RAB JALAN

238 

Loading....

Loading....

Loading....

Loading....

Loading....

Teks penuh

(1)

INPUT (MASUKAN) DATA ANALISA

PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

KOLOM UNTUK DIISI

DISIAPKAN OLEH :

TGL. / BULAN / TAHUN :

PROPINSI : PAPUA K O D E : ( 82 )

KABUPATEN : KOTA JAYAPURA

K O D E : JAYAPURA

INSTANSI :

: JAYAPURA

LOKASI PROYEK : KOTA JAYAPURA - TA. 2008

NAMA PROYEK : PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

: PERHITUNGAN ALAT

NILAI KURS HARGA PER DOLAR SAMA DENGAN NILAI (PADA SAAT DIHITUNG) RP. 9,500.00

FAKTOR ANGKUTAN UNTUK LOKASI KOTA JAYAPURA 1.10

PERINCIAN NILAI HARGA SEWA ALAT & HARGA BAHAN YAITU :

NILAI TERSEBUT YAITU : NILAI SEBELUM PAJAK DAN PROFIT (REAL COST) = 1.00 (100 %) DITAMBAH PROFIT DLL = 0.10 (10 %)

NILAI SETELAH PROFIT = 1.10 (110 %)

DITAMBAH PAJAK PENAMBAHAN NILAI (PPn 10 %) = 0.00 (110 x 0 %)

TOTAL NILAI SEWA ALAT PER JAM DAN BAHAN YAITU = 1.10 (110 %)

K E T E R A N G A N :

# JARAK PROYEK KE LOKASI MATERIAL RATA-RATA DIASUMSIKAN = 10 S/D 50 KM # HARGA STANDARD PELUMAS DI JAYAPURA = Rp. 20,000.00 (M. 145) # HARGA STANDARD SOLAR DI JAYAPURA = Rp. 10,000.00 (M. 143)

# HARGA STANDARD BENSIN DI JAYAPURA = Rp. 8,500.00 (M. 144)

# HARGA MATERIAL TIMBUNAN-ROYALTY / KERIKIL GALIAN ROYALTY 100,000.00 (MR. 011) # HARGA MATERIAL TIMBUNAN-ROYALTY / SIRTU SUNGAI ROYALTY 100,000.00 (MR. 012)

HARGA DIBAWAH INI HANYA UNTUK CHEK DATA SEBAGAI DASAR PERHITUNGAN

PERHITUNGAN HARGA PELUMAS DI SITE /LOKASI = Rp. 22,104.97 ( M.185 ) PERHITUNGAN HARGA SOLAR DI SITE /LOKASI = Rp. 11,098.02 ( M.183 ) PERHITUNGAN HARGA BENSIN DI SITE /LOKASI = Rp. 9,467.85 ( M.184 ) PERHITUNGAN UPAH PEKERJA / BURUH TAK TERAMPIL PER HARI = Rp. 55,000.00 ( L.101 ) PERHITUNGAN UPAH PEKERJA / BURUH TAK TERAMPIL PER JAM = Rp. 7,857.14 ( L.101 ) PERHITUNGAN BIAYA DUMP TRUK PERJAM (SEBELUM PAJAK & PROFIT) = Rp. 220,783.02 ( E. 211 ) PERHITUNGAN BIAYA WHEEL LOADER PERJAM (SEBELUM PAJAK & PROFIT) = Rp. 437,728.89 ( E. 052 )

(2)

PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

REVISI 8 FEB 2005 200.00

(3)

DAFTAR TENAGA KERJA DAN BAHAN-BAHAN -PERALATAN

PEKERJAAN : PEMELIHARAAN PERIODIK JALAN KOYA KOSO

NO.

U R A I A N

SATUAN

KODE

HARGA (Rp.)

T E N A G A K E R J A

1, MANDOR / KELOMPOK PEKERJA

OH.

L.061

93,500.00

2, OPERATOR - Trampil

OH.

L.081

110,000.00

3, PEMBANTU OPERATOR

OH.

L.083

82,500.00

4, SOPIR -Trampil

OH.

L.091

93,500.00

5, PEMBANTU SOPIR

OH.

L.099

82,500.00

6, PEKERJA - Kasar

OH.

L.101

60,500.00

7, PEKERJA - Trampil

OH.

L.106

71,500.00

BAHAN / MATERIAL

1, Batu quarry/Batu besar (ukuran crusher)

M3

M.010

248,059.40

2, Kerikil Sirtu

M3

M.011

274,176.54

3, Kerikil sungai (tidak disaring)

M3

M.012

245,293.69

4, Batu kali (besar)

M3

M.013

246,676.54

5, Batu Split 5 - 7 cm

M3

M.022

418,957.02

6, Batu Split 3 - 5 cm

M3

M.023

583,957.02

7, Batu Split 2 - 3 cm

M3

M.024

611,457.02

8, Batu Split 1 - 2 cm

M3

M.025

638,957.02

9, Bahan timbunan/pengikat pilihan

M3

M.040

61,962.85

10, Agregat halus/pasir bersih (pasir beton)

M3

M.041

272,321.25

11, Kerikil berpasiran alami/Sirtu Gunung

M3

M.042

201,106.21

12, Urugan pilihan

M3

M.050

170,361.00

13, Bitumen (ASPHALT)

Kg

M.061

9,628.52

14, Kerosine

Liter

M.065

9,733.95

15, Kayu Bakar

M3

M.070

959,755.40

16, Pasir Hol/filler/abu batu

M3

M.081

139,176.02

17, Alat bantu / alat-alat kerja (3 set)

@ Set

M.170

150,000.00

18, Acuan dari kayu

M3

M.180

55,929.46

19 Solar

Liter

M.183

11,098.02

20 Premium/bensin

Liter

M.184

9,467.85

21 Minyak pelumas/oli

Liter

M.185

22,104.97

PERALATAN

1, Buldozer

Jam

E.001

623,972.13

2, Buldozer

Jam

E.003

324,446.07

3, Motor grader

Jam

E.010

493,575.92

4, Exavator Hidrolik 1.0 m3

Jam

E.020

534,046.77

5, Stone Crusher/Scr 30 ton/h

Jam

E.031

860,914.19

6, Stone Crusher/Scr 20 ton/h

Jam

E.032

491,723.07

7, Stone Crusher/Scr 10 ton/h

Jam

E.033

232,000.78

8, Loader tracked

Jam

E.051

498,023.56

9, Loader wheeled

Jam

E.052

481,501.78

10, Tractor wheeled

Jam

E.053

172,703.48

11, Three Wheel Roller 6-8 ton

Jam

E.080

284,111.33

12, Tandem Roller 6-12 ton

Jam

E.081

632,526.62

13, Vibrator Roller self p. 6-7 ton

Jam

E.082

314,607.31

14, Asphalt sprayer 4000l

Jam

E.152

378,535.15

15, Asphalt sprayer 1000l

Jam

E.153

140,421.84

16, Asphalt sprayer towed 400 l

Jam

E.154

50,085.34

17, Fuel tank truck

Jam

E.172

331,845.82

18, Water tank truck

Jam

E.182

371,943.51

19, Low loader + tractor

Jam

E.192

607,499.26

20, Dump Truck 3,5 ton

Jam

E.211

268,125.33

21, Dump Truck 5 ton

Jam

E.212

357,572.00

22, Dump Truck 8 ton

Jam

E.213

456,500.05

23, Flat bed truck 3,5 ton

Jam

E.221

242,861.32

Jayapura 7 April 2008

PT. JAYAKSI

JOHNY GUNAWAN

Direktur

(4)

DAFTAR HARGA SATUAN ANALISA "K"

DAFTAR HARGA SATUAN ANALISA "K" LANJUTAN

(Untuk Perhitungan Rencana Anggaran Biaya) (Untuk Perhitungan Rencana Anggaran Biaya)

PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

KOTA JAYAPURA - TA. 2008 KOTA JAYAPURA - TA. 2008

NO. URAIAN PEKERJAAN KODE HARGA SATUAN SATUAN

ANALISA Rp. ANALISA

1 PENGADAAN KERIKIL GALIAN (TIDAK DISARING) - DGN ALAT K.010 248,237.37 M3 2 PENGADAAN KERIKIL GALIAN (TIDAK DISARING) - DGN BURUH K.011 314,580.66 M3 3 PENGADAAN KERIKIL SUNGAI (TIDAK DISARING) - DGN ALAT K.012 243,037.60 M3 4 PENGADAAN KERIKIL SUNGAI (TIDAK DISARING) - DGN BURUH K.013 305,714.00 M3 5 PENGADAAN KERIKIL GALIAN TERSARING - DGN ALAT K.014 407,628.81 M3 6 PENGADAAN KERIKIL SUNGAI TERSARING - DGN ALAT K.016 380,399.01 M3 7 PRODUKSI BATU PECAH TERSARING (BATU SUNGAI) - DGN ALAT K.017 490,825.94 M3 8 PRODUKSI BATU PECAH TERSARING (BATU QUARY) - DGN ALAT K.018 443,262.14 M3

9 PRODUKSI DAN SUPLAI LATASIR - DGN ALAT K.020 1,258,974.18 TON

10 PRODUKSI DAN SUPLAI LATASIR - DGN BURUH K.020 M 1,727,072.24 TON

11 PRODUKSI DAN SUPLAI LABUTAG - DGN BURUH K.023 500,444.43 TON

12 PRODUKSI DAN SUPLAI LASTON ATAS - DGN ALAT K.026 1,274,652.76 TON

13 PRODUKSI DAN SUPLAI LATASTON - DGN ALAT K.035 1,289,452.27 TON

14 MEMBUAT PARIT - DGN ALAT K.111 41,696.74 M3

15 MEMBUAT PASANGAN BATU PADA PARIT - DGN BURUH K.112 322,778.84 M'

16 PAS. BATU PD PARIT DGN PNTP PLAT BERTULANG - DGN BURUH K.113 612,201.87 M1 17 MEMBUAT SALURAN MELINTANG PD BAHU JALAN - DGN BURUH K.114 758,346.47 M3 18 PEMB. PIPA BETON BERTULANG DIA 60 CM x 1 M - DGN BURUH K.115 187,297.42 M' 19 PEMB. PIPA BETON BERTULANG DIA 80 CM x 1 M - DGN BURUH K.116 300,167.92 M' 20 PEMB. PIPA BETON BERTULANG DIA 100 CM x 1 M - DGN BURUH K.117 465,443.63 M' 21 PAS. PIPA BETON TDK. BERTULANG DIA 60 CM x 1 M - DGN BURUH K.121 813,817.85 M'

