• Tidak ada hasil yang ditemukan

Q2 2017 Investors Update

N/A
N/A
Protected

Academic year: 2017

Membagikan "Q2 2017 Investors Update"

Copied!
19
0
0

Teks penuh

(1)
(2)

1

Executive Summary

Overall financial performance as at YTD June 2017 better than YTD June 2016

and the Budget

Overall sales volumes at YTD June 2017 were higher than the Budget mainly due to increased production at Tabang.

Actual ASP was higher than the Budget as market prices remained above the Budgeted levels.

1) Revenue, Gross Profit include coal and non-coal sales ;

1) Average Selling Price includes coal and non-coal sales ; 2) Average Cash Costs include Royalty, Barging, SGA;

Revenue (1) 221.7 347.6 423.1 22% Gross Profit (1) 65.4 136.1 214.1 57%

Gross Profit Margin 29% 39% 51% 29%

(3)

2

Executive Summary - continued

www.bayan.com.sg

Sales volumes 2Q17 was 4.7 million MT which was higher than 1Q2017 and the Budget of 4.2 million MT mainly due to increased production at

Tabang.

2Q17 Coal Production achieved was 4.3 million MT which was principally

in line with the Budget of 4.3 million MT. However, it was higher than

1Q17 mainly due to the relocation of our contractor at Tabang to low strip

areas during the quarter in order to better match production and trucking

capacity, earlier commencement of mining at Wahana and the arrival of

additional mining fleets at PIK.

(4)

3

Executive Summary - continued

2Q17 Cash costs of US$ 28.6/MT was lower than the Budget of US$

29.5/MT mainly due to:

Higher actual sales volumes which decreased certain unit costs

Lower spend on material and spare parts as well as repair and

maintenance

Lower unit rates at Tabang in OB Removal, coal mining and hauling as a result of a discount received from subcontractor to increase the volumes from the original contract

Lower than Budgeted demurrage;

General lower actual fuel price rate which resulted decrease in barging cost and fuel consumption cost;

Partially offset by:

Higher weighted stripping ratio at PIK and TSA/FKP;

(5)

4

2Q 2017

www.bayan.com.sg

Overburden Removal

Coal Production

Weighted Average Strip Ratio

Average Cash Costs

Coal Sales

Average Selling Price

Committed & Contractual Sales

Debt and Cash Position

(6)

5

Overburden Removal (OB)

(million BCM)

Overburden Removal

2Q17 Overburden removal of 17.1 million BCM was higher than the 1Q17 and 2Q17 Budget

15.0 17.1

1Q17 2Q17B 2Q17

16.6 2Q17 OB was 17.1 million

BCM which was higher than 1Q17 and the Budgeted mainly due to:

Contractor has

mobilized additional equipment in 2Q17 to rectify the shortfall and new geological model was prepared to correct for the discrepancies (TSA/FKP)

Mobilization of

additional mining fleets at PIK coupled with lower rainfall

2Q17B 2Q17

Gunungbayan Pratamacoal-

Block II 1.5 -Teguh Sinar Abadi/ Firman

(7)

6

Coal Production

(million MT)

Coal Production Volume

www.bayan.com.sg 2Q17 coal production of 4.3 million MT was in line with the 2Q17 Budget

4.0 4.3

1Q17 2Q17B 2Q17

4.3

2Q17 coal production of 4.3

million MT was principally in line with 2Q17 Budget, however it was higher than 1Q17 mainly due to :

The relocation of our contractor at Tabang to low strip areas during the quarter in order to better match production and trucking capacity and also as a result of higher rainfall which flooded certain sections of the working area

Earlier commencement of mining at Wahana

Arrival of an additional mining fleet in early April 2017 (PIK)

(8)

7

Actual Weighted Average Stripping Ratio (SR)

Weighted Average Strip Ratio

2Q17 actual weighted average strip ratio of 3.9 : 1 was principally in line with 1Q17 and the 2Q17 Budget 1Q17 and 2Q17 Budget

Higher SR at TSA/FKP in

2Q17 compared to the

Budget due to change in

scheduling required to

develop the pit at higher production rate compared to Budget and variations in the geological model

Higher stripping ratio at

PIK due to change in production plan following the contractor’s Q2

equipment deliveries

(9)

8

Average Cash Costs per MT(*)

Average Cash Costs

www.bayan.com.sg (1) Average Cash Costs include Royalty, Barging, SGA

(2) US$ is a convenience translation using the average quarterly exchange rate for the quarter numbers

(3) B stands for Budget Figure

( Budget of US$29.5/MT mainly due to:

Higher actual sales volumes which decreased certain unit costs

Lower spend on material and spare parts as well as repair and maintenance

Lower unit rates at Tabang in OB Removal, coal mining and hauling as a result of a discount received from subcontractor to increase the volumes from the original contract

Lower than Budgeted demurrage;

General lower actual fuel price rate which

Higher royalty cost mainly due to higher ASP;

27.2 28.6

1Q17 2Q17B 2Q17

29.5

(10)

9 due to changes in shipping schedule.

