The Stability of
The Stability of
Underground
Underground
Ope
Ope
ning
ning
Review from Last Week
Review from Last Week
Insitu Stress (gravitational, tectonic, residual stresses)
An underground opening changes the stress condition Æ Induced Stress
Induced Stress Æ could triger unstability
Review from Last Week
Review from Last Week
Empirical equation to estimate insitu stresses e.g. Shoerey
) z 1 ( 0.001 E
7 0.25
Stress distribution around various opening Stress distribution around various opening shapes (circle, horseshoe, square, ellipse)
shapes (circle, horseshoe, square, ellipse)
Review from Last Week
Review from Last Week
Case Study A
Case Study A
An orebody XYZ has been defined as a block caving deposit. What we should design first?
Plan View Section A-A’
A A’
Orebody XYZ
Orebody XYZ
Surface
7 km 1.4
k
Case Study A
Case Study A
ACCESS
Orebody XYZ
Surface shaft
decline
Case Study A
Case Study A
The access for the orebody are decided to be twin adits, 6.8 m wide and 6.0 m high.
The opening size considers the following factors:
Biggest dimension
Effective size after ground support
Drainage pipe & trench
Case Study A
Case Study A
For the design purpose, how far apart should these two adits be?
Access Surface
?
Orebody XYZ
Access Adits Plan View
A A’
Case Study A
Case Study A
Assuming the simplest condition, the
axisymmetric stress distribution could be used.
0.00
Jarak dari batas terowongan, r/R
Te
al Tegangan radial Tegangan tangensial
r = 5R, the pre-mining stress would not be significantly different from the virgin stress field.
r = 17 meter as an early indication.
Might be further
analyzed using pillar stability calc and
Insitu Stress
Insitu Stress
For a depth of 1,400 m, the equation gives the vertical stress σ
v
= 38 MPa , theratio
k
= 0.5 (forEh
= 25 GPa) and hence the average horizontal stress σh
= 19 MPa During preliminary design, the empirical
Stress Distribution around
Stress Distribution around
Insitu Stress
Insitu Stress
Given the rock mass strength is around 70-80 MPa, a preliminary analysis of the
stresses induced around the proposed
tunnel shows that these induced stresses are likely to exceed the strength of the rock and that the question of stress
Insitu Stress Measurement
Insitu Stress Measurement
Various ways to measure insitu stress
Overcoring - Triaxial Strain Cell
Hydraulic Fracturing
Flatjack Measurement
Borehole Breakout
Acoustic Emission
The most common set of procedures is based on the determination of strains in the wall of a borehole, induced by
Overcoring
Overcoring
(CSIRO Cell)
(CSIRO Cell)
The CSIRO cell, referred to as a hollow inclusion The CSIRO cell, referred to as a hollow inclusion
cell. It consists of a thin epoxy tube, with three
cell. It consists of a thin epoxy tube, with three
strain gage rosettes, embedded within the
strain gage rosettes, embedded within the
epoxy.
epoxy.
Overcoring methods are measuring in situ stress Overcoring methods are measuring in situ stress
based on the stress relief around the borehole.
based on the stress relief around the borehole.
The relief of external forces by overcoring
The relief of external forces by overcoring
causes the changes in strain on the borehole
causes the changes in strain on the borehole
wall.
wall.
Overcoring
Overcoring
(CSIRO Cell)
(CSIRO Cell)
The field procedures consist of drilling a The field procedures consist of drilling a
concentric EX
concentric EX--size borehole, installation of the size borehole, installation of the deformation gage, and overcoring a stress relief
deformation gage, and overcoring a stress relief
borehole.
borehole.
If the elastic properties of the rock are known, If the elastic properties of the rock are known,
the changes in borehole diameter or strains can
the changes in borehole diameter or strains can
be converted to in situ stress in the rock.
The CSIRO cell is designed to measure diametral The CSIRO cell is designed to measure diametral
deformations of an EX
deformations of an EX--size (1.5" in diameter) size (1.5" in diameter) borehole during overcoring a concentric
borehole during overcoring a concentric
borehole (6" in diameter). The diametral
borehole (6" in diameter). The diametral
deformations are measured in three directions
deformations are measured in three directions
(60 degree apart) in the same diametral plane.