22 PAS. PIPA BETON BERTULANG DIA 60 CM x 1 M - DGN BURUH K.122 732,339.78 M'

23 PAS. PIPA BETON TDK. BERTULANG DIA 80 CM x 1 M - DGN BURUH K.123 1,047,666.61 M'

24 PAS. PIPA BETON BERTULANG DIA 80 CM x 1 M - DGN BURUH K.124 929,562.57 M'

25 PAS. PIPA BETON TDK. BERTULANG DIA 100 CM x 1 M - DGN BURUH K.125 1,310,048.33 M' 26 PAS. PIPA BETON BERTULANG DIA 100 CM x 1 M - DGN BURUH K.126 1,353,765.79 M'

27 PENGUPASAN & PEMBERSIHAN SEMAK PD DAMIJA - DGN BURUH K.210 208,041.67 ARE

28 PENGUPASAN & PEMBERSIHAN SEMAK PD DAMIJA - DGN ALAT K.211 147,452.53 ARE

29 PENGURUGAN TANAH - DGN BURUH K.220 295,561.51 M3

30 PENGURUGAN TANAH - DGN ALAT K.221 191,265.03 M3

31 GALIAN TANAH UNTUK KONSTRUKSI - DGN BURUH K.224 52,212.50 M3

32 PENIMBUNAN DAN PEMADATAN (UTK. JEMBATAN & GORONG2) DGN BURUHK.225 506,734.21 M3

33 PENIMBUNAN BADAN JALAN - DGN ALAT K.311 282,903.76 M3 34 GALIAN TANAH DAN PEMBUANGAN - DGN BURUH K.320 89,628.54 M3 35 GALIAN TANAH DAN PEMBUANGAN - DGN ALAT K.321 79,317.07 M3 36 PENYIAPAN TANAH DASAR - DGN ALAT K.342 131,140.59 ARE

37 PEMBENTUKAN BAHU JALAN KERAS - DGN BURUH K.410 443,047.07 M3

38 PEMBENTUKAN BAHU JALAN KERAS - DGN ALAT K.411 #REF! M3

39 MEMOTONG BAHU JALAN TINGGI - DGN BURUH K.420 173,223.47 M3 40 MEMOTONG BAHU JALAN TINGGI - DGN ALAT K.421 92,082.19 M3

41 PEMBERSIHAN SEMAK DLL PD BAHU JALAN - BURUH K.422 127,066.67 ARE

42 PEMBERSIHAN PARIT - DGN BURUH K.424 10,074.23 M'

43 LAPIS PONDASI BAWAH (LPB) KLAS A - DGN ALAT K.510 444,573.83 M3

44 LAPIS PONDASI BAWAH (LPB) KLAS A - DGN BURUH K.511 464,425.21 M3

45 LAPIS PONDASI BAWAH (LPB) KLAS B - DGN ALAT K.512 386,110.77 M3

46 LAPIS PONDASI BAWAH (LPB) KLAS B - DGN BURUH K.513 519,266.72 M3

47 LAPIS PONDASI BAWAH (LPB) KLAS C - DGN ALAT K.514 351,768.90 M3

48 LAPIS PONDASI BAWAH (LPB) KLAS C - DGN BURUH K.515 435,044.70 M3

49 LAPIS PONDASI BAWAH (LPB) KLAS C - DGN ALAT K.517 465,619.71 M3

50 LAPIS PONDASI ATAS (LPA) KLAS A - DGN ALAT K.520 621,475.64 M3

51 LAPIS PONDASI ATAS (LPA) KLAS A - DGN BURUH K.521 572,446.23 M3

52 LAPIS PONDASI ATAS (LPA) KLAS B - DGN ALAT K.522 550,046.38 M3

53 LAPIS PONDASI ATAS (LPA) KLAS B - DGN BURUH K.523 543,686.67 M3

54 PENGHAMPARAN LAPIS PONDASI ATAS ASPAL BETON - DGN ALAT (A.T.B)K.528 3,152,698.22 M3

55 LAPEN/PONDASI ATAS MACADAM 7 CM - DGN BURUH K.530 1,947,131.99 M3

56 PENYIAPAN JAPAT 100 MM - DGN BURUH K.610 47,701.54 M2

57 PENYIAPAN JAPAT 100 MM - DGN ALAT K.611 53,449.89 M2

58 LABURAN ASPAL PASIR (BURAS) - DGN ALAT K.612 13,979.88 M2

59 PEMBTKAN & PENGKERIKILAN ULANG JAPAT 4 CM -DGN ALAT K.613 21,801.15 M2 60 LAPIS PENETRASI (LAPEN) MACADAM 5 CM - DGN BURUH K.618 115,125.89 M2

61 PENGHAMPARAN LATASIR 2 CM - DGN ALAT K.621 58,280.08 M2

62 PENGHAMPARAN LATASIR 2 CM - DGN ALAT K.621 M 75,934.06 M2

63 PENGHAMPARAN LASBUTAG 2 CM - DGN BURUH K.631 45,261.22 M2

64 PENGHAMPARAN LASTASTON 3 CM - DGN ALAT (H.R.S) K.636 106,725.34 M2

65 PENGHAMPARAN LATASIR 2 CM - DGN BURUH (Dgn. Minyak Bakar) K.638 58,712.39 M2 66 PENGHAMPARAN LATASIR 2 CM - DGN BURUH (dgn. Kayu Bakar) K.638 M 76,640.08 M2

67 KONSTRUKSI PASANGAN BATU - DGN BURUH K.705 508,202.08 M3

Suplement

PENYIAPAN TANAH DASAR (DENGAN BURUH) K.341 2,195.80 M2 PENGUPASAN DAN PERATAAN BADAN JALAN (ASPAL) K.342. M #REF! M2

1 GALIAN TANAH UNTUK KONSTRUKSI - DGN BURUH s.d. kedalaman 1 M K.224 M1 28,012.50 M3 2 GALIAN TANAH UNTUK KONSTRUKSI - DGN BURUH s.d. kedalaman 2 M K.224 M2 37,087.50 M3

(5)

DAFTAR HARGA SATUAN ANALISA "K" LANJUTAN

(Untuk Perhitungan Rencana Anggaran Biaya)

PEMBANGUNAN JALAN, JEMBATAN DAN BANGUNAN PELENGKAP LAINNYA

KOTA JAYAPURA - TA. 2008

NO. URAIAN PEKERJAAN KODE HARGA SATUAN SATUAN

ANALISA Rp. ANALISA

68 ACUAN UNTUK BETON STRUKTUR - DGN BURUH K.710 37,777.88 M2

69 MEMOTONG, MEMBENGKOK & PAS.TUL. BESI BETON - DGN BRH K.715 1,913.87 KG

70 BETON NON STRUKTUR/RABAT KLAS Bo K.719 723,482.22 M3

71 BETON MASSA KLAS K125 (MESIN MOLLEN 125 LITER) K.720 771,375.26 M3 72 BETON STRUKTUR KLAS K175 (MESIN MOLLEN 125 LITER) K.721 740,656.85 M3 73 BETON STRUKTUR KLAS K225 (MESIN MOLLLEN 125 LITER) K.722 728,190.69 M3 74 BETON MASSA KLAS K125 (MESIN MOLLEN 250 LITER) K.723 725,169.56 M3 75 BETON STRUKTUR KLAS K175 (MESIN MOLLEN 250 LITER) K.724 789,198.20 M3 76 BETON STRUKTUR KLAS K225 (MESIN MOLLLEN 250 LITER) K.725 746,295.40 M3 77 BETON STRUKTUR KLAS K175 (MESIN MOLLEN 500 LITER) K.727 778,330.38 M3 78 BETON STRUKTUR KLAS K225 (MESIN MOLLLEN 500 LITER) K.728 741,060.75 M3 79 BETON STRUKTUR KLAS K275 (MESIN MOLLLEN 500 LITER) K.729 757,824.45 M3 80 BETON STRUKTUR KLAS K350 (MESIN MOLLLEN 500 LITER) K.730 771,988.60 M3 81 BIAYA PEMEL. RUTIN TAHUNAN JL. KERIKIL KLAS 1 - BURUH K.801 #REF! KM 82 BIAYA PEMEL. RUTIN TAHUNAN JL. KERIKIL KLAS 2 - BURUH K.802 #REF! KM 83 BIAYA PEMEL. RUTIN TAHUNAN JL. ASPAL KLAS 1 - BURUH K.803 #REF! KM 84 BIAYA PEMEL. RUTIN TAHUNAN JL. ASPAL KLAS 2 - BURUH K.804 #REF! KM 85 BIAYA PEMEL. RUTIN TAHUNAN JL. ASPAL KLAS 3 - BURUH K.805 #REF! KM 86 BIAYA PEMEL. RUTIN TAHUNAN JL. ASPAL KLAS 4 - BURUH K.806 #REF! KM

87 BRONJONG PENAHAN TANAH - DENGAN BURUH K.815 455,611.80 M3 88 PEMBENTUKAN DAN PERATAAN BAHU JALAN - DGN ALAT K.855 603,975.92 KM

89 PERATAAN KEMBALI JALAN KERIKIL - DGN ALAT K.860 2,461,298.57 KM

90 PERBAIKAN LUBANG JALAN KERIKIL - DGN BURUH K.865 102,875.41 M2

91 PERBAIKAN LEGOKAN JALAN KERIKIL - DGN BURUH K.870 308,830.90 M2

92 PENGHAMPARAN ULANG JL. KERIKIL PADAT 5 CM - DGN BURUH K.875 36,630.95 M2 93 PENGHAMPARAN ULANG JL. KERIKIL PADAT 5 CM - DGN ALAT K.877 33,101.24 M2

94 PERBAIKAN LUBANG JALAN ASPAL - DGN BURUH K.880 151,230.66 M2

95 PERBAIKAN LEGOKAN JALAN ASPAL - DGN BURUH K.885 362,284.88 M2

HARGA BETON

MUTU BETON K.175

(cor beton massa)

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 BETON STRUKTUR K. 175 K. 721 1 x 740,656.85 740,656.85 M3

HARGA BETON MASSA PER M3 929,546.27 M3

PPN 10 % 92,954.63

TOTAL HARGA BETON MASA/M3 1,022,500.89 M3

NO MUTU BETON K.225 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

(cor beton massa)

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 BETON STRUKTUR K. 225 K. 722 1 x 728,190.69 728,190.69 M3

HARGA BETON MASSA PER M3 917,080.11 M3

PPN 10 % 91,708.01

TOTAL HARGA BETON MASA/M3 1,008,788.13 M3

NO MUTU BETON K.175 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 110 x 1,913.87 210,525.22 Kg

