems L1 - Olof Samuelsson 15 H SLAYA SRANG GNDUL CNJUR KSBRU JTLHR PDLRG CRATA MRICA WSOBO RWALO GBONG BNTUL KLTEN JELOK SGRAH CEPU RBANG BABAT GRSIK KRIAN NGAWI MNRJO KDBRU KKTES KBAGN MKRTO PBLGO LMJNG PMKSN STBDO BDWSO JMBER BWNGI LMNIS PWRJO BOJLI JAJAR
WLERI UNGAR BLORA KUDUS WLNGI BJGRO LNGAN SMNEP GLTMR JTAKE SLIRA PKLON GARNG ASAHI KKSTL CLGON CBBAT TBROK SGMDU U REGION II REGION III PITON GU BNGIL JAVA MADURA BALI SALAK DRJAT BNJAR U KRPYK BKLAN PMLNG GRATI GU A MKRNG BGBRU CIBNG SGLNG TGRNG GU REGION I GU PRIOK P A P BDSLN SRAGI UBRNG KMJNG TSMYA GARUT BMAYU MJNNG KBSEN P SRGEN A U U CBATU MTWAR BKASI KMBNG KNTUG PALUR PERAK A A U U GU SPANG A GLNUK KAPAL GNYAR NSDUA G AMLRA SANUR NGARA PSGRH PMRON REGION IV A
PETA SISTEM KELISTRIKAN JAMALI
•
SUTET 500 kV jalur selatan baru selesai Paiton – Pedan
(Pedan – Tasikmalaya – Depok selesai 2005)
•
GITET 500 kV Kediri teleh beroperasi pada Sept. 2003
•
PLTG MUARA TAWAR 6 x 100 MW rencana selesai th. 2004
Electric Power Systems L1 - Olof Samuelsson 16
PETA PERMASALAHAN PENYALURAN
REGION JAWA TIMUR & BALI TAHUN 2002
(Sumber Data PLN UBS P3B)
SWHAN WARU KLANG GRSIK PLTGU LNGAN SMSIK BRATA PKMIA TUBAN BABAT BJGRO KEREK ke CEPU BBDAN DYRJO TARIK MIWON ISPDO MPION PRONG BDRAN PLOSO NGJUK CRBAN NGAWI MRGEN SYZAG ke PALUR GGRAM DLOPO PNRGO TRGLK PLTA TLGNG TLGNG BLTAR LDOYO WLNGI SIMAN MDLAN SLRJO PCTAN BNGIL GDTAN RJOSO PBLGO LJANG TNGUL BDWSO STBDO BWNGI NGARA PMRON KAPAL GNYAR AMPRA SANUR PGRAN NSDUA SPM NGORO ke UNGARAN CKMIA SGMDU MWANG BENDO JKTAS DGRAN PERAK MKBAN JMBER GTENG MNYAR ALPMA BRITI ASARI SKTIH BNGUN SBRAT MGTAN MJAAGN TUBAN 3 SAMPG PKSAN SMNEP BKLAN PATON GLNUK GLMUR CERME KJTIM GBONG UDAAN KPANG MNRJO AJMTO BNRAN SLILO WKRMO SIMPG RNKUT TNDES NGAGL KTSNO 1 3 4 2 5 6 7 8 10 11 PDAAN GRATI SGRUH KKTES STAMI SKLNG KGUNG BLBNG SKRJO PLHAN GPGAN TUREN PIER BMKRO PAKIS LWANG BLKDG UJUNG KJRAN KRSAN GDING 12 14 15 9 13 PEDAN REGION-3
Keterangan :
1
Electric Power Systems L1 - Olof Samuelsson 17 0 2000 4000 6000 8000 10000 12000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
---> Jam
--->
M
W
Rumah Tangga
Komersil
Publik
Industri
Total
Electric Power Systems L1 - Olof Samuelsson 18
Power system operation
•
Daily routine
–
Production planning
–
P and V control
•
Goals
–
Economy
–
Safety
–
Reliability
–
Environment
Electric Power Systems L1 - Olof Samuelsson 19
Electric power consumption
•
Daily variation
•
Yearly variation
•
Production
=
consumption
S ourc e: norde l.or gElectric Power Systems L1 - Olof Samuelsson 20
Power system phenomena
•
Short-circuits and other faults
•
Automatic operations
•
Thermal stress = overload
•
Angle stability
•
Voltage stability
•
Frequency stability
•
…
Electric Power Systems L1 - Olof Samuelsson 21
Common System Failures
•
Overloads
–
Demand exceeds safety level of
equipment
•
How or when might this occur?