Overcoring
Overcoring
(CSIRO Cell)
(CSIRO Cell)
Need Need YoungYoung’’ss modulus and Poissonmodulus and Poisson’’s inputss inputs
LimitedLimited to within to within 1010--3030 meters of existing meters of existing
opening
opening
Overcoring Cost Overcoring Cost –– CSIRO Cells (2 sites)CSIRO Cells (2 sites)
NIRM US$ 61KNIRM US$ 61K
ES&S US$ 44K approx. 20K per siteES&S US$ 44K approx. 20K per site
Price does not include drilling which will be Price does not include drilling which will be
around US$ 120K / m
Hydraulic Fracturing
Hydraulic Fracturing
Typically hydraulic fracturing is conducted in Typically hydraulic fracturing is conducted in
vertical boreholes. A short segment of the hole
vertical boreholes. A short segment of the hole
is sealed off using an straddle packer. This is
is sealed off using an straddle packer. This is
followed by the pressurization of the fracture
followed by the pressurization of the fracture- -free segment of the hole by pumping in water.
The pressure is raised until The pressure is raised until the rock surrounding the
the rock surrounding the
hole fails in tension at a
hole fails in tension at a
critical pressure.
critical pressure.
Hydraulic Fracturing
Hydraulic Fracturing
Following breakdown, the Following breakdown, the shut
shut--in pressure, the in pressure, the lowest test
lowest test--interval interval pressure at which the
pressure at which the
hydrofrac closes
hydrofrac closes
completely under the
completely under the
action of the stress acting
action of the stress acting
normal to the
normal to the
hydrofracture
Hydraulic Fracturing
Hydraulic Fracturing
Limited to drill/pump equipment and ground Limited to drill/pump equipment and ground
conditions
conditions –– Max range 300m Max range 300m –– 1000m1000m
““QualitativeQualitative””
AssumptionsAssumptions
S1 Maximum Principle Stress is Vertical or S1 Maximum Principle Stress is Vertical or
aligned with
aligned with holehole
HydofracingHydofracing
NIRMNIRM US$ 87KUS$ 87K
Borehole Breakout
Borehole Breakout
Extensive field evidence and laboratory Extensive field evidence and laboratory
experiments suggest that borehole breakouts,
experiments suggest that borehole breakouts,
defined as borehole cross
defined as borehole cross--section elongations section elongations resulting from preferential rock failure, is a
resulting from preferential rock failure, is a
direct consequence of the in situ stress in the
direct consequence of the in situ stress in the
rock.
Borehole Breakout
Borehole Breakout
One of the early observations of breakouts was One of the early observations of breakouts was
in the quartzite and conglomerates of the
in the quartzite and conglomerates of the
Witwatersrand gold mine in South Africa
Witwatersrand gold mine in South Africa
(Leeman, 1964). The spalling was observed to
(Leeman, 1964). The spalling was observed to
occur at diametrically opposed points on the
occur at diametrically opposed points on the
borehole wall perpendicular to the direction of
borehole wall perpendicular to the direction of
the maximum principal stress.
Borehole Breakout
Borehole Breakout
The most publicized The most publicized
observation of breakouts
observation of breakouts
was in the 3 m diameter
was in the 3 m diameter
drift at 420 m level in the
drift at 420 m level in the
Underground Research
Underground Research
Laboratory (URL), Canada.
Laboratory (URL), Canada.
Two diametrically opposed
Two diametrically opposed
breakouts were
breakouts were
approximately aligned with
approximately aligned with
the vertical stress, which is
the vertical stress, which is
the overall least principal
the overall least principal
stress at URL.
Case Study A
Case Study A
From insitu stress measurement, the bearing of the major principal stress is around 38-40 degree. What is the preferable panel/undercut drift orientation?
Orebody XYZ
Orebody XYZ Panel/ Drill Drift
Case Study A
Case Study A
Ideally, the panel/undercut drift and the
direction of cave advance are aligned with the principal horizontal in situ stresses.
If the direction of advance is perpendicular, the levels of stress in the abutment ahead of the undercut will be high and will increase as the undercut advances
Stress Induced in the
Stress Induced in the
Extraction and Undercut Level
Extraction and Undercut Level
High abutment stresses induced in the vicinity of an advancing undercut front is resulted from undercutting activity.
Stress Induced in the
Stress Induced in the
Extraction and Undercut Level
Extraction and Undercut Level
The magnitude of abutment stresses in the cave vicinity could reach up 2 to 3 times
the insitu stress magnitude.