3 BETON STRUKTUR K. 175 K. 721 1 x 740,656.85 740,656.85 M3

HARGA BETON BERTULANG PER M3 1,140,071.48 M3

PPN 10 % 114,007.15

TOTAL HARGA BETON BERTULANG/M3 1,254,078.63 M3

NO MUTU BETON K.225 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 200 x 1,913.87 382,773.12 Kg

3 BETON STRUKTUR K. 225 K. 722 1 x 728,190.69 728,190.69 M3

HARGA BETON BERTULANG PER M3 1,299,853.24 M3

NO MUTU BETON K.175 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 110 x 1,913.87 210,525.22 Kg

3 BETON STRUKTUR K. 175 K. 724 1 x 789,198.20 789,198.20 M3

HARGA BETON BERTULANG PER M3 1,188,612.84 M3

NO MUTU BETON K.225 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 200 x 1,913.87 382,773.12 Kg

3 BETON STRUKTUR K. 225 K. 725 1 x 746,295.40 746,295.40 M3

HARGA BETON BERTULANG PER M3 1,317,957.94 M3

NO MUTU BETON K.175 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 110 x 1,913.87 210,525.22 Kg

3 BETON STRUKTUR K. 175 K. 727 1 x 778,330.38 778,330.38 M3

HARGA BETON BERTULANG PER M3 1,177,745.01 M3

NO MUTU BETON K.225 ANALISA VOLUME HARSAT JUMLAH HARGA SATUAN

MUTU BAJA U.24

1 ACUAN (Bekisting) K. 710 5 x 37,777.88 188,889.42 M2

2 PEK. PEMBESIAN K. 715 200 x 1,913.87 382,773.12 Kg

3 BETON STRUKTUR K. 225 K. 728 1 x 741,060.75 741,060.75 M3

HARGA BETON BERTULANG PER M3 1,312,723.30 M3

SATUAN

(6)

DAFTAR PERHITUNGAN UPAH BURUH DAN PERHITUNGAN PENGADAAN BAHAN/MATERIAL

KOTA JAYAPURA - TA. 2008

N KODE HARGA DI HARGA JARAK TEMPUH KAPASITAS KECEPATAN WAKTU BIAYA WAKTU WAKTU HARGA JUMLAH WAKTU MUAT WAKTU JML. WAKTU JML. BIAYA PROSEN - NILAI PROFIT TOT BIAYA PPN TOT BIAYA

O ~ LOKASI ATAU PER JAM DARI LOKASI ANGKUT RATA-RATA TEMPUH LOADER/ MUAT BONGKAR TENAGA TENAGA DENGAN BONGKAR TEMPUH + BONGKAR TASE PE (10 %) SETELAH + (10 %) SMP LOKASI

M NAMA URAIAN MA DI QUARY TRUK ANGKUT S/D LOKASI TRUK TRUK TRUK PP. DOZER DENGAN DGN KEEP KERJA KERJA TENAGA DGN TENAGA BONGKAR MUAT NYU PROFIT PROYEK

O TE RY (Rp./LT) MATERIAL PROYEK (DLM. LT) PER LOADER PER MANUSIA MANUSIA MUAT (Rp./LT) PENYU - SUTAN (Rp./LT) (Rp./LT) (Rp./LT) (Rp./LT)

R RI (Rp./KG) (DLM. M3) (Rp./KG) SUTAN (Rp./LT) (Rp./M3) (Rp./M3) (Rp./M3) (Rp./M3)

AL (Rp./M3) ( Rp.) ( KM ) (DLM. KG) KM/JAM (JAM) (Rp./JAM) (JAM) ( JAM ) ( JAM ) ORANG ( JAM ) ( JAM ) ( JAM ) (Rp./M3) ( % ) (Rp./KG) (Rp./KG) (Rp./KG) (Rp./KG) (Rp./KG)

((15+16)x13x14

1 2 3 4 HARGA 6 7 8 (2 x 6)/8 HARGA 11 12 HARGA 14 15 16 9+11+12+15+16 + 19 (19/4)x100 (4+18+20)x10% (4+18+20)+21 21 x 10 % 22 + 23

E.211 E.052 L.101/5 (9+12)x5+10x11))/7

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

TENAGA KERJA / UPAH

1. MANDOR / KELOMPOK PEKERJA L.061 85,000.00 - - - 8,500.00 93,500.00 0.00 93,500.00

2. MEKANIK - Trampil L.071 0.00 - - - 0.00 0.00 0.00 0.00

3. MEKANIK - Semi Trampil L.072 0.00 - - - 0.00 0.00 0.00 0.00

4. KEPALA TUKANG L.073 0.00 - - - 0.00 0.00 0.00 0.00

5. TUKANG L.079 0.00 - - - 0.00 0.00 0.00 0.00

6. OPERATOR - Trampil L.081 100,000.00 - - - 10,000.00 110,000.00 0.00 110,000.00

7. OPERATOR - Semi Trampil L.082 0.00 - - - 0.00 0.00 0.00 0.00

8. PEMBANTU OPERATOR L.083 75,000.00 - - - 7,500.00 82,500.00 0.00 82,500.00

9. SOPIR -Trampil L.091 85,000.00 - - - 8,500.00 93,500.00 0.00 93,500.00

10. SOPIR -Pribadi L.092 0.00 - - - 0.00 0.00 0.00 0.00

11. PEMBANTU SOPIR L.099 75,000.00 - - - 7,500.00 82,500.00 0.00 82,500.00

12. PEKERJA - Kasar L.101 55,000.00 - - - 5,500.00 60,500.00 0.00 60,500.00

13. PEKERJA - Semi Trampil L.103 0.00 - - - 0.00 0.00 0.00 0.00

14. PEKERJA - Trampil L.106 65,000.00 - - - 6,500.00 71,500.00 0.00 71,500.00

BAHAN / MATERIAL

1. BATU GUNUNG ATAU QUARY M.010 100,000.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.10 7,857.14 4 0.50 - 1.85 125,508.55 - 0.00 22,550.85 248,059.40 0.00 248,059.40

2. KERIKIL SIRTU MR.011 125,000.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.10 7,857.14 4 0.40 - 1.75 124,251.40 - 0.00 24,925.14 274,176.54 0.00 274,176.54

3. KERIKIL SUNGAI (TDK DISARING) M.012 100,000.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.10 7,857.14 4 0.30 - 1.65 122,994.26 - 0.00 22,299.43 245,293.69 0.00 245,293.69

4. BATU KALI M.013 100,000.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.10 7,857.14 4 0.40 - 1.75 124,251.40 - 0.00 22,425.14 246,676.54 0.00 246,676.54

5. BATU KALI (KECIL DISARING) M.014 - - -

6. BATU PECAH 10 - 15 CM M.020 - - - 7. BATU PECAH 7 - 10 CM M.021 - - - 8. BATU PECAH 5 - 7 CM M.022 250,000.00 220,783.02 25.00 2.50 40.00 1.25 437,728.89 0.08 0.07 - - - - 1.40 130,870.02 - 0.00 38,087.00 418,957.02 0.00 418,957.02 9. BATU PECAH 3 - 5 CM M.023 400,000.00 220,783.02 25.00 2.50 40.00 1.25 437,728.89 0.08 0.07 - - - - 1.40 130,870.02 - 0.00 53,087.00 583,957.02 0.00 583,957.02 10. BATU PECAH 2 - 3 CM M.024 425,000.00 220,783.02 25.00 2.50 40.00 1.25 437,728.89 0.08 0.07 - - - - 1.40 130,870.02 - 0.00 55,587.00 611,457.02 0.00 611,457.02 11. BATU PECAH 1 - 2 CM M.025 450,000.00 220,783.02 25.00 2.50 40.00 1.25 437,728.89 0.08 0.07 - - - - 1.40 130,870.02 - 0.00 58,087.00 638,957.02 0.00 638,957.02 12. BATU PECAH 0,5 - 1 CM M.026 - - -

13. GORONG - 2 BETON DIA. 60 CM M.030 0.00 220,783.02 15.00 3.50 40.00 0.75 - - - 7,857.14 4 0.50 0.50 1.75 56,290.24 - 0.00 5,629.02 61,919.26 0.00 61,919.26

14. GORONG - 2 BETON DIA. 80 CM M.033 0.00 220,783.02 15.00 3.50 40.00 0.75 - - - 7,857.14 6 0.50 0.50 1.75 60,780.04 - 0.00 6,078.00 66,858.04 0.00 66,858.04

15. GORONG - 2 BETON DIA. 100 CM M.035 0.00 220,783.02 15.00 3.50 40.00 0.75 - - - 7,857.14 6 0.50 0.50 1.75 60,780.04 - 0.00 6,078.00 66,858.04 0.00 66,858.04

16. BAHAN TIMBUNAN/PENGIKAT PILIHAN M.040 0.00 220,783.02 10.00 2.50 40.00 0.50 - - 0.07 7,857.14 4 0.50 - 1.07 56,329.87 - 0.00 5,632.99 61,962.85 0.00 61,962.85

17. PASIR AYAK UNTUK BETON M.041 125,000.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.07 7,857.14 4 0.50 - 1.82 122,564.77 - 0.00 24,756.48 272,321.25 0.00 272,321.25

18. KERIKIL BERPASIRAN ALAMI/SIRTU GunungM.042 100,000.00 220,783.02 16.00 2.50 40.00 0.80 - - 0.07 7,857.14 4 0.50 - 1.37 82,823.83 - 0.00 18,282.38 201,106.21 0.00 201,106.21

19. URUGAN PILIHAN / KARANG GUNUNG M.050 100,000.00 220,783.02 10.00 2.50 40.00 0.50 - - 0.10 7,857.14 4 0.15 - 0.75 54,873.64 - 0.00 15,487.36 170,361.00 0.00 170,361.00

20. ASPAL BITUMEN M.061 8,700.00 220,783.02 12.00 3,500.00 40.00 0.60 - - - 7,857.14 4 1.14 0.57 2.31 53.20 - 0.00 875.32 9,628.52 0.00 9,628.52

21. ASPAL BUTON M.062 - - -

22. MINYAK FLUX ( UNTUK EMULSI ) M.063 0.00 220,783.02 28.00 3,500.00 40.00 1.40 - - - 7,857.14 4 0.36 0.36 2.12 94.78 0.50 0.00 9.48 104.26 0.00 104.26

23. MINYAK TANAH M.065 8,710.00 220,783.02 28.00 3,500.00 40.00 1.40 - - - 7,857.14 4 0.40 0.40 2.20 95.50 0.50 43.55 884.90 9,733.95 0.00 9,733.95

24. KAYU BAKAR M.070 850,000.00 220,783.02 5.00 3.50 40.00 0.25 - - - 7,857.14 4 0.50 0.25 1.00 22,504.91 - 0.00 87,250.49 959,755.40 0.00 959,755.40