India and China are the top two

destinations in 2Q2017

Top Customers 2Q17 (by Sales Volume)

are TNB Fuel, Noble Resources and Sembcorp Gayatri Power Limited

2Q17 coal sales volume was 4.7 million MT which was higher than 1Q17 and 2Q17 Budget due to changes in shipping schedule

Note : B stands for Budget Figure

Geographic Distribution (1Q17)

(11)

10

Average Selling Price (ASP)

www.bayan.com.sg

Average Selling Price (*)

2Q17 ASP was US$ 50.2/ MT which was higher than the Budget as the Company benefited from more exposure to the current higher benchmark prices

(1) ASP includes coal and non-coal sales

(2) US$ is a convenience translation using the average quarterly exchange rate for the quarter numbers

(3) B stands for Budget Figure *

Higher benchmark prices in 2Q17

than the 2Q17 Budget

(US$ 79.8/MT vs US$ 65.0/MT)

2Q17 average CV was 4,682 GAR kcal

(12)

11

EBITDA

Note : B stands for Budget Figure

2Q17 EBITDA generation was

stronger than Budgeted due to:

Higher than Budgeted ASP

Higher than Budgeted sales

volume

Lower than Budgeted Cash

Costs 86.8

101.6

1Q17 2Q17B 2Q17

46.8

(US$ Million)

(13)

12

Committed and Contracted Sales for 2017

www.bayan.com.sg

2017

Fixed Price Floating Price

17.7 million MT

72%

28%

Note : June 2017

As at 30 June 2017 committed and

contracted sales were 17.7 million MT with an average CV of 4,629 GAR kcal

2017 Fixed Price element at US$

(14)

13

Net Debt and Cash

As of 30 June 2017, the total TLF Loan was US$ 399.2 million (excluding PIK

Interest)

The Company reduced the Net Debt to EBITDA to 0.86x as at 30 June 2017

470.3 465.6 465.4

Note : Total Net Debt and Cash + Debt Service Reserve Account (DSRA)

(15)

14

Capital Expenditure

www.bayan.com.sg CAPEX (*)

* US$ is a convenience translation using the average annual exchange rate;

* B stands for Budget Figure

2Q17 Capex was US$ 14.3 million

which was higher than the Budget of US$ 11.9 million, principally consisted of:

Heavy equipments (i.e. Komatsu

Bulldozer, Dump Trailer and Terrain Crane)

Tabang related infrastructure at

Senyiur Jetty (i.e. Palu Gravel, relocation & re installment of Silo from Pakar to ICF)

11.9

14.3

(16)

15

PT Perkasa Inakakerta PIK

PT Teguh Sinarabadi TSA

PT Firman Ketaun Perkasa FKP

PT Wahana Baratama Mining WBM

PT Fajar Sakti Prima FSP

PT Bara Tabang BT

PT Brian Anjat Sentosa BAS

PT Tanur Jaya TJ

PT Silau Kencana SK

PT Orkida Makmur OM

PT Tiwa Abadi TA

PT Sumber Api SA

PT Dermaga Energi DE

PT Bara Sejati BS

PT Apira Utama AU

PT Cahaya Alam CA

PT Mamahak Coal Mining MCM

PT Bara Karsa Lestari BKL

PT Mahakam Energi Lestari MEL

PT Mahakam Bara Energi MBE

PT Graha Panca Karsa GPK

Tabang

Pakar

(17)

16

www.bayan.com.sg

Appendix

Kangaroo Resources Limited KRL

PT Dermaga Perkasapratama DPP

PT Indonesia Pratama IP

PT Muji Lines Muji

PT Bayan Energy BE

PT Metalindo Prosestama MP

PT Sumber Aset Utama SAU

(18)

17

Disclaimer

This presentation contains forward-looking statements based on assumptions and forecasts made by PT. Bayan Resources Tbk management. Statements that are not historical facts, including statements about our beliefs and expectations, are forward-looking statements. These statements are based on current plans, estimates and projections, and speak only as of the date they are made. We undertake no obligation to update any of them in light of new information or future events.

(19)

18

Thank You

Referensi

Dokumen terkait

Paket pengadaan ini terbuka untuk penyedia yang teregistrasi pada Layanan Pengadaan Secara Elektronik (LPSE) dan memenuhi persyaratan sebagai berikut : memiliki izin usaha seperti

8agi penggunajalan yang sedang da1am keadaan beresiko tinggi itu disarankan agartidak mengendarai kendaraannya dulu sampai keadaannyakembali menjadi nor- mal, sedangkan bagi

Bahwa pada hari ini Rabu tanggal Dua Puluh Lima bulan Juni tahun Dua Ribu Empat Belas (25-06- 2014) pada pukul 15.01 WIB, ULP Pokja Konstruksi secara resmi menutup masa

Alamat Perusahaan NPWP. Harga Penawaran

[r]

Dengan ini diberitahukan bahwa setelah diadakan penelitian oleh Kelompok Kerja Konsultan VII (Tujuh) ULP Kabupaten Lampung Tengah menurut ketentuan – ketentuan yang berlaku,

Sehubungan dengan telah ditetapkannya Pemenang Seleksi Paket : Pengawasan Jalan Lingkungan, sesuai dengan Surat Penetapan Pemenang Nomor : 08/ X/12 /JKBU-ULP/2015 tanggal

Regresi Poisson menyaratkan keadaan nilai mean dan varians dari variabel respon sama (Myers et al. [3]), pada kenyataannya sering terjadi nilai varians yang lebih besar