This abutment stress could devastate development drifts if does not maintain properly
For XYZ Mine, the vertical stress σ
v
= 38 Mpa. The abutment stress = 76 - 114Failure of yielding arch support
Failure of yielding arch support
El Salvador Mine, Chile
Rockburst at Extraction Level,
Rockburst at Extraction Level,
DOZ Mine, Indonesia
Collapse of an extraction level drift,
Collapse of an extraction level drift,
El Teniente Mine, Chile, 1989
El Teniente Mine, Chile, 1989
CONCRETE DAMAGE
CONCRETE DAMAGE
Panel 15, 28 June 2003
Stress Induced in the
Stress Induced in the
Extraction and Undercut Level
Extraction and Undercut Level
Several factors have the potential to
influence the levels of stress induced in the extraction level excavation:
Cave Hydraulic Radius
Undercut direction
In situ Stress regime
The timing of undercut relative to the extraction level development
Case Study A
Case Study A
The timing of undercut relative to the
extraction level development relates to the selected undercutting method.
In general, there are three main undercutting strategies:
1.Post Undercutting
2.Pre Undercutting
3.Advanced Undercutting
Terminology
Terminology
Drill Drift - Undercut
Fan Drilling
Draw Bell
Major Apex
Conventional
Conventional
Panel
Panel
Caving
Caving
Undercutting and drilling takes place after development of the underlying extraction level has been completed.
Advance
Advance
Undercut
Undercut
Panel
Panel
Caving
Caving
Undercutting and drilling takes place above a partially developed extraction level.
The partial development on the extraction level can consist of either extraction drift only or
Advance
Advance
Undercut
Undercut
Panel
Panel
Caving
Caving
Drawbells are always prepared in the de-stressed zone behind the undercut,
Comparing Abutment Stress Impact
Comparing Abutment Stress Impact
Measuring abutment stress changes could be done indirectly by monitoring its impact.
The stress impact reflects in displacement / deformation occurred in the underground opening.
There are many different methods for
monitoring displacement. The simplest and most common among them is a
Comparing Abutment Stress Impact
Comparing Abutment Stress Impact
A convergence gage usually consists of a tape, wire, rod, or tub in series with a
deformation indicator.
3
Case Study A
Case Study A
Near XYZ BC Mine, there is an active BC mine, called KLM Mine, where the trial between Post Undercut and Advanced Undercut will take
place.
Plan View Orebody
XYZ
KLM Mine
Undercut Trial at KLM Mine
Undercut Trial at KLM Mine
Panel 15 Post
43
Undercut Trial at KLM Mine
Undercut Trial at KLM Mine
Result of KLM Mine Trial
Result of KLM Mine Trial
Advanced Undercut vs Post Undercut
Advanced Undercut vs Post Undercut
Stable after Cave Front
Passing
Post Undercut
Anomaly
Result of KLM Mine Trial
Result of KLM Mine Trial
Advanced Undercut vs Post Undercut
Advanced Undercut vs Post Undercut
Anomaly
Cave Advance Stable after
Anomaly
Anomaly
The anomaly from KLM Mine Trial could be explained as the result of remnant undercut pillar or stump.
Stump is created when the undercut
blasting fails to break the rock completely.
Cave Cave
Advance Remnant Pillar
Examples
Case Study A
Case Study A
The KLM Mine trial shows that the
advanced undercut has the advantage to reduce the stress induced impact to
undercut and extraction level.
Considering the KLM Mine trial result, XYZ BC Mine will implement the advanced
undercutting method.
A note has been made that XYZ BC should establish undercut blasting control such
Stress Induced in the
Stress Induced in the
Extraction and Undercut Level
Extraction and Undercut Level
Several factors have the potential to
influence the levels of stress induced in the extraction level excavation:
Distance between Undercut and Extraction
Cave Hydraulic Radius
Undercut direction
In situ Stress regime
The timing of undercut relative to the
Case Study A
Case Study A
The undercut face shape is controlled by the
undercut opening sequence and the lead and lag among drill drift cave front
Irregularities of cave front could create
Undercutting Sequence
Lead and Lag
Lead and Lag
Lead and Lag: the
distance between the
caving front on adjacent panels
Cave Front
Undercutting Sequence
Undercutting Sequence
Undercutting Sequence
Undercutting Sequence
When comparing the results of the undercut sequence models, the main useful criteria to examine have proven to be:
1.Peak stress levels (in the stronger ground) induced on the production level elevation.