25. SEMEN PORTLAND (PC)/ZAK M.080 0.00 220,783.02 12.00 87.50 40.00 0.60 - - - 7,857.14 4 0.60 0.60 1.80 1,944.96 - 0.00 194.50 2,139.46 0.00 2,139.46

26. PASIR HOL / FILLER/ABU BATU M.081 0.00 220,783.02 25.00 2.50 40.00 1.25 - - 0.13 7,857.14 4 0.37 - 1.75 126,523.66 - 0.00 12,652.37 139,176.02 0.00 139,176.02

27. BATU KAPUR M.082 - - - 0.00 0.00 0.00 0.00 0.00 28. CAT JEMBATAN M.090 0.00 220,783.02 12.00 - 10.00 - - - - 7,857.14 1 - - - 0.00 0.00 0.00 0.00 0.00 29. BAJA TERALIS M.161 - - - 0.00 0.00 0.00 0.00 0.00 30. KAWAT BRONJONG M.162 0.00 220,783.02 12.00 3,500.00 35.00 0.69 - - - 7,857.14 4 4.50 1.00 6.19 92.64 - 0.00 9.26 101.91 0.00 101.91 31. BAUT BAJA M.163 0.00 220,783.02 - - - 0.00 0.00 0.00 0.00 0.00 32. BESI GALVANIS M.164 0.00 220,783.02 12.00 139.33 35.00 0.69 - - - 7,857.14 4 0.75 1.00 2.44 1,481.32 - 0.00 148.13 1,629.45 0.00 1,629.45 33. BAJA KONSTRUKSI M.165 0.00 220,783.02 12.00 3,500.00 35.00 0.69 - - 0.20 7,857.14 4 2.00 - 2.89 73.83 - 0.00 7.38 81.21 0.00 81.21 34. PAKU JEMBATAN M.166 0.00 220,783.02 - - - 7,857.14 - - - 0.00 0.00 0.00 0.00 0.00

35. BAJA TULANGAN/BESI BETON M.167 0.00 220,783.02 12.00 3,500.00 35.00 0.69 - - 0.20 7,857.14 4 2.00 - 2.89 73.83 - 0.00 7.38 81.21 0.00 81.21

36. ALAT 2 BANTU M.170 150,000.00 - - - 150,000.00

37. KAYU UNTUK PERANCAH M.180 0.00 220,783.02 12.00 4.00 40.00 0.60 - - 0.25 7,857.14 4 0.50 - 1.35 50,844.96 - 0.00 5,084.50 55,929.46 0.00 55,929.46

38. KAYU UTK KONS. JEMBATAN M.181 0.00 220,783.02 12.00 4.00 40.00 0.60 - - 0.25 7,857.14 4 0.50 - 1.35 50,844.96 - 0.00 5,084.50 55,929.46 0.00 55,929.46

39. MINYAK DIESEL / SOLAR M.183 10,000.00 220,783.02 12.00 3,000.00 30.00 0.80 - - - 7,857.14 2 0.60 0.40 1.80 64.11 0.25 25.00 1,008.91 11,098.02 0.00 11,098.02

40. BENSIN PREMIUM M.184 8,500.00 220,783.02 12.00 3,000.00 30.00 0.80 - - - 7,857.14 2 0.60 0.50 1.90 64.64 0.50 42.50 860.71 9,467.85 0.00 9,467.85

(7)

1,444,278.60

Aspal (Pelabuhan) per Drum Rp. 1,197,000.00 7,980.00 BESI GALVANIS 25.12

besi beton dia. 12 mm Rp. 7,352.581 3 INCH

#REF! 1.25 1,466.40

DAFTAR PERHITUNGAN UPAH BURUH DAN PERHITUNGAN PENGADAAN BAHAN/MATERIAL

N KODE HARGA DI HARGA JARAK TEMPUH KAPASITAS KECEPATAN WAKTU BIAYA WAKTU WAKTU HARGA JUMLAH WAKTU MUAT WAKTU JML. WAKTU JML. BIAYA PROSEN - NILAI PROFIT TOT BIAYA PPN TOT BIAYA

O ~ LOKASI ATAU PER JAM DARI LOKASI ANGKUT TRUK RATA-RATA TEMPUH LOADER/ MUAT BONGKAR TENAGA TENAGA DENGAN BONGKAR TEMPUH + BONGKAR TASE PE 0.00 SETELAH + 0.00 SMP LOKASI

M NAMA URAIAN MA DI QUARY TRUK ANGKUT S/D LOKASI (DLM. LT) TRUK TRUK PP. DOZER DENGAN DGN KEEP KERJA KERJA TENAGA DGN TENAGA BONGKAR MUAT NYU PROFIT PROYEK

O TE RY (Rp./LT) MATERIAL PROYEK (DLM. M3) PER LOADER PER MANUSIA MANUSIA MUAT (Rp./LT) PENYU - SUTAN (Rp./LT) (Rp./LT) (Rp./LT) (Rp./LT)

R RI (Rp./KG) ~CRANE (DLM. KG) (Rp./KG) SUTAN (Rp./LT) (Rp./M3) (Rp./M3) (Rp./M3) (Rp./M3)

AL (Rp./M') ( Rp.) ( KM ) (DLM. TON) KM/JAM (JAM) (Rp./JAM) (JAM) ( JAM ) ( JAM ) ORANG ( JAM ) ( JAM ) ( JAM ) (Rp./M3) ( % ) (Rp./KG) (Rp./KG) (Rp./KG) (Rp./KG) (Rp./KG)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

19. URUGAN PILIHAN M.050 15,000.00 220,783.02 1.00 2.60 40.00 0.05 - - 0.10 7,857.14 4 0.15 - 0.30 14,550.67 - 0.00 2,955.07 32,505.74 0.00 32,505.74

43. PIPA BETON DIA. 40 CM / TIANG PANCANGM. 250,000.00 456,500.05 5.00 8.00 20.00 0.50 - - 0.50 7,857.14 8 1.00 - 2.00 64,919.65 - 0.00 31,491.96 346,411.61 0.00 346,411.61

44. KAWAT LAS M. 20,000.00 - - - 22,000.00

(8)

62,857.12 60,571.44 75,428.56 61,714.32 61,714.32 50,285.68 42,285.68 620,148.50 40.00 685,441.36 40.00 613,234.22 40.00 616,691.36 40.00 -(1,047,500.00) 40.00 234,892.56 40.00 304,892.56 40.00 298,642.56 40.00 244,392.56 40.00 357,500.00 -375,000.00 40.00 412,500.00 35.00 321,750.00 40.00 337,500.00 40.00 680,803.12 35.00 -425,902.51 - 5,333.33 1,444,278.60 40.00 40.00 40.00 40.00 40.00 REVISI 3 FEB 2003 - 44,000.00 20.00 20.00 20.00 10.00 40.00 -10.00 10.00 -10.00 10.00 30.00 20.00 30.00 -10.00 10.00

(9)

-30.00 30.00 -30.00 -10.00 10.00 10.00 10.00 10.00 20.00

(10)

DAFTAR PERHITUNGAN ANALISA BIAYA PERALATAN

HARGA HARGA ALAT UMUR UMUR JUMLAH FAK BIAYA OPERASI JUMLAH JUMLAH HARGA KODE ALAT TH. BERJALAN KERJA KERJA JAM TOR SOLAR MAINTNC BIAYA SBL. PROFIT BIAYA PPN SEWA NO. NAMA PERALATAN HP ALAT TAHUN '91 HARGA ALAT ALAT PER - DEPRESIASI ASURANSI BIAYA MINYAK BENSIN PELUMAS & SPARE BIAYA PROFIT DLL SEBELUM 10 % ALAT 10^3 10^3 (THN) (JAM) TAHUN CRF PEMILIKAN DIESEL PART DLL PPN NIHIL PER JAM (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) HARGA (KURS DOLAR)x TABEL 0,158x 0,158x 0,006x (14) ATAU

(1) (2) (3) (4) THN. 91/92 (5)/Rp. 2000 x (7) (8) (8)/(7) 12,5% 0,9x(6)x(10)/(9) 0,033x(6)/(9) (11)+(12) (3)xM.183 (3)xM.184 (3)xM.185 0,6x(11) (15)+(16) (13)+(18) (19)x10 % (19)+(20) (21)x10 % (21)+(22)

1.10 +(17)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

1. Buldozer 110 E.001 225,533.00 1,178,409.93 10.00 9,600.00 960.00 0.18062 199,541.63 40,507.84 240,049.47 192,883.67 0.00 14,589.28 119,724.98 327,197.93 567,247.39 56,724.74 623,972.13 0.00 623,972.13

2. Buldozer 65 E.003 120,698.00 630,647.05 8.00 9,600.00 1,200.00 0.20483 96,881.58 17,342.79 114,224.37 113,976.72 0.00 8,620.94 58,128.95 180,726.60 294,950.97 29,495.10 324,446.07 0.00 324,446.07

3. Motor grader 100 E.010 166,782.00 871,435.95 9.00 9,300.00 1,033.33 0.19126 145,164.92 27,829.73 172,994.65 175,348.79 0.00 13,262.98 87,098.95 275,710.73 448,705.38 44,870.54 493,575.92 0.00 493,575.92

4. Excavator Hidrolik 1.0 m3 90 E.020 219,450.00 1,146,626.25 9.00 10,080.00 1,120.00 0.19126 176,226.22 33,784.52 210,010.74 157,813.91 0.00 11,936.68 105,735.73 275,486.33 485,497.07 48,549.71 534,046.77 0.00 534,046.77 Mini Excavator Hidrolik 1.0 m3 47.6 E.021 105,000.00 548,625.00 3.00 3,990.00 1,330.00 0.41993 155,899.01 13,612.50 169,511.51 83,466.03 0.00 6,313.18 93,539.41 183,318.61 352,830.12 35,283.01 388,113.14 0.00 388,113.14

5. Stone Crusher/Scr 30 ton/h 185 E.031 306,446.00 1,601,180.35 12.00 12,000.00 1,000.00 0.16519 238,049.08 52,838.95 290,888.04 324,395.27 0.00 24,536.51 142,829.45 491,761.23 782,649.27 78,264.93 860,914.19 0.00 860,914.19

6. Stone Crusher/Scr 20 ton/h 95 E.032 236,555.00 1,235,999.88 12.00 15,000.00 1,250.00 0.16519 147,005.87 32,630.40 179,636.27 166,581.35 0.00 12,599.83 88,203.52 267,384.71 447,020.97 44,702.10 491,723.07 0.00 491,723.07