•
Faults
–
Phase to ground
–
Phase to phase
Electric Power Systems L1 - Olof Samuelsson
22
PENGOPERASIAN SISTEM TENAGA
LISTRIK
•
SISTEM TENAGA LISTRIK YANG PERTAMA-TAMA DIBANGUN TERDIRI
DARI PUSAT-PUSAT PEMBANGKIT YANG TERPISAH-PISAH DAN
MASING-MASING PEMBANGKIT MENCATU BEBANNYA JUGA SECARA TERPISAH.
•
SAAT INI SISTEM TENAGA LISTRIK TERDIRI DARI SEJUMLAH
PUSAT-PUSAT PEMBANGKIT YANG BEKERJA PARALEL DAN MENCATU SEJUMLAH
PUSAT-PUSAT BEBAN MELALUI SALURAN TRANSMISI TEGANGAN TINGGI.
•
SISTEM TENAGA LISTRIK TERSEBUT BIASANYA DIHUBUNGKAN SECARA
INTERKONEKSI DENGAN BEBERAPA SISTEM TENAGA LISTRIK YANG LAIN
SEHINGGA TERBENTUK MULTI AREA SYSTEM.
•
HAL INI DILAKUKAN AGAR SISTEM TENAGA LISTRIK DAPAT BEKERJA
SECARA EKONOMIS DAN UNTUK MENAIKKAN KEANDALAN DARIPADA
SISTEM, DENGAN AKIBAT :
– PENGOPERASIAN SISTEM TENAGA LISTRIK BERTAMBAH KOMPLEKS
DENGAN TIMBULNYA LEBIH BANYAK PERSOALAN-PERSOALAN YANG HARUS DIATASI.
Electric Power Systems L1 - Olof Samuelsson 23
PERSOALAN-PERSOALAN
OPERASI
1.
LOAD FORCASTING
2.
UNIT COMMITMENT
3.
ECONOMIC DISPATCH
4.
ANALISIS ALIRAN DAYA
5.
ANALISIS HUBUNG SINGKAT
6.
ANALISIS STABILITAS
Electric Power Systems L1 - Olof Samuelsson
24
PERANAN KOMPUTER DALAM ANALISIS SISTEM
TENAGA
KEUNTUNGAN :
FLEXIBLE (DAPAT DIGUNAKAN UNTUK MENGANALISIS HAMPIR SEMUA PERSOALAN), TELITI, CEPAT DAN EKONOMIS
LANGKAH-LANGKAH :
1. MEMBUAT MODEL-MODEL MATEMATIS DARI PERSOALAN YANG AKAN DISELESAIKAN ( SATU
SET PERSAMAAN ALJABAR / DIFFERENSIAL )
2. MENENTUKAN METODE NUMERIK ( KETELITIAN CUKUP TINGGI DAN WAKTU KOMPUTASI CUKUP
CEPAT )
3. MENULIS / MENYUSUN PROGRAM KOMPUTER
PENGGUNAAN :
1. "OFF LINE" : DATA DIPEROLEH DARI OPERATOR ( MANUSIA), DENGAN DATA
TERSEBUT ANALISIS / PERHITUNGAN DILAKUKAN DENGAN KOMPUTER. UNTUK PERENCANAAN SISTEM, ANALISIS BILA ADA PERUBAHAN / PERLUASAN SISTEM, PERHITUNGAN PERIODIK SEHUBUNGAN DENGAN OPERASI SISTEM.
2. "ON LINE" : KOMPUTER MENERIMA DATA LANGSUNG DARI SISTEM YANG SEDANG OPERASI. PADA PENGATURAN BEBAN DAN FREKWENSI, ECONOMIC DISPATCH dan lain-lain.
Electric Power Systems L1 - Olof Samuelsson 25
Organization
•
Lectures
•
Problem solving
•
Laboratory exercises
•
Computer simulations
Source:powerworld.comElectric Power Systems L1 - Olof Samuelsson 26