2. Average and maximum values of strain (as a measure of the severity of damage
Undercutting Sequence
Undercutting Sequence
3. Areas of damage on the production level elevation, measured in terms of areas where shear strains exceed a set limit of 2 x 10-3 (2 millistrains). This value was chosen because it includes damage in the stronger ground and not just the weaker ground areas, which are known to become extensively damaged,
Undercut Opening Sequence
Undercut Opening Sequence
From modeling result, a wedge type sequence
appears preferable. Mining in weak ground
should be over a short front, and bordered by
Undercut Opening Sequence
Undercut Opening Sequence
The undercut wedge apex should advance into the weaker ground, close to the boundary with stronger ground, with the apex angle broad
Lead and Lag
Lead and Lag
To evaluate the lead To evaluate the lead
and lag, convergence
and lag, convergence
information from
information from
KLM mine is used.
KLM mine is used.
Cave Front
Displacement ( mm/ day)
Convergence data is Convergence data is
presented in velocity
presented in velocity
(mm/day) contour
(mm/day) contour
Increasing of horizontal and vertical velocity due to lead and lag (60 meter)
No Advanced
horizontal vertical
070501 140501
0.0 mm/day
070501 140501
-1.3
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (54 meter)
140501 290501
-1.3 mm/day
140501 290501
-0.74
mm/day -1.12 mm/day -0.1 mm/day
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (45 meter)
horizontal vertical
290501 120601
-0.74 mm/day
290501 120601
-0.5 mm/day
-0.1 mm/day
0.3 mm/day
Increasing of horizontal velocity due to no advanced of lead and lag distance (45 meter)
120601 260601
-0.5 mm/day
120601 260601
-0.65 mm/day
0.3 mm/day
-0.2 mm/day
Decreasing of horizontal and vertical velocity
Increasing of horizontal velocity due to no advanced of lead and lag distance (30 meter)
130701 070801
-0.4 mm/day
130701 070801
-0.8 mm/day
0.0 mm/day
-0.1 mm/day
Decreasing of horizontal and vertical velocity after reducing lead and lag distance (25 meter)
horizontal vertical
070801 230801
-0.8 mm/day
070801 230801
-0.1 mm/day
-0.1 mm/day
0.0 mm/day
Increasing of horizontal and vertical velocity due to no advanced of lead and lag distance (25 meter)
230801 150901
-0.1 mm/day
230801 150901
-0.75 mm/day
0.0 mm/day
-0.4 mm/day
Decreasing of horizontal and vertical velocity after reduce lead and lag distance (8 meter)
horizontal vertical
150901 260901
-0.75 mm/day
150901 260901
-0.4 mm/day
-0.4 mm/day
0.1 mm/day
Decreasing of horizontal and vertical velocity in the same of lead and lag distance (8 meter)
260901 091001
-0.4 mm/day
260901 091001
-0.1 mm/day
0.1 mm/day
0.0 mm/day
Decreasing of horizontal and vertical velocity below 8 meter of lead and lag distance (5 meter)
horizontal vertical
091001 261001
-0.1 mm/day
091001 261001
0.0 mm/day
0.0 mm/day
0.0 mm/day
Constant stable of horizontal and vertical velocity below 8 meter of lead and lag distance (5 meter)
261001 071101
0.0 mm/day
261001 071101
0.0 mm/day
0.0 mm/day
0.0 mm/day
Lead & Lag Issue
Lead & Lag Issue
Reading Displacement Velocity (mm/day)
Vertical Displacement Velocity (mm/day)
Lead & Lag Issue
Lead & Lag Issue
From the convergence measurement, From the convergence measurement, the ideal the ideal
lead and lag is between 5 to 8 meters
lead and lag is between 5 to 8 meters, cave , cave front can be stopped without any significant
front can be stopped without any significant
displacement
displacement
If the lead and lag is over the 12 m, the cave If the lead and lag is over the 12 m, the cave
face cannot be stopped for more than one week
face cannot be stopped for more than one week
because excessive damage will occur in the
because excessive damage will occur in the
panels
Case Study A
Case Study A
XYZ Mine
Plan View Access
Adits
Undercut Sequence and
Direction