7. Stone Crusher/Scr 10 ton/h 15 E.033 129,030.00 674,181.75 12.00 12,000.00 1,000.00 0.16519 100,231.27 22,248.00 122,479.27 26,302.32 0.00 1,989.45 60,138.76 88,430.53 210,909.80 21,090.98 232,000.78 0.00 232,000.78

8. Butas Crusher 15 E.039 25,000.00 130,625.00 8.00 12,000.00 1,500.00 0.20483 16,053.55 2,873.75 18,927.30 26,302.32 0.00 1,989.45 9,632.13 37,923.90 56,851.20 5,685.12 62,536.32 0.00 62,536.32

9. Screening plant 80 E.040 107,525.00 561,818.13 8.00 12,000.00 1,500.00 0.20483 69,046.32 12,360.00 81,406.32 140,279.04 0.00 10,610.38 41,427.79 192,317.21 273,723.54 27,372.35 301,095.89 0.00 301,095.89

10. Loader tracked 135 E.051 160,423.00 838,210.18 8.00 11,100.00 1,387.50 0.20483 111,366.87 19,935.81 131,302.68 236,720.87 0.00 17,905.02 66,820.12 321,446.02 452,748.69 45,274.87 498,023.56 0.00 498,023.56

11. Loader wheeled 115 E.052 158,698.00 829,197.05 11.00 11,600.00 1,054.55 0.17211 121,798.25 25,948.15 147,746.40 201,651.11 0.00 15,252.43 73,078.95 289,982.49 437,728.89 43,772.89 481,501.78 0.00 481,501.78

12. Tractor wheeled 60 E.053 42,937.00 224,345.83 10.00 15,000.00 1,500.00 0.18062 24,312.81 4,935.61 29,248.41 105,209.28 0.00 7,957.79 14,587.68 127,754.75 157,003.16 15,700.32 172,703.48 0.00 172,703.48

13. Three Wheel Roller 6-8 ton 37 E.080 100,000.00 522,500.00 7.00 6,860.00 980.00 0.22260 106,813.93 17,594.39 124,408.32 64,879.05 0.00 4,907.30 64,088.36 133,874.71 258,283.03 25,828.30 284,111.33 0.00 284,111.33

14. Tandem Roller 6-12 ton 95 E.081 240,000.00 1,254,000.00 7.00 7,840.00 1,120.00 0.22260 224,309.25 36,948.21 261,257.46 166,581.35 0.00 12,599.83 134,585.55 313,766.73 575,024.20 57,502.42 632,526.62 0.00 632,526.62

15. Vibrator Roller self p. 6-7 ton 51 E.082 107,892.00 563,735.70 7.00 7,350.00 1,050.00 0.22260 107,560.77 17,717.41 125,278.18 89,427.88 0.00 6,764.12 64,536.46 160,728.47 286,006.65 28,600.66 314,607.31 0.00 314,607.31

16. Roller Towed Vibro 2-3 ton 6 E.083 53,946.00 281,867.85 8.00 12,000.00 1,500.00 0.20483 34,641.00 6,201.09 40,842.09 10,520.93 0.00 795.78 20,784.60 32,101.30 72,943.39 7,294.34 80,237.73 0.00 80,237.73

17. Pneumatic Tire Roller 8-15 ton 95 E.084 215,259.00 1,124,728.28 10.00 9,000.00 900.00 0.18062 203,148.42 41,240.04 244,388.46 166,581.35 0.00 12,599.83 121,889.05 301,070.24 545,458.69 54,545.87 600,004.56 0.00 600,004.56

18. Vibrator roller ped. 1 ton 12 E.087 22,503.00 117,578.18 6.00 7,200.00 1,200.00 0.24668 21,753.14 3,233.40 24,986.54 21,041.86 0.00 1,591.56 13,051.88 35,685.30 60,671.83 6,067.18 66,739.02 0.00 66,739.02

19. Vibro plate tamper 4 E.088 3,517.00 18,376.33 6.00 4,500.00 750.00 0.24668 5,439.69 808.56 6,248.24 0.00 6,324.52 530.52 3,263.81 10,118.86 16,367.10 1,636.71 18,003.81 0.00 18,003.81

20. Concrete vibrator 4 E.089 2,195.00 11,468.88 10.00 2,000.00 200.00 0.18062 9,321.79 1,892.36 11,214.15 0.00 6,324.52 530.52 5,593.07 12,448.12 23,662.27 2,366.23 26,028.49 0.00 26,028.49

21. Stab/pulver mixer attachmant E.100 9,000.00 47,025.00 5.00 3,000.00 600.00 0.28085 19,810.46 2,586.38 22,396.83 0.00 0.00 0.00 11,886.27 11,886.27 34,283.11 3,428.31 37,711.42 0.00 37,711.42

22. Chip spreader 3 ton 8 E.130 8,587.00 44,867.08 6.00 3,600.00 600.00 0.24668 16,601.72 2,467.69 19,069.40 14,027.90 0.00 1,061.04 9,961.03 25,049.97 44,119.38 4,411.94 48,531.31 0.00 48,531.31

23. Asphalt sprayer 4000l 68 E.152 120,363.00 628,896.68 11.00 9,000.00 818.18 0.17211 119,063.35 25,365.50 144,428.85 119,237.18 0.00 9,018.83 71,438.01 199,694.01 344,122.86 34,412.29 378,535.15 0.00 378,535.15

24. Asphalt sprayer 1000l 25 E.153 44,887.00 234,534.58 11.00 9,000.00 818.18 0.17211 44,402.32 9,459.56 53,861.88 43,837.20 0.00 3,315.74 26,641.39 73,794.34 127,656.22 12,765.62 140,421.84 0.00 140,421.84

25. Asphalt sprayer towed 400 l 5 E.154 10,305.00 53,843.63 11.00 4,500.00 409.09 0.17211 20,387.46 4,343.39 24,730.84 0.00 7,905.66 663.15 12,232.47 20,801.28 45,532.12 4,553.21 50,085.34 0.00 50,085.34

26. Asphalt mixing plant 30 ton/h 200 E.155 547,708.00 2,861,774.30 11.00 4,300.00 390.91 0.17211 1,133,987.38 241,586.99 ########## 350,697.59 0.00 26,525.96 680,392.43 ########## 2,433,190.35 243,319.04 ########## 0.00 2,676,509.39

27. Asphalt mixing plant 10 ton/h 75 E.156 284,808.00 1,488,121.80 10.00 4,000.00 400.00 0.20483 685,826.97 122,770.05 808,597.02 131,511.60 0.00 9,947.23 411,496.18 552,955.01 1,361,552.04 136,155.20 ########## 0.00 1,497,707.24

28. Asphalt finisher 1,82 m 30 E.157 219,450.00 1,146,626.25 10.00 11,500.00 1,150.00 0.20483 183,806.18 32,903.19 216,709.37 52,604.64 0.00 3,978.89 110,283.71 166,867.24 383,576.61 38,357.66 421,934.27 0.00 421,934.27

29. Fuel tank truck 115 E.172 31,000.00 161,975.00 10.00 5,600.00 560.00 0.18062 47,018.45 9,544.96 56,563.41 201,651.11 0.00 15,252.43 28,211.07 245,114.61 301,678.01 30,167.80 331,845.82 0.00 331,845.82

30. Water tank truck 115 E.182 75,000.00 391,875.00 7.00 8,000.00 1,142.86 0.22260 68,694.71 11,315.39 80,010.10 201,651.11 0.00 15,252.43 41,216.82 258,120.36 338,130.46 33,813.05 371,943.51 0.00 371,943.51

31. Trailer towed 1 ton 18 E.191 7,506.00 39,218.85 12.00 9,000.00 750.00 0.16519 7,774.27 1,725.63 9,499.90 31,562.78 0.00 2,387.34 4,664.56 38,614.68 48,114.59 4,811.46 52,926.05 0.00 52,926.05

32. Low loader + tractor 175 E.192 108,822.00 568,594.95 10.00 7,500.00 750.00 0.18062 123,239.54 25,018.18 148,257.72 306,860.39 0.00 23,210.21 73,943.73 404,014.33 552,272.05 55,227.21 607,499.26 0.00 607,499.26

33. Dump Truck 3,5 ton 115 E.211 38,000.00 198,550.00 5.00 9,000.00 1,800.00 0.28085 27,881.38 3,640.08 31,521.47 181,700.00 0.00 13,800.00 16,728.83 212,228.83 243,750.30 24,375.03 268,125.33 0.00 268,125.33

34. Dump Truck 5 ton 145 E.212 55,000.00 287,375.00 5.00 8,000.00 1,600.00 0.28085 45,398.96 5,927.11 51,326.07 229,100.00 0.00 17,400.00 27,239.38 273,739.38 325,065.45 32,506.55 357,572.00 0.00 357,572.00

35. Dump Truck 8 ton 177 E.213 75,000.00 391,875.00 6.00 8,000.00 1,333.33 0.24668 65,250.71 9,698.91 74,949.62 279,660.00 0.00 21,240.00 39,150.43 340,050.43 415,000.05 41,500.00 456,500.05 0.00 456,500.05

36. Flat bed truck 3,5 ton 100 E.221 39,000.00 203,775.00 5.00 9,000.00 1,800.00 0.28085 28,615.10 3,735.88 32,350.98 158,000.00 0.00 13,262.98 17,169.06 188,432.04 220,783.02 22,078.30 242,861.32 0.00 242,861.32

37. Pickup truck 61 E.222 38,157.00 199,370.33 11.00 9,000.00 818.18 0.17211 37,744.99 8,041.27 45,786.26 106,962.76 0.00 8,090.42 22,646.99 137,700.18 183,486.43 18,348.64 201,835.08 0.00 201,835.08

38. Jeep 4 wheel drive 61 E.223 38,333.00 200,289.93 11.00 9,000.00 818.18 0.17211 37,919.09 8,078.36 45,997.45 0.00 86,589.50 8,090.42 22,751.45 117,431.37 163,428.82 16,342.88 179,771.70 0.00 179,771.70

39. Flat bed truck 5 ton 145 E.224 50,000.00 261,250.00 10.00 7,800.00 780.00 0.18062 54,446.51 11,052.88 65,499.39 254,255.75 0.00 19,231.32 32,667.91 306,154.98 371,654.37 37,165.44 408,819.81 0.00 408,819.81

40. Flat bed truck with crane 148 E.225 69,774.00 364,569.15 10.00 9,000.00 900.00 0.18062 65,848.48 13,367.54 79,216.02 259,516.21 0.00 19,629.21 39,509.09 318,654.51 397,870.53 39,787.05 437,657.58 0.00 437,657.58

41. Motor cycle 125 cc 14 E.226 2,398.00 12,529.55 12.00 6,000.00 500.00 0.16519 3,725.56 826.95 4,552.51 0.00 22,135.84 1,856.82 2,235.34 26,227.99 30,780.50 3,078.05 33,858.55 0.00 33,858.55

42. Mobile workshop 5 ton 145 E.231 108,822.00 568,594.95 8.00 9,600.00 1,200.00 0.20483 87,348.98 15,636.36 102,985.34 254,255.75 0.00 19,231.32 52,409.39 325,896.46 428,881.80 42,888.18 471,769.98 0.00 471,769.98

43. Lube truck 5 ton 145 E.232 56,691.00 296,210.48 8.00 9,600.00 1,200.00 0.20483 45,504.59 8,145.79 53,650.38 254,255.75 0.00 19,231.32 27,302.76 300,789.83 354,440.21 35,444.02 389,884.23 0.00 389,884.23

44. Concrete mixer 0,125 m3 6 E.251 2,796.00 14,609.10 10.00 6,000.00 600.00 0.18062 3,958.04 803.50 4,761.54 0.00 9,486.79 795.78 2,374.83 12,657.39 17,418.94 1,741.89 19,160.83 0.00 19,160.83

45. Concrete mixer 0,25 m3 10 E.252 12,903.00 67,418.18 10.00 7,500.00 750.00 0.18062 14,612.48 2,966.40 17,578.88 17,534.88 0.00 1,326.30 8,767.49 27,628.67 45,207.55 4,520.76 49,728.31 0.00 49,728.31

46. Concrete mixer 0,5 m3 20 E.253 25,806.00 134,836.35 10.00 7,500.00 750.00 0.18062 29,224.97 5,932.80 35,157.77 35,069.76 0.00 2,652.60 17,534.98 55,257.34 90,415.11 9,041.51 99,456.62 0.00 99,456.62

47. Rock breaker Excavator 90 E.281 219,400.00 1,146,365.00 11.00 7,500.00 681.82 0.17211 260,437.16 55,484.07 315,921.23 157,813.91 0.00 11,936.68 156,262.30 326,012.89 641,934.12 64,193.41 706,127.53 0.00 706,127.53

48. Air compressor 210 m3/h 35 E.301 21,908.00 114,469.30 10.00 6,000.00 600.00 0.18062 31,013.17 6,295.81 37,308.98 61,372.08 0.00 4,642.04 18,607.90 84,622.02 121,931.00 12,193.10 134,124.10 0.00 134,124.10

49. Generator 3-5 kVA 10 E.311 3,884.00 20,293.90 8.00 4,800.00 600.00 0.20483 6,235.20 1,116.16 7,351.36 17,534.88 0.00 1,326.30 3,741.12 22,602.30 29,953.66 2,995.37 32,949.03 0.00 32,949.03

50. Generator las 10 E.311.a 3,884.00 20,293.90 12.00 4,800.00 400.00 0.16519 7,542.79 1,674.25 9,217.03 17,534.88 0.00 1,326.30 4,525.67 23,386.85 32,603.88 3,260.39 35,864.27 0.00 35,864.27

51. Water Pump (5cm) 30 m3/hr 8 E.341 1,720.00 8,987.00 4.00 3,000.00 750.00 0.33271 3,588.08 395.43 3,983.51 0.00 12,649.05 1,061.04 2,152.85 15,862.93 19,846.44 1,984.64 21,831.08 0.00 21,831.08

52. Water Pump (10cm) 40 m3/hr 10 E.342 2,151.00 11,238.98 4.00 3,000.00 750.00 0.33271 4,487.18 494.51 4,981.70 0.00 15,811.31 1,326.30 2,692.31 19,829.92 24,811.62 2,481.16 27,292.78 0.00 27,292.78

53. Jack hammer equipment etc 10 E.351 2,633.00 13,757.43 9.00 3,750.00 416.67 0.19126 5,683.49 1,089.59 6,773.08 0.00 15,811.31 1,326.30 3,410.09 20,547.70 27,320.78 2,732.08 30,052.86 0.00 30,052.86

54. Tractor equipment etc 20 E.401 21,835.00 114,087.88 5.00 3,000.00 600.00 0.28085 48,062.37 6,274.83 54,337.20 35,069.76 0.00 2,652.60 28,837.42 66,559.78 120,896.98 12,089.70 132,986.68 0.00 132,986.68

55. Diesel hammer / Pile driver 120 E.402 385,000.00 2,011,625.00 6.00 10,800.00 1,800.00 0.24668 248,113.83 36,879.79 284,993.62 210,418.55 0.00 15,915.58 148,868.30 375,202.42 660,196.04 66,019.60 726,215.65 0.00 726,215.65

56. Crane, 10 - 15 ton 100 E.403 275,000.00 1,436,875.00 12.00 10,800.00 900.00 0.16519 237,357.38 52,685.42 290,042.80 175,348.79 0.00 13,262.98 142,414.43 331,026.20 621,069.00 62,106.90 683,175.90 0.00 683,175.90 BIAYA PEMILIKAN

(11)

MADYA Konsultan

ANALISA HARGA SATUAN K O D E

JAYAPURA PENGADAAN KERIKIL GALIAN (TDK DISARING) K.010

(MENGGUNAKAN ALAT)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 . Buldozer menggusur lapis penutup dan me- 1. Menggunakan alat berat 360 m3/hari nyiapkan kerikil galian untuk wheel loader. 2. Kapasitas wheel loader 60 m3/jam

2. Wheel Loader memuati dump truk 3. Wheel Loader memuati 18 truk/jam (6 jam kerja/hari) 3. Dumptruk mengangkut kerikil galian ke lo - 4. 50 cm lapisan penutup dibuang untuk mendapatkan kerikil galian

kasi pekerjaan atau penimbunan. 5. Jumlah lapis penutup 1 m3 per 8 m3 kerikil galian

4. Buldozer menghampar lapis penutup dan 6. Sumber material tersedia bebas /dengan ganti rugi royalti yang berlaku menyiapkan area untuk tanam ulang 7. Pengadaan /penimbunan material 1 trip/jam/truk, 10 km dari Sumber

8. Volume yang diukur berdasarkan 5ton lepas /truk (Bj=1,6) 9. Umur alat bantu rata-rata 1 bulan /orang /set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 3.00 1.00 L.081 3.00 110,000 330,000 K Pembantu operator 3.00 1.00 L.083 3.00 82,500 247,500 E Supir terampil 18 1.00 L.091 18 93,500 1,683,000 R Pembantu supir 18 1.00 L.099 18 82,500 1,485,000

J Buruh tak terlatih 8.00 1.00 L.101 8.00 60,500 484,000

A

PEKERJA 4,323,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Material timbunan-Royalty M3 MR.011 360.00 100,000.00 36,000,000.0

A Alat bantu (set @ 3 alat) set M.170 0.32 150,000.00 48,000.0

T E R I A L MATERIAL 36,048,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Buldozer 2.00 1.00 E.001 12.00 623,972.13 7,487,665.6

E Wheel Loader 1.00 1.00 E.052 6.00 481,501.78 2,889,010.7

R Dump truk 18.00 1.00 E.212 108.00 357,572.00 38,617,775.6

A L A T A N PERALATAN 48,994,451.88 TOTAL (Rp.) 89,365,451.88 VOLUME = 360.0 SATUAN : M3 HARGA SATUAN Rp. 248,237.37 per m3

(12)

ANALISA HARGA SATUAN K O D E

JAYAPURA PENGADAAN KERIKIL GALIAN (TDK DISARING) K.011

(MENGGUNAKAN BURUH)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Membuang lapisan penutup dengan tenaga 1 Menggunakan tenaga manusia (60 m3/hari) dalam dua kelompok manusia. 2 50 cm lapisan penutup dibuang untuk mendapatkan kerikil 2 Menggali kerikil galian dan memuat ke truk 3 Jumlah lapis penutup 1 m3 per 8 m3 kerikil galian

dengan tenaga manusia. 4 Sumber material tersedia bebas/dengan ganti rugi yang berlaku terhadap pemilik 3 Truk mengangkut kerikil kelokasi pekerjaan material

penimbunan 5 Waktu muat 12 min/10 orang/truk; waktu bongkar 5 min/5 orang/truk 4 Membongkar muatan truk dengan tenaga 6 Jarak angkut 10 Km, 72 menit/trip, 5 trip/hari/truk

manusia. 7 Volume yang diukur berdasarkan 3,5 ton lepas/truk (BJ=1,6) 8 Umur alat bantu rata - rata 1 bulan/set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.)

P M a n d o r 2.00 1.00 L.061 2.00 93,500 187,000

E Supir terampil 5.00 1.00 L.091 5.00 93,500 467,500

K Pembantu supir 5.00 1.00 L.099 5.00 82,500 412,500

E Buruh tak terampil 68.00 1.00 L.101 68.00 60,500 4,114,000

R J A

PEKERJA 5,181,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Kerikil-Royalty M3 MR.011 60.00 100,000.00 6,000,000.00

A Alat bantu (set @ 3 alat) set M.170 2.72 150,000.00 408,000.00

T E R I A L MATERIAL 6,408,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Truk bak terbuka 5.00 1.00 E.221 30.0 242,861.32 7,285,839.7

E R A L A T A N PERALATAN 7,285,839.70 TOTAL (Rp.) 18,874,839.70 VOLUME = 60.0 SATUAN : M3 HARGA SATUAN Rp. 314,580.66 per m3

(13)

ANALISA HARGA SATUAN K O D E

JAYAPURA PENGADAAN KERIKIL SUNGAI (TDK DISARING) / KARANG K.012

(MENGGUNAKAN ALAT)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Buldozer membuat timbunan kerikil di tepi - 1 Menggunakan alat berat (360 m3/hari)

sungai 2 Kapasitas wheel loader 60 m3/jam

2 Wheel loader memuati dumptruk dari tim - 3 Wheel Loader memuati 18 truk/jam (6 jam kerja/hari)

bunan. 4 Material diambil dari tempat penimbunan dengan ganti rugi yang berlaku 3 Dumptruk mengangkut kerikil sungai tidak 5 Pengadaan /penimbunan material 1 trip/jam/truk, 10 Km dari Waena

disaring ke lokasi pekerjaan/penimbunan. 6 Volume yang diukur berdasarkan 5 ton lepas/truk (BJ= 1,6) 7 Umur alat bantu rata - rata 1 bulan/orang/set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 3.00 1.00 L.081 3.00 110,000 330,000 K Pembantu operator 3.00 1.00 L.083 3.00 82,500 247,500 E Supir terampil 18.00 1.00 L.091 18.00 93,500 1,683,000 R Pembantu supir 18.00 1.00 L.099 18.00 82,500 1,485,000

J Buruh tak terlatih 8.00 1.00 L.101 8.00 60,500 484,000

A

PEKERJA 4,323,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Material timbunan-Royalty M3 MR.012 360.00 100,000.00 36,000,000.0

A Alat bantu (set @ 3 alat) set M.170 0.32 150,000.00 48,000.0

T E R I A L MATERIAL 36,048,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Buldozer 2.00 1 E.001 9.0 623,972.13 5,615,749.19

E Wheel Loader 1.00 1 E.052 6.0 481,501.78 2,889,010.69

R Dump truk 18 1 E.212 108.0 357,572.00 38,617,775.61

A L A T A N PERLATAN 47,122,535.48 TOTAL (Rp.) 87,493,535.48 VOLUME = 360.0 SATUAN : M3 HARGA SATUAN Rp. 243,037.60 per m3

(14)

ANALISA HARGA SATUAN K O D E

JAYAPURA PENGADAAN KERIKIL SUNGAI (TDK DISARING) K.013

(MENGGUNAKAN BURUH)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Menggali kerikil sungai dan memuat ke truk 1 Menggunakan tenaga manusia (60 m3/hari) dalam dua kelompok dengan tenaga manusia disungai. 2 Sumber material tersedia bebas/dengan ganti rugi royalti yang berlaku 2 Truk mengangkut kerikil sungai kelokasi - 3 Muatan 5 truk perjam (3 m3/orang/hari)

pekerjaan / penimbunan. 4 Waktu muat 12 menit/ 10 orang/truk ; waktu bongkar 5 menit /5 orang/truk 3 Membongkar muatan truk dengan tenaga 5 Dua tim @ 5 orang membongkar truk

manusia 6 Jarak angkut 10 Km, 72 menit per trip, 5 trip/hari/truk 7 Volume yang diukur berdasarkan 3,5 ton lepas/truk (BJ=1,6) 8 Umur alat bantu rata - rata 1 bulan/orang/set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.)

P M a n d o r 2.00 1.00 L.061 2.00 93,500 187,000

E Supir terampil 5 1 L.091 5.00 93,500 467,500

K Pembantu supir 5 1 L.099 5.00 82,500 412,500

E Buruh tak terampil 60.00 1.00 L.101 60.00 60,500 3,630,000

R J A

PEKERJA 4,697,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Sirtu sungai - Royalty m3 MR.042 60.00 100,000.00 6,000,000.00

A Alat bantu (set @ 3 alat) set M.170 2.40 150,000.00 360,000.00

T E R I A L MATERIAL 6,360,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Truk Bak Terbuka 5 1 E.221 30.0 242,861.32 7,285,839.70

E R A L A T A N PERALATAN 7,285,839.70 TOTAL (Rp.) 18,342,839.70 VOLUME = 60.0 SATUAN : M3 HARGA SATUAN Rp. 305,714.00 per m3

(15)

ANALISA HARGA SATUAN K O D E

JAYAPURA PENGADAAN KERIKIL GALIAN TERSARING K.014

(MENGGUNAKAN ALAT)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Buldoser menggusur lapis penutup dan 1 Menggunakan alat berat (60 m3/hari) dengan 6 jam kerja/hari menimbun stok untuk loader. 2 50 cm lapisan penutup dibuang untuk mendapatkan kerikil 2 Dumptruk memuat dan mengangkut kerikil 3 Jumlah lapis penutup 1 m3 per 8m3 kerikil galian

galian ketempat saringan 4 Material diambil dari tempat penimbunan dengan ganti rugi yang berlaku 3 Kerikil disaring sesuai ukuran 5 Kapasitas penyaringan 20 ton/jam, dengan surplus 25 %

4 Loader memuati dumptruk 6 Pengadaan/penimbunan material 1 trip/jam/truk, 10 km dari sumber 5 Dumptruk mengangkut kerikil galian yang 7 Tiga truk, mengangkut kelokasi dan satu truk mensuplai tempat saringan

disaring ke lokasi pekerjaan/penimbunan 8 Volume yang diukur berdasarkan 5 ton lepas/truk (BJ=1,6) 9 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 3.00 1.00 L.081 3.00 110,000 330,000 K Pembantu operator 3.00 1.00 L.083 3.00 82,500 247,500 E Supir terampil 4 1 L.091 4 93,500 374,000 R Pembantu supir 4 1 L.099 4 82,500 330,000

J Buruh tak terlatih 4.00 1.00 L.101 4.00 60,500 242,000

A Buruh terampil 2.00 1.00 L.106 2.00 71,500 143,000

PEKERJA 1,760,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Kerikil galian - Royalty m3 MR.011 80.00 100,000.00 8,000,000.00

A Alat bantu (set @ 3 alat) set M.170 0.20 150,000.00 30,000.00

T E R I A L MATERIAL 8,030,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Bulldozer 1.00 1 E.001 3.0 623,972.13 1,871,916.40

E Mesin penyaring 1.00 1 E.040 6.0 301,095.89 1,806,575.33

R Wheel loader 1.00 1 E.052 5.0 481,501.78 2,407,508.91

A Dump truk 4 1 E.212 24.0 357,572.00 8,581,727.91

L A T A N PERALATAN 14,667,728.55 TOTAL (Rp.) 24,457,728.55 VOLUME = 60.0 SATUAN : M3 HARGA SATUAN Rp. 407,628.81 per m3

(16)

ANALISA HARGA SATUAN K O D E

PEGADAAN KERIKIL SUNGAI TERSARING K.016

(MENGGUNAKAN ALAT)

PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Buldozer menimbun stok di sungai untuk loader 1 Menggunakan alat berat (60 m3/hari)

2 Dumptruk memuat dan mengangkut kerikil 2 Loader memuati bergantian diantara truk pengangkut dan truk pengisi tempat sungai ketempat saringan saringan

3 Kerikil disaring sesuai ukuran 3 Material diambil dari tempat penimbunan dengan ganti rugi yang berlaku 4 Loader memuati dump truk 4 Volume yang diukur berdasarkan 5 ton lepas /truk (BJ=1,6) 5 Dump truk mengangkut kerikil sungai yang 5 Suplai ke lokasi jarak 10 km dari sumber; 1 trip/jam/truk (dengan 3 truk)

disaring ke lokasi pekerjaan/penimbunan 6 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

7 Kapasitas saringan rata-rata 20 ton/jam, dengan ditambah bagian halus 20 % dengan dibuang ovesize 25 %

TOTAL VOL UPAH B I A Y A SUB TOTAL (org.hari) (Rp./org/hari) (Rp.) (Rp.)

P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500

E Operator terampil 3.00 1.00 L.081 3.00 110,000 330,000

K Operator semi terampil 1.00 1.00 L.082 1.00 0 0

E Supir terampil 4.00 1.00 L.091 4.00 93,500 374,000

R Buruh tak terlatih 4.00 1.00 L.101 4.00 60,500 242,000

J Buruh semi terampil 4.00 1.00 L.103 4.00 0 0

A

PEKERJA 1,039,500.00 T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Kerikil sungai - Royalty m3 MR.012 67.50 100,000.00 6,750,000.00 A Ganti rugi Kerikil sungai - Royalty m3 MR.042 12.50 100,000.00 1,250,000.00

T Alat bantu (set @ 3 alat) set M.170 0.20 100,000.00 20,000.00

E R I A L MATERIAL 8,020,000.00

HARI JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Buldozer 1.00 1.00 E.001 3.00 623,972.13 1,871,916.40

E Mesin penyaring 1.00 1.00 E.040 3.00 301,095.89 903,287.67

R Wheel Loader 1.00 1.00 E.052 5.00 481,501.78 2,407,508.91

A Dump truk 4.00 1.00 E.212 24.00 357,572.00 8,581,727.91

L A T A N PERALATAN 13,764,440.88 TOTAL (Rp.) 22,823,940.88

VOLUME = 60.0 SATUAN : M3 HARGA SATUAN Rp. 380,399.01 per m3

P E K E R J A VOL HARI

P E R A L A T A N JUMLAH K O D E

K O D E

(17)
(18)
(19)
(20)
(21)

ANALISA HARGA SATUAN K O D E

PRODUKSI BATU PECAH TERSARING K.017

MEMPERGUNAKAN BATU SUNGAI (MENGGUNAKAN ALAT) PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Buldozer membuat timbunan di sungai untuk 1 Menggunakan alat berat (60 m3/hari), material diolah tiga kali loader 2 Batu diambil dari sungai & diangkut kesaringan pertama (30 t/j)

2 Loader memuat ke dump truk yang 3 Ex saringan1:oversize 25 %(7,5t/j) kepemecah1 & 75 %(22,5t/j) ke saringan2 membongkar ke saringan 1 4 Ex saringan2:7,5t/j kepemecah1 7,5t/j kepemecah2 & 7,5t/j terbuang 3 Batu oversize ke pemecah 1 5 Ex saringan1:7,5t/j kepemecah2 & 7,5t/j untuk dikirim

4 Hasil pecahan batu dicampur ulang dengan 6 Ex saringan2:15t/j untuk dikirim

hasil saringan untuk pemecah 2 7 Volume yang diukur berdasarkan 5 ton lepas /truk (BJ=1,6)

5 Dump truk angkut batu pecah tersaring 8 Jarak kirim dari sumber bahan kelokasi pekerjaan 10 km, 1 trip/jam/truk

TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.)

P M a n d o r 1.00 1.00 L.061 1.00 93,500.00 93,500.00

E Operator terampil 3.00 1.00 L.081 3.00 110,000.00 330,000.00

K Operator semi terampil 2.00 1.00 L.082 2.00 0.00 0.00

E Supir terampil 4.00 1.00 L.091 4.00 93,500.00 374,000.00

R Buruh tak terampil 4.00 1.00 L.101 4.00 60,500.00 242,000.00

J Buruh semi terampil 4.00 1.00 L.103 4.00 0.00 0.00

A

PEKERJA 1,039,500.00 T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Kerikil sungai - Royalti M3 MR.012 80.00 100,000.00 8,000,000.00

A Alat bantu (set @ 3 alat) set M.170 0.20 150,000.00 30,000.00

T E R I A L MATERIAL 8,030,000.00

HARI JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Buldozer 1.00 1.00 E.001 6.00 623,972.13 3,743,832.79

E Pemecah batu 1.00 1.00 E.031 6.00 860,914.19 5,165,485.15

R Wheel Loader 1.00 1.00 E.052 6.00 481,501.78 2,889,010.69

A Dump truk 4.00 1.00 E.212 24.00 357,572.00 8,581,727.91

L A T A N PERALATAN 20,380,056.55 TOTAL (Rp.) 29,449,556.55 VOLUME = 60.0 SATUAN = M3 HARGA SATUAN Rp. 490,825.94 per m3 P E K E R J A M A T E R I A L P E R A L A T A N JUMLAH K O D E VOL HARI K O D E K O D E SATUAN

(22)

ANALISA HARGA SATUAN K O D E

JAYAPURA PRODUKSI BATU PECAH TERSARING K.018

MEMPERGUNAKAN BATU QUARY (MENGGUNAKAN ALAT) PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Material ditimbun pada jarak maks. 10 km 1 Menggunakan alat berat (60 m3/hari), bahan diolah tiga kali dari lokasi 2 Batu diambil dari quarry & diangkut kesaringan pertama (25t/j) 2 Loader memuat ke dumptruk yang membong 3 Ex saringan1:2t/j) kepemecah1,21t/j kesaringan 2 & 2t/j terbuang

kar kesaringan1 4 Ex saringan2:19,2t/j kepemecah1 & 1,8t/j kepemecah2

3 Batu oversize kepemecah 1 5 Ex saringan1:12,2t/j kepemecah2, 7,2t/j utk dikirim & 1,8t/j terbuang 4 Hasil pecahan batu dicampur ulang dengan 6 Ex saringan2:14t/j untuk dikirim

hasil saringan untuk pemecah 2 7 Volume yang diukur berdasarkan 5 ton lepas /truk (BJ=1,55)

5 Dumptruk angkut batu pecah tersaring 8 Jarak kirim dari sumber bahan ke lokasi pekerjaan 10 km, 1 trip/jam/truk 9 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 4.00 1.00 L.081 4.00 110,000 440,000 K E Supir terampil 4.00 1.00 L.091 4.00 93,500 374,000 R

J Buruh tak terampil 5.00 1.00 L.101 5.00 0 0

A Buruh terampil 4.00 1.00 L.106 4.00 0 0

PEKERJA 907,500.00

M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Batu quarry - Royalti m3 MR.010 70.00 100,000.00 7,000,000.00

A Alat bantu (set @ 3 alat) set M.170 0.20 150,000.00 30,000.00

T E R I A L MATERIAL 7,030,000.00 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Buldozer 1.00 1.00 E.001 6.00 623,972.1 3,743,832.8

E Pemecah batu 1.00 1.00 E.031 4.00 860,914.2 3,443,656.8

R Wheel Loader 1.00 1.00 E.052 6.00 481,501.8 2,889,010.7

A Dump truk 4.00 1.00 E.212 24.00 357,572.0 8,581,727.9

L A T A N PERALATAN 18,658,228.16 TOTAL (Rp.) 26,595,728.16

(23)

ANALISA HARGA SATUAN K O D E

JAYAPURA LAPIS TIPIS ASPAL PASIR (LATASIR) K.020

PRODUKSI DAN SUPLAI (MENGGUNAKAN ALAT) PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Semua material dikirim pemasok 1 LATASIR dibuat di AMP produksi 100 ton/hari

2 Loader menjaga tetap penuh 2 Aspal dipanaskan lebih dahulu agar sudah siap saat dimulai 3 Produksi AMP 100 ton /hari 3 Biaya produksi termasuk pengangkutan s/d 10 km dari AMP

4 Dumptruk dimuati dan ditutup terpal untuk 4 Produksi dimuat ke dalam dump truk 5 ton dan dikirim ke tempat pekerjaan mempertahankan suhu 5 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

5 Dump truk membongkar langsung ke dalam 6 Spek.B.M.No. 12/PT/B/1983 dan revisi Spesifikasi Umum Maret 1989-Buku3 mesin penghampar aspal

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 3.00 1.00 L.081 3.00 110,000 330,000 K E Supir terampil 4.00 1.00 L.091 4.00 93,500 374,000 R

J Buruh tak terlatih 4.00 1.00 L.101 4.00 0 0

A Buruh terlatih 5.00 1.00 L.106 5.00 0 0

PEKERJA 797,500.00

M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Pasir ayak untuk beton m3 M.041 45.00 272,321.25 12,254,456.22

A Aspal kg M.061 9,000.00 9,628.52 86,656,715.8

T Semen 40 kg M.080 98.00 2,139.46 209,666.81

E Kapur/Pasir Hol/filler m3 M.081 6.00 139,176.02 835,056.13

R Alat bantu (set @ 3 alat) set M.170 0.24 150,000.00 36,000.00

I Batu sungai pecah tersaring m3 K.017 1.50 490,825.94 736,238.91 A

L

MATERIAL 100,728,133.91 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Wheel Loader 1.00 1.00 E.052 5.00 481,501.78 2,407,508.91

E Mesin penyampur aspal 1.00 1.00 E.155 5.00 2,676,509.39 13,382,546.94 R Dump truk 5 ton/120 HP 4.00 1.00 E.212 24.00 357,572.00 8,581,727.91 A T A N PERALATAN 24,371,783.77 TOTAL (Rp.) 125,897,417.68 VOLUME = 100.0 SATUAN = tonne HARGA SATUAN Rp. 1,258,974.18 per tonne

(24)

ANALISA HARGA SATUAN K O D E

LAPIS TIPIS ASPAL PASIR (LATASIR) K.020.M

PRODUKSI DAN SUPLAI (MENGGUNAKAN TENAGA BURUH) PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Semua material dikirim pemasok 1 Latasir dibuat secara manual

2 Produksi Latasir dilaksanakan secara manual 2 Aspal dipanaskan lebih dahulu agar sudah siap saat dimulai

3 Dumptruk dimuati dan ditutup terpal untuk 3 Biaya produksi termasuk pengangkutan s/d 10 km dari tempat pembuatan mempertahankan suhu 4 Produksi dimuat ke dalam dump truk 5 ton dan dikirim ke tempat pekerjaan 4 Dumptruk membongkar langsung kedalam 5 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

mesin penghampar aspal 6 Spek.B.M.No. 12/PT/B/1983 dan revisi Spesifikasi Umum Maret 1989-Buku3

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.)

P M a n d o r 3.00 1.00 L.061 3.00 93,500 280,500

E Supir terampil 6.00 1.00 L.091 6.00 93,500 561,000

K Buruh tak terlatih 75.00 1.00 L.101 75.00 60,500 4,537,500

E Buruh semi terlatih 6.00 1.00 L.103 6.00 0 0

R J A

PEKERJA 5,379,000.00 M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Pasir ayak untuk beton m3 M.041 45.00 272,321.25 12,254,456.2

A Aspal kg M.061 9,000.00 9,628.52 86,656,715.8

T Alat bantu (set @ 3 alat) set M.170 15.00 150,000.00 2,250,000.00

E Kayu bakar m3 M.070 60.00 959,755.40 57,585,324.04 R I A L MATERIAL 158,746,496.10 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Dump truk 5 ton/120 HP 4.00 1.00 E.212 24.00 357,572.00 8,581,727.91 E R A T A N PERALATAN 8,581,727.91 TOTAL (Rp.) 172,707,224.01

(25)

ANALISA HARGA SATUAN K O D E LAPIS TIPIS ASBUTON DAN AGREGAT HALUS (LASBUTAG) K.023

PRODUKSI DAN SUPLAI (MENGGUNAKAN BURUH) PROPINSI : PAPUA KOTA : KOTA JAYAPURA DISIAPKAN OLEH : KODE : ( 82 ) KODE : JAYAPURA TGL. /BULAN/TAHUN :

P R O S E S : ANGGAPAN :

1 Semua material dikirim pemasok 1 Menggunakan tenaga manusia 30ton/harihari 2 Pengaduk diisi asbuton tersaring + minyak 2 Kapasitas mixer 6 ton/jam bekerja 5 jam / hari

flux secara manual 3 Pengisian ke bin agar tetap penuh dengan sekop tangan 3 Timbunan produksi ditutup terpal agar tetap - 4 Asbuton tidak baik (kadar air dll) dan terbuang 12,5 %

kering sampai dipakai 5 Material tersaring dicampur dgn minyak flux/aspal/bunker dipengaduk 4 Dumptruk didisi secara manual dan me - (0,4m3/campuran) selama 6 menit (campuran/jam)

ngangkut kelokasi pekerjaan 6 hasil campuran disimpan tertutup terpal selama 3 s/d 5 hari 5 Muatan dibongkar secara manual 7 Truk pengangkut s/d 10km dari depot dan dibongkar secara manual

8 Spec. B.M.No.15/PT/1989 dan revisi Spesifikasi umum Maret 1989 buku 3

P E K E R J A VOL HARI K O D E TOTAL VOL UPAH B I A Y A SUB TOTAL

(org.hari) (Rp./org/hari) (Rp.) (Rp.) P M a n d o r 1.00 1.00 L.061 1.00 93,500 93,500 E Operator terampil 1.00 1.00 L.081 1.00 110,000 110,000 K Pembantu operator 1.00 1.00 L.083 1.00 0 0 E Supir terampil 2.00 1.00 L.091 2.00 93,500 187,000 R Pembantu supir 2.00 1.00 L.099 2.00 0 0

J Buruh tak terlatih 25.00 1.00 L.101 25.00 0 0

A Buruh terlatih 2.00 1.00 L.106 2.00 0 0

PEKERJA 390,500.00

M A T E R I A L SATUAN K O D E T O T A L H A R G A B I A Y A SUB TOTAL

VOL (Rp./unit) (Rp.) (Rp.)

M Pasir ayak untuk beton m3 M.041 2.00 272,321.25 544,642.50

A Aspal kg M.061 460.00 9,628.52 4,429,121.03

T Asbuton tonne M.062 12.00 0.00 0.00

E Minyak flux lt M.063 630.00 104.26 65,681.5

R Minyak bakar lt M.065 210.00 9,733.95 2,044,129.83

I Kapur/Pasir hol/filler m3 M.081 0.33 139,176.02 45,928.09

A Alat bantu (set @ 3 alat) set M.170 1.00 150,000.00 150,000.00

L Batu sungai pecah tersaring m3 K.017 9.00 490,825.94 4,417,433.48

MATERIAL 11,696,936.44 P E R A L A T A N JUMLAH HARI K O D E JAM H A R G A B I A Y A SUB TOTAL

KERJA KERJA (Rp./unit) (Rp.) (Rp.)

P Truk bak terbuka 2 1 E.221 10.0 242,861.32 2,428,613.23

E Pengaduk beton 1.00 1 E.253 5.0 99,456.62 497,283.08

R A L T A N PERALATAN 2,925,896.32 TOTAL (Rp) 15,013,332.76 VOLUME = 30.0 SATUAN = tonne HARGA SATUAN Rp. 500,444.43 per tonne

Figur

Memperbarui...

Referensi

Memperbarui...

Related subjects :